4201 East Arkansas Avenue, Room 262, Denver, CO 80222 P 303.757.9262 F 303.757.9656 www.coloradodot.gov MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: RYAN D. RICE, DIRECTOR, DIVISION OF TSM&O DATE: MARCH 15, 2017 SUBJECT: TSM&O Workshop Purpose To inform the TC on current performance of Safety and System Performance (Planning Time Index), the purpose of the Division of TSM&O, and current main efforts of the Division to improve safety and mobility. Action Information only. Background & Details Since its founding in July 2013, CDOT’s Division of TSM&O has become FHWA’s national model for organizing for Operations. TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated by other State DOTs. Since 2013 TSM&O has developed 10 new robust programs that previously did not exist at CDOT since its founding in 2013: Statewide Traffic Signal & Ramp Meter Program; Traffic Incident Management; Operations Policy & Support; Planning, Performance, & TDM; I-70 Corridor Operations; I-25 Corridor Operations; Statewide Traffic Management Centers Program; TSM&O Evaluation; COBRA Program; Connected & Autonomous Technologies Program Key Benefits Current benefits of TSM&O efforts are as follows: Effective real-time management of I-70 Mountain Express Lane and I-25 North Express Lanes; 1,580 miles of fiber optic cable, 178 miles of fiber optic installed in the past two years; Established CDOT’s second TMC at EJMT and increased staffing at the CTMC in Golden; Cutting edge video analytics for incident detection and increased TMC efficiency; Expanded Safety Patrol and Heavy Tow coverage hours and improved vehicles and equipment; Increased Colorado First Responders trained in Traffic Incident Management from 8% to 22% the past two years; Bottleneck Reduction projects studied and designed; TSM&O Evaluation being conducted on all CDOT projects; Ramp meter expansion; Traffic Signal controller upgrades, central software system upgrade, and adaptive signal expansion. Attachments Presentation on TSM&O programs and current performance. 4201 East Arkansas Avenue Denver, CO 80222

Upload: truongnhan

Post on 20-Aug-2019

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

4201 East Arkansas Avenue, Room 262, Denver, CO 80222 P 303.757.9262 F 303.757.9656 www.coloradodot.gov

MEMORANDUM

T0: TRANSPORTATION COMMISSION FROM: RYAN D. RICE, DIRECTOR, DIVISION OF TSM&O DATE: MARCH 15, 2017 SUBJECT: TSM&O Workshop Purpose To inform the TC on current performance of Safety and System Performance (Planning Time Index), the purpose of the Division of TSM&O, and current main efforts of the Division to improve safety and mobility. Action Information only. Background & Details Since its founding in July 2013, CDOT’s Division of TSM&O has become FHWA’s national model for organizing for Operations. TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated by other State DOTs. Since 2013 TSM&O has developed 10 new robust programs that previously did not exist at CDOT since its founding in 2013:

• Statewide Traffic Signal & Ramp Meter Program; • Traffic Incident Management; • Operations Policy & Support; • Planning, Performance, & TDM; • I-70 Corridor Operations; • I-25 Corridor Operations; • Statewide Traffic Management Centers Program; • TSM&O Evaluation; • COBRA Program; • Connected & Autonomous Technologies Program

Key Benefits Current benefits of TSM&O efforts are as follows:

• Effective real-time management of I-70 Mountain Express Lane and I-25 North Express Lanes; • 1,580 miles of fiber optic cable, 178 miles of fiber optic installed in the past two years; • Established CDOT’s second TMC at EJMT and increased staffing at the CTMC in Golden; • Cutting edge video analytics for incident detection and increased TMC efficiency; • Expanded Safety Patrol and Heavy Tow coverage hours and improved vehicles and equipment; • Increased Colorado First Responders trained in Traffic Incident Management from 8% to 22% the past two

years; • Bottleneck Reduction projects studied and designed; • TSM&O Evaluation being conducted on all CDOT projects; • Ramp meter expansion; • Traffic Signal controller upgrades, central software system upgrade, and adaptive signal expansion.

