1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com March 27, 2019 Robert Welch Project Manager City of Beverly Hills 345 Foothill Road Beverly Hills, CA 90210 Joseph DeMello Director, Construction Manager Westside Purple Line Extension Section 1 Los Angeles County Metropolitan Transportation Authority One Gateway Plaza, 17 th Floor Los Angeles, CA 90012 Subject: Segment 1 - Purple Line Extension Project ICM Weekly Report March 17, 2019 March 23, 2019 Dear Mr. Welch and Mr. DeMello, Environmental Intelligence, LLC (EI) has been retained by the City of Beverly Hills (COBH) and the Los Angeles County Metropolitan Transportation Authority (Metro) to serve as the independent compliance monitor (ICM) during construction of the Purple Line Extension Project. Monitoring is required to ensure construction is in compliance with (1) the Memorandum of Agreement (MOA) for Advance Utilities Relocation Phase of the Purple Line Extension Project Segment 1 Between the City of Beverly Hills and the Los Angeles Metropolitan Transportation Authority (City Agreement No. 452-14), and (2) the MOA for Contract C1045 of the Purple Line Extension Project Segment 1 Between the City of Beverly Hills and the Los Angeles County Metropolitan Transportation Authority (City Agreement No. 66-16). The following information summarizes the ICM monitoring activities that occurred at the Segment 1 site (La Cienega Station site) during the week of March 17, 2019 March 23, 2019. No construction activities were conducted on March 17. Construction activities during the week included excavating and lagging below deck in the Gale shaft, stockpiling soil in the Gale yard, hoisting soil, hauling soil offsite, materials deliveries, lowering and setting wood beams, building timber mats in the Gale yard, cleaning and sweeping the perimeter of the Gale and La Cienega yards, mechanical work on heavy equipment, assembling and disassembling the North Gale Drive closure, and Ump repair/MPBX installation. EI ICMs were present on site during all construction activities and conducted routine noise measurements at selected noise monitoring locations as well as compliance checks in accordance with the MOAs and associated attachments, exhibits, traffic closure notifications, and traffic management plans. At the conclusion of each work shift, daily monitoring reports were prepared by the ICM. Any violations for that date were also prepared by the ICM then reviewed and submitted to the COBH and Metro by EI’s Project Manager. VIOLATION SUMMARY During the week, EI ICMs identified a total of one (1) violation during construction activities. Table I provides a summary of the violation identified during the week of March 17, 2019 March 23, 2019 and Exhibit 1 provides a location map for the submitted violation. Details for the violation are included as Attachment A. Daily monitoring reports and photographs of construction activities are provided as Attachment B. Daily noise monitoring data are provided in Attachment C.

Upload: others

Post on 17-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    March 27, 2019

    Robert Welch

    Project Manager

    City of Beverly Hills

    345 Foothill Road

    Beverly Hills, CA 90210

    Joseph DeMello

    Director, Construction Manager

    Westside Purple Line Extension Section 1

    Los Angeles County Metropolitan Transportation Authority

    One Gateway Plaza, 17th Floor

    Los Angeles, CA 90012

    Subject: Segment 1 - Purple Line Extension Project ICM Weekly Report

    March 17, 2019 – March 23, 2019

    Dear Mr. Welch and Mr. DeMello,

    Environmental Intelligence, LLC (EI) has been retained by the City of Beverly Hills (COBH) and the Los

    Angeles County Metropolitan Transportation Authority (Metro) to serve as the independent compliance

    monitor (ICM) during construction of the Purple Line Extension Project. Monitoring is required to ensure

    construction is in compliance with (1) the Memorandum of Agreement (MOA) for Advance Utilities

    Relocation Phase of the Purple Line Extension Project – Segment 1 – Between the City of Beverly Hills

    and the Los Angeles Metropolitan Transportation Authority (City Agreement No. 452-14), and (2) the

    MOA for Contract C1045 of the Purple Line Extension Project – Segment 1 – Between the City of Beverly

    Hills and the Los Angeles County Metropolitan Transportation Authority (City Agreement No. 66-16). The

    following information summarizes the ICM monitoring activities that occurred at the Segment 1 site (La

    Cienega Station site) during the week of March 17, 2019 – March 23, 2019. No construction activities

    were conducted on March 17.

    Construction activities during the week included excavating and lagging below deck in the Gale shaft,

    stockpiling soil in the Gale yard, hoisting soil, hauling soil offsite, materials deliveries, lowering and setting

    wood beams, building timber mats in the Gale yard, cleaning and sweeping the perimeter of the Gale and

    La Cienega yards, mechanical work on heavy equipment, assembling and disassembling the North Gale

    Drive closure, and Ump repair/MPBX installation. EI ICMs were present on site during all construction

    activities and conducted routine noise measurements at selected noise monitoring locations as well as

    compliance checks in accordance with the MOAs and associated attachments, exhibits, traffic closure

    notifications, and traffic management plans. At the conclusion of each work shift, daily monitoring reports

    were prepared by the ICM. Any violations for that date were also prepared by the ICM then reviewed and

    submitted to the COBH and Metro by EI’s Project Manager.

    VIOLATION SUMMARY

    During the week, EI ICMs identified a total of one (1) violation during construction activities. Table I

    provides a summary of the violation identified during the week of March 17, 2019 – March 23, 2019 and

    Exhibit 1 provides a location map for the submitted violation. Details for the violation are included as

    Attachment A. Daily monitoring reports and photographs of construction activities are provided as

    Attachment B. Daily noise monitoring data are provided in Attachment C.

  • Robert Welch

    Joseph DeMello

    March 27, 2019

    Weekly_Report_Section_1_0317-0323_EI01_20190327

    CONCLUSION

    To date, 201 violations have been issued, 18 of which have been rescinded since the beginning of

    construction on the C1045 Contract for the Purple Line Extension Project – Segment 1. Project construction

    activities are ongoing and EI ICMs continue to monitor all construction activities applicable to the MOAs

    on a daily basis.

    If you have any questions or comments regarding this letter, please contact me directly at 310.469.8989 or

    [email protected].

    Sincerely,

    ENVIRONMENTAL INTELLIGENCE, LLC

    Jeremiah George

    Project Manager

    Attachments: Attachment A: Violations

    Attachment B: Daily Monitoring Reports

    Attachment C: Noise Monitoring Data Log

    cc: Valerie Mudegoren, City of Beverly Hills

    Nell Mardirosian, Los Angeles County Metropolitan Transportation Authority

    Michelle Marquez-Riley, Los Angeles County Metropolitan Transportation Authority

    Candace Lee, Los Angeles County Metropolitan Transportation Authority

    Brett Barnett, Psomas

    Bill Zein, Psomas

    Alex Kay, City of Beverly Hills

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    TABLE I: VIOLATION SUMMARY (MARCH 17 – MARCH 23, 2019)

    Violation

    ID Date Time ICM Location Condition Violated

    Iteration -

    Violation Metro Response

    201 3/19/2019 07:34 Annamarie

    Hand 112 N. Gale Dr.

