![Page 1: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/1.jpg)
MEASURE L BOND CONSTRUCTION UPDATE
October 18, 2016
![Page 2: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/2.jpg)
IntroductionThe following presentation is intended to provide the Board of Trustees with an update on the progress of Measure L Construction Bond Projects. These are projects that are currently active throughout the District.
Vinci Park MPR Floor Sierramont ChillerPiedmont
![Page 3: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/3.jpg)
Ø Phase 2 Technology Upgrade –Cable
Ø Remaining Work by School
Ø Energy Conservation – Solar
Ø Central Kitchen – Expected start date – 10/28/16
Measure L – 2016 Project Overview
Vinci Park PavingSummerdale – Site of the 2016 Ribbon Cutting Event
![Page 4: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/4.jpg)
Measure L – 2016 Project DetailsØ Phase II Technology Upgrade -‐ Cabling
a. Stage I Cabling Upgrades: • Majestic Way, Piedmont, Toyon, Summerdale – completed
• Laneview:ü Buildings B, D & portables to be
completed Feb. & Apr. 2017 breaks• FIS Cabling & Exterior Wireless Access Points – in progress
b. Stage II Cabling Upgrades –• MOT awarded – Thanksgiving Break
c. Stage III Cabling Upgrades: • Noble awarded – Winter Break
Laneview
Ruskin
Laneview
![Page 5: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/5.jpg)
Measure L – Remaining Work by School1. Noble ES:
• Shade structure: 10/16/16• FIS Furniture: 10/28/16• Stage curtain replacement: 11/9/16• Front gate replacement: 11/14/16• Specialty doors : 11/21/16• Punch list items: 11/23/16• FIS & MPR Audio Visual: 11/30/16
2. Northwood ES:• FIS Furniture: 10/28/16• Library wall graphics: 10/5/16• Wood ceiling & lighting: 10/14/16• FIS Furniture: 10/28/16• Specialty partition wall: 11/15/16• Façade backing: 11/23/16• Punch list items: 11/28/16• FIS & MPR Audio Visual: 11/30/16
Northwood FIS
Noble FIS
![Page 6: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/6.jpg)
Measure L – Remaining Work by School3. Sierramont MS:
• Playground restrooms: 10/14/16• FIS Furniture: 10/28/16• East access paving: 11/4/16• FIS & MPR Audio Visual: 11/25/16• Specialty partition walls: 11/22/16• Punch list items: 11/22/16
4. Summerdale ES:• FIS Furniture: 10/28/16• Fence installation: 11/11/16• FIS & MPR Audio Visual: 11/29/16• Punch list items: 11/29/16
5. Vinci Park ES:• Punch list items: 10/28/16• MPR Audio Visual: 11/16/16• Fence installation: Winter Break
Sierramont FIS & Chromebooks
Summerdale FIS Ceiling
Vinci Park – Ms. Jensen instructing
![Page 7: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/7.jpg)
Measure L – Energy Conservation SolarØ Solar Installation:• All interconnects complete as of 10/9/16
except Morrill and Brooktree. PG&E schedule for Morrill and Brooktree are pending.
• Permission to Operate – pending PG&E commissioning.
Majestic Way Interconnect
Piedmont – PG&E Interconnected Thur. 9/29/16
![Page 8: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/8.jpg)
1. Stage IV Cabling Upgrades• Brooktree, Northwood, Ruskin, Vinci Park –
awarded – Summer 20172. Central Kitchen – expected completion
April 20173. F.I.S./Modernization/Classroom Furniture• Laneview, Majestic Way• Vinci Park (F.I.S. only)
4. Modernization/Classroom Furniture • Piedmont, Ruskin
5. Pavement Rehabilitation• Brooktree, Cherrywood, Majestic Way• Piedmont Drop-‐Off Area
Measure L – 2017 Project Overview
Central Kitchen
Majestic Way
![Page 9: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/9.jpg)
Construction Legend Furniture LegendDesign Furniture Order FinalizedBid Quote DateAward AwardConstruction Furniture OrderedStart of School Start of SchoolLong Lead Items & Added Project Scope Lead TimeProject Complete Furniture Received and Placed
2016 Construction Projects
1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4Central Kitchen Const & Equip
Sierramont Chiller Upgrade COMPLETED
Sierramont FIS/Modernization
Noble FIS/Modernization
Northwood FIS/Modernization
Summerdale FIS/Modernization
Vinci Park/Modernization
Paving Rehabilitation
Solar Project
Stage I Cabling Upgrades
Stage II Cabling Upgrades
Stage III Cabling Upgrades
2016 Furniture Projects
Furniture COMPLETED
FIS Furniture
OctoberWeek
DecemberWeek
FebruaryWeek
JanuaryWeek Week
November
2016 Construction & Furniture Projects
SeptemberWeek
![Page 10: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/10.jpg)
Construction Legend Furniture LegendDesign Furniture Order FinalizedBid Quote PricingAward PO GeneratedConstruction Furniture OrderedStart of School Start of SchoolLong Lead Items Lead TimeProject Complete Furniture Received and Placed
2017 Construction Projects
1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4Laneview FIS/Modernization
Majestic Way FIS/Modernization
Vinci Park FIS
Piedmont/Modernization
Ruskin/Modernization
Paving Rehabilitation
Piedmont Dropoff
Stage IV Cabling Upgrades
2017 Furniture Projects
Furniture
FIS Furniture
2017 Construction & Furniture Projects
JanuaryWeek Week Week Week Week
September October November December FebruaryWeek
![Page 11: MEASURE L BOND...Northwood FIS/Modernization Summerdale FIS/Modernization Vinci Park/Modernization Paving Rehabilitation Solar Project Stage I Cabling Upgrades Stage II Cabling Upgrades](https://reader033.vdocuments.site/reader033/viewer/2022043009/5f9b1063989bad0dd7625a37/html5/thumbnails/11.jpg)
Thank You