mep- building services

84
BUILDING SERVICES Aniket Khandelwal 9096871414 Email id- [email protected]

Upload: aniket-khandelwal

Post on 07-Jan-2017

1.729 views

Category:

Presentations & Public Speaking


33 download

TRANSCRIPT

Page 1: MEP- Building services

BUILDING SERVICES

Aniket Khandelwal9096871414

Email id- [email protected]

Page 2: MEP- Building services

Imagine yourself in the most fabulous building in the

world. Now take away the lighting, heating and

ventilation, the lifts and escalators, acoustics,

plumbing, power supply and energy management

systems, the security and safety systems.

You are left with a cold, dark, uninhabitable shell !!!

BUILDING SERVICES

Page 3: MEP- Building services

Everything inside a building which makes it safe and comfortable to be in comes under the title of 'Building services'.

A building must do what it was designed to do - not just provide shelter but also be an environment where people can live, work and achieve.

Building services are what makes a building come to life.

BUILDING SERVICES

Page 4: MEP- Building services

MECHANICAL SERVICES PLUMBING SERVICES

ELECTRICAL SERVICES

MEP

CIVIL CO-ORDINATION

INTRODUCTION TO MEP

Page 5: MEP- Building services

MECHANICAL SERVICES

1. HVAC – HEATING VENTILATION & AIR CONDITIONING

2. REFRIGERATION

3. FIRE PROTECTION

Page 6: MEP- Building services

ELECTRICAL SERVICES

1. ELECTRICAL HT & LT POWER DISTRIBUTION2. LIGHTING3. EARTHING & LIGHTNING PROTECTION4. FIRE DETECTION & ALARM SYSTEM5. PUBLIC ADDRESS SYSTEM6. ACCESS CONTROL SYSTEM7. CCTV SYSTEM & MONITORING SYSTEM8. BUILDING SECURITY SYSTEM9. BUILDING MANAGEMENT SYSTEM

Page 7: MEP- Building services

PLUMBING SERVICES

1. DOMESTIC WATER SYSTEM2. FLUSHING WATER SYSTEM3. SEWAGE WATER SYSTEM4. RAIN WATER SYSTEM5. SEWAGE TREATMENT PLANT 6. WATER TREATMENT PLANT7. ALL PIPING & SANITARY FIXTURES THAT PROVIDE WATER FOR ANY USE (Drinking, cooking, bathing, laundry, process, etc.)

