maintenance of the vessel and its equipment -...
TRANSCRIPT
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 1 of 13
Uncontrolled when Printed
6.1 DRYDOCKING / REPAIRS - GENERAL
Dry-docking Policy & Planning: Dry-docking intervals planned as per ship and classification society
requirements, keeping owner’s charter party, commercial commitment, trading pattern, urgency of
repairs, total time and costs in mind. Company issues dry-docking schedule for the fleet.
Superintendent fills in estimation of time and remarks on dry-docking. Opportunity should be taken
during docking to complete all deferred and outstanding repairs.
Progressive Repair Specifications: Master/Chief Engineer: Each time a defect is noted, which in
the opinion of Master/Chief Engineer has to be repaired in dry-dock, a Repair specification should be
duly completed with sketches, photographs or drawings and to the office. Ideally the specifications
preparations for the next docking must commence from the time of departure from dry-dock using dry
dock specification Form as provided by the Technical Suptd.
Superintendent: Maintain & update docking file. Monitor vessel’s itinerary 3 to 4 months ahead of
docking plans. Remind Master/Chief Engineer to update office on dry-dock repairs. Make pre-docking
inspection visit to vessel if considered essential. Complete specifications. Add/delete repairs as
essential. Include paint/general services. Discuss with Fleet Manager / Head of tech department and
decide tentative area (Europe, Far East etc.) and scope of repairs.
The choice of Dry Docks selected to tender will depend upon:
Geographic location matching the vessels required trading route
Yard capability and facilities
Yards past performance
Details of Tender Document
Pass repair specification to suitable yards. Compare quotations (3-4 yards) on price, total time,
payment terms, penalty clause and deviation. Consider yard experience on critical jobs, past
relationship, quotation reliability, weather conditions, yard congestion, port costs, safety/pollution
hazards, possibility of strikes etc. Advice Head of Ops & tech team / Head of Ship Management team
on extraordinary or out of budget expenses. Co-ordinate with Fleet Manager for yard decision and
inform principals for approval of additional costs, if any. Superintendent negotiates time, price
conditions and payment terms.
Owner/Superintendent/Accounts: Once Owner approves additional costs, Superintendent advises
Accounts of total estimated dry-docking cost. Accounts follow up for funds/receipt from owner.
Superintendent: Once yard is finalised, place firm order in company specific format. Inform
Master/Chief Engineer for preparatory work on board. Inform/appoint direct sub-contractors for
specific items e.g. radars, gyro, hatch covers, electronics or others as agreed with yard. Inform
classification society on intentions. Call tender for paints if necessary. Confirm paint orders. Check for
spares confirmation, e.g. stern tube seal, underwater fittings, anodes, review exigencies (if jobs
anticipated) e.g. availability of rudder bushes, facility for reconditioning of vital components, yard
capability for rebushing stern tube etc. Review fall back position and alternative options.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 2 of 13
Uncontrolled when Printed
Inform/arrange for required specialist/service engineers. Review for H&M, P&I claims if any. Discuss
crew matters with Fleet Personnel Department.
Superintendent/Master/Chief Engineer: Inspect jobs/vessel on arrival at dry-dock port/yard. Re-
evaluate items to be done at yard vis à quoted price. Continuously inform yard all additions/deletions
to specification as soon as possible. Obtain time cost quotations progressively prior to
commencement of extra work if possible. Maintain daily communication channel with Head of Ops &
tech team on progress. Communicate additional works, costs, over-budgets as soon as possible &
clear with Fleet manager /owners as required. Superintendent to inform Accounts of extra costs, if
substantial. Instruct and advise Master/Chief Engineer for required supervision on materials, and to
maintain log of labour/work progress as required.
Superintendent/Master/Chief Engineer/Yard Representative: Maintain record of all delays,
incorrect work, stoppages, labour shortages, interruptions etc. and arrange to keep detailed accounts
by ship staff of work processes where verification on final completion of job is not possible (e.g. sand
blast areas for quality and quantity). Maintain full documentation for items under H&M or P&I claims.
