march 28, 2014

16
MARCH 28, 2014 John P. Buechler NYISO EXECUTIVE REGULATORY POLICY ADVISOR IPSAC WebEx FERC Order 1000: Interregional Planning Implementation Update

Upload: moshe

Post on 07-Jan-2016

39 views

Category:

Documents


1 download

DESCRIPTION

March 28, 2014. John P. Buechler. NYISO EXECUTIVE REGULATORY POLICY ADVISOr. IPSAC WebEx. FERC Order 1000: Interregional Planning Implementation Update. Overview. Order 1000: Background Summary of Order 1000 Interregional Planning Requirements Northeast ISO/RTO Compliance Filings - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: March 28, 2014

M A R C H 2 8 , 2 0 1 4

John P. BuechlerN Y I S O E X E C U T I V E R E G U L A T O R Y P O L I C Y A D V I S O R

IPSAC WebEx

FERC Order 1000:Interregional Planning Implementation Update

Page 2: March 28, 2014

Overview

• Order 1000: Background

• Summary of Order 1000 Interregional Planning Requirements

• Northeast ISO/RTO Compliance Filings

• Implementation Challenges

• Next Steps

2

Page 3: March 28, 2014

Order 1000 Background

3

Page 4: March 28, 2014

The Road to FERC Order 1000• FERC Order 888 - 1996

– Open Access

• FERC Order 2000 - 2000– Formation of RTOs

• Energy Policy Act 2005 - 2005– FERC Backstop Transmission Siting Authority– FERC Incentive Rates for Transmission

• FERC Order 890 - 2007– Regional Planning– Economic Planning

• FERC Order 1000 - 2011– Regional planning & cost allocation revisited and made mandatory– Mandatory interregional planning & cost allocation– Added transmission planning to achieve public policy goals– Elimination of right-of-first-refusal (ROFR) for incumbent TOs

4

Page 5: March 28, 2014

Order 1000: Background

• FERC Order 1000: Final Rule on Transmission Planning & Cost Allocation– Issued on 7/21/11 (Docket RM10-23-000)– Builds on the requirements of Order 2000 and Order 890

• Key Provisions– Establishes a Regional Planning requirement for all FERC jurisdictional

Transmission Providers– Requires a public policy transmission planning process – Requires comparable treatment for incumbents & non-incumbents– Requires an expanded interregional planning process– Establishes six principles for regional and interregional cost allocation– Requires cost allocation methodology for planned regional and

interregional projects

5

Page 6: March 28, 2014

Summary of Order 1000Interregional Requirements

6

Page 7: March 28, 2014

Planning • Each transmission provider must develop further procedures with each of

its neighboring regions within its Interconnection– Final Rule identifies a number of specific requirements, including:

• Data sharing on a regular basis—at least annually• Sharing of information on regional needs and potential solutions• A formal procedure for the “identification and joint evaluation of interregional

facilities that may be more efficient or cost effective solutions to regional needs”• Transparency – post information on a website

• Separate interregional planning agreements are not required– An interregional “plan” is not required

• Multilateral or interconnection-wide planning is encouraged —but not required

• An interregional stakeholder process is encouraged

• Jurisdictional entities to attempt to develop interregional coordination procedures with neighbors in another country

7

Page 8: March 28, 2014

Planning, cont.

Procedural Framework Under the Final Rule:• A developer must first propose an interregional project in each regional

planning process

• The interregional evaluation must be conducted in the “same general timeframe” as the regional evaluations– FERC declines to set a specific timeline and leaves that to the regions

• An interregional project must first be selected in both of the regional planning processes in order to receive inter-regional cost allocation

8

Page 9: March 28, 2014

Interregional Cost Allocation

General Requirements:• Transmission providers in each pair of neighboring regions to develop a

mutually agreeable cost allocation methodology for a transmission facility located in both regions

• Multi-lateral cost allocation is encouraged—but not required

• Final Rule does not propose a uniform methodology – Interregional cost allocation methodology may be different from the

respective regional methodologies– Cost allocation for a region’s share of an interregional facility may differ

from the cost allocation for a regional facility

• All proposals must satisfy Six Interregional Cost Allocation Principles

9

Page 10: March 28, 2014

Northeast ISO/RTOs Compliance Filings

10

Page 11: March 28, 2014

Compliance Filings Based on the Northeast Protocol• The Northeast ISO/RTO Planning Coordination Protocol already met

many of the Interregional Planning requirements of the Final Rule– Some modifications/clarifications were made to comply with Order 1000’s procedural

framework (New Section 7), and data sharing requirements (modified Section 3)– Revisions to individual Tariffs were also needed—primarily to incorporate an

interregional cost allocation methodology

• Existing provisions which exceed Order 1000 requirements were retained, including:– The existing interregional stakeholder process (IPSAC)– Periodic issuance of the Northeast Coordinated System Plan (NCSP)– Coordination of interconnection and transmission service requests

• Our Canadian neighbors expressed their willingness to continue participation in interregional planning activities taking place under the Protocol

11

Page 12: March 28, 2014

Northeast Compliance Activities

• Northeast ISO/RTOs prepared modifications to the existing Northeast Protocol to address Order 1000 requirements

• Interregional cost allocation was developed in consultation with the Transmission Owners in each region

• Stakeholder input was discussed through numerous IPSAC and regional stakeholder meetings– Beginning in November 2011

• Compliance filings were made by ISO-NE, NYISO an PJM as well as the TOs in each region on July 10, 2013

• Still awaiting FERC approval

12

Page 13: March 28, 2014

Implementation Challenges

13

Page 14: March 28, 2014

Implementation Challenges• Implementation of changes to regional planning in parallel with

changes to interregional planning– Regional planning is the foundation for interregional planning under

Order 1000– Order 1000 requires significant changes to the ISO/RTOs’ regional

planning processes

• Reconciliation of differences in regional practices and assumptions

• Synchronization of interregional planning timeline with regional planning cycles

• Development of selection procedures for the “more efficient or cost effective transmission project”

14

Page 15: March 28, 2014

Next Steps

15

Page 16: March 28, 2014

Next Steps• While awaiting FERC approval of Order 1000 compliance

filings, ISO-NE, NYISO and PJM are examining ways to improve interregional planning processes and procedures

• New Section 7 of the Protocol may require process modifications in the following areas: – Review of regional needs and solutions– Data & information exchange– Joint analysis and consideration of potential interregional

transmission projects– Coordination of regional consideration of interregional transmission

projects

16