mcalway/churchill storm drainage improvement...
TRANSCRIPT
Project Status:Charlotte-Mecklenburg Storm Water Services and engineering consultant, Parsons Brinckerhoff, Inc., have finalized the construction plans and begun the bid phase. During this phase, the final design plans will be circulated to qualified contractors for a competitive bidding process.
Next Steps:After City Council approval, the construction contract is awarded to the lowest responsible bidder. Construction is estimated to begin in late spring or early summer 2016.
For more information:Please contactWilliam Harris, Project Manager [email protected]
November 2015
McAlway/Churchill Storm Drainage Improvement Project
Engineering & Property ManagementStorm Water Services Division600 East Fourth StreetCharlotte, North Carolina 28202
McAlway/Churchill Storm Drainage Improvement Project
For more information: StormWater.CharMeck.org
Investing in InfrastructureThe City replaces pipes, storm drains and other structures when they deteriorate or become too small to handle increases in stormwater. Investing in infrastructure protects public safety, guards private property, improves water quality and enhances quality of life.
The McAlway/Churchill Storm Drainage Improvement Project goal is to reduce flooding of streets and structures throughout the neighborhood.