manchester united soccer club rock rimmon soccer complex expansion plans darren hamilton
TRANSCRIPT
Manchester United Soccer ClubRock Rimmon Soccer Complex Expansion Plans
Darren Hamilton
Outline Current status Requirements Constraints Resources Responsibilities Timeframe Costs Return on Investment Tracking
Manchester United Soccer Club Located in Manchester, New Hampshire Training facility for young athletes 24 boys and girls, ranging from 9 to 16
years of age Owns Rock Rimmon Soccer complex
Summer Tournament Manchester United Soccer Club wants to
host a summer tournament Possible revenue of
$50,000-$70,000/Year Current complex consists of 3 fields Complex needs 2 additional fields to
host tournament Existing fields need refurbished Funding needed for scholarship program
Current Situation Nicolette Larson voted tournament
director First meeting was not productive Few useful ideas were generated Conversations got off track Discussions resulted in arguments
Work Breakdown StructureTournament
Remodeled Complex
New Fields
Survey, Blueprints Dirt Work Field Dressings
Turf
WP-1 TWP-2 TWP-3 TWP-4 T
Lighting
WP-1 LWP-2 LWP-3 L
Goals
WP-1 G
Corner Posts
WP-1 CP
Bleachers
WP-1 B
Remodeled Fields
Landscaping Replace Equipment
Field Treatments
Funds
Sponsors Fund Raising
Apparel
Design Clothing manufactured
Fund Raising Activities
Grants
Plan for moving ahead Determine scope statement of project Create organizational breakdown
structure Estimate times, costs, and resources
needed Create a project plan Approval Execute through completion
Constraints and Resources Constraints
Limited Time Project Funding People, Materials, Equipment
Resources Funding Apparel Design Apparel Production
Resources Cont. Survey Blueprints Development Turf contractors and supplies Electricians and lighting Landscapers to refurbish existing fields Contractor to install field dressing
Responsibility MatrixTask Jayhawk
Landscap
ing
Lightning
Electricia
ns
Thompso
n
Excavatio
n
Jim’s Turf
Co.
Skyline
Surveyors
Survey
land
X
Develop
land
X
Install
turf
X
Refurbish
existing
fields
X
Install
lighting
X
Responsibility Matrix Cont.Task Tom Spiffy
Designs
Decal
Graphics
All Star
Sports
Cathy
Fund
Raisers
X
Design
Apparel
X
Produce
Apparel
X
Dress
Field
X
Develop
scholarsh
ip
X
Schedule Fall
Survey and blueprints for new fields Develop land for new fields Design and obtain manufacturer for
clothing Begin refurbish of existing fields Raise funds
Schedule Cont. Spring
Replace equipment on existing fields Lay turf on new fields Install Lights Install new equipment Continue fund raising
CostsDeliverables Dollar Amount Quantit
y
Totals
Each new Field $600,000 (Fresenburg,
2006)
2 $1,200,000
Lighting/field $200,000 (SAFE) 2 $400,000
Apparel Design $500 (Costhelper, 2009) 1 $500
Apparel
Production
$5000 1 $5000
Field equipment $7400 5 $37,000
Existing field
improvements
per field
$10,000 (U.S. Soccer
Foundation)
3 $30,000
TOTAL: $1,672,500
Return on investment Total Cost = $1,672,500 Partner with other organizations to
reduce cost by 40% = $1,003,500 Annual income of $210,000 $1,003,500/$210,000 = Complex paid
off in 4.8 years.
Risk Assessment
Likelihood Scale Impact Scale Detection Difficulty Scale
1 = Highly Unlikely 1= No Impact 1= Easy Detection2 = Unlikely 2 = Minimal Impact 2 = Average
Detection3 = Moderately Likely
3 = Average Impact 3 = Difficult Detection
4 = Highly Likely 4 = Significant Impact 4 = Undetectable
Risk Assessment Cont. Risk Event Likelihood Impact Detection
Difficulty When
Bad
Weather
2 3 3 During
execution
Not enough
funding
3 4 2 During
execution
Losing a
contractor
2 4 2 During
execution
Increasing
resource
cost
3 3 1 During
execution
Not popular 2 3 3 After
completion
Failure to
complete in
time
2 4 2 After
expected
completion
Lack of
Materials
2 4 3 During
execution
Project Tracking Tracking Gantt chart Cost Performance Index Microsoft Project Status update meetings
Conclusions Project should move ahead!
Questions?