memo - kelownaapps.kelowna.ca/citypage/devapps/tup21-0001 baron rd 2205... · 2021. 4. 9. · the...
TRANSCRIPT
Landmark 6, Suite 700
1631 Dickson Avenue
Kelowna, BC
Canada V1Y 0B5
T: +1 250 980-5500
F: +1 250-980-5511
wsp.com
MEMO
TO: City of Kelowna, Jason Issler
FROM: WSP Canada Inc, Andrew Bruce
SUBJECT: Temporary Use Permit for Operation of a Crusher
DATE: January 27, 2021
INTRODUCTION
Please find the accompanying application forms, fees and title information for a Temporary Use
Permit for 2205 and 2125 Baron Road and 1880 Leckie Road. This is the site for the proposed
new Costco Warehouse. 1901 Baron Road is also part of the overall development site but the
Temporary Use Permit does not need to apply to this address.
The request for the temporary use permit is to permit the use of a mobile rock crusher on site for a
limited portion of the construction stage and within limited operating hours per day. The City of
Kelowna’s current position is that crushing plants are not permitted to operate outside of I5 –
Extraction zoned properties. The material that would be processed would consist of “oversized”
rock or cobble. This native material is too large to be used for any part of the site grading or
underground works. If it can be processed or crushed on site, it can be made into a range of
material from appropriate base material, granular fills and structural fill. If it cannot be processed
on site, it needs to be hauled off-site to a gravel pit.
Our proposal includes specific siting criteria to provide adequate distance separation from adjacent
residential, a specific number of days of operation (duration), and mitigation efforts for dust.
Finally, we provide some data on noise that compares the operation of the mobile crushing plant to
source of noise emission that are considered as acceptable normal construction activities. We will
also speak to the reasons why allowing the mobile crushing operation on site has broader benefits
to the community.
PROPOSED LOCATION
The attached Schedule A shows the proposed location parameters for the mobile crushing plant.
The larger green circle is the proposed minimum distance away from residential uses where the
crushing plant could be placed to operate. While these crusher are “mobile” they typically aren’t
moved more than once a day. It is more likely that they would be moved to a location and operate
for several days in one place. They are really only moved to get them out of the way of other site
work.
Page 2
The 20 m smaller circle is the actual extent of the operation zone around the crushing plant.
OPERATION PARAMETERS
WSP is providing Civil Engineering services to the Costco group, has reviewed the Geotechnical
Engineering reports and coordinated with civil contractor to estimate the amount of material that
could be processed for re-use on the site. There is not material that will be process and exported
from the overall Costco development site (Warehouse and Gas Bar sites). The estimated amount
of material is approximately4,500 cubic metres. This would equate to approximately 320 tandem
dump truck loads if the material could not be processed on site.
These quantity estimates have been used to calculate the amount of time required to process the
oversized material into usable granular material for site construction. It is proposed that crushing
operation be permitted to operate the same as any other equipment on site which is subject to the
City of Kelowna Noise Bylaw. In order to minimise crushing duration, material will be stockpiled
at or near the crushing plant to be processed in batches. This means that the crushing may run for a
few days consecutively and then stop until the next batch of material is ready to process. The
contractor estimates that based on 8 hours of crushing per day, there will need to be a total of 21
days of crushing activity, not necessarily in one consecutive period of time. In order to account for
possible mechanical maintenance or other contingency, the requested number of days of operation
is 28 days.
DUST MITIGATION
Most of the newer mobile crushing plants have built in “wash bars” that introduce water into the
material during crushing. This dampens the dust at the source and reduces wind borne dust
migrating from the crushing plant. In the case that the crusher plant available to the site does not
have this built in dust suppression system, the contractor has committed to apply water manually
to the material prior to crushing and after it has been produced. It should be noted that this is a
large site that will regraded in its entirety. Dust suppression throughout construction will follow
standard procedures but elimination of dust is not possible. The contributory dust from the
crushing operation is not anticipated to make the overall level of dust on the site any worse than
normal construction practices would dictate.
NOISE IMPACTS
WSP has collected some limited data on rock crushers and has reviewed published data on other
construction equipment such as large bulldozers and excavators that would be commonly used on
a construction site such as Costco’s. Noise data differs between brands for the same type of
equipment and the mechanical condition of the machines can also provide variable noise
emissions. The contractor for Costco has also provided recent data from a quarry in Vernon that
supports the publicly available data but suggests that the noise levels are generally lower than the
published data.