Page 8: MEP- Building services

ELECTRICAL SERVICES

Page 9: MEP- Building services

CLASSIFICATION OF ELECTRICAL SYSTEMS

EXTERNAL INTERNAL

ELECTRICAL SYSTEMSTRANSFORMERS

HT PANELS

BUSDUCTS

EXTERNAL CABLING

FLAME PROOF ELECTRICAL

EQUIPMENTS

DG SETS

LIGHTING ARRESTORS

SOLAR SYSTEMS

LT PANELS

DISTRIBUTION BOARDS

EARTHING

CABLE CONTAINMENT

LIGHTING WIRING

POWER WIRING

LT CABLING

RECEPTACLES

LUMINAIRES

CLASSIFICATION OFELECTRICAL SYSTEMS

Page 10: MEP- Building services

DG SETS

UPS

POWERLIGHTING PROCESS

TYPICAL ELECTRICAL SCHEMATIC

HT PANELHT CABLE

TRANSFORMERSHT CABLE

LT PANELSBUS DUCTS / CABLES

DISTRIBUTION BOARDS

BUS DUCTS / CABLES

CAPACITOR BANKS

CABLES

HT INCOMING SUPPLY

HT INCOMING SUPPLY

HT CABLE

METERING KIOSK

HT METERING KIOSKHT PANELTRANSFORMERSLT PANELSDG SETSDISTRIBUTION BOARDS

LIGHT FIXTURES

POWER SOCKETSUPSAPFC PANEL

Page 11: MEP- Building services

LOW VOLTAGE SYSTEMS

1. FIRE DETECTION & ALARM SYSTEM

2. PUBLIC ADDRESS SYSTEM

3. ACCESS CONTROL SYSTEM

4. CCTV SYSTEM & MONITORING SYSTEM

5. BUILDING SECURITY SYSTEM

6. BUILDING MANAGEMENT SYSTEM

FIRE DETECTION & ALARM SYSTEMPUBLIC ADDRESS SYSTEM

ACCESS CONTROL SYSTEMCCTV SYSTEM & MONITORING SYSTEM BUILDING MANAGEMENT SYSTEM

Page 12: MEP- Building services

FIRE DETECTION SYSTEM

• A FIRE ALARM SYSTEM IS NUMBER OF DEVICES WORKING TOGETHER

TO DETECT AND WARN PEOPLE THROUGH VISUAL AND AUDIO

APPLIANCES WHEN SMOKE, FIRE, CARBON MONOXIDE OR OTHER

EMERGENCIES ARE PRESENT. THESE ALARMS MAY BE ACTIVATED FROM

SMOKE DETECTORS, AND HEAT DETECTORS FIRE DETECTION & ALARM SYSTEM

PUBLIC ADDRESS SYSTEM

• A PUBLIC ADDRESS SYSTEM (PA SYSTEM) IS AN ELECTRONIC SOUND

AMPLIFICATION AND DISTRIBUTION SYSTEM WITH A MICROPHONE,

AMPLIFIER AND LOUDSPEAKERS, USED TO ALLOW A PERSON TO

ADDRESS A LARGE PUBLIC, FOR EXAMPLE FOR ANNOUNCEMENTS OF

MOVEMENTS AT LARGE AND NOISY AIR AND RAIL TERMINALS OR AT A

SPORTS STADIUM.

Page 13: MEP- Building services

INTELLIGENT ADDRESSABLE FIRE ALARM

CONTROL PANEL

REPEATER PANEL

INPUT MODULE

MCP

CONTROL RELAY

MODULE

ADD. SMOKE DETECTOR FOR ROOM

ADD. SMOKE DETECTOR

FOR CEILING

ADD. DUCT DETECTOR

ADD. SMOKE DETECTOR FOR ROOM

ADD. SMOKE DETECTOR

FOR CEILING

INPUT MODULE

MCP

2Cx1.5 SQMM CABLE

WORKSTATION

FOR BMS SYSTEM

TO NEXT FACP FROM PREVIOUS FACP

FIRE DETECTION SYSTEM

Page 14: MEP- Building services

ACCESS CONTROL SYSTEM

• IN THE FIELDS OF PHYSICAL SECURITY AND INFORMATION

SECURITY, ACCESS CONTROL IS THE SELECTIVE RESTRICTION

OF ACCESS TO A PLACE OR OTHER RESOURCE

• ACCESS CONTROL REFERS TO SECURITY FEATURES THAT

CONTROL WHO CAN ACCESS RESOURCES IN THE OPERATING

SYSTEM. APPLICATIONS CALL ACCESS CONTROL FUNCTIONS

TO SET WHO CAN ACCESS SPECIFIC RESOURCES OR CONTROL

ACCESS TO RESOURCES PROVIDED BY THE APPLICATION. ACCESS CONTROL SYSTEM

Page 15: MEP- Building services

SCHEMATIC – ACCESS CONTROL SYSTEM

ENTRYDOOR

EXITDOOR

EML EMLLAN CONNECTIONFIRE INTEGRATION

ENTRY READER WITH CONTROLLER

EMERGENCY DOOR RELEASEEXIT PUSH BUTTONEXIT READER

ELECTROMAGNETIC DOOR LOCK

CONTROL ROOM WORK STATION WITH ACS SOFTWARE

LAN NETWORK

READER CUM CONTROLLER-1 READER CUM CONTROLLER-3READER CUM CONTROLLER-2

Page 16: MEP- Building services

CCTV & MONITORING SYSTEM

• CLOSED-CIRCUIT TELEVISION (CCTV), ALSO KNOWN AS VIDEO

SURVEILLANCE, IS THE USE OF VIDEO CAMERAS TO TRANSMIT A

SIGNAL TO A SPECIFIC PLACE, ON A LIMITED SET OF MONITORS

• IN INDUSTRIAL PLANTS, CCTV EQUIPMENT MAY BE USED TO OBSERVE

PARTS OF A PROCESS FROM A CENTRAL CONTROL ROOM, FOR

EXAMPLE WHEN THE ENVIRONMENT IS NOT SUITABLE FOR HUMANS.

• CCTV SYSTEMS MAY OPERATE CONTINUOUSLY OR ONLY AS REQUIRED

TO MONITOR A PARTICULAR EVENT.

