melting practice & wheel casting gc-08

Upload: krabhijeet72356587

Post on 07-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    1/24

    SECONDARY STEEL MAKING

    &WHEEL CASTING

    G. CHOWDHURY Prof. (Met)

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    2/24

    STEEL MELTING PRACTICE

    Electric steel making is a SECONDARY

    STEEL Making process

    High alloy & sophisticated steels are

    made in electric arc furnace.

    Both S & P can be controlled in this

    process

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    3/24

    6/29/2011 3

    REFRACTORIES

    Basic refractories are used.

    Bottom is monolithic made of MagnesiteDry Ramming Mass (DRM).

    Slag line is made of Mag-Carb. Brick.

    Remaining portion is Magnesite brick.

    Roof is high alumina brick.

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    4/24

    6/29/2011 4

    CHARGING SEQUENCE & ARCING

    Pet coke and 50% of total lime to becharged at the bottom

    Then light scrap

    Heavy scrap and foundry returns

    Light boring & turning

    Closing the hood

    Lowering of Electrodes

    Start Arcing

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    5/24

    6/29/2011 5

    DESULPHERISATION

    CONDITIONS FOR DESULPHERISATION

    Reducing condition of bath.

    Low basicity preferably 2.00 High fluidity of slag.

    Intimate contact between slag & metal

    High temperature of the bath(preferablygreater than 15500C)

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    6/24

    6/29/2011 6

    DEPHOSPHORISATION

    CONDITIONS FOR DEPHOSPHORISATION

    Low temperature

    Viscous slag

    Oxidizing condition

    High Basicity (more than 2.5)

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    7/24

    6/29/2011 7

    PROCESS OF OXIDATION

    After melting lance oxygen (Carbon boiling) May charge iron ore.

    Keep the furnace door open for entry ofadequate air.

    This is purification stage of steel.

    Phosphorus is eliminated in this stage.

    Gases like H2 & N2 are eliminated in thisstage.

    Over oxidation is to be avoided.

    All siliceous impurities are eliminated as slag.

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    8/24

    6/29/2011 8

    PROCESS OF REDUCTION

    O2 potential in the bath is brought down

    by adding reducing agents

    Reducing agents are FeSi, FeMn, Al,SiMn etc.

    Based on the steel to be manufactured

    reducing agents are to be selected Sulpher is eliminated at this stage

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    9/24

    6/29/2011 9

    ALLOYING

    Depending on the chemical composition of

    steel, it is alloyed.

    Alloying always to be made at thereducing state except Ni & V.

    Best sequence of alloying is FeSi, FeMn,

    FeCr & at the last Al.

    Killing by Al to be avoided or else to be

    minimised.

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    10/24

    6/29/2011 10

    POURING

    Final deoxidation should be in the ladle.

    Temp of pouring depends on the Carbon &other alloying elements in the steel.

    The size and geometry of casting alsodetermines the temp of pouring.

    Pouring temp should be optimised in the

    lower side. Speed of pouring should be optimised on

    the higher side.

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    11/24

    6/29/2011 11

    LADLE PREPARATION

    Steel shell layered with Alumina brick (IS 8) High Alumina Ramming Mass at the bottom

    Layer of High Alumina Brick at the bottom

    Gaps are filled up by Ramming Mass Side wall also with High Alumina Brick

    Gaps are filled up by High Alumina Mortar

    Gap between IS-8 and High Alumina brickfilled with slurry of Burnt Magnesite bricks,Chips of other bricks, Ramming Mass etc.

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    12/24

    6/29/2011 12

    LADLE PREPARATION Contd.

    The lip and edges are prepared by

    Ramming Mass

    Allowed to air dry for24 hours Subjected to curing cycle through specific

    heating plan to 9000C over72 hours

    Brought down to75

    00

    C Hold Ready Ladle preparation and heating cycle is very

    important to get clean metal and long life

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    13/24

    6/29/2011 13

    POWER CONSUMPTION

    IDEAL CONSUMPTION OF POWER

    462 KWH/MT (Ref. MSTS)

    Normally it should not exceed more

    than 20% of the ideal Power.

