maurizio monina remo grandori aristodemo busillo roberto ...€¦ · 812 852 892 932 972 1012 1052...
TRANSCRIPT
![Page 1: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/1.jpg)
HIGH PRESSURE EPB TUNNELING UNDER SENSITIVE BUILDINGS
Maurizio Monina S.E.L.I Spa, Rome, Italy
Remo Grandori S.E.L.I Spa, Rome, Italy
Aristodemo Busillo S.E.L.I Spa, Rome, Italy
Andrea Sciotti Roma Metropolitane, Rome, Italy
Roberto Ginanneschi S.E.L.I Spa, Rome, Italy
Metro Line B1 is a branch of the existing Line B, and the section currently under construction is characterized by the excavation of 2 tunnels (with a total length of approximately 6 km) and 3 stations (Conca d’Oro, Gondar and Annibaliano).
The works of the new metro line are located in a heavily built-up area on an axis from Piazza Conca d’Oro to Piazza Bologna, and affecting Via delle Valli, Viale Libia, Piazza Annibaliano and Viale XXI Aprile.
Excavation of the tunnels started was in the early months of 2008. The choice of the system for excavation, mucking system and logistical management of the activities
required to make the tunnels of this line was defined on the basis of various factors, including the altimetric profile of the route, the geological, geotechnical and hydrogeological characteristics of the terrain and above all the evaluation o the interferences of the excavation with previously existing structure.
The evaluation of the aspects mentioned above led to the decision to use mechanized excavation with the EPB method, with the use of a mucking system with continuous conveyor belts and a vertical conveyor belt at the initial station (Conca d’Oro Station).
ROUTE
The route of the two tunnels has a total length of 6,050m and is characterized by a maximum slope of 4%, numerous horizontal curves (with minimum radius of 130m) and a low planimetric and altimetric wheelbase, between 8.70m and 11.30 m, at the station entry/exit areas.
In particular, the planimetric and altimetric profile involves reaching the maximum depth (40 m) in the stretch going under the Aniene River, while the point of minimum coverage is at the Bologna Station, with a depth of approximately 8 m with respect to the current ground level.
GEOLOGY
The line tunnels planned in this project have a depth ranging between 15 and 40 meters below ground level. The geological formations involved in the excavation, from the top downwards, and under the surface layers consisting of fill, are as follows:
![Page 2: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/2.jpg)
- “Alluvioni recenti” (Late Pleistocene – Holocene) - these are recent sediments of the Aniene River and its tributaries, with soil consisting of plastic clayey silt, interlayered with sandy silt.
- Tuff coverage (Middle Pleistocene) - related to the volcanic activity of the Sabatini Hills and the Alban Hills; brown pyroclastic formations interlayered with volcanic ash.
- “Paleo-Tevere 2” sediments (Middle Pleistocene) - these formations include a series of heterogeneous deposits deriving from different phases, subdivided as follows: a) Upper layer: consisting of silty clays and/or clayey silt interlayered with sand; b) Lower layer: consisting fluvial and lake sediments, mainly clay and clayey silt; c) Base layer: characterized by limestone gravel embedded in very fine sand and/or sandy silt.
The underlying layer of these formations, which will not in any case be involved by the works, consists of Pleistocene clay and gray-blue clayey silt formations. The distribution of the soil types involved in the excavation of the line tunnels is shown in Table 1.
Table 1. Soil formations
Formations Frequency % Even Track
Frequency % Odd Track
Frequency % Total
Alluvioni Recenti - AR 16.3% 30.6% 23.6%
Pyroclastic – P - 7.1% 3.5%
Upper layer “Paleo-Tevere 2 formations” – P2S -
18.9% 24.0% 21.5%
Lower layer “Paleo-Tevere2 formations” – P2L -
11.8% 23.4% 17.7%
Base layer “Paleo-Tevere 2 formations” – P2G -
45.9% 22.0% 33.7%
From the hydrogeological point of vista, the layer types described above are characterized by the constant
presence of groundwater, with permeability recorded between 1.0 E-05 cm/sec and 3.0 E-02 cm/sec, as shown in detail in Table 2.