Attachments Presentation on TSM&O programs and current performance.

4201 East Arkansas Avenue Denver, CO 80222

Page 2: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Division of Transportation Systems Management & OperationsTransportation Commission WorkshopRyan Rice

1

Page 3: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Division of Transportation Systems Management and Operations

Mission• Synthesize Technology, Engineering,

and Operations to save lives and reduce congestion

• Seek innovative solutions, notexpensive capacity expansion projects

• Enable the Department to make the best use of transportation funding: higher ROI

• Division was formed in 2013• 87 employees and 4 Branches

Overview of TSM&O

2

Page 4: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Why TSM&O for CDOT?• Over 606 traffic fatalities in Colorado in 2016

• 45 hours of annual delay for Denver commuters

• 59% of our system’s lane miles are congested

• $1.6 Billion annual cost of congestion

• $14 Billion annual economic cost of crashes

• 17 minutes of average daily delay, 44 minutes in 2022

• Incredible impacts to health, the environment, and the enconomy

Fixing these problems with only traditional methods is cost and time

prohibitive

Overview of TSM&O

3

Page 5: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

TSM&O Achievements

• CDOT TSM&O has become a national model for organizing for Operations.

• TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated by other State DOTs.

• TSM&O has developed 10 new programs that previously did not exist at CDOT since its founding in 2013: Statewide Traffic Signal & Ramp Meter Program; Traffic Incident Management; Operations Policy & Support; Planning, Performance, & TDM; I-70 Corridor Operations; I-25 Corridor Operations; Statewide Traffic Management Centers Program; TSM&O Evaluation; COBRA Program; Connected & Autonomous Technologies Program

4

Page 6: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

TSM&O Strategic Efforts

Governor's Vision 2018: Economic Development WIG: Travel Time Reliability

Best DOT: 3 Peaks

• Directly responsible for/major contributor on 8 of the 20 Trails of the 3 Peaks – 40%

• Directly responsible for/major contributor on 8 of the 9 Vision 2018 Projects – 89%

55

Page 7: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Causes of Congestion - UrbanSignal Timing

Special Events

Work Zones

Bad Weather

Traffic Incidents

Bottlenecks

Overview of TSM&O

6

Page 8: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Causes of Congestion – Rural

Overview of TSM&O

7

Page 9: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

700 CCTVs

TSM&O Core Programs

468 Variable Message Signs

1,000 Miles Fiber Optics

Toll Lanes, Active Traffic Management, Variable

Speed Limits

Intelligent Transportation Systems (ITS) Branch

1800 Traffic Signals140 Weather

Stations130 Ramp Meters

UAS

Connected Vehicles (V2X) Systems

8

Planning, Engineering, IT, Maintenance, Signals, Connected Vehicles

Page 10: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

• Safety Mitigation Programs (FASTER, HSIP, SHSP)• Operations Engineering• Corridor Operations & Bottleneck Reduction Assistance (COBRA)

Program• Traffic and Safety Data Management & Analysis • Roadway Guidance (signing, striping, in-pavement LEDs)• Work Zone Management• Specs and Standards

TSM&O Core Programs

Safety & Traffic Engineering Branch

9

Page 11: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

TSM&O Core Programs

Operations Management Branch

Safety Patrol

Heavy Tow

Traffic Management Centers

Traffic Incident Management

Corridor Operations

Real-Time Monitoring and Management

10

Page 12: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

• TSM&O & and Statewide Planning Efforts• Performance Management• Travel Demand Management • RoadX Support

TSM&O Core Programs

Planning, Performance, and TDM

11

Page 13: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Incident Detection Software

Operators & Cameras

Co-Locating CSP with CMTC for

Dispatching

Courtesy Patrol &

Heavy Tow Staffing

TIM Training and TIM

Plans

TIM Training

Driver Education:

