medium voltage on shore power supply plant for cruise ......the electric vector are duly adapted: in...
TRANSCRIPT
![Page 1: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/1.jpg)
AUTORITA ‘ DI SISTEMA PORTUALE MAR TIRRENO SETTENTRIONALE PORTO DI LIVORNO
Medium Voltage On shore Power Supply Plant for Cruise Ships in the
Port of Livorno
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director
![Page 2: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/2.jpg)
• Livorno Port Authority & Porto di Livorno 2000 s.r.l. Environmental
Commitment
•Basic Analysis
• The solution carried out for the Onshore Power Supply and theconsequent environmental advantages
•Livorno O.P.S. Technical Characteristics
•Official testing
•Future Developments
•Acknowlegments
2
Summary
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director
![Page 3: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/3.jpg)
The Environmental Commitment
3
• The Livorno Port Authority and Porto di Livorno 2000,since the beginning of their activity, have inserted theenvironmental component in their decision makingprocess;
• This was put into practice by making effective anEnvironment Managing System complying with ISO14001 and EMAS regulations.
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director
![Page 4: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/4.jpg)
Basic Analysis
4
• By the studies performed in the last years itwas found out that the quality of the air inthe port area, and, more generally, in thetown of Livorno is strongly influenced by theemissions of the ships operating at the portquays.
Distribution of the energy consumption in the port Area (Year 2012)
Shore Activities 17%
Ships 83%
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director
![Page 5: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/5.jpg)
5
Basic Analysis
• The fuel consumption and the consequentemissions are mainly caused by thenecessity to keep running in the port all theship electrical apparatus and this is valid inparticular for the passenger ships whomoreover are berthed at the quays locatedas near as possible to the cities.
Cruise & Ferries 34%
RO/RO 18%
Container 23%
Various 25%
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 5
![Page 6: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/6.jpg)
• The utilization of an OnShore Power Supplyng (O.P.S.) Plantallows the elimination of the emission sources and thesubstantial reduction of the pollutants emitted remotely, dueto the intrinsic better efficiency of the electric generation in ashore power station versus the generation made aboard theship. In particular Porto di Livorno 2000 is member of anelectricity purchasing consortium, who can grant thesupplying of 100% power produced by renewable sources.
6
The Environmental Commitment
Main pollutants reduction by O.P.S. plant utilization vs:
Dust VOS
Use on board of 2,7% Sulfur Fuel Oil:
Use on board of 0,1% Sulfur Refined Fuel Oil:
Ing. Giovanni Paolo Spadoni -Technical & Commercial Director
6
![Page 7: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/7.jpg)
7
The Solution Carried out
Power supplying sub-station
(out of the port area)
Power Cables Pier Sub-Station
Pier Connecting
Terminal
On Board Installement
The possible mitigation interventions for these phenomenaconsist in the utilization of reduced environmental impact fuelsand the supplying of electrical power to the ships during theirstaying at the port berth(Onshore Power Supply)
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 7
![Page 8: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/8.jpg)
- Local impact mitigation on the air matrix through the eliminationof some relevant emission sources;
- Global reduction of the emitted pollutants through the utilizationof electrical power generation systems more efficient than thoseused aboard the ships;
- Acoustic impact reduction for the ships moored in port on thetown residential areas thanks to switching off the generators ofthe ships berthed in the proximity of the passenger terminal.
The main environmental advantages
8Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 8
![Page 9: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/9.jpg)
- For the completion of the project Livorno PortAuthority received specific co-financing fromthe Italian Ministry of Environment (60%) andfrom the Region of Tuscany (20%);
- The intervention was performed by a totalexpenditure of about € 3,5 millions;
The solution carried out
9Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 9
![Page 10: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/10.jpg)
- The plant was located at the “Calata” (Quay)Sgarallino nearby the town and where themedium size cruise ships take berth.
The solution carried out
10Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 10
![Page 11: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/11.jpg)
- In the absence of a technical standard theplant was planned and built to supplyelectrical power according to thecharacteristics of the ship installment.
- Some technical information:§ Maximum Deliverable Power: 12 MW§ Maximum Available Power: 7 MW§ Supply Voltage: 6,6 and 11 kV§ Supply Frequency: 50 and 60 Hz
The solution carried out
11Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 11
![Page 12: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/12.jpg)
- The power, supplied by ENEL Distribution, is furnished atmedium voltage in the electrical sub-station at the pier;
- Through a dedicated section of the plant, the characteristic ofthe electric vector are duly adapted: in particular, according tothe ship type to be supplied, the converter – transformer systemfurnish the power at 6,6 or 11 kV, at 50 or 60 Hertz.