Our general finding is that a typical bulldozer or excavator emits between 80 and 90 decibels
during normal operations. These pieces of equipment are mobile and will move around the site
during operations. As such, the distance from the equipment to the adjacent residential will be
constantly changing.
The rock crusher will be placed in one location and may move once or twice during the entire
duration of the crushing operation. Therefore, we can assure that the placement of the machine can
Page 3
be done in a way to maximise separation from the residential use. The data we have on rock
crushers show that, immediately adjacent to the machine, noise emissions are between 90 and 99
decibels. However, we also have data of the noise level at a 20 m separation which ranges from 74
to 85 decibels. Given that the crushing plant will not be located closer than 50 m from residential,
the noise levels will be significantly less than at the 20 m data measurements. In terms of
comparative noise emission experienced by adjacent residential users, the crushing plant will not
produce any greater impact than other machinery being used and accepted as common
construction activity.
The more recent data collected from the Quarry in Vernon suggested that the noise levels at 20 m
distance from the machine were in the range of 70-75 decibels and at 50 m, they were as low as 62
decibels.
As a final note, all mobile equipment is required to use movement awareness beepers as a safety
precaution. These beepers are, by design, louder than the operating equipment and produce noise
emissions in the range of 90-110 decibels.
ENVIRONMENTAL AND EFFICIENCY CONSIDERATIONS
As previously noted, the estimated volume of oversized material that would be processed on site is
approximately 4,500 cubic metres which is the equivalent of approximately 320 tandem dump
truck loads. If the material cannot be processed on-site, it has to be removed from the site. The two
closest gravel pits to export this material to are either in West Kelowna (12 kms) or Lake Country
(17 km). Considering round trips to haul to the pit and return to site, this equates to between 7,680
to 10,880 kms of truck trips that could be eliminated by the on-site processing.
In terms of efficiency, not only does the on-site processing eliminate the truck trips to export the
material, but it facilitates a waste material being converted into a useable and necessary product
for the construction. Aggregates of all kinds are a valuable and non-renewable resource and every
effort should be made to use them as efficiently as possible.
CONCLUSION
This application for a Temporary Use Permit is being submitted to allow for a rock crushing plant
to be used on the new Costco Warehouse site intermittently for a total duration of 28 days during
the construction in 2021. The hours of operation are proposed to be the same as for the rest of the
equipment on site and regulated by the City of Kelowna Noise Bylaw.Mitigation measures will be
applied to reduce dust and we propose that the noise impacts will be no greater than other
machinery used under accepted construction practises. Furthermore, the operation of the crusher
on site will provide efficiency and reduce environmental impacts by eliminating between 7,680
and 10,880 kilometers of truck travel on local roads.
Andrew Bruce
Practice Lead, Private Development
SCHEDULE A
v
v
v
v
v
v
EX. 300m
m PERF. PVC STM
EX. 3
00mm
PER
F. P
VC S
TM
EX. 300mm PERF. PVC STM
EX. 2
400x
2400
CON
C ST
M BOX C
ULV.
EX. 2400x2400 CONC STM BOX CULV.
EX. 2400x2400 CONC STM BOX CULV.
EX. 7
50mm
PVC
SAN
EX. 2
00mm
PVC
WAT
EX. 200mm PVC WAT
EX. 750mm PVC SAN
EX. 200m
m PVC WAT
EX. 200m
m PVC SAN
EX. 750m
m PVC SANEX. 250mm PVC W
AT
900m
m PE
RF S
TM
900mm PERF STM
900m
m PERF S
TM
900mm PERF STM
150mm PVC STM
150mm PVC STM
525m
m PV
C ST
M52
5mm
PVC
STM
450mm PVC STM450mm PVC STM
450mm PVC STM450mm PVC STM
525mm PVC STM525mm PVC STM
525m
m PV
C ST
M
525mm PVC STM
750mm PERF S
TM
750mm PERF STM
750mm PERF STM150mm PVC STM
300m
m PV
C ST
M25
0mm
PVC
STM
250mm PVC STM
900mm PERF STM900mm PERF STM
200mm PVC SAN 200mm PVC SAN
200mm PVC SAN
200m
m PV
C SA
N 20
0mm
PVC
SAN
200mm PVC WAT 200mm PVC WAT
200m
m PVC WAT
200m
m PV
C W
AT 20
0mm
PVC
WAT
200mm PVC WAT
200mm PVC WAT 200mm PVC WAT
200mm PVC WAT
200m
m PV
C W
AT
200m
m PV
C W
AT
200m
m PV
C W
AT
200m
m PVC W
AT
200m
m PVC W
AT
200m
m PV
C W
AT 20
0mm
PVC
WAT
PLOT
TED:
2021
-02-
02 -
11:38
AM
FILE
: p:\2
017\1
7m-0
2290
-01 k
elown
a bar
on ro
ad -
reloc
ate\3_
tech\3
_cad
d\3_s
heets
\05 -
on-si
te\wa
reho
use\1
7m-0
2290
-01-
05-w
h-c1
_site
_plan
s.dwg
CTB:
wsp
_bc_
int-p
artia
lcolou
r.ctb
PROJECT:
TITLE:
CLIENT:
CLIENT REF. #:
REVISION:
DESCRIPTIONDATEREV
DISCIPLINE:
25mm
IF THIS BAR IS NOT25mm LONG, ADJUST
YOUR PLOTTING SCALE.
