Metropolitan Mine Background
• Operations constrained by geography & the vintage of
facilities - located in residential area
• Large Central Lease (60Mt) area has remained
unmined due to geological features restricting access
• Central Lease Area development (Part 3 Approved),
provides opportunity to continue mining & expand
• Metropolitan Colliery is located in the Southern Coal fields of New South Wales,
Australia
• Production
began in
1888 at
Metropolitan
Mine and
has operated
for 125 years
![Page 3: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/3.jpg)
Metropolitan Mine Plan
3
● Most of future mining
under Sydney Catchment
Authority
● New JOY Longwall Mining
equipment will commence
within the Reservoir
Notification Area (LW 23a)
● Metropolitan Exports
Metallurgical coal via Port
Kembla
● Currently mining LW22b
![Page 4: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/4.jpg)
Stables
![Page 5: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/5.jpg)
Pre 1950
![Page 6: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/6.jpg)
Mine site
6
![Page 7: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/7.jpg)
Proximity to township of Helensburgh
7
![Page 8: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/8.jpg)
Southern Coal Fields – New South Wales
8
![Page 9: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/9.jpg)
Metropolitan Project
● Metropolitan gained Peabody capital approval to
undertake modernization of its infrastructure and to
increase production capacity. The project focused on 7
elements to modernization. Todays presentation will
focus on
– the replacement of the existing Longwall with a JOY state of the
art Long wall,
– safety initiatives
– engineering design and functionality improvements.
– delay in drift completion and alternate transportation
arrangements and engineering challenges
9
![Page 10: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/10.jpg)
Replacement Long wall
● The replacement Long wall was to be transported via the
new drift as part of the Metropolitan expansion project
● JOY were successful in winning the Turn Key contract to
manufacture and supply
– 89 1.75m roof supports (Alternate testing Protocol used)
– AFC and BSL
– 7LS2a Shearer (Landmark, cowl less)
– Macquarie Manufacturing Monorail
– Inhoxihp pump station - monorail mounted
– Ampcontrol Electrics and lighting system
10
![Page 11: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/11.jpg)
Innovations
11
![Page 12: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/12.jpg)
Man Down Technology
● The Metropolitan Contract was specific in relation to the
man down protection in the shearer controller and
required JOY to supply shearer remotes with the
technology.
● During the process Metropolitan drove the compliance to
Australian standards and required functionality between
the remote, shearer and roof supports.
● Final product is a credit to JOY and the Project Team
12
![Page 13: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/13.jpg)
UPS backed Lighting
● Project team wanted to improve the lighting in and
around the longwall during maintenance periods and
loss of power events.
● A plan was developed to utilize Led lights supplied from
Uninterruptable Power supplies from the TG roof
supports to MG Corner and MG Corner to the Freek
Station (First Response Emergency Evacuation Kit)
(CABA)
● Each UPS supplies 4 Led lights for approximately 10
hours operation. Benefits
– In the event of emergency Lighting will remain on
– Permanent lighting during Maintenance activities
– Permanent lighting during breakdowns
13
![Page 14: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/14.jpg)
Outbye lighting layout – 41 ups supplied lights between sub and MG, UPS backed light on every roof support
14
![Page 15: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/15.jpg)
Roof support Testing Protocol
● Pat Solars Twenty Mile underground General Manager developed a
strenuous testing protocol after dealing with significant engineering
failures of Twenty mile roof support bases.
● The testing protocol was focused around the inclusion of blocks to
simulate the maximum amount of transverse and longitudinal
camber (manufacturing tolerances) allowed by the OEM during
manufacture of the base and canopy. The testing cycles were also
increased to 70105 cycles.
● The Metropolitan roof support was designed and manufactured to
meet the stringent testing protocol.
● The roof support passed the testing protocol with minor issues
during testing; 90k cycles were completed without a failure that
would result in the roof support experiencing a catastrophic failure
over its intended design life.
15
![Page 16: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/16.jpg)
Testing Requirments
16
![Page 17: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/17.jpg)
Roof support Tip Pressure
● Metropolitan currently run combination of 1.5m Metropolitan shields
and 1.75 ex Shoeshone shields.