CCTV SYSTEM & MONITORING SYSTEM

Page 17: MEP- Building services

VIDEO WALL 4x2 CONFG.CONTROL ROOM

VIDEO MANAGEMENT SOFTWARE & CAMERA LICENSES

HIGH CONFIGURATION SERVER WITH STORAGE

HIGH CONFIGURATION CLIENT WORKSTATIONS

JOYSTICK CONTROLLER

LAN/ OFC NETWORK POE SWITCHES

BULLET CAMERA FIXED DOME CAMERA

PTZ DOME CAMERABOX CAMERA

SCHEMATIC – CCTV & SURVEILLANCE SYSTEM

Page 18: MEP- Building services

IBMS SYSTEM

• A Building Management System (BMS) or Building Automation

System (BAS) is a computer-based control system installed in

buildings that controls and monitors the building’s mechanical and

electrical equipment

• They help you plan operations and assess performance; make

operation easier; improve building comfort, enhance safety, improve

efficiency, save energy, and protect your assets.

• Their function is to control, monitor and optimize building services,

such as heating, ventilation, air conditioning, lighting, alarm systems

and certain electrical appliances. BUILDING MANAGEMENT SYSTEM

Page 19: MEP- Building services

BMS DISPALY BMS SEVER WITH BMS SOFTWARE & LICENSE

TCP/IP NETWORK

DDC CONTROLER WITH 3RD PARTY

INTEGRATION

DDC CONTROLER WITH 3RD PARTY

INTEGRATION

HVAC SYSTEMVENTILATION & EXHUST SYSTEMSELECTRICAL DISTRIBUTION SYSTEMFIRE FIGHTING SYTEMSPHE SYSTEMSELEVATOR SYSTEMS

FIELD DEVICES

LASER PRINTER

DDC CONTROLER WITH 3RD PARTY

INTEGRATION

DDC CONTROLER WITH 3RD PARTY

INTEGRATION

DDC CONTROLER WITH 3RD PARTY

INTEGRATION

SCHEMATIC – IBMS SYSTEM

Page 20: MEP- Building services

HVAC – HEATING VENTILATION & AIR CONDITIONING

Page 21: MEP- Building services

HVAC – HEATING VENTILATION & AIR CONDITIONING

WHAT IS TR - TON OF REFRIGERATION

1 TR IS AMOUNT OF HEAT EXTRACTED FROM ATMOSPHERE FOR MELTING 1 METRIC TONNE OF ICE IN 24 HOURS.

1 TR = BTU/HR1 TR = 3025 KCAL/HR

Page 22: MEP- Building services

FUNCTIONS OF HVAC

• CONTROL OF AIR TEMPERATURE

• CONTROL OF MOISTURE CONTENT IN THE AIR

• PROPER AIR MOVEMENT

• TO HOLD AIR CONTAMINATION WITHIN

ACCEPTABLE LIMITS

Page 23: MEP- Building services

TYPES OF HVAC SYSTEMS

AIR CONDITIONING

NON DUCTED PRODUCTS DUCTABLE SYSTEMS

SPLIT AIR CONDITIONING WINDOW AIR CONDITIONING PACKAGED AIR CONDITIONING CENTRAL PLANT

FLOOR MOUNTED

WALL MOUNTED

CEILING MOUNTED

EXPOSED TYPE

CASSETTE TYPE

HIDE AWAY TYPE

FLOOR STANDING PACKAGED AC AIR COOLED DUCTABLE SPLITS

AIR COOLED WATER COOLED

DX SYSTEM CHILLED WATER SYSTEM

VAPOUR COMPRESSION UNIT

VAPOUR ABSORPTION UNIT

RECIPROCATING UNITS AIR &

WATER COOLED

CENTRIFUGAL UNITS WATER

COOLED

SCREW TYPE UNITS AIR &

WATER COOLED

RECIPROCATING UNITS AIR &

WATER COOLED

CENTRIFUGAL UNITS WATER

COOLED

SCREW TYPE UNITS AIR &

WATER COOLED

Page 24: MEP- Building services

FIRE PROTECTION SYSTEM

Page 25: MEP- Building services

WHAT IS FIRE ?

• An exothermic reaction resulting from combination of heat fuel

and oxygen.

• Fire involves rapid oxidation at high temperatures

accompanied by the evolution of highly heated gaseous

products of combustion and emission of visible and invisible

radiation.

