major plant modifications - vtt
TRANSCRIPT
SAFIR2018FortumAri-Pekka Kirkinen22.3.2019
Presentation Outline
Major Plant Modifications 2014-2018
PRA
Ensure Design Integrity and Nuclear Safety
Conclusions
2
• Nitrogen closure valves of the emergency core coolantaccumulators renewed
• Lo1 discharge channel gate VA01S002 elevation up to+3,00 m
• 10AT01 transformer renewed• Protection against high sea level• Procedure update on the loss of instrument room cooling
(UV20/25)• TK-RY connection testing every 8 years
• Independent cooling towers• Operation procedures against high sea level• Introduction of the flow chart emergency operating
procedures for leaks in shutdown states• Service water drainage during annual outage
3
Major Plant Modifications
2014 2015
2016
• AEFW feed also to steam generatorsYB15 and YB52 & battery backed-uppower to control valves
• Temporary dam in VC10 replaced bytemporary gate
• Loviisa 1 main steam safety relief valvesrenewed
• Preventive Actuation and IndicationSystem (PAIS) introduced
• 3 turbine bypass valves (RC) hydraulicoil stations replaced by water hydr.
• AEFW “blind operation” procedures• Improvement of procedures for “forced
convection”• Procedures for leaks and transients
during shutdown states• Regular training for auxiliary RHR system• Lifting reactor internal parts every 8 years
instead of 4
• Remaining 5 RC hydraulic oilstations replaced
• Accident ManagementPrioritization System (AMPS)introduced
• Opening steam generator specificauxiliary emergency feed watervalves prior to a high sea level
• Improvement in practices: filling upsea water channel before lifting uptemporary gates
20182017
• Secondary side safety improvementproject (SETU)
• Automation renewal project introduces– Reactor Trip System (RTS) and its
Automatic (ABS) and Manual (MBS)Backup Systems (MBS also includesmanual backup of ESFAS & HRFHS)
– Neutron Flux Measurement System– Reactor Power Control System– Reactor Power Limitation System
• Polar-crane modernization (Lo2)• Improvement of fuel pool cooling in
ALPO project• Last temporary dam replaced by
temporary gate
Major Plant Modifications
4
European Stress Tests for Nuclear Power PlantsStatus of Activities Presented in the Finnish Action Plan, 5.7.2017
5
Current situation
101 Evaluation of fragility of the spent fuel pools at high temperature and at highpressure
Implemented
102 Updating the seismic fragility analyses of- the spent fuel pools- fire fighting systems
ImplementedImplemented
103 improving preparedness for high seawater level Implemented
104 Analysis of consequences of beyond design basis low and high temperature Implemented
105 Analysis of consequences of tornados and downbursts on plant structures andsystems
Implemented
106 Implementation of an alternative ultimate heat sink Implemented
107 Securing the availability of the auxiliary emergency feed water system Implemented
108 Acquiring a container to transfer diesel fuel at site Implemented109 Enhancing the battery power sources Implemented
Note: Further ongoing changes due to reg. Req.
110 Acquiring mobile power supply and mobile pumps Not to be implemented111 Connecting the additional diesel power engine to the plant switchgears by a
dedicated cableImplemented
112 Evaluation of demineralised water reservoirs Implemented
113 Evaluation of demineralised water usage in an accident concerning all units andspent fuel pools at the site
Implemented
European Stress Tests for Nuclear Power PlantsStatus of Activities Presented in the Finnish Action Plan, 5.7.2017
6
Current situation
114Enhancing the diesel fuel transfer capabilities onsite; acquiring a newdiesel fuel storage tank at site Implemented
115 Evaluation of suitability of biodiesel for the diesel engines Implemented
116Ensuring the water injection into the spent fuel pools and monitoring theconditions of the pool In progress
117Capability of dealing with multi-unit severe accidents; updating ofemergency plans and organisation Implemented
118Improving the containment decay heat removal in case of multi-unitaccidents Situation OK without modifications
119 Plans for restoring the access routes to the site Implemented
120Evaluation of suitability of emergency preparedness personnel to theirduties Implemented
121Plans for access control and radiation monitoring of the staff anddecontamination measures in extreme natural hazards Instructions are done
Probabilistic Risk Analysis (PRA)• Requirements for full-scope PRA at Levels 1 and 2 for
power operation and low-power and shut-down states– Internal events, fires, floods, seismic events, harsh weather
and other external events
• Several risk-informed PRA applications required and inuse– Plant modifications, in-service inspection program, in-
service testing, Tech Specs, preventive maintenance duringpower operation, event analysis risk follow-up, safetyclassification, staff training, development of EOPs and otherprocedures
• Several risk informed plant modifications implementedat NPP e.g.– Fire and seismic risk is reduced significantly– Better preparedness against oil spills in the Gulf of Finland
7
Ensure Design Integrity and Nuclear Safety
• New process KPI for Regulatory Compliance is taken in use– Fulfillment of Nuclear Regulation measures overall status how
national and international requirement levels are met
• Compliance with national regulations and regulatory guides inhigh level for an operating nuclear power plant– YVL Compliance Rate
• Benchmark to international nuclear requirements still showsthe potential for further development actions– WANO Performance Objectives & Criterias Indicator– IAEA Osart Indicator
• Loviisa Compliance Digitalization continues with Polarion ALM
8
Good reputationDemand for expertise
Fortum supportbased on strategy
Strong Competence and Good R&DCo-operation with Universities & Research
Competent personnelThe plant is operated by a motivated and skillful working communityapplying high safety culture, co-operating to achieve common goals.
Concept of plant wide co-operationFocus on excellent performance
O&M,Operations and
Maintenance
Fuel and WasteManagement
Design Integrity& Nuclear Safety
Safe, reliable andprofitable production
Ensure availability of the power plant
Loviisa operates with the lowest costs in majority of cost areas,it ranks as leading performer in fuel front and availability
ConclusionsKey success factors of the Loviisa NPP
Reference Material
/1/ Regulatory Guides on nuclear safety and security (YVL), http://www.stuk.fi/web/en/regulations/stuk-s-regulatory-guides/regulatory-guides-on-nuclear-safety-yvl-
/2/ STUK decision, 5/A42213/2015, Loviisa nuclear power plant, PSR2015, 4.2.2017
http://www.stuk.fi/documents/88234/254201/1694439-stuks-decision-concerning-the-loviisa-npp-periodic-safety-review.pdf/1a1beb6c-9ae8-cd0b-0c6e-c001e7452ac9
/3/ STUK annual report, STUK-B 205 / JULY 2016, Finnish report on nuclear safety, Finnish 7th nationalreport as referred to in Article 5 of the Convention Nuclear Safety
https://www-ns.iaea.org/downloads/ni/safety_convention/7th-review-meeting/finland-7th-rm-national-report.pdf
/4/ STUK annual report 2016, STUK-B 214 / JUNE 2017, Regulatory oversight of nuclear safety in Finland
https://www.julkari.fi/bitstream/handle/10024/134790/stuk-b214.pdf?sequence=1
10
THANK YOU!