measuring time - earned schedule vanhoucke ipma award_prese… · measuring time an earned value...

11
Measuring Time An earned value simulation study Mario Vanhoucke Presentation for the IPMA Research Award 2008 Rome (Italy) - November 11, 2008

Upload: lynhi

Post on 17-Sep-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Measuring TimeAn earned value simulation study

Mario VanhouckePresentation for the IPMA Research Award 2008Rome (Italy) - November 11, 2008

Drivers of forecast accuracy during project tracking

Improve corrective actions

Using Earned Value Management (EVM) and Schedule Risk Analysis (SRA)

General conclusion instead of case-specific examples

Research scope

Concept Project definition Project scheduling Project executionProject control

Feedback loop(earned value performance management)

Project structure(topological indicators)

Baseline schedule(activity criticality)

Schedule adherence(p-factor)

Determinants of forecast accuracy

Project termination

Forecast accuracy

Review period(percentage completed)

Corrective action decision making

Management’s attention(activity or project based)

Study 1 Study 2

Study 3

Methodology

1

2

3

4

5

6

Project network

123456

Project data Project execution Project progress Project output

Project schedule

Critical activities

Non-critical activities

Performance measurement(stage of completion)

123456

Early stage

Middle stage

Late stage

Performance measurement(WBS level)

Project

Objective

Work

Item

Work

package

Activity

Work

Item

Work

Item

Work

Item

Work

package

Work

package

Work

package

Work

package

Work

package

Work

package

Work

package

Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity ActivityActivity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity ActivityActivity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity

Project

Objective

Work

Item

Work

Item

Forecast accuracy

Influence of project networkInfluence of completion stageInfluence of WBS levelInfluence of activity criticality

0

5.5

11.0

16.5

22.0

W0 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11

EAC(t) forecasts

PVM EDM ESM

Real duration (horizontal line) = 11

Early On time Late

Early On time Late

> 4,000 projects 9 simulation scenarios

Measure Performance(SPI and SPI(t))

and predict

Measure Accuracy of Forecasts

Forecast accuracy

Drivers of forecast accuracy

Project structure and activity criticality are the main static drivers

Periodic tracking interval and schedule adherence are the main dynamic drivers

Earned Value Management works for more serial projects (well-structured)

Schedule Risk Analysis works for more parallel projects (more chaotic)

Project

Objective

Work

Item

Work

package

Activity

Work

Item

Work

Item

Work

Item

Work

package

Work

package

Work

package

Work

package

Work

package

Work

package

Work

package

Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity ActivityActivity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity ActivityActivity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity

Project

Objective

Work

Item

Work

Item

Project

Objective

Work

Item

Work

package

Activity

Work

Item

Work

Item

Work

Item

Work

package

Work

package

Work

package

Work

package

Work

package

Work

package

Work

package

Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity ActivityActivity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity ActivityActivity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity

Project

Objective

Work

Item

Work

Item

Accuracy = actions?

Project performance problem!

Which activities are criticaland responsible for the problem?

Negative effect on project performance?

Highly sensitive activities in trouble!

EVM: top-down SRA: bottom-upWBS levels

Project

Work item

Work package

Activities

Earned Value Management works for more serial projects (well-structured)

Schedule Risk Analysis works for more parallel projects (more chaotic)

Improved corrective actions

0%

10%

20%

30%

40%

50%

0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9

Trac

king

Effi

cien

cy

Parallel networks Serial networks

TD-SPITD-SPI(t)BU-SRA

Top-down project tracking using EVM with SPI(t) is particularly useful for serial networks -

Bottom-up project tracking using SRA is particularly useful for parallel networks

General conclusion

Activity based project tracking

(bottom-up time sensitivity)

Project based project tracking

(Top-down earned value)

Parallel project networks

Yes!Focus on a subpart

of activity set

No!Inaccurate time forecasts

Serial project networks

No!Focus not possible

Yes!Accurate time forecasts using Earned Schedule

The research project

The EV terminology

The software

Static drivers of forecast accuracy

Dynamic drivers of forecast accuracy

Top-down or bottom-up project tracking

A case study

An EVM introduction

Time sensitivity and corrective actions

A new book (coming soon)

ProTrackCRITERIA

Project Planning

CPM based planning

Network visualization

Automatic Project Creation

Project simulation options

Activity Time/Cost Simulation

Schedule Risk Analysis

EVM forecast accuracy Analysis

Project Tracking

Earned Value and Earned Schedule

Earned Value Forecasting**

Automatic Tracking Generation

p-factor calculation

Book “Measuring Time”

Price

ProTrack ProTrack ProTrack ProTrack

Standard Sensitivity Scan Time Shuttle Smart Version

yes yes yes yes

- yes yes yes

- yes yes yes

- Advanced module Standard Module Standard/Advanced modules

- yes - yes

- - yes yes

yes yes yes yes

yes yes yes yes

- - yes yes

- - yes yes

- - - yes

299 € 399 € 399 € 599 €

New software tool (available)

ContactInterested about

The new book

The new software tool

Future research results

Subscribe to our newsletter on www.or-as.be

or give me your email address to receive the newsletter today!Cover might be subject to change upon publication

THANK YOU!

Interested about

The new book

The new software tool

Future research results

Subscribe to our newsletter on www.or-as.be

or give me your email address to receive the newsletter today!