DATE:
PROJECT NUMBER:
SEAL:
DISCLAIMER: COPYRIGHT:THIS DRAWING AND DESIGN IS COPYRIGHT PROTECTED WHICH SHALL NOT BE USED,REPRODUCED OR REVISED WITHOUT WRITTEN PERMISSION BY WSP. THE CONTRACTORSHALL CHECK AND VERIFY ALL DIMENSIONS AND UTILITY LOCATIONS AND REPORT ALLERRORS AND OMISSIONS PRIOR TO COMMENCING WORK.
BY
ORIGINAL SCALE:
DESIGNED BY:
DRAWING NUMBER: REV.
MODIFIED BY:
DRAWN BY:
APPROVED BY:
ASSISTED BY:
N
F F F
F
T | www.wsp.com
WSP Canada Inc.700-1631 Dickson Ave, Kelowna, BC V1Y 0B5
250-980-5500
17M-02290-01-05
--
COSTCO KELOWNAWAREHOUSE
COMPOSITE UTILITY PLAN
C103 3A
1:500
S. Cadieux, P.Eng.
S. Springstead, GradTech
S. Springstead, GradTech
K. Unger, GradTech
S. Cadieux, P.Eng.
2020-11-20
INFRASTRUCTURE
TITL
E BL
OCK
VERS
ION
1.0
0 5 25m1:500
BARO
N RD
LECKIE RD
SPRINGFIELD RD
ELECTRICAL SERVICE CONNECTION.REFER TO SHALLOW UTILITY
DRAWINGS FOR DETAILS.
STORM SERVICECONNECTION. REFER TODWG C501 FOR DETAILS.
GAS SERVICE CONNECTION.REFER TO FORTIS DRAWINGS
FOR DETAILS
WATER SERVICECONNECTION. REFER TODWG C503 FOR DETAILS.
SANITARY SERVICECONNECTION. REFER TODWG C502 FOR DETAILS.
STORM SERVICECONNECTION. REFER TODWG C501 FOR DETAILS.
REFER TO MECHANICALDRAWINGS LIGHTING DETAILS
SIGNALED INTERSECTION(BY OTHERS)
1A 2021-01-15 ISSUED FOR 90% DESIGN REVIEW SDS
GAS METER.REFER TO FORTISDRAWINGS FOR DETAILS
PROPOSED GAS MAIN EXTENSIONCROSSES DRIVEWAY. CONTRACTOR
TO COORDINATE WITH FORTIS.
PROPOSED GAS MAIN EXTENSIONCROSSES DRIVEWAY. CONTRACTOR
TO COORDINATE WITH FORTIS.
LEGEND:
LIMITS OF CONSTRUCTION
2A 2021-02-01 ISSUED FOR BUILDING PERMIT SDS
COMMUNICATION SERVICECONNECTION. REFER TO SHALLOWUTILITY DRAWINGS FOR DETAILS.