    Article XIIi - Haul

    Routes and

    Overload Routes

    3 - $25,000

    Violation

    “In response to Violation #201, STS and Metro

    agree with this violation. STS will continue to

    remind trucking subs about approved haul

    routes in the COBH.”

  • Exhibit 1 : Violation Location (March 17 - March 23, 2019)Section 1 - La Cienega Station | City of Beverly Hills, CA

    SOUR

    CE: bin

    g Maps

    , ESRI W

    orld Tra

    nsporta

    tion an

    d World

    Image

    ry Base

    Maps,

    LACMT

    A, City o

    f Bever

    ly Hills

    !( Violation Location (with Violation ID)

    Environ

    menta

    l Intellig

    ence. I

    :\City o

    f Bever

    ly Hills\

    Complia

    nce Mo

    nitoring

    Svc R

    FQ 17

    -3 - Ma

    rch 20

    17\02_

    GIS_Da

    ta\maps

    \2019\

    Weekly

    Reports

    \Sectio

    n1_LaC

    ienega

    \20190

    317_to

    _20190

    323\Ex

    h01_Vi

    ol_EI01

    _20190

    326.mx

    d

    City ofLos AngelesCity ofBeverly Hills

    «0 300150 Feet1:1,800 1 in = 150 feet

    Updated: 3/26/2019

    Coordin

    ate Sy

    stem: NA

    D 1983

    StateP

    lane C

    alifornia

    V FIPS

    0405

    Feet, P

    rojectio

    n: Lam

    bert Co

    nforma

    l Conic,

    Datum

    : North

    Americ

    an 198

    3

  • ICM Violation Form - Section 1 DB MOA 66-17 (1)

    Latitude:Longitude:Elevation: 41.8329391479492

    34.0656-118.374124

    UID:2902  Date:3/19/2019  ICM Violation Form - Section 1 DB MOA 66-17

    NotesViolation ID: 201At 07:34 hours, the ICM Annamarie Hand observed a haul truck driving southbound on N. Gale Dr. from San Vicente Blvd. Gale Dr. is not an approved overload/oversized vehicle route, therefore, driving oversized vehicles down this residential street is a violation of Article XII and Exhibits A and E of the MOA. The ICM notifies Metro Inspector German Garcia and STS Superintendent Howard Jordan of the violation. This is the third incidence of this violation at this location within the last 10 days.

    Violation Details1. Violation ID 2012. Violation Iteration 3 - $25,0000 Violation3. Time of Violation 7:344. Address 112 N Gale

    Applicable Measures5. Memorandum of Agreement No. 66-17 Article XIIi - Haul Routes and Overload Routes•6. Exhibit A: PDD Permit and City of Beverly Hills Conditions for Approval

    Hauling Routes (See also Article XII of MOA)•

    7. Exhibit C: Detour Routes During Full Closures of Wilshire Boulevard

    Not Applicable•

    8. Exhibit D: Saban Theatre Pedestrian Access Plan Not Applicable•9. Exhibit E: Metro 5-Step Noise Control Plan Hauling and Staging•10. Other Plans Not Applicable•11. Other Plan Description

    Attachment AViolations

    This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019)1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931 1/1

    Report Tracking: Created by Annamarie Hand on 3/19/2019 5:44:47 AM, Approved by Jeremiah George on 3/20/2019 5:37:49 AM

  • This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    1/13

    Attachment B Daily Monitoring Reports

    3/17/2019 - 3/23/2019

    Summaries (11)

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Monday, March 18, 2019

    Daniel Chang

    La Cienega Station

    05:15:00 to 14:30:00

    Yes

    Contractors/Subcontractors: STS, Century Sweeping, Mad Transportation, Kleinfelder

    Representatives On-Site: Alex Morales (STS); Grover Williams (Kleinfelder); Lorena Vella (STS); German Garcia (Metro)

    Work Location(s): Gale yard; below deck along Wilshire Boulevard; and North Gale Drive closure

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 05:15 hours to 14:30 hours on March 18th, 2019. EI ICM Daniel Chang met with STS foreman Alex Morales to discuss the day’s activities. At the beginning of the shift, the ICM calibrated the sound meter at 93.9 dB (to 94.00 dB).

    Work for the day included mucking underground, hoisting of soil, load out, hauling of soil off site, pipe and sand delivery, stockpiling of soil in Gale yard, cleaning and sweeping perimeter of Gale yard, lowering and setting wooden beams, mechanical work on heavy machinery and equipment, and assembling and disassembling the closure on North Gale Drive.

    The road closure on Wilshire Boulevard was set up at approximately 05:40 hours. The first haul trucks arrived on site at 06:05 hours. STS began operating the crane at 06:50 hours.

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Monday, March 18, 2019

    Christian Elgabalawi

    La Cienega Station

    13:45:00 to 00:45:00

    Yes

    Contractors/Subcontractors: STS

    Representatives On-Site: Bill Dimalanta (STS); Darrell Lee (STS); Richard Garcia (Metro); Adnan Aldwir (Psomas)

    Work Location(s): Gale yard; below deck along Wilshire Blvd; road closure on North Gale Drive.

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 13:45 hours to 00:45 hours on March 18, 2019. EI ICM Christian Elgabalawi met with Bill Dimalanta to discuss the day’s activities. At the beginning of the shift, the ICM calibrated the sound meter at 94.00 dB (to 94.00 dB).

    Work for the day included spoils excavation and stockpiling within the Gale yard and lagging below deck in the Gale shaft.

    The Gale Drive closure was removed at 14:45 hrs.

    http://www.enviro-intel.com/http://www.enviro-intel.com/

  • This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    2/13

    Attachment B Daily Monitoring Reports

    3/17/2019 - 3/23/2019

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Tuesday, March 19, 2019

    Annamarie Hand

    La Cienega Station

    05:15:00 to 14:00:00

    No

    Contractors/ Subcontractors: STS, Century Sweeping, SSC Trucking, FTI Trucking; Miranda Trucking

    Representatives On-Site: Alex Morales (STS); Lorena Vela (STS); Adnan Aldwir (Psomas); Martin Mai (PSOMAS); German Garcia (Metro); Howard Jordan (STS); Grover Williams (Kleinfelder); Art Gomez (Kleinfelder); Thomas Smith (Kleinfelder)

    Work Location(s): Gale yard; North Gale Drive closure; below deck along Wilshire Blvd.

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 05:15 hours to 14:00 hours on March 19th, 2019. EI ICM Annamarie Hand met with STS Foreman Alex Morales to discuss the day’s activities. At the beginning of the shift, ICM Annamarie Hand calibrated the sound meter to 94.00 dB.

    The North Gale closure was set up at 05:50 hours and included 4 additional sound barriers. Haul trucks arrived at 06:10 hours. The crane started at 06:55 hours.

    Work for the day included excavating below deck, lagging, hauling equipment into Gale yard shaft, building timber mats in the yard, and hauling dirt from Gale yard shaft and haul trucks moving dirt from Gale yard.