• Initiation of fire requires combustible materials, oxygen and an

energy source (heat) to provide ignition. Three components -

fuel , oxygen & heat are referred as the fire triangle

Page 26: MEP- Building services

CLASSIFICATION OF FIRE

• Class-A - Fires involving ordinary combustible materials like wood, paper, textiles, rubber

etc.

• Class-B -Fires involving flammable liquids or liquefiable solids, such as oils, solvents,

petroleum products, paints, varnishes etc.

• Class-C - Fire involving gases or liquefied gases under pressure for eg. LPG, Hydrogen

etc.

• Class-D Fire involving combustible metal such as Magnesium, sodium Zinc, Titanium etc.

Page 27: MEP- Building services

PRINCIPLE OF FIRE EXTINCTION

• Starvation - Removing or blanketing the fuel

• Smothering - Cutting off the oxygen supply

• Cooling - Removing heat from the fire.

Page 28: MEP- Building services

FIRE FIGHTING SYSTEM

• FIRE WATER RESERVOIR

• PUMPING UNITS

• FIRE WATER NETWORK

• FIRE FIGHTING HYDRANT SYSTEM

• FIRE FIGHTING SPRINKLER SYSTEM

• FIRE PROTECTION EQUIPMENTFIRE WATER RESERVOIRPUMPING UNITS

FIRE WATER NETWORKFIRE FIGHTING HYDRANT SYSTEMFIRE FIGHTING SPRINKLER SYSTEM

FIRE PROTECTION EQUIPMENT

Page 29: MEP- Building services

MUNCIPAL WATER SUPPLY TANKER WATER / BORE WELL

FIRE TANK

HYDRANT SRINKLER

DP HP JSPJB

DP – DIESEL PUMPHP – HYDRANT PUMPSP – SPRINKLER PUMPJ – JOCKEY PUMPB – BOOSTER PUMP

EXTERNAL HYDRANT INTERNAL HYDRANT

BRIDGE INLET

TYPICAL FIRE PROTECTION SYSTEM SCHEMATIC

Page 30: MEP- Building services

PUBLIC HEALTH ENGINEERING - PHE

Page 31: MEP- Building services

DIFFERENT AREAS OF PHE

• SANITARY AND CP FITTINGS

• HOT & COLD WATER SUPPLY SYSTEM

• DRAINAGE & SEWAGE SYSTEM

• EXTERNAL WATER SUPPLY

• SEWAGE TREATMENT PLANT

• EXTERNAL SEWER NETWORK AND CONNECTION TO

SEWAGE TREATMENT PLANT/ MUNICIPAL NETWORK

Page 32: MEP- Building services

What is a plumbing system

THE PLUMBING SYSTEM IS REALLY MADE UP OF TWO SYSTEMS:

• The supply system that brings in fresh water

• The drain-waste-vent system that takes out used water and sewage

• THE DRAIN-WASTE-VENT SYSTEM ALSO LETS AIR IN AND WASTE GASES OUT.

• BETWEEN THESE TWO SYSTEMS ARE THE FIXTURES (SINKS, TUBS, TOILETS, AND SO ON).

Page 33: MEP- Building services

SCHEMATIC– PHE (WATER SUPPLY)

MUNCIPAL WATER SUPPLY TANKER WATER / BORE WELL

FIRE TANK

RAW WATER TANK

WTP

DOMESTIC WATER TANK

TOILETS & PANTRY/ KITCHEN

OVERFLOW FROM FIRE TANK

Page 34: MEP- Building services

SCHEMATIC– PHE (SEWAGE & FLUSHING WATER)

SEWAGE FROM TOILETS

INSPECTION CHAMBER

STP

FLUSHING WATER TANK

FLUSHING WATER FOR TOILETS

PANTRY/ KITCHEN

GREASE TRAP

DISPOSAL TO MUNICIPAL LINE

TREATED WATER

Page 35: MEP- Building services

SCHEMATIC– STP (MBBR )