The solution carried out
12
Panoramic sight of the electrical sub-station at the pier Sgarallino
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 12
![Page 13: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/13.jpg)
- From this sub-station, equipped by the necessary protection andmaneuvering devices at medium voltage, together with theauxiliary services, the power is transferred to the pier side by anunderground line consisting of a set of three 630 mm2 sectioncables;
- At the pier side are available n. 3 connection sub-stations.According to the position along the pier of the ship to besupplied, the power will be collected by one or the otherconnecting point.
Plant Characteristics
13
Position of the connecting sub-stations at the pier.View of the connections present at any connecting station at the pier.
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 13
![Page 14: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/14.jpg)
- The connecting stations at the pier are joint to the electric sub-station by an underground duct. A mobile rubber-tired device,carrying about 65 meters of cable consisting in n.4 triple-pole300 mm2 section cables, connects the pier sub-station and theplant onboard the ship;
- Once on board the medium voltage line will be connected to theship receiving switchboard.
Plant Characteristics
14
Mobile rubber-tired trolley.
Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 14
![Page 15: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/15.jpg)
- The new port plan was developed with the aim to adequate theport capacity to the expected increase (in number anddimensions) of the passenger ships.
- By the same environmental considerations the Port Authority isplanning to extend the electrical power supplying to threeadditional connecting sub-stations (marked in red), at the AltoFondale and Orlando quays.
The future developments
15Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 15
![Page 16: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/16.jpg)
- The Sgarallino Quay O.P.S. was tested on November 9th 2015connecting the Italian Navy Fregate “Carlo Bergamini”.
- At the beginning of 2017 the plant was transferred under thePorto di Livorno 2000 s.r.l. concession and management and anagreement was established with CRE (Consortium for EnergyResources) for the supplying of 100% green electrical power tothe plant, under the brand “Renewable Energy”.
Official testing
16Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 16
![Page 17: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/17.jpg)
- Before entering in a new executive project it will benecessary to understand the trend of the cruiseindustry under the emission reduction point of view.
- The new-building orders seem to privilege the LNGfuelling system, that can be used both for the mainengines and the generators substantially reducing theemissions while the ships are in port but also when innavigation.
- By recent information, only the 20% of the cruise shipnew buildings will be equipped by the shore powerconnecting switchboard.
The future developments
17Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 17
![Page 18: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/18.jpg)
- Responsible of the Project: Ing. Giovanni Motta- Feasibility Study: Ing. Mario Morretta – for Sintesis s.r.l- Final Project: Ing. Fabrizio Bernini- Executive Project: Ing.Claudio Ciucciarelli for Galileo Engineering s.r.l.- Site Managers: Ing.Fabio Bonacci- Ing. Massimiliano Micheletti- Director of Operation: Fabio Ceccarini- Safety & Security Coordinator: Ing. Massimo Vivaldi- Works Execution: GEMMO S.P.A. –Arcugnano VI- Sub Contractors & Suppliers:
- Tecnoelectric s.r.l.- Conductix s.r.l.- Nidec-ASI S.p.A.- Costruire s.r.l.- Costruzioni Santi s.r.l.- IL Mare s.r.l.
- Official Test: Ing. Stefano Rum- Porto di Livorno 2000 s.r.l. Technical Staff:
- Ing. Giovanni Paolo Spadoni- Ing. Francesco Deri
Acknowledgments
18Ing. Giovanni Paolo Spadoni - Technical & Commercial Director 18
![Page 19: Medium Voltage On shore Power Supply Plant for Cruise ......the electric vector are duly adapted: in particular, according to the ship type to be supplied, the converter – transformer](https://reader033.vdocuments.site/reader033/viewer/2022051907/5ffa38f6bbd971533275483b/html5/thumbnails/19.jpg)
Ing. Giovanni Paolo Spadoni -Technical & Commercial Director 19
Giovanni SpadoniPorto di Livorno 2000 srl Technical & Commercial Director
Thanks for the Attention!
Medium Voltage On shore Power Supply Plant for Cruise Ships in the Port of Livorno