    Violation ID: 201 At 07:34 hours, the ICM Annamarie Hand observed a haul truck driving southbound on N. Gale Dr. from San Vicente Blvd. Gale Dr. is not an approved overload/oversized vehicle route, therefore, driving oversized vehicles down this residential street is a violation of Article XII and Exhibits A and E of the MOA. The ICM notified Metro Inspector German Garcia and STS Superintendent Howard Jordan of the violation. This is the third incidence of this violation at this location within the last 10 days.

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Tuesday, March 19, 2019

    Daniel Chang

    La Cienega Station

    13:30:00 to 00:00:00

    Yes

    Contractors/Subcontractors: STS, PSOMAS, Century Sweeping

    Representatives On-Site: Bill Damalanta (STS); Alex Morales (STS); Richard Garcia (Metro); Adnin Aldwir (PSOMAS); Marvin Mai (PSOMAS); Lorena Vella (STS)

    Work Location(s): North Gale Drive enclosure; Gale yard; below deck along Wilshire Blvd

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 13:30 hours to 00:00 hours on March 19th, 2019. EI ICM Daniel Chang met with STS superintendent Bill Damanlata to discuss the day’s activities. At the beginning of the shift, the ICM calibrated the sound meter at 93.9 dB (to 94.00 dB).

    Work for the day included hoisting and stockpiling soil in the Gale yard, hauling of soil off site, lowering wooden beams, drilling wooden beams, placing matting underground; lowering gravel, setting gravel underground, disassembling the North Gale Drive closure, hoisting machinery and equipment into the Gale yard shaft, cleaning heavy machinery, and excavation below deck. The construction street sweeper also cleaned the adjacent work areas surrounding the La Cienega and Gale yards.

    The closure on North Gale Drive was removed at approximately 15:15 hours.

    http://www.enviro-intel.com/

  • This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    3/13

    Attachment B Daily Monitoring Reports

    3/17/2019 - 3/23/2019

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Wednesday, March 20, 2019

    Annamarie Hand

    La Cienega Station

    05:15:00 to 14:15:00

    Yes

    Contractors/ Subcontractors: STS, Century Sweeping, SSC Trucking, FTI Trucking; Miranda Trucking

    Representatives On-Site: Alex Morales (STS); Lorena Vela (STS); Adnan Aldwir (Psomas); Marvin Mai (Psomas); German Garcia (Metro); Howard Jordan (STS); Alex Kay (COBH); Drew Polley (Kroner)

    Work Location(s): Gale yard; North Gale Drive closure; below deck along Wilshire Blvd.

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 05:15 hours to 14:15 hours on March 20th, 2019. EI ICM Annamarie Hand met with STS Foreman Alex Morales to discuss the day’s activities. At the beginning of the shift, ICM Annamarie Hand calibrated the sound meter to 94.00 dB.

    The North Gale closure was set up at 05:38 hours and included 4 additional sound barriers. Haul trucks arrived at 06:02 hours. The crane started at 06:55 hours. Its use did not produce a noise exceedance. Sound panels were taken down at 8:55 hours.

    Work for the day included excavating below deck, lagging, hauling equipment into Gale yard shaft, hauling dirt from Gale yard shaft and haul trucks moving dirt from Gale yard.

    Note: Precipitation in the late morning/ early afternoon interrupted recordings.

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Wednesday, March 20, 2019

    Daniel Chang

    La Cienega Station

    13:45:00 to 23:30:00

    Yes

    Contractors/Subcontractors: STS, PSOMAS, Century Sweeping

    Representatives On-Site: Bill Damalanta (STS); Alex Morales (STS); Richard Garcia (Metro); Adnin Aldwir (PSOMAS); Marvin Mai (PSOMAS); Lorena Vella (STS); Art Moreno (STS)

    Work Location(s): North Gale Drive enclosure; Gale yard; below deck along Wilshire Blvd.

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 13:45 hours to 23:30 hours on March 20th, 2019. EI ICM Daniel Chang met with STS superintendent Bill Damanlata to discuss the day’s activities. At the beginning of the shift, the ICM calibrated the sound meter at 93.9 dB (to 94.00 dB).

    Work for the day included hoisting and stockpiling soil in the Gale yard, hauling of soil off site, timber delivery, lowering wooden beams, drilling wooden beams, placing matting underground; lowering gravel, setting gravel underground, disassembling the North Gale Drive closure, hoisting machinery and equipment into the Gale yard shaft, cleaning heavy machinery, and excavation below deck. The construction street sweeper also cleaned the adjacent work areas surrounding the La Cienega and Gale yards.

    The closure on North Gale Drive was removed at approximately 15:30 hours.

    http://www.enviro-intel.com/

  • This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    4/13

    Attachment B Daily Monitoring Reports

    3/17/2019 - 3/23/2019

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Thursday, March 21, 2019

    Annamarie Hand

    La Cienega Station

    05:15:00 to 13:00:00

    Yes

    Contractors/ Subcontractors: STS, Century Sweeping, SSC Trucking, FTI Trucking; Miranda Trucking

    Representatives On-Site: Alex Morales (STS); Lorena Vela (STS); Adnan Aldwir (Psomas); Marvin Mai (Psomas); German Garcia (Metro); Howard Jordan (STS); Alex Kay (COBH); Andrea Morales (Kroner); Howard Jordan (STS)

    Work Location(s): Gale yard; North Gale Drive closure; below deck along Wilshire Blvd.

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 05:15 hours to 13:00 hours on March 21st, 2019. EI ICM Annamarie Hand met with STS Foreman Alex Morales to discuss the day’s activities. At the beginning of the shift, ICM Annamarie Hand calibrated the sound meter to 94.00 dB.

    The North Gale closure was set up at 05:45 hours and included 4 additional sound barriers. Haul trucks arrived at 06:01 hours. The crane started at 06:55 hours. Its use did not produce a noise exceedance. Sound panels were taken down at 11:00 hours.

    Work for the day included deliveries of timber to the yard, excavating below deck, lagging, hauling equipment into Gale yard shaft, hauling dirt from Gale yard shaft and haul trucks moving dirt from Gale yard.

    Note: due to precipitation throughout the early morning/ early afternoon, readings were not taken.

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Thursday, March 21, 2019

    Christian Elgabalawi

    La Cienega Station

    12:45:00 to 23:00:00

    Yes

    Contractors/Subcontractors: STS; MAD Trucking

    Representatives On-Site: Bill Dimalanta (STS); Darrell Lee (STS); Richard Garcia (Metro); Adnan Aldwir (Psomas)

    Work Location(s): Gale yard; below deck along Wilshire Blvd; road closure on North Gale Drive.

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 12:45 hours to 23:00 hours on March 21, 2019. EI ICM Christian Elgabalawi met with Bill Dimalanta to discuss the day’s activities. At the beginning of the shift, the ICM calibrated the sound meter at 94.00 dB (to 94.00 dB).

    Work for the day included spoils excavation and stockpiling within the Gale yard; hauling of excavated spoils from the Gale yard; lagging below deck in the Gale shaft.