P

TUBE DECK MEDIA

DUAL MEDIA FILTER

ACTIVATED

CARBON FILTER

PEXCESS SLUDGESCREEN

CHAMBER

OIL & GREASE TRAP EQUILISATION

TANK

TUBE SETTLER TANK

FAB REACTOR CHLORINE DOSING TANK

CHLORINE DOSING

P

TREATED WATER TANK

SLUDGE DISPOSAL TANK

TREATED WATER FOR USE

SEWAGE INLET

SLUDGE DISPOSAL

BACK

WAS

H LI

NE

SQU

EEZE

D W

ATER

Page 36: MEP- Building services

PIPING/ CONTAINMENT CATEGORISED

• HORIZONTAL PIPELINE

• VERTICAL PIPELINE

MEP SERVICE LINES - CATEGORISED

Page 37: MEP- Building services

PIPELINE CATEGORIES

HORIZONTAL PIPELINE

VERTICAL PIPELINE

EMBEDDED PIPELINE

EXPOSED PIPELINE

Plumbing

Electrical

Telecommunications

Fire Protection

HVAC

Water Supply, Waste Water & Sewage, Vent, Rainwater Recycling

Bus-ducts, Cable Containments, Generator Exhaust & Cooling water Piping

CCTV, Network, Audio, Telecommunications

Fire Protection water Supply, Sprinklers

Air Duct, chilled water & Condensate water (Supply & Return)

BEAM WEB OPENINGS

UNDER BEAMS

Lighting Conduits, Telecommunications Conduits, Fire Alarm Conduits

Water Supply, Lighting Conduits, Waste Water, Sewage, Fire Alarm & Fire Sprinkler

NEXT PAGE

PIPELINE LAYOUT CATEGORIES OF MEP SYSTEM

Page 38: MEP- Building services

PIPELINE CATEGORIES

VERTICAL PIPELINE

EMBEDDED PIPELINE (WITHIN PARTITION)

EXPOSED PIPELINE(SHAFTS)

Plumbing

Electrical

Telecommunications

Fire Protection

HVAC

Water Supply, Waste Water & Sewage, Vent

Bus-ducts, Cable Containments, Generator Exhaust & Cooling water Piping

CCTV, Network, CATV, Audio, Telecommunications

Fire Protection water Supply, Sprinklers

Chilled water & Condensate water (Supply & Return)

Plumbing

Electrical

Telecommunications

Water Supply, Waste Water & Sewage, Vent

Lighting & Sockets

CCTV, Network, CATV, Audio, Telecommunications

PIPELINE LAYOUT CATEGORIES OF MEP SYSTEM

HORIZONTAL PIPELINE

Page 39: MEP- Building services

FA/VA, BMS & Security

containmentLV Cable Trays

Lighting & Power Trunking

Blockwork Walls

Slab

HV Ladder Rack

SoffitFire Protection

Pipe Work

Incoming Water Mains

Drainage Pipe

Duct WorkDuct Work

Branch

Chilled Water Pipes

• Typically a MEP Contractor each install their own supports from the soffit.

• Followed by water mains, drainage and fire protection pipe work. Generally MEP services that would not require any further access once they had been installed, tested and insulated.

• Followed by the ductwork and its branches to adjacent rooms, which would require testing and insulation.

• Then the chilled water pipework, which also branches off to adjacent rooms and needs to be accessible.

• Electrical containment is always the lowest and final service to be installed. Its completion and subsequent cable installation will be dependent on the mechanical services completion.

• The coordinated installation sequence needs to prioritize the earliest release for HV & LV cable installations.

MEP – TYPICAL SECTION OF CORRIDOR

Page 40: MEP- Building services

CIVIL –MEP COORDINATION

CIVIL MEP

Page 41: MEP- Building services

Foundation for MEP Heavy Equipment

Page 42: MEP- Building services

Sleeves For MEP Services Wall Penetration

Note : It is very Important to Close this Sleeves with Fire sealant Post Installation of Service Lines

Page 43: MEP- Building services

Services within Sub-Structure of Building

Page 44: MEP- Building services

Services before casting of Floor Slab

Page 45: MEP- Building services

Services before casting of RCC Walls

Page 46: MEP- Building services

Plaster after laying of wall services

Page 47: MEP- Building services

Cut-outs for Pulling of Cables

Page 48: MEP- Building services

Ceiling MEP Services before False Ceiling

Page 49: MEP- Building services

Ceiling MEP Services before False Ceiling

Page 50: MEP- Building services

Ceiling MEP Services before False Ceiling

Page 51: MEP- Building services

Toilet Sunk drainage

Page 52: MEP- Building services

MEP INTERFACING – PROBLEMS ASSOCIATED

According to the characteristics of the problem, integration requirements,

and construction necessities, the Interface Problems is divided in following eight classifications.

