mary lin elementary school 586 candler park drive phasing plan march 25, 2010
TRANSCRIPT
Site Plan
PhasingPhase 1Site Utilities (Storm Drainage System, Fire Line, Water Line)
Phase 2AConstruction of New 2-Story Classrooms and Support SpacesPaving and Landscaping Improvements.
Phase 2BRenovation of Cafeteria/Kitchen, and Classrooms
Phase 3Select Renovations on Main and Upper Levels, Classrooms and RestroomsGym Renovations
Phase 4AConstruction of New Administration, Media Center, and Connecting CorridorSite Utilities, Paving and Landscaping Improvements
Phase 4BSelect Renovations on the Main Level, Chorus, Band, and Classrooms
Project LocationAerial View with Phases 1 and 2
Phase 1North SiteSite Utilities (storm, fire, water)Sep 23,2013 - Dec 18, 2013
Phase 2ANew 2-Story Classroom AdditionNov 4, 2013 – Jul 1, 2014
Phase 2BRenovation of Cafeteria/Kitchen and ClassroomJul 21, 2014 – Feb 23, 2015