Table 2. Permeability index Formations Permeability
cm/sec Alluvioni Recenti - AR 1.0 E-05 Pyroclast – P - 1.0 E-04
1.0 E-03 Upper layer “Paleo-Tevere 2formations” – P2S -
7.3 E-03
Lower layer “Paleo-Tevere 2formations” – P2L -
5.6 E-04
Base layer “Paleo-Tevere 2formations” – P2G-
3.0 E-02
ANALYSIS OF THE MAIN EXCAVATION PARAMETERS
Because of the requirements of planning and design related not only to the tunnel excavation operations, but also the ones for the execution of the preliminary works, especially the construction of the various parts of the Conca d’Oro Station, the excavation of the two tunnels (Even Track tunnel & Odd Track tunnel) along the stretch between Conca d’Oro-Gondar, was conducted on an alternating and not continuous basis with the two TBMs. This
![Page 3: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/3.jpg)
was to avoid creating interference between the two excavation faces. The non-continuity of advance has undoubtedly influenced the excavation parameters, and therefore in order to ensure a more correct interpretation, the data for the sections of between Gondar Station and Bologna Station (total length 4,120 m), where, however, excavation was conducted on a continuous basis.
TBM excavation parameters In general, as shown in Table 3, as well as in Figures 1 and 2, the machine parameters recorded during
excavation were always under the alert levels assigned to this type of TBM. Table 3. TBM Excavation Parameters Even Track Tunnel Odd Track Tunnel Parameters Averag
e value Max. value
Min. value
Parameters Average value
Max. value
Min. value
Excavation time (min) 40 100 19 Excavation time (min)
38 86 19
Penetration speed (mm/min)
36 72 11 Penetration speed (mm/min)
39 72 16
Total Thrust (KN) 18777 36456 9407 Total Thrust (KN) 15302 34329 5650 Active Articulation Thrust (KN)
1222 2100 648 Active Articulation Thrust (KN)
1018 1921 608
Cuttinghead RPM (rpm) 1.90 2.30 1.20 Cuttinghead RPM (rpm)
1.90 2.40 1.00
Torque (KN*m) 2710 4200 1130 Torque (KN*m) 2280 3910 960
Figure 1. Even track TBM Boring Parameters
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Pari
TBM Boring Parameters
0
5000
10000
15000
20000
25000
30000
35000
812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1533 1573 1613 1653 1693 1733 1773 1813 1865 1905 1945 1985 2025 2065 2105 2145 2185 2225 2265
Anello (n°)
To
tal t
hru
st (
KN
) / A
rtic
ula
tio
n T
hru
st
(KN
)
0
0,5
1
1,5
2
2,5
3
3,5
4
4,5
Torq
ue
(MN
*m)
/ Cu
ttin
gh
ead
RP
M
(rp
m)
Articulation Thrust (KN) Total Thrust (KN)
Cuttinghead RPM (rpm) Torque (MN*m)
![Page 4: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/4.jpg)
Figure 2. Odd track TBM Boring Parameters
Figure 3. Even Track – Correlation Torque vs EPB Pressure top and TBM Penetration speed
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario DispariTBM Boring Parameters
0
5000
10000
15000
20000
25000
30000
35000
830 870 910 950 990 1030 1070 1110 1150 1190 1230 1270 1310 1350 1390 1559 1599 1639 1679 1719 1759 1799 1839 1892 1932 1972 2012 2052 2092 2132 2172 2212 2252 2292 2332 2372 2412
Ring (n°)
Para
metr
i di s
cavo T
BM
0
0,5
1
1,5
2
2,5
3
3,5
4
4,5
To
rqu
e (
MN
*m)
/ Cu
ttin
gh
ead
RP
M
(rp
m)
Articulation Thrust (KN) Total Thrust (KN)
Cuttinghead rpm (rpm) Torque (MN*m)
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Pari
Correlation Torque vs EPB Pressure top and TBM Penetration speed
0
10
20
30
40
50
60
70
80
812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822 1874 1914 1954 1994 2034 2074 2114 2154 2194 2234 2274
Ring (n°)
Pen
etra
tio
n s
pee
d (
mm
/min
)
0
0,5
1
1,5
2
2,5
3
3,5
4
4,5
To
rqu
e (M
N*m
) / E
PB
Pre
ssu
re T
op
(b
ar)
Penetration speed (mm/min)Torque (MN*m)EPB Pressure top (bar)
Alluvioni Formazione Del Paleotevere 2 Piroclastiti Recenti (AR)
![Page 5: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/5.jpg)
Figure 4. Odd Track – Correlation Torque vs EPB Pressure top and TBM Penetration speed
Figure 5. Torque of the cutterhead for both tracks
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Dispari
Correlation Torque vs EPB Pressure top and TBM Penetration speed
0
10
20
30
40
50
60
70
80
830 870 910 950 990 1030 1070 1110 1150 1190 1230 1270 1310 1350 1390 1559 1599 1639 1679 1719 1759 1799 1839 1892 1932 1972 2012 2052 2092 2132 2172 2212 2252 2292 2332 2372 2412
Ring (n°)
Pen
etra
tio
n s
pee
d (m
m/m
in)
0
0,5
1
1,5
2
2,5
3
3,5
4
4,5
Torq
ue
(MN
*m)
/ EPB
Pre
ssure
top
(bar
)
Penetration speed (mm/min)Torque (MN*m)EPB Pressure top (bar)
Alluvioni Recenti Formazione del Paleotevere 2
![Page 6: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/6.jpg)
Furthermore, the analysis of Figures 3 and 4 shows that the cuttinghead torque of the TBM has been more significantly affected by the geological and geotechnical characteristics of the soil excavated than by the variations of EPB pressure rates recorded during the excavation. In particular, in both tunnels this parameter showed an increase in the most relevant levels, i.e. the clays normal consolidated or overconsolidated in the Formation of Alluvioni Recenti deposits, and cemented gravels in the Paleo-Tevere 2 Formation, thus leading to a decrease of the TBM speed of penetration.
Nevertheless, as shown in Figure 5, during the excavation operations by both the TBMs, the torque values recorded in relation to the rotation speed of the cutterhead were well within the range set by the maximum allowable values for this type of TBM.
Injection pressures and volumes of the backfilling grout The ring space between the excavation section and the extrados of the lining segments was backfilled with bi-
component mortar, injected during the excavation phase by special nozzles positioned on the shield tail. The bi-component system consists in the injection of a grout (component A) and of a setting accelerator
(component B) through separate lines to the rear part shield tail where, using nozzles, the grout is sprayed with component B, triggering the reaction behind the shield. Lab tests, confirmed by tests conducted on site, have shown that gelling time is approximately 8-10 seconds. Table 4. Backfilling grout volume injected Even Track Tunnel Odd Track Tunnel Parameters Volume (mc) Ring N# Parameters Volume (mc) Ring N# Maximum value 7.5 1268 Maximum value 7.9 1163 Minimum value 2.8 1609 Minimum value 2.9 1971 Average value 4.1 Average value 4.1 Theoretical value 4,23 Theoretical value 4,23 Table 5. Backfilling grout Injection pressure Even Track Tunnel Odd Track Tunnel Parameters Pressure (bar) Ring N# Parameters Pressure (bar) Ring N# Maximum value 5.23 1370 Maximum value 4.67 945 Minimum value 1.18 2015 Minimum value 1.30 2273 Average value 3.12 Average value 2.98
From the data shown in tables 4 and 5 and figures 6 and 7 herebelow, we can conclude the following: for both tunnels, the same average value of the volume of backfilling grout injected was observed, (4.10 m3), virtually corresponding to the theoretical value (4.23 m3), considering that the difference between the two is 3.10%.
This can be considered in line with and correlated to the values of weigh extracted during the excavation phases, which remain constantly under the theoretical ones indicated in the design guidelines.
During the excavation of the Even Track Tunnel and the Odd Track, the injection pressures were constantly above of the ones forecast by the design in the various sectors of tunnel, with positive results regarding the backfill of the ring gap behind the lining, and therefore regarding the surface settlements triggered by the excavation.
![Page 7: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/7.jpg)
Figure 6. Even Track – Backfilling Grout and Pressure Analysis
Figure 7. Odd Track – Backfilling Grout and Pressure Analysis
This seems to be confirmed in Figures 8 and 9, showing, by way of example, on the Gondar-Annibaliano stretch, the surface settlements recorded on the tunnel axis, both with the support pressure of the face, and with the of injection pressure of the backfilling grout. The graphs, in fact, not only show a correlation between the parameters considered, but also a direct effect of the support pressure of the face and, above all, of the injection pressure of the backfilling grout on surface settlements, thus confirming, among other things, a marked lack of concern and an evident “response” in the terrain affected by the excavation operations.
METROPOLITANA DI ROMA - LINEA B1 -Galleria BinarioPari
Backfilling Grout and Pressure Analisys
0
1
2
3
4
5
6
7
8
812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1533 1573 1613 1653 1693 1733 1773 1813 1865 1905 1945 1985 2025 2065 2105 2145 2185 2225 2265
Ring (n°)
Vo
lum
e (m
c) /
Inje
ctio
n P
ress
ure
(b
ar)
Volume (mc)
Injection Pressure (bar)
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Dispari
Backfilling Grout Volume & Pressure Analysis
0
1
2
3
4
5
6
7
8
830 870 910 950 990 1030 1070 1110 1150 1190 1230 1270 1310 1350 1390 1559 1599 1639 1679 1719 1759 1799 1839 1892 1932 1972 2012 2052 2092 2132 2172 2212 2252 2292 2332 2372 2412
Ring (n°)
Vo
lum
e (
mc
) / I
nje
cti
on
Pre
ss
ure
(b
ar)
Volume (mc)
Injection Pressure (bar)
![Page 8: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/8.jpg)
Figure 8. Even Track – EPB pressure and injection pressure vs surface settlements
Figure 9. Odd Track – EPB pressure and injection pressure vs surface settlements
Muck weight
Considering that the system of muck removal, using continuous conveyor belts, does not provide for measurement of the volume removed, the monitoring of its weight is a fundamental aspect in excavation management. Therefore, two scales were installed on the main conveyor belt on the TBM back up, allowing the continuous monitoring of the weight of the material removed during excavation.
The theoretical value of the weight of material to be removed for each thrust, indicated in the guidelines, is purely indicative, since it was obtained with a � rate for undisturbed (and unconditioned) terrain of 1.8 t/m3;
METROPOLITANA DI ROMA - LINEA B1 -Galleria BinarioPari
EPB pressure and Injection pressure vs Surface settlements
-15
-13
-11
-9
-7
-5
-3
-1
1
3
5
7
875 889 904 918 932 946 961 975 989 1004 1046 1061 1075 1089 1111 1125 1139 1154 1168 1189 1204 1225 1239 1254 1268 1289 1311 1325 1346
Ring (n°)
Su
rfa
ce
se
ttle
me
nts
8m
m)
0
0,5
1
1,5
2
2,5
3
3,5
4
4,5
5
EP
B P
res
su
re t
op
(b
ar)
/ b
ac
kfi
llin
g g
rou
t In
jec
tio
n
pre
ss
ure
(b
ar)
Surface settlements (mm)
Injection Pressure (bar)
EPB Pressure top (bar)
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Dispari
EPB pressure and Injection pressure vs Surface settlements
-15
-13
-11
-9
-7
-5
-3
-1
1
3
5
7
886 900 915 936 950 965 979 993 1007 1022 1036 1050 1072 1086 1100 1122 1136 1150 1172 1207 1222 1236 1250 1265 1279 1293 1307 1322 1336 1350 1372 1386
Ring (n°)
Vo
lum
e (
mc
) / I
nje
cti
on
Pre
ss
ure
(b
ar)
0
1
2
3
4
5
6
EP
B P
ress
ure
to
p (
bar
) /
bac
kfil
lin
g g
rou
t p
ress
ure
(b
ar)
Surface settlements (mm)Injection Pressure (bar)EPB Pressure top (bar)
![Page 9: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/9.jpg)
therefore, without considering the volume of liquid injected and necessary for conditioning. Analysis of the data shows that in both tunnels the values recorded during excavation are lower than those
indicated by the designer.
Table 6. Muck Weight and Liquid Injected Even Track Tunnel Odd Track Tunnel Parameters Muck
weight (ton)
Liquid injected (ton)
Parameters Muck weight (ton)
Liquid injected (ton)
Average value 76.0 3.4 Average value 73.8 3.6
Theoretical value
92.1 Theoretical value
92.1
Likewise, Figures 10 and 11 show that in the stretches of tunnel excavated in the Paleo-Tevere 2 Formation,
the values of the weights excavated are lower compared to those recorded in the clays of Alluvioni Recenti sediments.
This aspect confirms the greater compacting effect of the Paleo-Tevere 2 soils, due to the thrust and the pressure produced during excavation on the face by the TBM, and can be correlated with the partial reduction of the ring gap and thus the volume of backfilling grout injected.
In particular, if we consider the weights of the material extracted, minus the liquids injected during the excavation and necessary for the conditioning, we obtain average values corresponding to 79% of the theoretical value for the Even Track Tunnel and 76.2% for the Odd Track Tunnel.
Figure 10. Even Track – Muck weight and liquid injected Analysis
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Pari
Muck Weight and Liquid injected Analisys
50
60
70
80
90
100
110
120
811 851 891 931 971 1011 1051 1091 1131 1171 1211 1251 1291 1331 1371 1532 1572 1612 1652 1692 1732 1772 1812 1864 1904 1944 1984 2024 2064 2104 2144 2184 2224 2264
Ring n°
Mu
ck
Weig
ht
(ton
)
0
0,5
1
1,5
2
2,5
3
3,5
4
EP
B p
res
su
re t
op
(ba
r)
Muck w eight (ton)Real Muck w eight (ton)Total w eight w it liquid (ton)EPB Pressure top (bar)
![Page 10: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/10.jpg)
Figure 11. Odd Track – Muck weight and liquid injected Analysis
Conditioning of the soil In the tunnels analyzed, the conditioning proved to be more difficult in the stretches characterized by the
presence of silty clays of the recent alluvial sediments, compared to the situation in the gravels and sandy silts of the Paleo Tevere 2 Formation. This aspect is above all due to the different permeability of the single formations excavated. The low permeability of Alluvioni Recenti sediments has led to a number of problems in achieving the optimal physical characteristics of the material conditioned (e.g.: high cohesion, low permeability and a consistency bordering between liquid and plastic) necessary to guarantee the even distribution of the ground pressure on the excavation face, and at the same time avoiding flooding of the excavation chamber. Table 7. Soil Conditioning Parameters Even Track Tunnel Alluvioni Recenti Formation Paleo-Tevere2 Formation Pyroclastic deposits Parameters UM Value Parameters UM Value Parameters UM Value TA Concentration % 1.3 TA
Concentration % 1.5 TA Concentration % 1.8
FER 3 FER 3.4 FER 2 FIR % 20 FIR % 21 FIR % 32 Surfactant Volume lt/ring 49 Surfactant Volume lt/ring 56 Surfactant Volume lt/ring 100
Table 8. Soil Conditioning Parameters Odd Track Tunnel Alluvioni Recenti Formation Paleo-Tevere2 Formation Parameters UM Value Parameters UM Value TA Concentration % 1.5 TA
Concentration % 1.5
FER 3.1 FER 3.0 FIR % 27 FIR % 20 Surfactant Volume lt/ring 59 Surfactant Volume lt/ring 45
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Dispari
Muck Weight and Liquid Injected Analisys
0
20
40
60
80
100
120
836 876 916 956 996 1036 1076 1116 1156 1196 1236 1276 1316 1356 1396 1560 1600 1640 1680 1720 1760 1800 1840 1880 1920 1960 2000 2040 2080 2120 2160 2200 2240 2280 2320 2360 2400 2440
Ring n°
Mu
ck
We
igh
t (t
on
)
0
0,5
1
1,5
2
2,5
3
3,5
EP
B p
res
su
re t
op
(b
ar)
Muck w eight (ton)Real Muck w eight (ton)Total Weight w ith Liquid (ton)EPB Pressure top (bar)
![Page 11: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/11.jpg)
Therefore, from an operational point of view, this situation has required a type of conditioning characterized by:
- injection of foam exclusively through the 5 dedicated lines on the cutterhead, in order to ensure entry of already conditioned material in the excavation chamber;
- rather low FER values (3 – 4), aimed obtaining a rather “thick” and stable foam, and above all to prevent the formation of air in the excavation chamber, also improving the maintenance of support pressure on the excavation face (see Figures 12 and 13);
- a degree of conditioning that is not too high (FIR: 20-35), with no excessive injection of foam, in order to prevent its separation from the material (see Figures 12 and 13);
- conducting excavation without injecting water on the face and/or in the chamber together with the foam, in order to prevent phenomena of separation between the liquid phase and the material excavated, which would have led to the worsening of its homogeneity inside the chamber. This aspect is enhanced in the clay soils of the Alluvioni Recenti sediments;
- conditioning obtained without the use of polymers added to the foam; - use of higher volumes of foam through the nozzles located in the central part of the cutterhead, in order to
keep the central load windows free, limiting possible blockage caused by the excavation material. In some cases, the occurrence of this phenomenon led to an overall worsening of the TBM excavation parameters, with considerable increases both in the thrust rates and in torque, and consequently the reduction of the penetration speed, making maintenance measures necessary, executed in hyperbaric conditions, for the removal and cleaning of the windows.
Figure 12. Even Track – Soil conditioning Parameters
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Pari
Soil Conditioning Parameters
0
10
20
30
40
50
60
70
80
90
811 851 891 931 971 1011 1051 1091 1131 1171 1211 1251 1291 1331 1371 1532 1572 1612 1652 1692 1732 1772 1812 1864 1904 1944 1984 2024 2064 2104 2144 2184 2224 2264
Ring (n°)
FIR
( %
)
0
2
4
6
8
10
12
14
FE
R /
Liq
uid
Inje
cted
FIR ( % )FERLiquid Injected (mc)
![Page 12: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/12.jpg)
Figure 13. Odd Track – Soil conditioning Parameters
METROPOLITANA DI ROMA - LINEA B1 -Galleria Binario Dispari
Soil Conditioning Parameters
0
10
20
30
40
50
60
70
80
90
830 870 910 950 990 1030 1070 1110 1150 1190 1230 1270 1310 1350 1390 1559 1599 1639 1679 1719 1759 1799 1839 1892 1932 1972 2012 2052 2092 2132 2172 2212 2252 2292 2332 2372 2412
Ring (n°)
FIR
( %
)
0
1
2
3
4
5
6
7
8
9
10
FE
R /
Liq
uid
inje
cte
d (
mc
)
FIR ( % )FERLiquid injected (mc)
![Page 13: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/13.jpg)
Figure 14. Alluvioni Recenti sediments (clayey silts) Figure 15. PaleoTevere 2 (gravel) inside the on the surface TBM belt exit of the screw muck pit
CRITICAL ASPECTS IN THE ROUTE
The route of the tunnels examined here has some zones that should be considered as especially critical; these are the stretch crossing under the Rome-Florence railway line and under the foundations of the Ponte delle Valli bridge and of some important historical buildings.
The stretch under the Ponte delle Valli was especially difficult due to the direct interference between the Odd Track Tunnel (at a higher level) and the piles foundation of the bridge.
The design phase provided for consolidation measures for the distribution of the loads on the piles interfering with the excavation face both depth-wise and far from the tunnel, as well as improving the geotechnical characteristics of the soil. Furthermore, an operational procedure was defined and implemented for stopping the advance of the TBM at the points where the foundation piles were encountered at the face, with intervention in hyperbaric conditions to remove the metal reinforcement of the piles that could have damaged the cutterhead.
The inspections described above showed the presence of concrete foundation piles at the excavation face level but without metallic reinforcement, so that boring could be conducted without special measures.
Nevertheless, the effectiveness of the consolidation was confirmed during excavation by the variation of some parameters, such as:
- the increase of the thrust by 75% (from 18 MN to 31 MN); - the reduction of the speed of advance by 50% (from 35 mm/min to 19 mm/min); - the increase of torque by 80% ( from 2.4 MN*m to 4.3 MN*m). Furthermore, the cement and chemical mixtures present in the soil after consolidation underwent
“reactivation” due to the conditioning used during excavation, thus producing a gradual obstruction of the TBM windows (as confirmed by subsequent inspections under pressurized conditions) and thus contributing to the worsening of excavation performance rates. Therefore, while on the one hand the improvement of the geotechnical conditions of the soil after treatment helped to guarantee practically zero surface settlements, on the other it definitely had a negative impact on the excavation operations.
In the final part of the two tunnels, the TBMs crossed under a series of buildings having considerable historical and architectural importance, with serious interference occurring due to the very shallow layer between the top of the excavation and the base level of the foundations (from 8 to 15 m). Because of this problem, compensation grouting was conducted in these areas, involving injections of pre-treatment and pre-compensation cement mixtures, executed before boring by the TBMs , and aimed to improve the geotechnical characteristics of the soil above the tunnel chambers, and to provide pre-lifting to be exploited during the excavation phase (from 3 to 5 mm).
In order to jointly monitor the effects of the excavation and the Compensation Grouting operations on the soil and the structures, a complex monitoring system consisting of livelometer gauges was installed on the buildings involved, associated with a series of tiltmeters, together with software for data recording and processing, and an automatic system (with optical and acoustic devices) to monitor the threshold values.
![Page 14: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/14.jpg)
Figure 16. Even Track - Hydraulic monitoring cell system
Figure 17. Odd Track - Hydraulic monitoring cell system
As we can see in Figures 16 and 17, the operation of the TBMs caused very slight subsidence in the buildings, much lower than the alert threshold set in the design phase. In particular, the absolute value of the settlements caused after excavation was less than or equal to the lifting induced in the building during the pre-treatment and pre-compensation phases conducted before the excavation in these areas.
The results obtained have therefore ensured the safety of the buildings involved, and the conditions required for undertaking compensation measures were not reached. All this is closely connected with the regular execution of the excavation, which was conducted maintaining the supporting pressure on the face constantly near to or equal to the maximum value set by the designer in the guidelines, and characterized by the constantly lower levels of material removed as well as the complete backfilling of the ring gap with backfilling grout.
SURFACE SETTLEMENTS
FAB 9 ‐ Tazze livellometriche
‐5
‐4
‐3
‐2
‐1
0
1
2
3
4
5
6
7
8
9
10
26/07/10
31/07/10
05/08/10
10/08/10
15/08/10
20/08/10
25/08/10
30/08/10
04/09/10
09/09/10
14/09/10
19/09/10
Quota [mm]
TL901
TL902
TL903
TL904
TL905
TL906
TL907
TL908
TL909
TL910
TL911
TL912
FAB 5 ‐ Tazze livellometriche
‐5
‐4
‐3
‐2
‐1
0
1
2
3
4
5
6
7
8
9
10
21/07/10
31/07/10
10/08/10
20/08/10
30/08/10
09/09/10
19/09/10
Quota [mm]
TL501
TL502
TL503
TL504
TL505
TL506
TL507
TL508
TL509
TL510
TL511
TL512
![Page 15: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/15.jpg)
As we can see in Figures 18 and 19, the above conclusions are confirmed by topographical monitoring on the surface, indicating slight settlement rates along the tunnels, and in any case lower than the design thresholds. These can also be correlated with the slight losses of volume, at between 0.15% and 0.40% (max loss of design volume: 0.60%).
In particular, the settlements and the consequent losses of volume may be considered as insignificant also for the excavations under the areas previously defined as “critical”, providing positive responses on the methodology and conducting of the excavation operations.
Figure 18. Even Track – Surface settlements in tunnel axis Gondar - Annibaliano
Figure 19. Odd Track – Surface settlements in tunnel axis Gondar - Annibaliano
METROPOLITANA DI ROMA ‐ LINEA B1 ‐
Galleria Binario Pari
Surface settlements in tunnel axis Gondar‐Annibaliano
‐20
‐15
‐10
‐5
0
5
875
885
895
905
915
925
935
945
955
965
975
985
995
1005
1015
1025
1035
1045
1055
1065
1075
1085
1095
1105
1115
1125
1135
1145
1155
1165
1175
1185
1195
1205
1215
1225
1235
1245
1255
1265
1275
1285
1295
1305
1315
1325
1335
1345
Ring n°
Surface settlemens (m
m)
ANNIBALIANO
METROPOLITANA DI ROMA ‐ LINEA B1 ‐
Galleria Binario Dispari
Surface settlements in axis tunnel Gondar‐Annibaliano
‐20
‐15
‐10
‐5
0
5886
896
906
916
926
936
946
956
966
976
986
996
1006
1016
1026
1036
1046
1056
1066
1076
1086
1096
1106
1116
1126
1136
1146
1156
1166
1176
1186
1196
1206
1216
1226
1236
1246
1256
1266
1276
1286
1296
1306
1316
1326
1336
1346
1356
1366
1376
1386
Surface settlements (mm)
ANNIBALIANO
![Page 16: Maurizio Monina Remo Grandori Aristodemo Busillo Roberto ...€¦ · 812 852 892 932 972 1012 1052 1092 1132 1172 1212 1252 1292 1332 1372 1542 1582 1622 1662 1702 1742 1782 1822](https://reader034.vdocuments.site/reader034/viewer/2022050609/5fb069d9f3b95a68767fcf39/html5/thumbnails/16.jpg)
As already stated previously, the excavation was, in fact, conducted maintaining the support pressures on the excavation face and backfilling inject pressures behind the lining near or corresponding to the maximum values indicated in the design for the various stretches of tunnel.
Considering the highly “sensitive” nature of the soils excavated, and the rather unfavorable geotechnical characteristics, the result has been the limitation of the volume lost on the front, and in the section deriving from the convergence of the excavation and the TBM', and subsequently, with the final lining ring, reducing surface settlements to very low levels, and providing positive results to the degree of backfilling of the ring gap behind the tunnel lining.