3A 2021-02-01 ISSUED FOR OWNERS REVIEW SDS
v
v
v
v
v
v
PLOT
TED:
2021
-02-
02 -
11:36
AM
FILE
: p:\2
017\1
7m-0
2290
-01 k
elown
a bar
on ro
ad -
reloc
ate\3_
tech\3
_cad
d\3_s
heets
\05 -
on-si
te\wa
reho
use\1
7m-0
2290
-01-
05-w
h-c2
_esc
.dwg
CTB:
wsp
_bc_
int-fu
llblac
k.ctb
PROJECT:
TITLE:
CLIENT:
CLIENT REF. #:
REVISION:
DESCRIPTIONDATEREV
DISCIPLINE:
25mm
IF THIS BAR IS NOT25mm LONG, ADJUST
YOUR PLOTTING SCALE.
DATE:
PROJECT NUMBER:
SEAL:
DISCLAIMER: COPYRIGHT:THIS DRAWING AND DESIGN IS COPYRIGHT PROTECTED WHICH SHALL NOT BE USED,REPRODUCED OR REVISED WITHOUT WRITTEN PERMISSION BY WSP. THE CONTRACTORSHALL CHECK AND VERIFY ALL DIMENSIONS AND UTILITY LOCATIONS AND REPORT ALLERRORS AND OMISSIONS PRIOR TO COMMENCING WORK.
BY
ORIGINAL SCALE:
DESIGNED BY:
DRAWING NUMBER: REV.
MODIFIED BY:
DRAWN BY:
APPROVED BY:
ASSISTED BY:
N
F F F
F
T | www.wsp.com
WSP Canada Inc.700-1631 Dickson Ave, Kelowna, BC V1Y 0B5
250-980-5500
17M-02290-01-05
--
COSTCO KELOWNAWAREHOUSE
EROSION & SEDIMENT CONTROLCONSTRUCTION STAGE
C201 3A
1:500
S. Cadieux, P.Eng.
S. Springstead, GradTech
S. Springstead, GradTech
K. Unger, GradTech
S. Cadieux, P.Eng.
2020-11-20
INFRASTRUCTURE
TITL
E BL
OCK
VERS
ION
1.0
0 5 25m1:500
NILEX SILT FENCE TO BE INSTALLED AROUNDSITE PERIMETER PRIOR TO CLEARING/GRUBBING.INSTALLATION AS PER DETAIL A, DWG C203.MAINTENANCE AS PER DRAWING NOTES.
TEMPORARY SITE ACCESS POINTS TO BECLEAN GRANULAR MATERIAL IN ORDER TOMITIGATE SEDIMENT TRANSFER OFFSITE.
TEMPORARY SITE ACCESS POINTS TO BECLEAN GRANULAR MATERIAL IN ORDER TOMITIGATE SEDIMENT TRANSFER OFFSITE.
TEMPORARY SITE ACCESS POINTS TO BECLEAN GRANULAR MATERIAL IN ORDER TOMITIGATE SEDIMENT TRANSFER OFFSITE.
TEMPORARY SITE ACCESS POINTS TO BECLEAN GRANULAR MATERIAL IN ORDER TOMITIGATE SEDIMENT TRANSFER OFFSITE.
SILT FILTER TO BE INSTALLEDPRIOR TO TIE-IN TO EXISTING STORM SYSTEM.INSTALLATION AS PER DETAIL B, DWG C203.MAINTENANCE AS PER DRAWING NOTES. (TYP.)
PROTECT EXISTING CATCH BASINS
1A 2021-01-15 ISSUED FOR 90% DESIGN REVIEW SDS
BARO
N RD
LECKIE RD
PROTECT EXISTING CATCH BASINS
PROTECT EXISTING CATCH BASINS
CONSTRUCTION ACCESSROAD BY COSTCO GC
7.60m
METAL BUILDING AREA80m X 35m
MIN. 30000 SQ.FT.TO BE PROVIDEDBY COSTCO GC
WINTERCAP 375.20m (FFE)
BUILDING PAD 374.90m
MAX 2:1 SLOPE
2A 2021-02-01 ISSUED FOR BUILDING PERMIT SDS
NILEX SILT FENCE
LEGEND:
INFILTRATION DITCH
TEMPORARY INFILTRATION DITCH TO BE0.5m BELOW CONSTRUCTION ACCESS ROAD
3A 2021-02-01 ISSUED FOR OWNERS REVIEW SDS
SCHEDULE 1 Site Profile
Version 4.0
–1–
Introduction Under section 40 of the Environmental Management Act, a person who knows or reasonably should know that a site has been used or is used for industrial or commercial purposes or activities must in certain circumstances provide a site profile. Schedule 2 of the Contaminated Sites Regulation sets out the types of industrial or commercial purposes or activities to which site profile requirements apply. If section 40 of the Environmental Management Act applies to you and you know or reasonably should know that the site has been used or is used for one of the purposes or activities found in Schedule 2 of the Contaminated Sites Regulation, you may be required to complete the attached site profile.