    At 15:30 hours, The ICM Christian Elgabalawi found graffiti on a City of Beverly Hills vinyl light box cover at the northwest corner of La Cienega Boulevard and Wilshire Boulevard. The ICM immediately reported it to Psomas inspector Adnan Aldwir and STS superintendent Bill Dimalanta. STS superintendent Bill Dimalanta advised its prompt removal to avoid a violation.

    Gale Drive closure was removed at 14:30 hrs.

    http://www.enviro-intel.com/

  • This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    5/13

    Attachment B Daily Monitoring Reports

    3/17/2019 - 3/23/2019

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Friday, March 22, 2019

    Annamarie Hand

    La Cienega Station

    05:15:00 to 13:00:00

    Yes

    Contractors/ Subcontractors: STS, Century Sweeping; SSC Trucking; FTI Trucking; Miranda Trucking; Morgner

    Representatives On-Site: Alex Morales (STS); Lorena Vela (STS); Adnan Aldwir (Psomas); Ram Konanur (Metro); Marvin Mai (Psomas); German Garcia (Metro); Howard Jordan (STS); Alex Kay (COBH); Howard Jordan (STS); Christian Camarena (Morgner)

    Work Location(s): Gale yard; North Gale Drive closure; below deck along Wilshire Blvd.; intersection of Wilshire and La Cienega

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 05:15 hours to 13:00 hours on March 22nd, 2019. EI ICM Annamarie Hand met with STS Foreman Alex Morales to discuss the day’s activities. At the beginning of the shift, ICM Annamarie Hand calibrated the sound meter to 94.00 dB.

    The North Gale closure was set up at 05:48 hours and included 4 additional sound barriers. Haul trucks arrived at 06:05 hours. The crane started at 06:55 hours. Its use did not produce a noise exceedance. Sound panels were removed at 10:30 hours.

    Work for the day included multiple deliveries of timber to the yard, excavating below deck, lagging, hauling equipment into Gale yard shaft, hauling dirt from Gale yard shaft and haul trucks moving dirt from Gale yard and Ump repair/ MPBX installation in the intersection of Wilshire and La Cienega

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Friday, March 22, 2019

    Christian Elgabalawi

    La Cienega Station

    12:30:00 to 23:00:00

    Yes

    Contractors/Subcontractors: STS; MAD Trucking; Century Sweeping

    Representatives On-Site: Bill Dimalanta (STS); Darrell Lee (STS); Richard Garcia (Metro); Adnan Aldwir (Psomas)

    Work Location(s): Gale yard; below deck along Wilshire Blvd; road closure on North Gale Drive.

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 12:30 hours to 23:00 hours on March 22, 2019. EI ICM Christian Elgabalawi met with Bill Dimalanta to discuss the day’s activities. At the beginning of the shift, the ICM calibrated the sound meter at 94.00 dB (to 94.00 dB).

    Work for the day included spoils excavation and stockpiling within the Gale yard; hauling of excavated spoils from the Gale yard; lagging below deck in the Gale shaft.

    The Gale Drive closure was removed at 15:15 hrs.

    http://www.enviro-intel.com/

  • This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    6/13

    Attachment B Daily Monitoring Reports

    3/17/2019 - 3/23/2019

    Date

    Monitor

    Location

    Time

    Compliant

    Summary

    Saturday, March 23, 2019

    Daniel Chang

    La Cienega Station

    05:30:00 to 14:30:00

    Yes

    Contractors/Subcontractors: STS, PSOMAS, Century Sweeping, Mad Transportation

    Representatives On-Site: Alex Morales (STS); Adnin Aldwir (PSOMAS); Howard Jordan (STS); Lorena Vella (STS); German Garcia (Metro)

    Work Location(s): North Gale Drive enclosure; Gale yard; below deck along Wilshire Blvd.

    The ICM was in possession of applicable COBH-approved closure notifications and TCP for the day’s work from 05:30 hours to 14:30 hours on March 23rd, 2019. EI ICM Daniel Chang met with STS superintendent Alex Morals to discuss the day’s activities. At the beginning of the shift, the ICM calibrated the sound meter at 93.9 dB (to 94.00 dB).

    Work for the day included hoisting and stockpiling soil in the Gale yard, hauling of soil off site, assembly and disassembling of the North Gale Drive closure, hoisting machinery and equipment into the Gale yard shaft, and excavation below deck. The construction street sweeper also cleaned the adjacent work areas surrounding the La Cienega and Gale yards. A CFL truck also brought fuel for heavy machinery in Gale yard.

    The closure on North Gale Drive was set up at approximately 06:00 hours and the first haul trucks arrived on site at 06:03 hours. The last haul truck left at 13:15 hours and the closure on North Gale Drive was taken down at 13:50 hours.

    The crane began running at approximately 06:15 hours, but did not produce a noise exceedance.

    Approximately 30 haul trucks with 3 trips for the day.

    http://www.enviro-intel.com/

  • This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    7/13

    Photos

    Photos (41)

    UID: 2909 Latitude: 34.065

    Date: Mar 18, 2019 Longitude: -118.3743

    Type:

    Notes

    Construction Activity Elevation: 129

    Photo shows the crane hoisting materials into the Gale shaft within the Gale yard.

    UID: 2910 Latitude: 34.065

    Date: Mar 18, 2019 Longitude: -118.3743

    Type: Construction Activity Elevation: 126

    Notes

    Photo shows the crane stockpiling soil in the Gale yard.

    UID:

    Date:

    2897

    Mar 18, 2019

    Latitude:

    Longitude:

    34.065395

    -118.374321

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS using bulldozer to load soil from stockpile in Gale yard into haul trucks to transport off site.

    UID:

    Date:

    2899

    Mar 18, 2019

    Latitude:

    Longitude:

    34.065472

    -118.374165

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS using forklift to unload sand from delivery truck and move into Gale yard.

    UID:

    Date:

    2896

    Mar 18, 2019

    Latitude:

    Longitude:

    34.06554

    -118.374062

    Type:

    Notes

    Construction Activity Elevation: - - -

    STS approves TCP closure on North Gale Drive with proper signs and sound blankets to mitigate noise pollution.

    http://www.enviro-intel.com/

  • Photos

    This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    8/13

    UID:

    Date:

    2898

    Mar 18, 2019

    Latitude:

    Longitude:

    34.065321

    -118.374321

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS operating crane to hoist soil out of Gale yard shaft and stockpile in Gale yard.

    UID: 2905 Latitude: 34.0657323735006

    Date: Mar 19, 2019 Longitude: -118.375244799149

    Type: General Elevation: 41.1856832504272

    Notes

    Photo shows the La Cienega yard from 117 N Hamilton, measuring sound from the La Cienega yard.

    UID: 2904 Latitude: 34.0656873314171

    Date: Mar 19, 2019 Longitude: -118.375257667748

    Type: General Elevation: 41.1856412887573

    Notes

    Photo shows a second view of the La Cienega yard from one of a number of locations monitored today for sound levels.

    UID: 2900 Latitude: 34.0654684823294

    Date: Mar 19, 2019 Longitude: -118.374028153948

    Type: General Elevation: 41.1849775314656

    Notes

    Photo shows road closure on Gale at Wilshire, note the presence of additional sound panels.