    Practical power consumption is 650-700

    KWH/MT for making medium carbon steel

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    14/24

    6/29/2011 14

    POWER CONSUMPTION

    TO REDUCE POWER CONSUMPTION

    Top surface of the f/c should be loadedwith turning & boring

    This will facilitate easy bore-in stage ofelectrodes

    Excess heavy scrap should not becharged at the bottom.

    This may cause damage to the bottom aswell as will take more time to lift thematerial in melt down stage.

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    15/24

    6/29/2011 15

    GOOD MELTING PRACTICE

    Power consumption at various stage (PF=0.75)

    Bore-in 300 unit

    Melt down 396 unit

    Refining 066 unit

    Total 762 unit

    Charge composition

    HMS 50% MMS 30%

    LMS, Turning & Boring 20%

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    16/24

    6/29/2011 16

    GOOD MELTING PRACTICE

    Over heating of furnace to be avoided Pre-heat ladle (5000C 7000C) before pouring

    Specific pre-heating cycle of ladle is essential

    Correct basicity of slag should be maintained

    Correct tap positions during melting isessential

    Pre-heated Ferro Alloys should be charged

    At least 20 point carbon boil is essential

    Ferro Alloys should be estimated based on thefurnace condition

    Clean steel can be produced in clean andhealthy furnace

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    17/24

    6/29/2011 17

    WHEEL CASTING

    Major slag is removed from the top of ladle

    Ladle placed in JOHN MOHR Pit

    Al. star thrust into as final deoxidiser Sample taken for Chemical Analysis & H2 Top cover with Silimenite tube sits on top

    Graphite Mould sits on the top of tube

    Pit pressurised by air to lift the liq. Metal

    Liq. Metal flow to the mould to fill cavity

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    18/24

    6/29/2011 18

    WHEEL CASTING Contd

    Plunger brought down to seal the gating Mould placed on conveyor, next one in

    Stripping after pre-determined time to take

    away the Risers along with top Wheels placed on conveyor to tunnel

    Moulds go back for cleaning and recycling

    Sprue Wash, Stamping & Hub Cutting

    Placed to Moving Bed NormalisingFurnace followed by Rim Quenching,Tempering and Hub Quenching

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    19/24

    6/29/2011 19

    WHEEL INSPECTION

    After Hub quenching, cooled to RT Shot blasting to clean and impart

    compressive stress

    Visual Inspection in normal light Magnaflux Test for surface & sub-surface

    under UV light

    Wheels with removable defect sent for defectremoval through grinding & rechecking

    Automated Multi probe UT in Sprue area

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    20/24

    6/29/2011 20

    WHEEL INSPECTION Contd

    Hardness Testing

    Final Hub boring

    Final shot blasting Warpage checking

    Final Dimensional checking

    Other Mech. Testing one in each Heat Closure Test & Hardness mapping 1 in 500

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    21/24

    6/29/2011 21

    CAST WHEELS AT RWF

    Wheels to RDSO Spec. No. R-19 Part-III/1993.

    Producing both BOXN & Carriage wheels

    Production target this year is 2 lacs Continuous three shift operation

    Looking forward for Loco wheel production

    Axle forging from bloom a parallel activity Final product: Wheel sets & loose wheels

    Total production connected by LAN

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    22/24

    6/29/2011 22

    CAST WHEELS AT RWF

    Metallurgically forging route better than casting

    Special technique of controlled pressure casting

    Equivalent to forging route, even better

    Cross dendritc structure barrier to dislocation

    movement

    Mechanical properties as stipulated are well met

    High K1C value Resistance against catastrophic failure in service

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    23/24

    6/29/2011 23

    CAST Vs FORGED WHEELS

    High rate of production

    Machining of wheel is eliminated, any plate design

    In casting internal defect position is known

    So, very easy to ensure soundness Very uniform Quality

    No non-uniform quality arising of non-uniform hotworking with wide difference of reduction ratio

    Cleanliness is achieved by refining of steel in EAF One thin series of inclusion as per ASTM E-45

    Unique deoxidation ensures globulized alumina

    This helps in achieving K1C value of the steel

  • 8/6/2019 Melting Practice & Wheel Casting GC-08

    24/24

    6/29/2011 24