● The existing shields are rated at approximately 800t and
Metropolitan do have significant strata issues due to the lack of
support density the shields are providing
● The opportunity to increase the roof support density was a welcome
relief; the roof supports were specified to provide
Yield – >115t/m2 before the cut;
● During Front End Engineering it was identified that the Gate End
roof support density had decreased from the 115t/m2 required.
● The project team provided guidance and instruction to add an
additional Compensating cylinder on the gate end supports, this
increased the tip pressure from <12t/m2 to >20tm2 and allow the
gate end supports to meet the contracted rate of 115t/m2
17
![Page 18: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/18.jpg)
Double Compensation cylinder – gate end
18
![Page 19: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/19.jpg)
Transportation of the New Longwall
● The expansion project at Metropolitan included the excavation of a
new Man, Material and belt access Drift. This was to be the
transport route to the underground workings for the new longwall.
● The drift project was post poned at the 562m mark until further
notice.
● A detailed analysis of the available options to transport the LW
underground was conducted; identifying 7 possible opportunities
● The safest, Cost effective and least disruptive to the day to day
operations was to transport the new long wall via the existing man
and materials winder.
● The following slides identify safety, productivity and engineering
challenges to transporting the long wall undergound via the man and
materials winder.
19
![Page 20: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/20.jpg)
Man and Material Winder
● The second hand man and material winder was installed
at Metropolitan in 1954, it is currently running under and
exemption from the NSW Department.
● Peabody Energy has committed to the purchase of a
new winder to replace the aging plant.
Challenges
● Remediation work Rail line
● Winder access dimensions
20
![Page 21: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/21.jpg)
Current Risks
LONGWALL
Issue
• Maintaining schedule of longwall equipment transport over and above regular operational
activities
Mitigation
• Weekly operational transportation meeting to focus on objectives
• Underground track repairs completed
• Specialist transportation equipment manufactured for ease of haulage. Low loader
successfully run into mine with PRS base
• Just in time delivery of equipment to surface to lessen burden on yard
21
![Page 22: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/22.jpg)
Rail Remediation work – replacement of old rail.
● Track being broken up ready to lift
22
![Page 23: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/23.jpg)
Each old rail was lifted and replaced
![Page 24: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/24.jpg)
Broken end found during remediation work
![Page 25: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/25.jpg)
Track being reinstalled with new sleepers
![Page 26: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/26.jpg)
Track being ballasted
![Page 27: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/27.jpg)
Winder Window
● The winder portal has height, width, length and weight
limitations
● Due to the limitations of the portal an analysis of the new
long wall equipment was completed identifying the plant
that would be required to be modified, disassembled, or
built underground.
● Equipment in Orange has been modified
27
![Page 28: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/28.jpg)
Winder Window
28
![Page 29: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/29.jpg)
Analysis
New Joy Longwall dimensions and weight QTY Description Length Width Height Weight Comments Action
AFC 80 Pan 1.75 2 1.25 3 OK N/A
1 M/G croner 3.7 3.6 1.55 30 Won't fit in current drift, this item does not lend itself to being cut down Re-engineered and costed
1 T/G tensioner 6.1 3.15 1.1 20 Won't fit in current drift, Base plate to be cut in half, and re attached U/G Re-engineered and costed
1 Ramp pan 4.3 3.1 1.55 12
Won't fit in current drift, could possibly be cut down, have not fully discussed with Joy this option, could be be modified to be half width and either be bolted or pinned together, extra cost Re-engineered and costed
5 Re-router pan 3.6 3.1 1.25 10
