mchs - montgomery county public schools · construction project update •buildings...

27
MCHS Construction Project Update – April 1, 2019

Upload: others

Post on 03-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

MCHSConstruction Project Update – April 1, 2019

Page 2: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

Construction Project Update

• Buildings

– CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof decking in progress, 85% complete. Light gauge metal walls in progress, 70% complete. Mechanical, electrical, plumbing in progress, first and second floors. Masonry crews performing CMU cleanup/patch work. Sprinkler pipe in progress.

– HS…Slab on grade for Area E/F (instructional wing) poured. Stairwell CMU constructed, elevator shaft in progress. Area C (office/media) steel in progress. Gymnasium roof decking in progress. Exterior Brick in progress. Area A (locker rooms) under slab utilities in progress.

Page 3: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

Construction Project Update

• Next 30 days

– CTE – Continue to install light gauge metal walls for Health Rooms. Continue mechanical, electrical, plumbing work over ceiling and in metal walls. Complete roof decking, begin roof installation.

– HS – Receive steel for Area E/F. Complete second floor decking Area C, pour second floor slab. Pour second half of Area A (men’s locker room) and Area B (kitchen). Set structural steel for Auditorium roof. Continue exterior spray foam insulation and brick veneer.

– Site – Pour footers for athletic buildings, begin CMU work. Move staged soil from student parking lot.

– Next Progress Meeting is scheduled for April 4, 2019.

Page 4: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

South Wall CTE Building

Page 5: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

West Stairwell – green area will have accent panels.

Page 6: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

West Wall CTE – Wood working – Agri-Science

Page 7: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

North Wall CTE Courtyard- note window frames in progress

Page 8: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

East Wall CTE Courtyard - Construction Trades

Page 9: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

East/North Walls CTE – Welding/Auto Shop Doors

Page 10: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

CTE Roof facing Northeast

Page 11: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

CTE Roof facing Northwest

Page 12: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

CTE office area light gauge metal walls

Page 13: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

CTE first floor main hallway MEP

Page 14: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

CTE second floor Health Rooms

Page 15: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

CTE second floor main hallway

Page 16: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

Athletic Fields – HS weight room/locker rooms

Page 17: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

HS Auxiliary/Main Gym roof deck in progress

Page 18: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

HS Auditorium – Band Room – West Stairwell

Page 19: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

HS Auditorium – Band Room – Foam Insulation in progress

Page 20: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

HS Area C office/media center being erected

Page 21: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

HS Media Center roof joist being welded down

Page 22: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

HS Computer Lab – Kitchen/Health rooms in background

Page 23: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

Instructional Wing main elevator shaft

Page 24: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

Center stage facing Operation Booth

Page 25: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

Operation Booth to facing Main Stage

Page 26: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof
Page 27: MCHS - Montgomery County Public Schools · Construction Project Update •Buildings –CTE…Exterior Brick completed. Windows in progress. Roof structural steel 99% complete. Roof

QUESTIONS?

Note: Photo is of the heaviest beam in our project at 431 pounds per foot. This 53’ beam is to be placed in Area F.