Move Over

Campaign

TSM&O Investments:Results In Action

12

Page 14: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

• Fatalities increases– 12% increase from 2014 to 2015– 10% increase from 2015 to 2016– 75% of fatality increase in 2016 was from pedestrians, motorcycles, bicyclists

• National Safety Performance Measures– Submit national performance targets for 2018 to FHWA and NHTSA by August 1 - fatalities,

fatality rate, serious injuries & rate, pedestrians and bicyclists fatalities

– Based upon statistical analysis and influencing factors, projections for 2017 and 2018 fatalities are increasing

– Assuming factors within our influence remain constant - funding, legislation, program delivery, incorporation of technology

Current Performance

13

Page 15: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Current PerformanceI-70 Vail to C470 Planning Time Index

14

Westbound EastboundDec ’16 - Feb ‘17Dec ’13 - Feb ‘14 Dec ’13 - Feb ‘14 Dec ’16 - Feb ‘17

Sundays

Page 16: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Current PerformanceI-25 C470 to E470 Planning Time Index

15

Southbound Northbound20162013 2013 2016

Monday-Friday

Page 17: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Current PerformanceI-25 Colorado Springs Planning Time Index

16

Southbound Northbound20162013 2013 2016

Monday-Friday

Page 18: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Current PerformanceI-25 SH66 to SH14 Planning Time Index

17

Southbound Northbound20162013 2013 2016

Monday-Friday

Page 19: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Fiber Expansion:• ITS currently manages 1200 miles of fiber optic cable statewide

• Private sector partners with ITS sharing 380 miles of fiber optic cable

• Total fiber optic cable available to ITS is 1580 miles of fiber excluding slack loops and laterals and 2800 devices statewide

• 178 miles is newly installed fiber optic cable for FY16-FY17

• 92 miles newly installed fiber optic cable expected during FY18-19

• 50 miles converted to heavy instrumented managed lane corridors for FY16-FY17300+ new devices US36 Managed lanes100+ new devices I25 segment 2 & 385 new devices I70 PPSL

• 28 miles convert to heavy instrumented managed lane corridors for FY18-FY19

• 10 miles converted to heavy instrumented managed lane corridor FY23

19

TSM&O ITS Fiber Optic Expansion

Page 20: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

TSM&O ITS Fiber Optic Expansion

Draft Fiber Expansion PrioritiesCriteria • Transportation Safety / Public

Safety• Level of Service / Redundancy• Corridor Classification• Connected Vehicle projects• Operations

19

Page 21: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Fiber Expansion Priority Corridors:

• ITS developed a fiber expansion priority map with input from regional traffic engineers. Summary below

• Expansion priority 1: 751.70 miles of new fiberExpansion priority 2: 620.53 miles of new fiberExpansion priority 2: 651.89 miles of new fiber

• Total 2024.12 miles proposed fiber optic cable

Benefits:

• Interconnect existing ITS devices, wildlife crossing, tunnel systems, signals, local TMC and police, fire, sheriffs, OEM

• Establish the communications infrastructure to support Connected Vehicles and Smart Traffic Management Systems

20

TSM&O ITS Fiber Optic Expansion

Page 22: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

TSM&O FY17 Budget Request

FY 17 Request Details:• Traffic Management Center Contracted Staff for EJMT and CTMC Golden: $1,100,000• Contracted Safety Patrol and Heavy Tow Programs: $900,000• Chain Law Enforcement: $140,000• Construction of one Bottleneck Reduction (COBRA) project in each Region: $600,000

R1: I-225 & Parker Road NB Off-Ramp Intersection Reconfiguration: $200,000; b/c: 30:1 R2: I-25 at SH 105 Monument Lane Drop: $200,000; b/c: 20:1 R3: Leadville Road Diet – Convert from 4 to 3 lanes with Bike Lanes: $75,000; b/c: 20:1 R4: Signal Optimization at SH 66 and I-25: $25,000; b/c: TBD R5: US 550 North of Durango Passing Lane Reallocation by Direction: $100,000; b/c: 10:1