Co-ordinate surveys as required. Maintain progressive records with photographs for all important
work.. Master / Chief Engineer must consult with attending Superintendent prior signing / stamping
any work completion reports submitted by yard. Make sure work done reports are endorsed with
relevant facts by Master/Chief Engineer where any discrepancy has been noted.
Superintendent/Yard Representative: Bill negotiation with yard. Verify costs/statements. Contact
Fleet Manager / Head of Ops & tech team / Head of Ship Management team prior to arriving at final
repair amount. Make settlement. If unable to arrival at final figure, consult Fleet manager, draw out
written document for items of differences prior to return, stating position of each side. Collect, if
possible, all invoices and reports from shipyard and contractors.
Superintendent: Upon return, fill in draft bill column of repair/dry-docking cost. Possible alteration of
amounts communicated to Accounts by Superintendent. After the dry-docking is completed the
superintendent will complete a final report and a contractor assessment for the dry-dock. This
assessment is used to build up a history of the dry-dock company for reference.
Superintendent/Shipyard/Accounts: Reach final agreement/discounts/payment terms. Final
amount column completed. Accounts follow up for funds & effect payment for schedule. Make
provision for accrual of all docking costs in the month in which docking completed (including cost of
agency, paint supply, spares, anodes, etc).
6.1.1. Preparing Dry-dock Specs
Ideally the specifications preparations for the next docking must commence from the time of departure
from last dry-dock. (Please Use dry dock specification Form as provided by the Technical Suptd.).
Each time a defect is noted, which in the opinion of Master/Chief Engineer has to be repaired in dry-
dock, a Repair specification should be duly completed with sketches, photographs or drawings and to
the office. The success of a good docking lies in compiling absolute water-tight specifications and
estimating the extent of job scope. This enables list down all jobs and eliminates hidden costs,
enabling the docking to be completed within OR close to the declared estimated budget.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 3 of 13
Uncontrolled when Printed
Risk assessment for all hazardous operations like tank inspections, hot work etc must be sent to
office at least one week before reaching dry-dock.
COMPILING DATA AND SPECIFICATIONS PREPARATION:-
Following a generic flow & checklist to enable compile and prepare:-
1. Defect list from vessel to obtain.
2. Major COCs to list.
3. Ship side damages & Cargo hold damages to be assessed and reported.
4. Survey list - CSM & SSH to list pending items.
5. Check Tail shaft survey and boiler survey due.
6. Recommendations from class and PSCs to check.
7. New regulations requirement to list.
8. List Major M/E Overhauls - T/C, Fuel pumps, Liner etc. Obtain running hours. Governor last
ovhl dates for M/E & A/Es. Any major defects which require attention during repairs.
9. Statutory surveys due.
10. Lifting gear load testing last dates.
11. Check last VIR & audit recommendations & NC - list down important jobs if same pending.
12. Compile following information from Ship & ship’s drawings / plans: -
Area of Hull.
Paint scheme.
Flat bottom, Vertical bottom, boot top and top side demarcation drawing or
area calculation details.
Area of holds - to calculate if not readily available.
Area of tanks - to calculate if not readily available.
Area of Main deck, forecastle deck, and poop deck if separate.
Area of hatch tops, sides and underside - or obtains dimensions separately.
No of bottom plugs - list against the tanks.
Mooring winch drums conditions, liner condition.
Anodes calculation details. ICCP details, MGPS details.
List of all Ship side valves, and intermediate valves - with details of sizes
(Also makes for standard Butterfly valves).
Hatch coaming - condition and measurements to decide if same to be done.
Navigational equipment status - gyro last overhaul etc.
Steering gear ram seals.
Ships particulars to obtain.
Check if Bead welded ships name and class symbols for plimsoll mark.
Check poker gauge and tramell gauge available - any other tools for rudder stock, pintle
bearing, shaft coupling, propeller etc.
Instruct ship staff to send Stern tube, bow thruster oil samples analysis.