Notes/Instructions:
Persons preparing a site profile must complete Section I, II and III, answer all questions in sections IV through IX, and sign section XI. If the site profile is not satisfactorily completed, it will not be processed under the Environmental Management Act and the Contaminated Sites Regulation. Failure to complete the site profile satisfactorily may result in delays in approval of relevant applications and in the postponement of decisions respecting the property.
The person completing this site profile is responsible for the accuracy of the answers. Questions must be answered to the best of your knowledge.
Section 27 (1) of the Freedom of Information and Protection of Privacy Act requires that provision of personal information concerning an individual must be authorized by that individual. Persons completing the site profile on behalf of the site owner must be authorized by the site owner.
One (1) site profile may be completed for a site comprised of more than one titled or untitled parcel, but individual parcels must be identified.
The latitude and longitude (accurate to 0.5 of a second using North American Datum established in 1983) of the centre of the site must be provided. Also, please attach an accurate map, containing latitude, longitude and datum references, which shows the boundaries of the site in question. Please use the largest scale map available.
If the property is legally surveyed, titled and registered, then all PID numbers (Parcel IDentifiers – Land Title Registry system) must be provided for each parcel as well as the appropriate legal description.
If the property is untitled Crown land (no PID number), then the appropriate PIN numbers (Parcel Identification Numbers – Crown Land registry system) for each parcel with the appropriate land description should be supplied.
If available, the Crown Land File Number for the site should also be supplied.
Anything submitted in relation to this site profile will become part of the public record and may be made available to the public through the Site Registry as established under the Environmental Management Act.
Under section 43 of the Environmental Management Act, corporate and personal information contained in the site profile may be made available to the public through the Site Registry. If you have questions concerning the collection of this information, contact the Site Registrar, at [email protected]. For questions on site profiles, please send a message to [email protected].
–2–
I CONTACT IDENTIFICATION
A. Name of Site Owner: Last First Middle Initial(s) (and/or, if applicable)
Company
Owner’s Civic Address
City____________________________________________Province/State
Country_________________________________________Postal Code/ZIP
B. Person Completing Site Profile (Leave blank if same as above): Last First Middle Initial(s) (and/or, if applicable)
Company
C. Person to Contact Regarding the Site Profile: Last First Middle Initial(s) (and/or, if applicable)
Company Mailing Address
City Province/State
Country Postal Code/ZIP
Telephone (______) ______ - __________ Fax (______) ______ - __________
II SITE IDENTIFICATION
Please attach a site location map
All Property Coordinates (using the North American Datum 1983 convention) for the centre of the site: Latitude: Degrees Minutes Seconds Longitude: Degrees Minutes Seconds Please attach a map of appropriate scale showing the boundaries of the site. For Legally Titled, Registered Property Site Street Address (if applicable) City Postal Code
–3–
PID numbers and associated legal descriptions. Attach an additional sheet if necessary. PID Legal Description Total number of titled parcels represented by this site profile is: _______ For Untitled Crown Land PIN numbers and associated Land Description. Attach an additional sheet if necessary. PIN Land Description Total number of untitled crown land parcels represented by this site profile is:
(and, if available) Crown land file numbers. Attach an additional sheet if necessary.
III COMMERCIAL AND INDUSTRIAL PURPOSES OR ACTIVITIES
Please indicate below, in the format of the example provided, which of the industrial and commercial purposes and activities from Schedule 2 have occurred or are occurring on this site.
EXAMPLE Schedule 2 Description Reference E1 appliance, equipment or engine repair, reconditioning, cleaning or salvage F10 solvent manufacturing or wholesale bulk storage Please print legibly. Attach an additional sheet if necessary Schedule 2 Description Reference
–4–
IV AREAS OF POTENTIAL CONCERN
Is there currently or to the best of your knowledge has there previously been on the site any (please mark the appropriate column opposite the question):
YES NO
A. Petroleum, solvent or other polluting substance spills to the environment greater than 100 litres?
B. Residue left after removal of piled materials such as chemicals, coal, ore, smelter slag, air quality control system baghouse dust?