    UID: 2901 Latitude: 34.065209995246

    Date: Mar 19, 2019 Longitude: -118.374209713984

    Type: Construction Activity Elevation: 41.1856451034546

    Notes

    Photo shows front loader moving spoils into a waiting haul truck.

    UID: 2903 Latitude: 34.0653821696716

    Date: Mar 19, 2019 Longitude: -118.374080613077

    Type: Construction Activity Elevation: 41.1854505539923

    Notes

    Photo shows front loader moving timber for the mats being built in the Gale yard.

    http://www.enviro-intel.com/http://www.enviro-intel.com/

  • Photos

    This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    9/13

    UID:

    Date:

    2908

    Mar 19, 2019

    Latitude:

    Longitude:

    34.065498

    -118.374153

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS picking up road closure on North Gale Drive.

    UID:

    Date:

    2911

    Mar 19, 2019

    Latitude:

    Longitude:

    34.065331

    -118.37442

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS using a hose and small mechanical jackhammer to clean dirt and mud off of bulldozer from underground.

    UID:

    Date:

    2906

    Mar 19, 2019

    Latitude:

    Longitude:

    34.065335

    -118.374489

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS drilling holes in wooden beams to connect multiple beams for underground matting.

    UID:

    Date:

    2907

    Mar 19, 2019

    Latitude:

    Longitude:

    34.065346

    -118.374252

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS using crane to hoist soil out of the shaft and stockpile in Gale yard.

    UID: 2912 Latitude: 34.0653120677104

    Date: Mar 20, 2019 Longitude: -118.374040083076

    Type: Construction Activity Elevation: 41.1848039627075

    Notes

    Photo shows trucks waiting in the staging area before hauling spoils out from the yard.

    UID: 2915 Latitude: 34.0656164300584

    Date: Mar 20, 2019 Longitude: -118.373984481491

    Type: Construction Activity Elevation: 41.8724555969238

    Notes

    Photo shows trucks waiting in the staging area before hauling spoils from the yard.

    http://www.enviro-intel.com/

  • Photos

    This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    10/13

    UID: 2914 Latitude: 34.0656508168008

    Date: Mar 20, 2019 Longitude: -118.3742202227

    Type:

    Notes

    Construction Activity Elevation: 42.8649749755859

    Photo shows crews removing broken machinery from the Gale yard.

    UID: 2913 Latitude: 34.0652344185949

    Date: Mar 20, 2019 Longitude: -118.374266318636

    Type: Construction Activity Elevation: 41.1857824325562

    Notes

    Photo shows trucks hauling out spoils from the yard.

    UID:

    Date:

    2917

    Mar 20, 2019

    Latitude:

    Longitude:

    34.064795

    -118.374092

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS picking up road closure on North Gale Drive.

    UID:

    Date:

    2916

    Mar 20, 2019

    Latitude:

    Longitude:

    34.065399

    -118.374176

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS using forklifts to unload timber into Gale yard from delivery truck.

    UID: 2921 Latitude: 34.0656823513054

    Date: Mar 21, 2019 Longitude: -118.37526161745

    Type: General Elevation: 41.4390907287598

    Notes

    Photo shows La Cienega yard from 117 N Hamilton; measuring exhaust fan noise from the yard.

    UID: 2918 Latitude: 34.0653552435674

    Date: Mar 21, 2019 Longitude: -118.374289184275

    Type: General Elevation: 41.184588432312

    Notes

    Photo shows trucks hauling out spoils from the Gale yard.

    http://www.enviro-intel.com/http://www.enviro-intel.com/

  • Photos

    This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    11/13

    UID: 2922 Latitude: 34.0656450110033

    Date: Mar 21, 2019 Longitude: -118.375338550268

    Type:

    Notes

    General Elevation: 41.185923576355

    Photo shows view from the north end of 112 N Hamilton; measuring the noise from the exhaust fan in the La Cienega yard

    UID: 2931 Latitude: 34.065

    Date: Mar 21, 2019 Longitude: -118.376

    Type: General Elevation: - - -

    Notes

    Photo shows graffiti on a City of Beverly Hills pink vinyl light box cover.

    UID:

    Date:

    2930

    Mar 21, 2019

    Latitude:

    Longitude:

    34.065

    -118.3744

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows crane stockpiling soil in the Gale yard.

    UID:

    Date:

    2929

    Mar 21, 2019

    Latitude:

    Longitude:

    34.065

    -118.3743

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows front loader tractor loading excavated spoils in the Gale yard.

    UID: 2920 Latitude: 34.0647970023604

    Date: Mar 21, 2019 Longitude: -118.374681016871

    Type: Construction Activity Elevation: 41.187026022934

    Notes

    Photo shows truck exiting the Gale yard after receiving a load of spoils.

    UID: 2919 Latitude: 34.0653049763881

    Date: Mar 21, 2019 Longitude: -118.374266220065

    Type: Construction Activity Elevation: 41.1860303878784

    Notes

    Photo shows front loader preparing timber mats to be hoisted into the shaft via the crane.

    http://www.enviro-intel.com/

  • Photos

    This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    12/13

    UID: 2927 Latitude: 34.0649441904517

    Date: Mar 22, 2019 Longitude: -118.376012836234

    Type:

    Notes

    General Elevation: 41.374454498291

    Photo shows sound blankets surrounding the exhaust fan in the La Cienega yard.

    UID: 2923 Latitude: 34.0651982196099

    Date: Mar 22, 2019 Longitude: -118.374222649042

    Type: Construction Activity Elevation: 42.8000946044922

    Notes

    Photo shows trucks hauling out spoils from the yard.

    UID: 2926 Latitude: 34.0651030182098

    Date: Mar 22, 2019 Longitude: -118.376259700847

    Type: Construction Activity Elevation: 41.8606147766113

    Notes

    Photo shows Ump repair/ MPBX installation in the intersection of Wilshire and La Cienega.

    UID: 2925 Latitude: 34.065105111679

    Date: Mar 22, 2019 Longitude: -118.376263772343

    Type: Construction Activity Elevation: 98.6780805059475

    Notes

    Photo shows Ump repair/ MPBX installation in the intersection of Wilshire and La Cienega.

    UID: 2924 Latitude: 34.065366980197

    Date: Mar 22, 2019 Longitude: -118.373829178857

    Type: Construction Activity Elevation: 41.6695022583008

    Notes

    Photo shows crane hauling spoils from the shaft onto the muck pile.

    UID: 2928 Latitude: 34.065288656649

    Date: Mar 22, 2019 Longitude: -118.37441947328

    Type: Construction Activity Elevation: 41.1859617233276

    Notes

    Photo shows front loader piling timber in the yard.

    http://www.enviro-intel.com/

  • Photos

    This report was generated by Environmental Intelligence, LLC - www.enviro-intel.com - Copyright (2019) 1590 S. Pacific Coast Hwy, Suite 17 | Laguna Beach, California 92651 | (949) 497-0931

    13/13

    UID:

    Date:

    2938

    Mar 22, 2019

    Latitude:

    Longitude:

    34.065

    -118.374

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows crane stockpiling soil in the Gale yard.