Instruct ship staff to make water tight specs and allot DD Spec numbers for the essential DD
jobs, such as Tail shaft, seal, rudder, propeller, hull blasting/ painting etc.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 4 of 13
Uncontrolled when Printed
Based on jobs check spares inventory & spares requisition and advice to raise requisition
individually against each DD specs. Boiler man hole doors and gaskets, Stern seals, Bow
thruster seals & Bearings, Steering gear ram seals.
Advice to raise requisition for DD stores - Joints, gland packing’s, packing extractors,
valve grinding tool, Apexior 3, zinc anodes, grinding paste, molykote, silicon, glass wool and
insulation, valves general (Only gate, globe etc – butterfly valves to make separate requisition
for seats and other spares).
Every docking all storm valves internals to be inspected and renewed as necessary.
As a practice, renew all storm valves alternate docking( i.e once in 5 years).
Every docking Main sea water pipe ( from sea chest to inlet of sea water pumps) thickness
measurement to be carried out( UT gauging) for ships which are older than 10 years.
Confirm if the following drawings available on board or office:-
a) General arrangement
b) Capacity plan.
c) Docking plan
d) Stern tube, propeller and shafting arrangement
PREAMBLE
1) To make preamble for the DD specs - based on above information.
2) Compile complete specs for quotations.
3) Send for quotations.
4) Obtain DD quotes and make cost comparison and work out budget.
SPARES & STORES
1) Send RFQ for Stern seals, anodes, paints, bow thruster spares/ seals, ram seals, butterfly
valve seat rings.
2) ME spares if reqd.
3) Hatch cover spares if requisition - including rams, cranes or grabs.
4) Stores RFQ & Supply.
5) Try connect at convenient ports.
6) Update the Requisition status.
7) Update specs with fresh ones and obtain quotes.
OWNERS CONFIRMATION & ORDER CONFIRMATION:-
1) Finalise and suggest Drydock available around area of off hire.
2) Visa arrangements for self.
3) Appoint agents and obtain quotes.
4) Arrival condition to Drydock to find out.
5) Arrangement for self stay.
6) Check Lubes required for DD.
7) Bunkers for DD & after DD.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 5 of 13
Uncontrolled when Printed
JOB PLAN TO BE PREPARED BY SHIP STAFF:-
1) Plan for Draining of HO & DO tanks - provision. Sludge disposal.
2) Bilges to empty prior arrival docks.
3) List of shipside valves with sizes & details to keep ready.
4) List of intermediate valves with sizes & details to keep ready.
5) List of other valves for overhaul to keep ready.
6) Stern tube draining arrangement and keep ready blank flanges etc.
7) Stern tube filling arrangement to find out and purging arrangement.
8) Empty drums for sludge disposal.
9) List of tanks to be cleaned.
10) Easing up of all vent and purging valves for SW pipelines and pumps to be completed prior to
dry dock arrival and rechecked again prior docking.
11) Confirm arrangement for AC , Fridge & ECR Cooling water.
12) Confirm arrangement for Sewage.
13) Confirm arrangement understood for shore power.
14) Check if ballast pump can be run on shore power.
15) Check if MSB can be feedback from E/G from ESB.
16) Check boiler can be kept fired in the docks by venting steam bypassing Dump condenser.
17) Prepare check list for Docking, undocking etc.
18) Work list - basis the jobs finalised by supt.
19) Work plan - basis 3 options of dock entry schedules and the same total number of days.
IMPORTANT
The responsibility of the safety of the vessel remains always with the Master.
6.2 ORGANISATION AND STRUCTURE
The normal organization structure of the ship must remain intact during the entire stay at the Yard.
Crew change is practical, but the safety aspects of the operation must be kept in mind. It must also be
considered whether it is wise to change senior staff during a docking period.
The Master will remain responsible for the safety of crew, ship and cargo during the docking period.
However, the following must be discussed and agreed upon prior to the stay at the Yard:
The division of responsibility between the Master and the Yard, while the ship is resting on the blocks
and ship systems may be closed down, with regard to:
Fire-fighting
Lifesaving, abandoning ship, etc.
Environmental issues, such as pollution, cleanup, etc.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 6 of 13
Uncontrolled when Printed
The Master - Pilot relationship will remain as under normal arrival/departure conditions. The
responsibilities and duties within the ship’s departments will also remain unchanged.
