megger test procedure
TRANSCRIPT
![Page 1: Megger Test Procedure](https://reader034.vdocuments.site/reader034/viewer/2022050704/549e0e9eb4795965208b45e2/html5/thumbnails/1.jpg)
Megger Test Procedure
1) Winding Continuity testusing a standard ohmmeter
2) Star - Insulation testusing a megger with leads4,7 5,8 6,9 connected and checking to ground
3) Winding to Winding testusing a megger
![Page 2: Megger Test Procedure](https://reader034.vdocuments.site/reader034/viewer/2022050704/549e0e9eb4795965208b45e2/html5/thumbnails/2.jpg)
Step #1 Winding Continuity Test
Procedure: With 4,7 5,8 6,9 connected together, perform a standard continuity test between 1,2 1,3 2,3 to make sure there are NO BLOWN OPEN windings within the motor.
NOTES:
![Page 3: Megger Test Procedure](https://reader034.vdocuments.site/reader034/viewer/2022050704/549e0e9eb4795965208b45e2/html5/thumbnails/3.jpg)
Step #2 STAR - Insulation Leak Test
Procedure: Note: for safety you may keep the setting on ohms until ready to testWith 4,7 5,8 6,9 connected together, 1) connect green megger lead to a good solid motor ground 2) Connect RED lead to #1 then press 1000 voltRED test button 3) Move RED lead to #2 and repeat, and move RED lead to #3 and repeat the test RESULT: you are looking for HIGH MEG OHMS
![Page 4: Megger Test Procedure](https://reader034.vdocuments.site/reader034/viewer/2022050704/549e0e9eb4795965208b45e2/html5/thumbnails/4.jpg)
Step #3 Winding-to-Winding Insulation Leak Test
Procedure: After connecting the windings as shown on the right , MEGGER as follows:1) a) Connect GREEN lead to T 7,8,9 and RED lead T 1,4 and do 1000V test b) Leave GREEN lead on T7,8,9 and RED lead T2,5 and do 1000V test c) Leave GREEN lead on T7,8,9 and RED lead T 3,6 and do 1000V test2) d) Connect GREEN lead to T 1,4 and RED lead T 2,5 and do 1000V test e) Connect GREEN lead to T 1,4 and RED lead T 3,6 and do 1000V test f ) Connect GREEN lead to T 2,5 and RED lead T 3,6 and do 1000V test
T 1,4
T 2,5
T 3,6
T 7,8,9