• Coordination with civil structure

• Safety aspects

• Functionality

• Constructability

• Economy

• Efficiency

• Expandability

• Maintainability

Page 53: MEP- Building services

• This refers to the process of installing Services, which must be well coordinated to embed the horizontal pipes and vertical sleeves in advance.

• Electrical pipes, monitor control pipes, and vertical sleeves of sewage pipes from the floor slab must be installed prior to slab grouting.

• The work involving the first completed concrete mat for moisture protection and vibration isolators must be executed in conjunction with the embedded sleeves and architectural construction works

COORDINATION WITH CIVIL STRUCTURE

Page 54: MEP- Building services

• Safety refers to safety considerations during installation.

• For example, safety is required to prevent hazards such as a water pipe leakage if a water pipe lies above an electrical pipe

SAFETY ASPECTS

Page 55: MEP- Building services

• Functionality refers to ensuring that the function of pipes is fully exploited while complying with building codes.

• For example, drainage slopes and routes must be taken into consideration for proper drainage of waste water.

• The installation of fire protection equipment and piping must be arranged prior to other systems in order for the entire fire protection system to comply with fire codes and fire protection permit drawings. Consequently, this has an impact on passing the fire protection inspection and obtaining the occupancy permits.

FUNCTIONALITY

Page 56: MEP- Building services

Constructability represents the factors influencing the sequence of installation. The conflicts can be categorized as follows:

• Conflict of equipment in a space - Because of the crowded space, the routing and sequence of installation for large equipment must be checked first.

• Conflict of pipeline in a space - Conditions for stacking and interlacing pipelines causes difficulty in installation and maintenance due to over-crowded spaces and lack of advance coordination

• Crowded installation - Conflicts within the installation space, idle laborers, and poor installation quality can result from problems such as crowded spaces or multiple workers operating simultaneously at a single site. Furthermore, the attitude of “first come first win” or “first do first win” causes conflict in the arrangement of pipelines.

• Pipe materials and dimensions - Installation suffers if the diameter of the pipe is oversized or if the material of the pipe is inflexible or too rigid to be easily cut or molded. If these kinds of materials are applied for the works, they should be installed earlier to prevent conflicts

• Installation of pipeline tiers - When the pipeline layout exceeds two layers, pipes

CONSTRUCTABILITY

Page 57: MEP- Building services

• Economy refers to the cost estimates associated with

integration, which can increase due to a lack of

coordination.

• For instance, re-routing a pipeline increases the

lengths of the pipeline and associated costs.

ECONOMY

Page 58: MEP- Building services

• Efficiency refers to a lack of integration causing descending

pressure and consuming capacity, which influences the basic

function of MEP systems.

• Additionally, venting conditions around equipment influences

equipment functionality, and should be noted during the

integration of the interface.

EFFICIENCY

Page 59: MEP- Building services

Expandability refers to the lifecycle of the facility

causing a demand for the expansion of pipelines due to

the changes in usage or upgrades to the facility.

This increasing demand requires consideration prior to

the installation phase to ensure space for future

expansion of the pipeline.

EXPANDABILITY

Page 60: MEP- Building services

• Maintainability refers to the convenience of

maintenance during the operation phase when

arranging the pipeline.

• Maintenance space and operation route must be

taken into consideration.

MAINTAINABILITY

Page 61: MEP- Building services

• The major MEP installation projects require the identification of separate arrangements for HVAC, power supply, plumbing, fire protection, telecommunications, and other related systems.

• Specialized consultants and contractors design and construct these systems. Currently, according to technical specifications, each specialty or trade subcontractor is assigned the responsibility of integrating MEP systems.

• Coordination of mechanical and electrical systems to detail their configuration provides a major challenge for complex building and industrial projects

• The knowledge required for MEP integration must be integrated to our System because specialty subcontractors of each system perform tasks individually, proposing a layout according to their own needs, leading to the fragmentation of MEP.

MEP INTEGRATION

Page 62: MEP- Building services

• Improper integration at the equipment/pipeline interface results in interference and

inappropriate sequence of jobs during installation can negatively influence the entire project.

• Moreover, the complete integration of the interface reduces the numbers of changes in the

design, decreases the work requiring demolition, addresses problems resulting from

installation error, and increases the overall construction quality of projects.

