method statement for water proffing works
DESCRIPTION
METHOD STATEMENT FOR WATER PROFFING WORKSTRANSCRIPT
![Page 1: METHOD STATEMENT FOR WATER PROFFING WORKS](https://reader035.vdocuments.site/reader035/viewer/2022082207/55cf9879550346d03397ddce/html5/thumbnails/1.jpg)
METHOD STATEMENT WATER PROOFING WORKS –
SUBSTRUCTURE AND SUPER STRUCTURE
2012
AL BALAGH TRADING & CONTRACTING CO. W.L.L.
![Page 2: METHOD STATEMENT FOR WATER PROFFING WORKS](https://reader035.vdocuments.site/reader035/viewer/2022082207/55cf9879550346d03397ddce/html5/thumbnails/2.jpg)
AL BALAGH TRADING AND CONTRACTING CO WLL
PO 5777-DOHA-QATAR
PH 44667714
PROPOSED DEVELOPMENT OF BARZAN CAMP-PHASE 2
A1-SUPREME COMMAND BUILDING
(AL BALAGH JOB NO. 18/12)
(PEO JOB NO. 06-005)
METHOD STATEMENT FOR WATER PROOFING
WORKS
DOCUMENT NO: MS-18/12 – 002 VERSION A
![Page 3: METHOD STATEMENT FOR WATER PROFFING WORKS](https://reader035.vdocuments.site/reader035/viewer/2022082207/55cf9879550346d03397ddce/html5/thumbnails/3.jpg)
LIST OF CONTENTS
1. PURPOSE
2. SCOPE
3. DEFANITIONS
4. APPROVED MATERIALS AND AREA OF APPLICATION
5. RESPONSIBLITIES
A. PERSONAL PROTECTIVE EQUIPMETNS
B. SAFETY ARRANGEMENTS
6. WORKING METHOD
A. SURFACE PREPARATION WORKS
B. TOOLS REQUIRED
C. PRIMING
D. MEMBRANE
E. TEMINATIONS
F. MOCK UP AND INSPECTIONS
G. PROTECTION FOR MEMBRANEANCE
7. REFERANCE
8. APPENDIX
a. ORGANIZATION CHART
b. EMERGENCY ACTION PLAN
![Page 4: METHOD STATEMENT FOR WATER PROFFING WORKS](https://reader035.vdocuments.site/reader035/viewer/2022082207/55cf9879550346d03397ddce/html5/thumbnails/4.jpg)
1 PURPOSE
• Purpose of this document is to clearly explain the installation procedure of the water
proofing membrane for the areas as specified in the scope statement
2 SCOPE
• Purpose of this document is to clearly explain the installation procedure of the water
proofing membrane for the sub structure, super structure including all wet areas like
Toiles, balcony, kitchens and pantry.
• Roof water proofing is not included in the scope of this statement for which a detailed
method statement will be submitted later.
3 DEFANITIONS
• CLIENT : PRIVATE ENGINEERING OFFICE
• CONSULTANT : MS DAR AL HANDASA
• CONTRACTOR : MS AL BALAGH TRADING AND CONTRACTING CO WLL
4 APPROVED MATERIAL AND AREAS OF APPLICATION
Water proofing system consists of application of priming membrane and 4 mm thk
bituminous membrane. Protection screed concrete of 50 mm thickness is done in areas
specified in drawing. Following materials are used for the water proofing
Primer : PolyPrime SB - (200 liter drum)
Membrane : 4mm thick Bituplus E 4200 (1 m x 10 m roll)
Protecton Board : Bituboard 4 mm thick – for vertical areas
Manufacturer : Henkel poly Bit Industries – UAE & KSA
![Page 5: METHOD STATEMENT FOR WATER PROFFING WORKS](https://reader035.vdocuments.site/reader035/viewer/2022082207/55cf9879550346d03397ddce/html5/thumbnails/5.jpg)
5 RESPONSIBLITIES
• SR PROJECT ENGINEER AND PROJECT ENGINEER is responsible for the proper
implementation of correct method statement. QA engineer will ensure QA and QA
aspects as per the contractors QA QC policy which is to be submitted as a separate
document
• PPE – Refer Clause 13 of Approved HSE Plan
• SAFETY ARRANGEMENTS
A. Safe access and Egress to provided
B. Proper lighting to be provided
C. Fire extinguishers and fire Blanket has to be provided with each torch
D. Proper welfare to be provided
5 WORKING METHOD
• SURFACE PREPARATION WORKS
After blinding is completed the surface is ensured dirt and dust free. This is
ensured by blowing air with a compressor or hand blower and by manual
cleaning. Approval from consultant is to be taken after this
• TOOLS REQUIRED.