Won't fit in current drift, could possibly be cut down, have not fully discussed with Joy this option, could be be modified to be half width and either be bolted or pinned together, extra cost Re-engineered and costed
8 Chain bin 5 1.4 1.8 8
Approximate values Would need to have special bins made up, and then would need to look at handling options with longer lower bins, what machines do we have to this with. Maybe a low loader flat top Re-engineering Required
29
![Page 30: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/30.jpg)
Analysis Cont
BSL 1 Ramp pan OK
1 Crusher 4 2.8 1.9 Ok
1 Delivery OK
1 convex OK
1 concave OK
1 Straight OK
1 mini pans OK
1 Boot end 8 3.2 1.4 OK
2 Chain bin 5 1.5 1.8 8
Approximate values Would need to have special bins made up, and then would need to look at handling options with longer lower bins, what machines do we have to this with. Maybe a low loader flat top Further Revew required
30
![Page 31: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/31.jpg)
Analysis Cont
Roof
supports 77 Run of Face 7.1 1.7 1.8 30
Won't fit down current drift, over weight and too high Will need a low loader flat top, and do something with the weight issue Canopy must come off
special Low loader required
10 Gate end 7.5 1.75 1.8 31
Won't fit down current drift, over weight and too high Will need a low loader flat top, and do something with the weight issue Canopy must come off
special Low loader required
2 Transition shields 7.9 1.7 1.8 31.5
Won't fit down current drift, over weight and too high Will need a low loader flat top, and do something with the weight issue Canopy must come off
special Low loader required
Electrics 1 Tx 10 3.55 2.2 45 Won't fit down current drift
Must be stripped, transported and assembled again underground, special
low loader required
1 Pump DCB 4.5 1.1 1.35 5.5 Ok
1 Face DCB 9.1 1.25 1 9.5 Ok
1 CME 2.5 1 1.3 5 Ok
1 AFC motor Ok
Pumps 2 Pump module 4.5 1.31 1.4 5.2 Ok
2 Tank Module 4.5 1.31 1.4 8 Ok
1 Dump valve pod 2.5 1.31 1.4 3 OK
31
![Page 32: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/32.jpg)
Analysis Cont
Shearer 1 Main body 8.5 1.8 1.4 36 Too heavy to go down current drift
Component Weights and sizes have been calculated will require stripping
2 Ranging arm 3.1 1.7 0.9 10.5 OK Requires Jig
2 Drum 2 2 0.9 4 OK
Mono rail 10 mono rail pump pods 2.3 1.8 0.8 To Big Reengineered
10 Hose cassette 17.4 2.9 2 6.5 tare
Won't fit down current drift Two cassettes in line to accommodate the length of hose required Reengineered
32
![Page 33: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/33.jpg)
33
Roof supports
● The roof supports were manufactured with the intent to install
underground as a fully assembled tested and fit for purpose plant.
● Engineering review identified
– Roof support collapsed 1850mm – Canopy removed 1750mm
– Frames required to ensure the canopy can be transported
underground
– Risk Analysis and Safe Work Procedures developed
– Low Loaders engineered and manufactured for the Base
– Underground crane purchased and installed
![Page 34: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/34.jpg)
Nice New Roof supports
34
![Page 35: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/35.jpg)
What we have to do to them
35
![Page 36: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/36.jpg)
Trials strips completed and SWP developed
36
![Page 37: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/37.jpg)
Procedure in fast forward
37
![Page 38: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/38.jpg)
Procedure in fast forward
38
![Page 39: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/39.jpg)
Procedure in fast forward
39
Position canopy on
frame
![Page 40: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/40.jpg)
Procedure in fast forward
40
Base ready for
transport to site.
![Page 41: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/41.jpg)
Canopy frame design and manufacture
● Transport frame design Considerations
– Remain lower than drift access portal
– Must be able to be transported by the underground battery
hauler and be positioned over the body of the machine.
● Final Design
– 2 Piece design
– Winder frame – carries all components and is lower than
1.45m
– Battery hauler transport plate, locating lugs and securing
points for the winder frame – bottom of the canopy must be
higher than 1.6m.
– Must be able to handle the braking force in event of winder
emergency stop.