    UID:

    Date:

    2937

    Mar 22, 2019

    Latitude:

    Longitude:

    34.065

    -118.374

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows crew preparing materials for the crane to lower into the Gale shaft.

    UID:

    Date:

    2932

    Mar 23, 2019

    Latitude:

    Longitude:

    34.06551

    -118.3741

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS setting up road closure on North Gale Drive with additional sound blankets and fencing to mitigate noise.

    UID:

    Date:

    2935

    Mar 23, 2019

    Latitude:

    Longitude:

    34.065323

    -118.374283

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS using crane to hoist soil out from Gale yard shaft and stockpile it in Gale yard.

    UID:

    Date:

    2934

    Mar 23, 2019

    Latitude:

    Longitude:

    34.065311

    -118.374023

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows haul trucks waiting in North Gale Drive Closure to enter Gale yard to load out soil.

    UID:

    Date:

    2933

    Mar 23, 2019

    Latitude:

    Longitude:

    34.06535

    -118.374283

    Type:

    Notes

    Construction Activity Elevation: - - -

    Photo shows STS using bulldozer to load soil from a stockpile in Gale yard into haul trucks for transport off site.

    http://www.enviro-intel.com/

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Attachment C – Construction Noise Monitoring Results

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    March 18, 2019

    SLC-2 5:56 55.5 64 No

    Construction haul trucks arriving on site, STS using bulldozer to load haul

    trucks with soil from stockpile in Gale yard.

    SLC-7 6:12 59.2 64 No

    Construction haul trucks arriving on site, STS using bulldozer to load haul

    trucks with soil from stockpile in Gale yard.

    SLC-7 6:37 60.2 64 No

    Construction haul trucks arriving on site, STS using bulldozer to load haul

    trucks with soil from stockpile in Gale yard.

    SLC-2 7:01 59.2 69 No

    Construction bulldozer moving soil in Gale yard and loading haul trucks

    with soil.

    SLC-7 7:31 59.9 69 No

    Construction crane is operating, hoisting soil, and bulldozer is stockpiling

    soil in Gale yard but does not produce an exceedance.

    SLC-4/L-

    9 8:17 62.2 67 No

    Primarily ambient noise reading. Construction activity is minimal to

    ambient noise at this location. Construction crane is operating but does not

    produce an exceedance.

    SLC-7 9:30 63.7 71.8 No

    Construction haul trucks arriving in closure on North Gale Drive and

    bulldozer loading haul trucks with soil in Gale yard. STS also drilling holes

    in wooden beams in Gale yard. Sirens on Wilshire Boulevard at 09:57

    hours.

    SLC-6/L-

    8 10:06 74.2 79 No

    Construction crane is operating but does not produce an exceedance.

    Most noise attributed from traffic on Wilshire Boulevard.

    SLC-2 11:20 59.7 71.9 No Construction crane is operating but does not produce an exceedance.

    SLC-6/L-

    8 11:45 74.4 74.2 Yes

    Construction crane is operating but does not produce an exceedance. Most

    noise from traffic on Wilshire Boulevard, causing exceedance.

    SLC-7 11:57 62 71.9 No

    Construction using forklift to unload pipes from delivery truck in North

    Gale Drive closure.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-2 12:41 64.6 71.9 No

    Construction crane is operating but does not produce an exceedance. Non-

    project shipping truck with high impact backup alarm at 12:43 hours. High

    impact backup alarm from Spectrum van at 12:52 hours.

    SLC-7 13:25 61.6 72.9 No

    Construction crane is operating but does not produce an exceedance.

    Loading haul truck with soil from Gale yard stockpile.

    SLC-7 14:36 63.6 72.1 No The crane is mucking in the Gale yard.

    SLC-2 15:07 64.8 72.3 No The crane is hoisting equipment into the Gale shaft.

    SLC-7 15:38 63.4 72.3 No The crane is stockpiling soil in the Gale yard.

    SLC-4/L-

    9 16:12 62.6 66.5 No The crane is hoisting equipment into the Gale shaft.

    SLC-6A 16:39 74.9 N/A N/A The crane is hoisting equipment into the Gale shaft.

    SLC-1 17:16 63.2 67.6 No The ventilation fans are operating at the La Cienega yard.

    SLC-2 18:01 64.4 70 No The crane is hoisting materials into the Gale shaft.

    SLC-7 18:20 65.5 70 No The crane is operating at low RPM in the Gale yard.

    SLC-4/L-

    9 19:08 61.1 64.3 No The crane is stockpiling soil in the Gale yard.

    SLC-6A 19:27 74.8 N/A N/A The crane is stockpiling soil in the Gale yard.

    SLC-1 19:47 61.6 67.2 No The ventilation fans are running at the La Cienega yard.

    SLC-7 20:13 64 68 No The crane is stockpiling soil in the Gale yard.

    SLC-2 20:31 60.9 68 No The crane is stockpiling soil in the Gale yard.

    SLC-1 21:22 62.3 65.1 No The ventilation fans are operating at the La Cienega yard.

    SLC-1 21:43 61.5 65.1 No The ventilation fans are operating at the La Cienega yard.

    SLC-7 22:08 62.9 66 No The crane is stockpiling soil in the Gale yard.

    SLC-2 22:28 60.2 66 No The crane is stockpiling soil in the Gale yard.

    SLC-7 23:08 61.6 65 No The crane is still operating, hoisting equipment in the Gale yard.

    March 19, 2019

    SLC-7 6:00 57.8 64 No Trucks are hauling out spoils from the yard.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-2 6:30 57.1 64 No Trucks are hauling out spoils from the yard.

    SLC-7 7:30 67.4 69 No Trucks are hauling out spoils from the yard.

    SLC-2 8:30 63.5 71.7 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils out of the Gale yard.

    SLC-7 9:00 68 71.8 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the Gale yard.

    SLC-2 9:32 65 71.8 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the Gale yard.

    SLC-7 10:00 64.1 71.9 No

    Crane is hauling spoils from the shaft onto the muck pile; Trucks are

    hauling spoils from the Gale yard.

    SLC-7 10:30 65.7 71.6 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the Gale yard. Crews are building the timber mats in

    the yard.

    SLC-1 11:00 61.9 65.7 No Exhaust fan audible from the La Cienega yard.

    SLC-1 11:15 62.8 65.7 No Exhaust fan audible from the La Cienega yard.

    SLC-7 12:30 63.7 71.9 No Crane is hoisting materials into the shaft.

    SLC-2 13:00 68.1 72.9 No

    Crane is hoisting materials and equipment into the shaft.

    Ambient noise: Arrowhead delivery truck.

    SLC-2 14:16 63.9 72.1 No

    Construction crane is operating but does not produce an exceedance. Non-

    project truck horn honking at 14:29 hours. Crane is hoisting soil, loud

    clanks of soil bin.