Following tools are made readily available during the works
A. Painting Brush and Roller Brush for priming
B. Gas With Torch
C. Measuring Tape, Knife, trowel etc
• PRIMING
Primer is applied to the concrete surface slowly at the rate of 4-6 l/SqM. Brush
or roller can be used for this. Allow primer to dry before application of
membrane. AS the viscosity of primer is low it easily penetrates into the holes in
the concrete. Primer allows the adhesion of membrane with the concrete
surface
![Page 6: METHOD STATEMENT FOR WATER PROFFING WORKS](https://reader035.vdocuments.site/reader035/viewer/2022082207/55cf9879550346d03397ddce/html5/thumbnails/6.jpg)
• MEMBRANE
Water proofing membrane is installed using propane gas torch. As the torching
progresses on the membrane, the embossing starts to melt exposing a shiny
bitumen surface. Membrane is roll forwarded and pressed firmly against the
primed surface to get it stick properly. Subsequent shifting of torching is done
when membrane is unrolled and adhered to the surface. All the ends are torched
very well for very clear fixation. It is ensured that air is not blocked inside the
membrane. This is possible as the primer surface is also torched and hot gases
will go upwards.
Over laps are the lapping distance between two adjacent sheets and they are as
follows. These are as per manufacturers recommendations.
Side over lap - 100 mm ( parallel of 10 m side)
End over lap - 150 mm ( parallel to 1m side)
Sealing of laps are done with round tipped trowel. Adequate heating is done and
this ensures flow of uniform melted bitumen compound evenly in the bead that
oozez from the membrane adges. Excess compound is pressed into the seam
with heated trowel.
• TEMINATIONS
Water proofing membrane is terminated in locations as per
drawings by providing a 25 mm x 25 mm groove. Heating of
membrane is done and the t ip is inserted to the groove. The groove
is sealed with sealant – Poly seal PS whip is recommended by the
manufacturer.
The area of termination in the wet areas l ike toi lets, balcony,
kitchen etc wil l have to be inside the skirt ing. So the vertical ly the
membrane wil l be coming by a distance of at least 150 mm. Angle
f i l ler of 50 x 50 mm sand cement mortar is provided in the corner
of rooms so that membrane is not bend 90 degrees in one turn.
For the substructure water proofing is terminated at the retaining
wal l just 200 mm below the FGL there. So that the termination
point is fully concealed and better performance is ensured.
![Page 7: METHOD STATEMENT FOR WATER PROFFING WORKS](https://reader035.vdocuments.site/reader035/viewer/2022082207/55cf9879550346d03397ddce/html5/thumbnails/7.jpg)
• MOCKUP AND INSPECTIONS
Mockup of the complete system may be done for an area not less
than 100 sqm and inspection request should be raised. Further
work should proceed after approval of the mockup.
Inspect ion for each area has to be done prior to applicat ion of
primer and concrete screed works.
• PROTECTION FOR MEMBRANEANCE
50 mm approved concrete screed is to be used for the protection
of water proofing for the horizontal areas. Vertical areas are
protected using approved Henkel Bituboard – 4 mm thick
7 REFERANCES
• Following documents are to be kept in site for ready reference and to be
produced before for consultant if asked to do so.
A. All shop drawings
B. Specifications
C. Typical details
D. General notes
E. IFC drawings (Latest revision) – structural
F. Previous inspection comments
G. etc
8 APPENDIX
• ORGANIZATION CHART - PREVIOUSLY SUBMITTED AND APPROVED
• EMERGENCY ACTION PLAN – AS PER HSE PLAN