Manual: Distribution Substation Manual (DSM) Section 8: Distribution Automation Standard Number: HPC-5DA-07-0008-2012
DM#3659750 Page 2 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
Document Control
Author Name: Viswa Easwaran
Position: Standards Engineer
Document Owner
(May also be the Process Owner)
Name: Justin Murphy
Position: Manager Asset & Works
Approved By * Name: Justin Murphy
Position: Manager Asset & Works
Date Created/Last Updated July 2013
Review Frequency ** 3 yearly
Next Review Date ** July 2016
* Shall be the Process Owner and is the person assigned authority and responsibility for managing the whole process, end-to-end, which may extend across more than one division and/or functions, in order to deliver agreed business results.
** Frequency period is dependent upon circumstances– maximum is 5 years from last issue, review, or revision whichever is the latest. If left blank, the default shall be 1 year unless otherwise specified.
Revision Control
Revision Date Description
0 12/07/2013 Initial Document Creation
STAKEHOLDERS The following positions shall be consulted if an update or review is required:
Manager Assets & Works
Manager Engineering Services
Manager Engineering Systems Planning
DM#3659750 Page 3 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
TABLE OF CONTENTS
1 PURPOSE .................................................................................................... 4
2 SCOPE ......................................................................................................... 4
3 CONTENTS .................................................................................................. 4 3.1 Index of Drawings ................................................................................................. 4
4 REFERENCE DOCUMENT .......................................................................... 4
5 REVISION INFORMATION .......................................................................... 5
6 LIST OF ACRONYMS .................................................................................. 5
DM#3659750 Page 4 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
1 PURPOSE
This Standard specifies the arrangements for Distribution Automation in relation to Distribution Substations used on Horizon Power Distribution networks.
This Standard supersedes the Western Power Document (record DM# 3246420]
previously in use by Horizon Power since disaggregation.
2 SCOPE
This Standard covers the following equipment:
Schneider RM6 connection diagrams for automation and remote operation;
3 CONTENTS
3.1 Index of Drawings
Drawing Number Drawing Title
DSM-8-07 Schneider RM6 RMU, RTU, AC power supply, modem, antenna and
fibre optic connection diagrams
4 REFERENCE DOCUMENT
The following Reference Documents have been used to prepare this Standard:
Doc Ref. Document Title Record No DM#
Publisher
AS 2067 - 2008
Substations & high voltage installations SAI Global
AS/NZS 3000 – 2007
Wiring Rules SAI Global
AS 3008 Cables for Alternating Voltages up to and Including 0.6/1 kV
SAI Global
HPC-5DA-07-0008-2012
Distribution Substation Manual - Section 8 Distribution Automation
3246420 (Superseded)
Horizon Power
Western Australian Distribution Connections Manual (WADCM)
Western Power & Horizon Power
Western Australian Electrical Requirements
Office of Energy safety
DM#3659750 Page 5 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
5 REVISION INFORMATION
(Informative) Horizon Power has endeavoured to provide standards of the highest quality and would appreciate notification if any errors are found or even queries raised.
Each Standard makes use of its own comment sheet which is maintained throughout the life of the standard, which lists all comments made by stakeholders regarding the
standard.
A comment sheet found in DM:3597516, can be used to record any errors or queries found in or pertaining to this standard, which can then be addressed whenever the
standard gets reviewed.
Date Rev No. Notes
12/07/2013 0 Original Issue
6 LIST OF ACRONYMS
CT – Current Transformer
MPS – Modular Packaged Substations
RTU – Remote Terminal Unit
RMU –Ring Main Unit
SPUD – Single Phase Underground Distribution
TFP –Truenet Fibre Panel
DM#3659750 Page 6 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
DM#3659750 Page 7 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
DM#3659750 Page 8 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
DM#3659750 Page 9 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
DM#3659750 Page 10 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
DM#3659750 Page 11 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.
DM#3659750 Page 12 of 12 Print Date 15/07/2013
© Horizon Power Corporation – Document Number: HPC-5DA-07-0008-2012 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.