41
![Page 42: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/42.jpg)
Final Canopy frame
42
![Page 43: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/43.jpg)
Canopy Frame includes the side shield
43
![Page 44: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/44.jpg)
Roof support Base Transport
● Conceptual design and functional requirement agreed
upon at site
● Engaged Reliance Hexham to complete final engineering
and detailed design of the low loader skip
● Restrictions
– Maximum radius of rail
– Off camber sequential changes in rail height and angle
– Drift has to locations where it flattens and then rolls over causing
clearance issues to the bogie floor and roof support to roof
– Weight – drift Max 22t
44
![Page 45: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/45.jpg)
45
![Page 46: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/46.jpg)
Manufacture
46
![Page 47: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/47.jpg)
Hosing and Cylinders
47
![Page 48: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/48.jpg)
Skip trial
48
![Page 49: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/49.jpg)
Test silhouette of roof support
49
![Page 50: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/50.jpg)
tight
![Page 51: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/51.jpg)
Tight
![Page 52: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/52.jpg)
Tight
![Page 53: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/53.jpg)
Touching but will only scar one shield
![Page 54: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/54.jpg)
First trial
Skip first trial on site was empty – we did not get past the
first turn on surface - Derail
– Jack hammer concrete
54
![Page 55: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/55.jpg)
Second Trial
● Skip second trial – derail
– Increase articulation of bogies
55
![Page 56: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/56.jpg)
Success Third Trial – Pit Bottom reached Empty
56
![Page 57: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/57.jpg)
First Trial entering drift loaded
![Page 58: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/58.jpg)
Shield at lowest travelling height
![Page 59: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/59.jpg)
Shield arrives pit bottom – Relief
![Page 60: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/60.jpg)
60
![Page 61: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/61.jpg)
Underground Crane workshop
● To enable the roof supports to be reassembled
underground an underground crane workshop was built
with a 25tonne crane concrete flooring.
● Process
– Excavate crane workshop to 8m high and support
– Secondary support installed
– Installation of crane frame no ground mounted pedestals
– Concreted floor level
– Wall Cranes installed to assist in the handling of the 160kg pins
– Ventilatation fans installed to allow for welding and other site
works.
61
![Page 62: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/62.jpg)
Underground Crane workshop
62
![Page 63: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/63.jpg)
UG Workshop construction by mine
![Page 64: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/64.jpg)
Assembly of Roof support
● Once the roof supports are underground they are moved
into the underground crane workshop and reassembled
following detailed Safe Work Procedures
● Disassembly = 4.5 hours, position canopy and secure on
frame.
● Assembly = 2 roof supports on day shift, 1 on afternoon
shift and setting up another 2 supports ready for day
work.
64
![Page 65: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/65.jpg)
AFC and BSL
● The AFC and BSL was identified as requiring
modification post mandatory drawing signing, luckily
prior to manufacture identified changes
– Ramp pans separated from bed plate
– TG sliding module and drive module bed frame split.
– Crusher requires rotor and base plate to be split and transported
seperately
– MG Drive base split into 2
– Ramp pan split
– Boot end will stripped into 4 discreet components
65
![Page 66: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/66.jpg)
AFC Transport Sizes
![Page 67: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/67.jpg)
AFC Transport Sizes
![Page 68: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/68.jpg)
Crusher Transport Sizes
![Page 69: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/69.jpg)
Boot End Transport Sizes
![Page 70: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/70.jpg)
Transformer
● Ampcontrol 4.5mva transformer will be required to be
fully stripped
– Remove low and high tension end enclosures
– Remove transformer tank
– Remove tracks
● The transformer tank will be transported on a specifically
manufactured low loader.
70
![Page 71: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/71.jpg)
Transformer dimensions
71
![Page 72: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/72.jpg)
Monorail
– Concertina sections delivered straight to site in discreet
components and assembled underground
– The transportation sleds were designed to transport the trolleys,
drives and sleds underground.
– Suitable 160m heading identified and monorail hung for the
assembly of the monorail underground.
72
![Page 73: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/73.jpg)
Monorail sled base
73
![Page 74: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/74.jpg)
Drive Transport Sled
74
![Page 75: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/75.jpg)
75
![Page 76: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/76.jpg)
Shearer
● Shearer chassis weighs 31.1tonnes without Ranging
arms (to be transported separately)
● Remove
– Down Drives – 4.3 t
– Sloughing Plate – 1.5 t
– Ranging arm cylinders - 1.6 t
– Faceside beams and skid shoe – 0.5 t
● Shearer will then be approximately 23 t, we will then
continue to strip until the machine weighs in at 22t.
76
![Page 77: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/77.jpg)
“A carelessly planned project takes three times longer to complete than
expected; a carefully planned project takes only twice as long
77
When presented with a challenge look
at it as an opportunity to change others
attitudes and expectations.
Thankyou for your valuable time!
Questions??
![Page 78: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/78.jpg)
78
![Page 79: Martin kime, metropolitan mine peabody energy](https://reader034.vdocuments.site/reader034/viewer/2022051515/54c368934a79599f298b4671/html5/thumbnails/79.jpg)
www.PeabodyEnergy.com