    SLC-7 15:07 62.5 72.3 No

    Construction crane is operating but does not produce an exceedance. The

    clinking of hammers hitting metal in Gale yard is also audible but has a

    minimal effect on LEQ.

    SLC-4/L-

    9 15:33 62.7 67 No

    Primarily ambient noise reading; construction activity is negligible to

    ambient noise at this location.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-6/L-

    8 16:04 74.7 75.1 No

    Primarily ambient noise reading; construction activity is negligible to

    ambient noise at this location. Most noise contribution from traffic on

    Wilshire Boulevard.

    SLC-1 16:45 61.6 66.6 No

    Construction ventilation fans are audible but do not produce a noise

    exceedance.

    SLC-2 17:29 65.7 72.4 No Construction crane is operating but does not produce an exceedance.

    SLC-4/L-

    9 18:11 63.5 65.3 No

    Primarily ambient noise reading; construction crane is audible from this

    location but main contribution to ambient noise from traffic on Wilshire

    Boulevard and cars driving.

    SLC-1 19:05 62.2 67.2 No

    Construction ventilation fans are audible but do not produce a noise

    exceedance. Construction crane is operating but does not produce an

    exceedance. Car parked waiting playing loud music in car, effecting

    ambient noise reading for this location.

    SLC-2 19:42 60.5 71 No Construction crane is operating but does not produce an exceedance.

    SLC-7 20:20 62.1 68 No Construction crane is operating but does not produce an exceedance.

    SLC-1 21:02 61.9 65.1 No

    Construction ventilation fans are audible but do not produce a noise

    exceedance. Crane operation is audible as well as drilling within Gale yard.

    Crane flipping over soil bin creates banging loud disturbances for a very

    short period of time at 21:09 hours.

    SLC-7 21:28 61.1 67 No

    Construction crane is operating but does not produce an exceedance. Flat

    tip jackhammer being used to clean bulldozer lifted from underground in

    Gale yard is audible but does not produce an exceedance.

    SLC-2 22:03 60 66 No

    Construction crane is operating hoisting soil but does not produce an

    exceedance. Construction drill whirring at beginning of reading for

    approximately 5 seconds.

    SLC-7 22:20 60.9 66 No

    Construction jackhammer used to clean bulldozer is audible but doesn’t

    produce high dB (spikes of 62.2), crane is operating but does not produce

    an exceedance.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-2 22:35 60.6 66 No Construction crane is operating but does not produce an exceedance.

    SLC-7 22:55 58.5 65 No Construction crane is operating but does not produce an exceedance.

    March 20, 2019

    SLC-7 6:00 60.9 64 No Trucks are hauling out spoils from the yard.

    SLC-2 6:30 57 64 No Trucks are hauling out spoils from the yard.

    SLC-2 7:00 58.2 69 No Trucks are hauling out spoils from the yard.

    SLC-7 7:30 61.4 69 No Trucks are hauling out spoils from the yard.

    SLC-2 8:00 62.4 71.7 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling out spoils from the yard.

    SLC-7 8:30 69.5 71.7 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling out spoils from the yard.

    Ambient noise: Garbage truck picking up dumpster.

    SLC-2 9:00 61.4 71.8 No

    Crews are removing broken/ needs to be replaced machinery from the

    shaft/yard using the crane and flatbed trucks.

    SLC-2 9:30 62.9 71.8 No

    Crane is hoisting machinery into the shaft. Trucks are hauling spoils from

    the shaft.

    SLC-2 11:30 65.8 71.8 No Crane is hoisting materials and equipment into the shaft.

    SLC-7 12:00 61.9 71.9 No Crane is hoisting materials and equipment into the shaft.

    SLC-2 12:30 61.5 71.9 No

    Crane is hoisting materials and equipment into the shaft. Trucks are

    hauling spoils from the yard.

    SLC-7 13:00 66.5 72.9 No Trucks are hauling out spoils from the yard.

    SLC-2 13:30 61.2 72.9 No Crane is hauling spoils from the shaft onto the muck pile.

    SLC-2 14:14 63 72.1 No Construction crane is operating but does not produce an exceedance.

    SLC-7 14:45 67.5 72.1 No

    Construction crane is operating but does not produce an exceedance.

    Forklifts unloading timber delivery in North Gale Drive closure.

    SLC-4/L-

    9 15:39 61.9 67 No

    Primarily ambient noise reading; construction activity is negligible to

    ambient noise at this location.

    SLC-2 17:02 64.4 72.4 No Construction crane is operating but does not produce an exceedance.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-7 17:34 64.5 72.4 No Construction crane is operating but does not produce an exceedance.

    SLC-6/L-

    8 18:22 75.4 74.6 Yes

    Construction crane is operating but does not produce an exceedance. Most

    sound coming from traffic and cars driving on Wilshire Boulevard.

    SLC-1 18:41 65.5 65.5 No

    Construction ventilation fans are audible but do not produce a noise

    exceedance. Approximately 63.2 dB from fans. Exact threshold reading

    with average traffic and cars driving and ventilation fans.

    SLC-4/L-

    9 19:00 66.4 67.2 No

    Construction ventilation fans are audible but do not produce a noise

    exceedance, but fairly close to threshold.

    SLC-1 19:17 63.3 67.2 No

    Construction ventilation fans are audible but do not produce a noise

    exceedance. Ventilation fans about 62 dB and other sound altering

    contributors include cars driving on Wilshire and North Hamilton.

    SLC-2 20:19 60.2 68 No Construction crane is operating but does not produce an exceedance.

    SLC-7 20:42 60.3 68 No Construction crane is operating but does not produce an exceedance.

    SLC-1 21:05 62.3 65.1 No

    Construction ventilation fans are audible but do not produce a noise

    exceedance, approximately 62 dB from ventilation fans.

    SLC-2 21:46 61.1 67 No Construction crane is operating but does not produce an exceedance.

    SLC-7 22:07 61 66 No Construction crane is operating but does not produce an exceedance.

    SLC-2 22:28 60.1 66 No

    Construction crane is operating hoisting equipment but does not produce

    an exceedance.

    March 21, 2019

    SLC-2 6:00 58.7 64 No Trucks are hauling out spoils from the yard.

    SLC-7 6:30 59.6 64 No Trucks are hauling out spoils from the yard.

    SLC-2 7:00 59.5 69 No Trucks are hauling out spoils from the yard.

    SLC-7 7:30 65.5 69 No

    Trucks are hauling out spoils from the yard; crane is hoisting timber into

    the shaft.

    SLC-7 7:45 63.3 69 No

    Trucks are hauling out spoils from the yard; crane is hoisting timber into

    the shaft.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-2 8:30 62.1 71.7 No

    Crane is hoisting materials into the shaft. Trucks are hauling spoils from

    the yard.

    SLC-5 9:00 65.2 71 No

    Trucks are hauling out spoils from the yard.

    Note: Project noise is inaudible from this receptor. Ambient noise is

    dominant.

    SLC-4/L-

    9 9:20 62.5 66.5 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-6/L-

    8 9:42 77.2 79 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-3 10:00 61.3 64 No Exhaust fan from the La Cienega yard.

    SLC-1 10:25 64 68.1 No Exhaust fan from the La Cienega yard.

    SLC-1 10:46 63.3 68.1 No Exhaust fan from the La Cienega yard.

    SLC-2 12:00 61.1 71.9 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-2 12:30 60.7 71.9 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-7 13:02 66.8 72.9 No The crane is stockpiling soil in the Gale yard.

    SLC-2 14:01 64.3 72.1 No The crane is stockpiling soil in the Gale yard.

    SLC-4/L-

    9 14:54 62.5 66.1 No The crane is stockpiling soil in the Gale yard.

    SLC-6A 15:13 74.6 N/A N/A The crane is stockpiling soil in the Gale yard.

    SLC-1 16:45 64.2 66.6 No The ventilation fans are operating at the La Cienega yard.

    SLC-1 17:08 63 67.6 No The ventilation fans are operating at the La Cienega yard.

    SLC-7 17:37 64.8 72.4 No The crane is stockpiling soil in the Gale yard.

    SLC-2 18:00 63.8 70 No The crane is stockpiling soil in the Gale yard.

    SLC-7 18:22 65.7 70 No The crane is stockpiling soil in the Gale yard.

    SLC-7 19:27 65 71 No The crane is stockpiling soil in the Gale yard.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-4/L-

    9 19:49 59.4 64.3 No The crane is stockpiling soil in the Gale yard.

    SLC-6A 20:09 72 N/A N/A The crane is stockpiling soil in the Gale yard.

    SLC-1 20:34 62.2 64.9 No The ventilation fans are operating at the La Cienega yard.

    SLC-1 20:54 62.4 64.9 No The ventilation fans are operating at the La Cienega yard.

    SLC-7 21:15 61.5 67 No The crane is stockpiling soil in the Gale yard.

    SLC-2 21:33 61.7 67 No The crane is stockpiling soil in the Gale yard.

    SLC-7 21:21 60.4 66 No The crane is stockpiling soil in the Gale yard.

    March 22, 2019

    SLC-2 7:30 61.1 69 No

    Crane is hoisting materials and equipment into the shaft. Trucks are

    hauling spoils from the yard.

    SLC-7 8:00 64.8 71.7 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-2 8:30 68.4 71.7 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    Ambient noise: water delivery truck.

    SLC-7 9:30 64.5 71.8 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-6/L-

    8 10:07 75.9 79 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-4/L-

    9 10:30 63.6 66.5 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-2 11:00 61.7 71.9 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-7 11:30 63.1 71.9 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-2 12:02 62.4 71.9 No

    Crane is hauling spoils from the shaft onto the muck pile. Trucks are

    hauling spoils from the yard.

    SLC-7 13:52 64.2 72.9 No The crane is stockpiling soil in the Gale yard.

    SLC-2 14:19 63 72.1 No The crane is stockpiling soil in the Gale yard.

    SLC-7 15:26 63.5 72.3 No The crane is stockpiling soil in the Gale yard.

    SLC-4/L-

    9 15:47 63.9 67 No The crane is stockpiling soil in the Gale yard.

    SLC-1 16:13 64.7 66.6 No The ventilation fans are operating at the La Cienega yard.

    SLC-1 16:31 63.3 66.6 No The ventilation fans are operating at the La Cienega yard.

    SLC-7 16:53 66.3 71.8 No The crane is operating at low RPM in the Gale yard.

    SLC-7 18:11 65.1 70 No The crane is mucking in the Gale yard.

    SLC-2 18:50 65.8 70 No The crane is stockpiling soil in the Gale yard.

    SLC-6A 19:46 75.2 N/A N/A Sound reading taken in front of Saban Theatre.

    SLC-4/L-

    9 20:08 60.5 63 No The crane is operating at low RPM in the Gale yard.

    SLC-1 20:30 61.6 64.9 No The ventilation fans are operating at the La Cienega yard.

    SLC-1 20:47 61.8 64.9 No The ventilation fans are operating at the La Cienega yard.

    SLC-7 21:15 61.5 67 No The crane is stockpiling soil in the Gale yard.

    SLC-2 21:36 60.9 67 No The crane is stockpiling soil in the Gale yard.

    SLC-2 22:04 60 66 No The crane is stockpiling soil in the Gale yard.

    March 23, 2019

    SLC-2 6:04 56.8 64 No

    STS setting up road closure on North Gale Drive, first 5 haul trucks

    arriving in North Gale closure and bulldozer loading haul trucks with soil

    in Gale yard. STS started up the crane at 06:16 hours.

  • 1590 South Coast Highway Suite #17, Laguna Beach, California, 92651 • Phone: 949.497.0931 • www. enviro-intel.com

    Receptor

    ID

    Time of

    Measurement

    Measured

    Noise

    Level Leq

    (15-

    Minute)

    Applicable

    Noise

    Threshold

    Exceeded

    Threshold? Notes

    SLC-7 6:31 60.2 64 No

    Construction crane is operating but does not produce an exceedance. Haul

    trucks arriving on site sitting idle in North Gale Drive Closure, bulldozer

    loading haul trucks in Gale yard.

    SLC-7 7:00 62.8 69 No

    Construction haul trucks driving into Gale yard and bulldozer loading haul

    trucks with soil from stockpile.

    SLC-2 7:30 62.1 69 No

    Construction crane is operating hoisting soil from Gale yard shaft, haul

    trucks arriving on site and sitting idle in North Gale Drive closure,

    bulldozer loading haul trucks with soil.

    SLC-7 8:00 62.3 71.7 No Construction crane is operating but does not produce an exceedance.

    SLC-4/L-

    9 9:21 59.1 66.5 No

    Construction crane is audible but does not produce an exceedance.

    Primarily ambient noise reading at this location.

    SLC-2 10:03 76.6 74.2 No

    Primarily ambient noise reading construction crane is operating but does

    not produce an exceedance. Sirens on Wilshire Boulevard at 10:09 hours

    raise LEQ to 78.5 dB.

    SLC-1 11:00 62.1 65.7 No

    Ventilation fans are audible but do not produce a noise exceedance.

    Ventilation fans produce approximately 62 dB of noise disturbance.

    SLC-1 11:20 63.2 65.7 No

    Ventilation fans are audible but do not produce a noise exceedance.

    Approximately 62 dB of disturbance.

    SLC-2 11:40 64.3 71.9 No Construction crane is operating but does not produce an exceedance.

    SLC-2 12:27 64.6 71.9 No

    Construction crane is operating but does not produce an exceedance. Sports

    car driving on North Gale Drive loudly at 12:40 hours.

    SLC-7 13:02 60.5 72.9 No Construction crane is operating but does not produce an exceedance.

    AttachmentA_Violations_0317-0323.pdfField SummaryViolationsICM Violation Form - Section 1 DB MOA 66-172902 - 3/19/2019

    PhotosGeneral2905 - 3/19/20192904 - 3/19/20192900 - 3/19/2019Construction Activity2903 - 3/19/20192901 - 3/19/2019

    Map