The Superintendent will have a consultative role towards the Master. Towards the Yard he will act as
the Manager’s Representative and, as such, be entitled to interfere within the framework set up by his
Superior.
6.3 RESPONSIBILITY - CO2 SYSTEMS
Most repair yards will have a paragraph in their general conditions similar to the following:
“In all cases of emergency, all fire-fighting and rescue operations will be under direct control of the
Yard Safety Department, in conjunction with the Master, who will remain ultimately responsible for the
crew and the vessel.”
Prior to work initiated in enclosed spaces equipped with CO2 systems, these shall be disconnected
and secured. The CO2 storage room and local release stations shall be locked and secured. It is the
responsibility of the Master to ensure that the system is physically disconnected. He has the authority
to reactivate the system if deemed necessary. He must ensure, beyond doubt, that the area has been
evacuated prior to releasing the system.
The Master does not need approval from the Yard to initiate fire-fighting operations.
When Head of Security of the Yard arrives at the scene of a fire, all available ship crew and
equipment shall be put at his disposal, the Yard taking command of the operation in conjunction with
the Master.
6.4 EMERGENCY PLAN PREPAREDNESS
The vessel’s Emergency Plan will remain in force throughout the repair period. The Plan must be
analyzed in conjunction with the work to be carried out and revised temporarily with regard to:-
Fire-fighting/lifesaving equipment out of operation
Locations/areas of the ship not accessible during periods of time
The normal alarm and communication systems not operational
Duties of the crew that changes
Based on the above conditions, changes to the Emergency Plan may be:
“Abandon ship” position will be changed
Fire stations/meeting points must be relocated
Parts or all of the alarm system disengaged
Parts or whole fire detecting system out of operation
Parts of the emergency equipment immobilised
In addition, the following information must be given the crew prior to arrival:
General information concerning hot work to be done
General information concerning enclosed space work to be done
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 7 of 13
Uncontrolled when Printed
General about the Yard’s alarm and emergency procedures
The crew must be made familiar with the temporary changes. The Master must also ensure that the
crew understands that, despite the fact that the Yard has its own emergency procedures and
equipment; it will always be their duty to safeguard themselves, the environment and the ship.
6.5 ABANDON SHIP PREPAREDNESS
The following should be considered before deciding on an abandon ship procedure:
Overbooking at the Yard, resulting in inconvenient mooring position/arrangement (double/triple
banking). The Emergency Plan does not cover eventualities where own ship might be “sandwiched”
between jetty and a burning ship. The Master must, if agreeing to such arrangement, at least consider
the following:
Strict safety measures with regard to hot work onboard own and other vessel(s)
Escape routes
Familiarise with Yard’s Emergency Plan concerning the ships in question
That tugs/mooring gangs are available
That the Yard takes full responsibility for damages
Caused by double/triple banked mooring
When own ship changes from one location to the next, the situation must be re-analyzed.
6.6 ALARM SIGNAL PREPAREDNESS
Parts of the alarm system might be disconnected either to prevent false alarms, due to maintenance
of the system itself, or lack of power supply. It should be the aim to maintain the major parts of the
alarm system engaged. Ensure that continuous watch is kept in those locations where fire alarm has
been disconnected.
Upon arrival at the Yard, the Ship and the Yard must compare emergency plans and agree on
common alarm systems and emergency procedures. The Master must also request a “silent test” of
those alarm systems and procedures.
6.7 FIRE-FIGHTING AND LIFESAVING EQUIPMENT PREPAREDNESS
The risk of fire is considerably increased during a Yard stay, compared to when in normal operation.
The Master must, after reviewing the situation, decide which parts of the equipment must and can be
put out of service. In principal, as much as possible of the equipment must be kept operational. If
possible, maintain fire main and sprinkler systems pressurized.
If parts of the ship’s emergency equipment are out of service during the Yard stay, the Master must
ensure that replacement equipment is made available. This may be the Yard equipment or equipment
rented and put onboard temporarily.