• Hence, the purpose of integrating the interface is to recognize problems, resolve conflicts,

and perfect the layout of the system for these mechanisms to serve their functions fully.

MEP INTEGRATION

Page 63: MEP- Building services

The discussed eight criteria are considered as MEP integration items because they are closely related to considerations of installation integration. To facilitate comparison, let us subcategorized these eight criteria according to three levels INTEGRATION SEQUENCING

The three levels are described as follows:

1. Basic Requirements and Coordination with Civil Structure WorksFunctionality of the 8 criteria fall under this first level of the integration sequencing.

2. Construction RequirementsThis is a second level integration task, comprising the evaluation of installation difficulty, problems associated with the installation of circulation interfaces, and the arrangement of sequencing

3. Cost and Operations RequirementsThis refers to the examination of the price of installation, cost-benefit ratio, and factors related to maintenance and expansion during the life circle of the facility.

INTEGRATION SEQUENCING

Page 64: MEP- Building services

MEPINTEGRATION SEQUENCING

LEVEL 1

Basic

Req

uire

men

ts &

Coo

rdin

ation

with

Ci

vil &

Str

uctu

re W

orks

SAFETY

FUNCTIONALITY

COORDINATION

Supply Side - Separate High Voltage Equipment's from water PumpsTrans. Side - Separate Water Pipes & Electrical Conduits from

telecommunication cable. Place Electric Conduits above water Pipes to avoid water leaking over conduits

Term. Side - Keep Safe Distance between sensors & Vents to avoid sensing interference

Supply Side - Comply with Fire Regulations for selection of Equipment. Separate Fire Pumps from Generators. Isolate Oxygen Tanks from Fire Protected Areas

Trans. Side - Consider Slopes For Gravity Drainages Comply with Fire Regulations for Pipes

Term. Side - Keep Safe Distance between HVAC Vents, intakes, Fire Protection sensors & Sprinklers

Supply Side - First Set Equipment Concrete Foundations.Trans. Side - Pre-bury and layout Pipes on Slabs

Openings on beams & Partitions must match Pipe Positions Equipment mobilization & Installation cannot interfere with partitions construction

Term. Side - Installation for illumination lights, vents, fire hydrants must be consistent with civil construction

Basic Requirements and Coordination with Civil Structure Works

Page 65: MEP- Building services

Construction Requirements

MEPINTEGRATION SEQUENCING

LEVEL 2

CON

STRU

CTIO

N R

EQU

IREM

ENTS

CONSTRUCTIBILITY

Supply Side - Consider Movement Circulation & Space For Large Equipment Layouts

Trans. Side - Maintain Sufficient Orientation Space. Avoid Conflicts & Multi Layers Overlap when Pipeline Space Is Not enough Consider Pipeline Sizes & Material Flexibility Install Top Layers Pipelines first

Term. Side - Check Whether Terminal Side Equipment's are obscured by other equipment that causes Conflicts Check Ceiling Heights & Match Ceiling horizontal layouts

Page 66: MEP- Building services

MEPINTEGRATION SEQUENCING

LEVEL 3

Cost

and

Ope

ratio

ns R

equi

rem

ents

ECONOMY

EFFICIENCY

EXPANDIBILITY

Supply Side - Keep Adequate Distance between large equipment Centralised Equipment design is generally more economic then scattered formats Equipment Position need to be close to load centre

Trans. Side - Apply Shortest, Closest Route Principle to pipeline layouts.Term. Side - Keep adequate distance among terminal side equipment.

Maintain Consistency with Ceiling Or Partition Plans

Supply Side - Consider Surrounding Environmental Factors & Ventilation Problems for Major Equipment

Trans. Side - Straight Pipes are preferable. Avoid Bend in PipesTerm. Side - Keep Distance between HVAC Vents & intakes

Supply Side - Reserve Space for future Equipment Expansion & Possible Flexible Adjustments

Trans. Side - Reserve Space for Future Pipeline DistributionTerm. Side - Consider Reservation, disbanding, flexible adjustments

Cost and Operations Requirements

MAINTAINABILITY CONSIDER MAINTAINANCE & MANAGEMENT SPACE & MOVEMENT LINES

Page 67: MEP- Building services

STEPS TO DEVELOP WORKSTATION AREAS

Page 68: MEP- Building services

STEP 1 – Laying of Under Floor Services

• Slab surface to be uniform for raceway laying

• FFL to be decided prior to any installations

• Raceway marking to be provided as per

approved workstation layout

• Placing the Raceway & Junction Boxes on the

floor.

