![Page 1: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/1.jpg)
MOCACSept 21, 2015
Market/Octavia -Octavia Boulevard Enhancement Project
![Page 2: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/2.jpg)
Enhancement Project Goals
Improve comfort & safety for all modes
Support traffic calming and parcel development needs
Data-driven assessment of Boulevard on 10th anniversary
Broaden awareness/consensus for upcoming projects
Octavia Boulevard Enhancement Project
PPA’s submitted
![Page 3: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/3.jpg)
7 pedestrian bulb-outs CAC Nov ’14 resolution / Feb ‘15 approval 2016 construction
Hayes Street Pedestrian Improvements
![Page 4: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/4.jpg)
Design Scope
N
Octavia Boulevard Enhancement Project
![Page 5: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/5.jpg)
Octavia Boulevard Enhancement Project
“Quick and Effective” treatments nearly completed
Hayes & Laguna pedbulbs: 2016 construction
Fell/Oak and other circulation changes undergoing environmental review
Market/Octavia: no near-term changes proposed, developing full plans for 2017 construction that include Guerrero/Laguna
![Page 6: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/6.jpg)
Octavia Boulevard Enhancement Project
![Page 7: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/7.jpg)
Project ScheduleSubject to Change
Octavia Boulevard Enhancement Project
![Page 8: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/8.jpg)
Thank You
www.sfmta.com/octavia
Thank You
www.sfmta.com/octavia
Octavia Boulevard Enhancement Project
![Page 9: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/9.jpg)
• 2013 List approved by SFCTA
• Additional funding led to 2014 revisions
• Current plans
M/O Project List
Project in design/planning
![Page 10: Market/Octavia - Octavia Boulevard Enhancement Projectdefault.sfplanning.org/Citywide/Market_Octavia/CAC/... · Octavia Boulevard Enhancement Project “Quick and Effective” treatments](https://reader034.vdocuments.site/reader034/viewer/2022042920/5f650a8d34e4166cbe1b7552/html5/thumbnails/10.jpg)
Temporary Treatments