Portable fire-fighting equipment should be serviced onboard.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 8 of 13
Uncontrolled when Printed
If brought ashore for service, the fire-fighting ability may be reduced / incapacitated.
6.8 MEETINGS
Regular meetings must be held during the stay, the Ship senior staff, the Yard personnel and sub-
contractors participating. The agenda must consist of aspects regarding the safety of personnel,
environment and property, in addition to work planning.
6.9 INFORMATION
The ship staff must be regularly informed with regard to issues on their personal safety, issues such
as:-
Hot work to be carried out, including location(s)
Danger points, deck openings, etc.
Changes in the alarm systems
Changes with regard to the Emergency Plan
Communication
Watch Officers and crew shall carry walkie-talkies, as shall crew involved in any other critical
operations such as hot work, work in enclosed spaces, etc.
The Ship will normally be connected to the Yard’s telephone system. A list of emergency numbers
must be displayed next to the telephone. The Master must also have a back-up telephone system,
such as a mobile phone.
6.10 CONTROL OF PERSONNEL AND VISITORS
Ship crew involved in critical operations such as hot work, work in enclosed spaces, etc. must be
accounted for. A log shall be maintained by the Officer on Watch.
It is not realistic to keep account of Yard personnel. The Officer on Watch must, however, make sure
Yard personnel stay out of areas with no relevance to the work being performed.
The Ship and the Yard must agree on a procedure for controlling visitors. Normally, the control
system will suffice. However, the Officer on Watch must ensure that unauthorized personnel stay out
of areas with no relevance to their visit on board the ship.
6.11 PERSONAL SAFETY EQUIPMENT
During a Yard stay it is more important than ever to use personal safety equipment. It must be made
absolutely certain that this is understood by all crew. Otherwise, Officers and crew shall dress as
during normal port stays.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 9 of 13
Uncontrolled when Printed
6.12 MONITORING OF ATMOSPHERE
Measurement of the atmosphere must be performed where hot work is carried out, in addition to
measurements done by the Yard. This work may be performed by the Officer on Watch and must be
done regularly, preferably during work breaks. Special attention must be paid to enclosed spaces. In
addition to gas measurements, regular inspections of such areas must be done.
6.13 MONITORING OF WORK
The Officer on Watch and his staff shall monitor all critical operations carried out by Yard personnel,
ship staff and sub-contractors. A “Statement of Facts” shall be maintained, i.e. Bell book records. All
irregularities shall be reported to the Senior Management of the ship who will, if found necessary,
bring the matter up with the Yard. This particularly concerns work where distinctive procedures have
to be followed.
6.14 CHANGE OF SHIP CONDITION
Whenever the condition of the ship is changing (change of trim and other technical conditions) all
critical operations shall be suspended until the condition of the area in question has been checked
and found safe.
The intention is that the Yard must supply resources to cope with a fire onboard when the vessel’s
fire-fighting systems are disconnected for safety reasons. These resources may be any kind of fire-
fighting equipment, or a combination of systems.
6.15 HSE MANAGEMENT PLAN – REPAIR PERIOD
6.15.1. HSE Management during repair periods.
A Safety Committee is to be formed with representatives from the Repair Yard and the Ship
Operator prior to the vessel’s arrival at the repair yard. The Safety Committee should address
the following issues:
Responsibilities and authority shall be established and communicated to the ship staff and all
supervisory staff, including contractor’s supervisors.
Emergency Response Procedures shall be discussed and agreed with the Ship Yard, as
described “Maintenance of Ship Condition”.
Adequate stability and trim requirements to be achieved before vessel enters dry dock.
Provision of adequate electrical power and water pressure for the fire main.
Monitoring and co-ordination of all work carried out by ship staff, in addition to monitoring of all
other work, to ensure adequate safety measures are in place.
Obtaining Gas Free Certificates - these must state whether the space is gas free for hot work
or entry only.
Established Work Permit procedures to be implemented as described in the Shipboard Main
Manual.
Material Safety Data Sheets to be made available as required.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 10 of 13
Uncontrolled when Printed
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 11 of 13
Uncontrolled when Printed
6.15.2. Safety Committee Meetings.
Daily meetings will be held by the Safety Committee to discuss HSE issues related to the
work. The Committee to be chaired by the Captain in conjunction with the Ship Repair
Manager from the yard. The agenda will include;
Résumé of work completed / planned.