• Clamping to be done on the floor end cover

the Junction Boxes by thermocoal.

• Care to be taken for JB’s during concreting

• After concrete thermocoals to be removed

from JB’s

Page 69: MEP- Building services

STEP 2 – SCREEDING/ IPS WORKS

Page 70: MEP- Building services

STEP 3 – CEILING TENDON MARKING

Page 71: MEP- Building services

STEP 4 – MEP FIRST FIX

LV CABLES-1FIRE LINE- 2

DUCTS-3

ELECTRICAL CONDUITS-1

Page 72: MEP- Building services

STEP 4 – MEP FIRST FIX - Inclusions

1. Conduit to be installed on ceiling and wall as per

approved point wiring.

2. Clamps to be fixed after proper drilling on ceiling (Tendon

marking to be avoided.)

3. LV Cables to installed as per Layout with clamping

4. Parallel fire line works to start.

5. For Fire line installation area to be surveyed

6. Main header line to be installed with clamps (Clamps to

be provided as per NFPA)

7. Sub header and branch pipes to be installed at ground

level and overhauled to ceiling

8. Clamps to be provided

9. After installation of sub header welding to the main

header to be welded

10. All welding to be properly executed with absolute perfection.

11. All pipes to be surface cleaned, primer applied and painting

done in RED.

12. Hydro testing to be conducted at 1.5 times the Pump

pressure

13. Duct to be fabricated in-situ with profiling

14. Hangers to be installed as per duct passage and tendon

markings to be taken care of.

Header duct to be installed as per BOD

15. Branches to be added to main header as per BOD

16. Sealing to be done so that no gaps are observed

17. Light test to be conducted before ceiling clearance

Page 73: MEP- Building services

STEP 4 – MEP FIRST FIX - Requirements

• Civil structure to be ready

• Tendon markings to be provided

• Proper cutouts for services bypass

• FFL level to be decided prior to any installations

• Cutouts to be mentioned in MEP penetration plan

• BOP, BOD, BOCT to be exact as per ceiling height

Page 74: MEP- Building services

STEP 5 – MEP FIRST FIX - Wall

REQUIREMENTS FOR WALL FIX:

1. ROUTING TO BE MENTIONED.

2. SURFACE OR CONCEALED TO BE MENTIONED

3. INTERCONNECTIVITY OF ROOMS THROUGH CONDUITS/

FLEXIBLE TO BE DECIDED.

Page 75: MEP- Building services

STEP 6 – Floor Tiling Works

Page 76: MEP- Building services

STEP 7 – MEP SECOND FIX

What is done during 2nd fix?

1. Fire- Flexible and sprinklers are fixed

2. HVAC- Spigot are fixed

3. Electrical- All wiring to be done in conduits

4. LV- Above ceiling detector boxes and related

cabling

Page 77: MEP- Building services

STEP 8 – GRIDWORK FOR CEILING

Page 78: MEP- Building services

STEP 9 – MEP FINAL FIX

Page 79: MEP- Building services

STEP 9 – MEP FINAL FIX - Requirements

• BOD, BOP, BOC should be inline with False ceiling levels• Grid ceiling gap should be maintained as per fixtures.• Special attention required for any gravity flow line such as drains

What is done in 3rd Fix?

1. Fire- Sprinklers are fixed on ceiling2. HVAC- Grills/ Diffusers are fixed on grid of ceiling3. Electrical- Light Fixtures/ Switch sockets on ceiling and wall4. LV- All LV Fixtures such as detectors/ RI/ Hooters/ CR/ Speakers on wall/ceiling/

doors

Page 80: MEP- Building services

STEP 10 – Cable Pulling & Area Clearance

Page 81: MEP- Building services

STEP 11 – Final Ceiling Works

Page 82: MEP- Building services

STEP 11 – Final Fixtures

Page 83: MEP- Building services

STEP 12 – Workstation Installation

Following activities proceed after workstation

installation works:

1. All Data cables to be brought to surface and Data

plates to be fixed

2. All UPS/ RAW power wiring works to surface and

switch plates are fixed

3. All Plates are tagged

4. JB opening to close using SS/ Aluminum sheet

Page 84: MEP- Building services

Thank You