• I-70 Travel Demand Management (TDM) & Media Campaign: $75,000• Traffic Incident Management Program Support: $40,000• TSM&O Evaluation, SHRP 2 and Program Support: $220,000• Bike Race Program Support: $125,000___________________________________________Total $3,200,000

21

Page 23: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Future Growth FY17-FY22

16.820

23.2 2427

0

5

10

15

20

25

30

FY18 FY19 FY20 FY21 FY22

FIVE YEAR FISCALLY CONSTRAINED GROWTHTSM&O Requested Funding Above Current Base

22• Above shows projected funds needed in future years above the current base.• Based funding in FY17 is $63 million; current base funding in FY18 is $58 million.

Page 24: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Future Growth FY17-FY22

56 6172.7

83.2 91.2

0

10

20

30

40

50

60

70

80

90

100

FY18 FY19 FY20 FY21 FY22

FIVE YEAR FISCALLY UNCONSTRAINED GROWTHTSM&O Requested Funding Above Current Base

23• Above shows projected funds needed in future years above the current base.• Based funding in FY17 is $63 million; current base funding in FY18 is $58 million.

Page 25: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

Mission

TSM&O Major ProjectsIntelligent Transportation Systems

Traffic & Safety Engineering

Traffic Incident Management & TMCs

TMC Co-Location with CSP-Golden/R2

March2017

July2017

Dec2017

July2018

Dec2018

July2019

Develop Fiber Optic Expansion Plan

Expand CV Infrastructure

TSM&O Evaluation

Planning, Performance, & TDM

Stand up Operations Academy

ITS Architecture Updates

Accelerate TIM Training

Construct COBRA Projects

Expand Performance Measures

Panasonic CV Ecosystem

C-470 Express Lane Operations

Striping Enhancements

Develop TIM Training Facility Project

Smart Ramp Metering Expansion

Adaptive Traffic Signals Expansion

Expand COBRA Program

24

Page 26: MEMORANDUM T0: TRANSPORTATION COMMISSION FROM: … · TSM&O Reorganization Report, Statewide TSM&O Plan, TSM&O Evaluation, and COBRA Program have all become models that are emulated

TSM&O Future Major MilestonesFY18• Panasonic & HERE Connected Vehicle RoadX Projects• CSP Co-Location in CTMC Golden• R2 TMC Built• Accelerate TIM Training• Accelerate Adaptive Signal Corridors• Expand Incident Detection Software• Accelerate Machine Learning Predictive Weather

System• UAS Operations begin• COBRA projects constructed• Expanded Metro Safety Patrol• Enhanced Staffing at CTMC and EJMT TMC• Support Developing RoadX Rural Safety Pilot• Support Developing RoadX Transport Pilot• Pilot Smart Workzone projects

FY19• Panasonic & HERE Connected Vehicle Projects• Accelerate TIM Training• R4 TMC Built• R2 TMC Staffed• Accelerate Adaptive Signal Corridors• Incentivized Towing implemented in Regions• Aggressive fiber and ITS expansion• COBRA projects constructed• ITS systems development for C470 Express Lanes• Expand Smart Workzones

FY20• 100% First Responders Trained in TIM• Panasonic & HERE Connected Vehicle Projects• R3 TMC Built• R4 TMC staffed• Expanded Safety Patrol along front range• COBRA projects constructed• Aggressive fiber and ITS expansion• ITS Maintenance and TMC Operators for C470 Express

Lanes (including Connected Vehicle infrastructure)• ITS systems development for I-25 North Express

Lanes

FY21• Panasonic Connected Vehicle Projects• R5 TMC Built• R3 TMC staffed• COBRA projects constructed• Aggressive fiber and ITS expansion• ITS Maintenance and TMC Operators for I-25 North

Express Lanes (including Connected Vehicle infrastructure)

25