C. Discarded barrels, drums or tanks?
D. Contamination resulting from migration of substances from other properties?
V FILL MATERIALS
Is there currently or to the best of your knowledge has there previously been on the site any deposit of (please mark the appropriate column opposite the question):
YES NO
A. Fill dirt, soil, gravel, sand or like materials from a contaminated site or from a source used for any of the activities listed under Schedule 2?
B. Discarded or waste granular materials such as sand blasting grit, asphalt paving or roofing material, spent foundry casting sands, mine ore, waste rock or float?
C. Dredged sediments, or sediments and debris materials originating from locations adjacent to foreshore industrial activities, or municipal sanitary or stormwater discharges?
VI WASTE DISPOSAL
Is there currently or to the best of your knowledge has there previously been on the site any landfilling, deposit, spillage or dumping of the following materials (please mark the appropriate column opposite the question):
YES NO
A. Materials such as household garbage, mixed municipal refuse, or demolition debris?
B. Waste or byproducts such as tank bottoms, residues, sludge, or flocculation precipitates from industrial processes or wastewater treatment?
C. Waste products from smelting or mining activities, such as smelter slag, mine tailings, or cull materials from coal processing?
D. Waste products from natural gas and oil well drilling activities, such as drilling fluids and muds?
E. Waste products from photographic developing or finishing laboratories; asphalt tar manufacturing; boilers, incinerators or other thermal facilities (e.g. ash); appliance, small equipment or engine repair or salvage; dry cleaning operations (e.g. solvents); or from the cleaning or repair of parts of boats, ships, barges, automobiles or trucks, including sandblasting grit or paint scrapings?
–5–
VII TANKS OR CONTAINERS USED OR STORED, OTHER THAN TANKS USED FOR RESIDENTIAL HEATING FUEL
Are there currently or to the best of your knowledge have there been previously on the site any (please mark the appropriate column opposite the question):
YES NO
A. Underground fuel or chemical storage tanks other than storage tanks for compressed gases?
B. Above ground fuel or chemical storage tanks other than storage tanks for compressed gases?
VIII HAZARDOUS WASTES OR HAZARDOUS SUBSTANCES
Are there currently or to the best of your knowledge have there been previously on the site any (please mark the appropriate column opposite the question):
YES NO
A. PCB-containing electrical transformers or capacitors either at grade, attached above ground to poles, located within buildings, or stored?
B. Waste asbestos or asbestos containing materials such as pipe wrapping, blown-in insulation or panelling buried?
C. Paints, solvents, mineral spirits or waste pest control products or pest control product containers stored in volumes greater than 205 litres?
IX LEGAL OR REGULATORY ACTIONS OR CONSTRAINTS
To the best of your knowledge are there currently any of the following pertaining to the site (please mark the appropriate column opposite the question):
YES NO
A. Government orders or other notifications pertaining to environmental conditions or quality of soil, water, groundwater or other environmental media?
B. Liens to recover costs, restrictive covenants on land use, or other charges or encumbrances, stemming from contaminants or wastes remaining onsite or from other environmental conditions?
C. Government notifications relating to past or recurring environmental violations at the site or any facility located on the site?
X ADDITIONAL COMMENTS AND EXPLANATIONS
(Note 1: Please list any past or present government orders, permits, approvals, certificates and notifications pertaining to the environmental condition, use or quality of soil, surface water, groundwater or biota at the site.
Note 2: If completed by a consultant, receiver or trustee, please indicate the type and degree of access to information used to complete this site profile. Attach extra pages, if necessary):
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
–6–
XI SIGNATURES
The person completing the site profile states that the above information is true based on the person's current knowledge as of the date completed.
Signature of person completing site profile Date completed: (YY-MM-DD)
XII OFFICIAL USE
Local Government Authority
Reason for submission (Please check one or more of the following) Soil removal
Subdivision application Zoning application Development permit Variance permit Demolition permit Date received:
Local Government contact : Name Agency Address Telephone ____________ Fax
Date submitted to Site Registrar:
Date forwarded to Director of Waste Management:
Director of Waste Management
Reason for submission (Please check one or more of the following)
Under Order Site decommissioning Foreclosure
Date received:
Assessed by: Name Region Telephone ____________ Fax If site profile entered, SITE ID #
Investigation Required? YES NO
Decision date:
Site Registrar
Date received:
Entered onto Site Registry by:
SITE ID #: Entry date: