Massaro – since 1967
Bethel Park High SchoolBethel Park, PA
Weekly Progress Slide ShowWeekly Progress Slide ShowMarch 05, 2010
Massaro
From the Old to the New
Massaro
Work Continues in Area F
Massaro
Walls being formed in Area Fg
Massaro
Wall Rebar and Forms continue in Area H
Massaro
Foundation of East Wall in Area H
Massaro
Mud Management in Area Cg
Massaro
Excavations Push Forward
Massaro
Forms are being set and staged across site.
Massaro
Scheduled Work For Next Few Weeks:
• Building foundations and wall formingBuilding foundations and wall forming.• Excavation of areas E,F,D,G, and H.
C ti t k il il t bili ti it• Continue stock pile, soil stabilization items, and back fill operations.
• Temporary Sanitary Tie-in being placed.• Underground building MEP items.g g• Steel Fabrication continues at Sippel Fab.• Plumbing pipes to stage
Massaro• Plumbing pipes to stage.
Thank You The End
By Jeremy Beitery Je e y e teIntern, Massaro CMS, LLC