mcgraw-hill/irwin© 2008 the mcgraw-hill companies, all rights reserved reducing project duration...

20
McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

Upload: elvin-barker

Post on 13-Dec-2015

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, All Rights Reserved

Reducing Project Duration

Chapter 9

Page 2: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-2

Page 3: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-3

Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs

Reducing the time of a critical activity usually incurs additional direct costs.

o Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project.

Reasons for imposed project duration dates:o Customer requirements and contract commitments

o Time-to-market pressures

o Incentive contracts (bonuses for early completion)

o Unforeseen delays

o Overhead and goodwill costs

o Pressure to move resources to other projects

Page 4: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-4

Options for Accelerating Project Completion

Adding Resources

Outsourcing Project Work

Scheduling Overtime

Establishing a Core Project Team

Do It Twice—Fast and Correctly

Fast-Tracking

Critical-Chain

Reducing Project Scope

Compromise Quality

Page 5: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-5

Explanation of Project Costs Project Indirect Costs

Costs that cannot be associated with any particular work package or project activity

o Supervision, administration, consultants, and interest

Costs that vary (increase) with timeo Reducing project time directly reduces indirect costs.

Direct Costs Normal costs that can be assigned directly to a

specific work package or project activityo Labor, materials, equipment, and subcontractors

Crashing activities increases direct costs

Page 6: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-6

Reducing Project Duration to Reduce Project Cost

Identifying direct costs to reduce project timeIdentifying direct costs to reduce project timeIdentifying direct costs to reduce project timeIdentifying direct costs to reduce project time

Compute total costs for specific durations and Compute total costs for specific durations and compare to benefits of reducing project time.compare to benefits of reducing project time.

Compute total costs for specific durations and Compute total costs for specific durations and compare to benefits of reducing project time.compare to benefits of reducing project time.

Search critical activities for lowest direct-cost Search critical activities for lowest direct-cost activities to shorten project duration.activities to shorten project duration.

Search critical activities for lowest direct-cost Search critical activities for lowest direct-cost activities to shorten project duration.activities to shorten project duration.

Gather information about direct and indirect Gather information about direct and indirect costs of specific project durations. costs of specific project durations.

Gather information about direct and indirect Gather information about direct and indirect costs of specific project durations. costs of specific project durations.

Page 7: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-7

Project Cost—Duration Graph

FIGURE 9.1

Page 8: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-8

Constructing a Project Cost—Duration Graph

Find total direct costs for selected project durations.

Find total indirect costs for selected project durations.

Sum direct and indirect costs for these selected project durations.

Compare additional cost alternatives for benefits.

Page 9: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-9

Constructing a Project Cost—Duration Graph

Determining Activities to Shorten Shorten the activities with the smallest increase in

cost per unit of time. Assumptions:

o The cost relationship is linear.

o Normal time assumes low-cost, efficient methods to complete the activity.

o Crash time represents a limit—the greatest time reduction possible under realistic conditions.

o Slope represents a constant cost per unit of time.

o All accelerations must occur within the normal and crash times.

Page 10: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-10

Activity Graph

FIGURE 9.2

Page 11: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-11

Cost—Duration Trade-off Example

FIGURE 9.3

Page 12: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-12

Cost—Duration Trade-off Example (cont’d)

FIGURE 9.3 (cont’d)

Page 13: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-13

Cost—Duration Trade-off Example (cont’d)

FIGURE 9.4

Page 14: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-14

Cost—Duration Trade-off Example (cont’d)

FIGURE 9.4 (cont’d)

Page 15: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-15

Cost—Duration Trade-off Example (cont’d)

FIGURE 9.4 (cont’d)

Page 16: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-16

Summary Costs by Duration

FIGURE 9.5

Page 17: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-17

Project Cost—Duration Graph

FIGURE 9.6

Page 18: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-18

Practical Considerations

Using the project cost—duration graph

Crash times

Linearity assumption

Choice of activities to crash revisited

Time reduction decisions and sensitivity

Page 19: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-19

What if Cost, Not Time Is the Issue?

Commonly Used Options for Cutting Costs

Reduce project scope

Have owner take on more responsibility

Outsourcing project activities or even the entire project

Brainstorming cost savings options

Page 20: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9

9-20

Key TermsCrash point

Crash time

Direct costs

Fast-tracking

Indirect costs

Outsourcing

Project cost–duration graph