All planned entries into enclosed spaces. A plan must be maintained of all manhole covers
that have been removed or replaced and checked by ships staff
All planned breaches of systems that may represent a hazard to staff.
Planned hot work and precautions required. Work permits to be available during the
meeting.
Cargo Hold Insulation work is of special concern. A competent AB, with no other duties,
equipped with SCBA and VHF portable radio is to be on watch at all times. Fireproof mats
should be rigged to protect vulnerable insulation from sparks and a charged fire hose
provided to hand. The Duty Officer may be employed for the night watches.
Planned testing and commissioning of equipment and machinery.
Minutes of all meetings are to be maintained by the vessel.
Résumé of work completed / planned.
All planned entries into enclosed spaces. A plan must be maintained of all manhole covers
that have been removed or replaced and checked by ships staff.
Planned hot work and precautions required. Work permits to be available during the
meeting.
Planned testing and commissioning of equipment and machinery.
Minutes of all meetings are to be maintained by the vessel.
6.15.3. Specific Responsibilities for Ship Operator Staff.
The Technical Superintendent will ensure that a meeting between the repair yard
team and the ship staff is arranged prior to work commencing to address HSE issues,
including individual responsibilities and the responsibility of the Safety Committee.
The Shipboard Management Team will consist of the Captain, Chief Officer, Chief Engineer,
1st Asst. Engineer and Reefer Engineer. The Team will co-ordinate the ship staff in all matters
related to the repair work including HSE related issues.
The Chief Officer is responsible for the safekeeping and replacement in position of any
bottom plugs that have been removed during the course of the dry-dock.
The 3rd
Officer will act as the Ships Safety Officer during the repair period and will have no
other duties other than tasks related to HSE issues. The Safety Officer will be a member of
the Safety Committee, liaising closely with the repair yard’s Safety Representative and the
Captain/Chief Officer if in any doubt.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 12 of 13
Uncontrolled when Printed
The Duty Officer for Deck and Engine will be nominated on a daily basis by the Chief Officer
and the Chief Engineer respectively and his name posted on the notice board. The Safety
Committee will also be notified about the watch arrangements. The Duty officer will carry out
safety rounds before being relieved and maintain all relevant logbooks.
From 0800 to 1800, ship staff will patrol the ship continuously whilst performing normal duties.
Between 1800 and 0800 designated ratings will be appointed to carry out fire patrol.
6.15.4. Safety Related issues.
If the ships emergency alarm sounds at any time during the repair period, ship staff will
muster in accordance with the vessel’s Emergency Plan/Muster Plan. It will be the
responsibility of the Master or his deputy to notify the repair yard’s emergency teams.
To ensure sufficient staffs are available at all times, at least 4 Officers and 6 ratings must be
onboard at any one time. This is the minimum staff required to efficiently respond to an
emergency situation. Reference is made to the Shipboard Main Manual under section
“Maintenance of Ship Condition” and the Vessel’s Casualty Contingency Plan.
It is important that all staffs are accounted for as soon as possible following an emergency
situation. This shall be achieved as follows.
All ship staffs are to be provided with nametags prior to entering the repair yard. The nametag
to be worn at all times while on duty onboard.
A Control Board is to be established by the vessel and placed at the shore gangway. All ship
staff leaving the vessel shall leave their nametag at the Control Board. If there are 2 shore
gangways, one is to be nominated for the Control Board.
Furthermore, additional Control Boards are to be provided and placed immediately outside
the entrance of enclosed spaces. Before entering the space, the nametag shall be left on the
Control Board. When leaving the space the nametag shall be put back on the boiler suit.
The Chief Officer and the Chief Engineer are responsible for issuing shore leave permission
to staff. They must liaise closely to ensure sufficient staff are available onboard the vessel at
all times.
The vessel’s alarm system to be tested every day, at noon time to ensure all yard staff is
familiar with emergency alarm system.
6.15.5. Repair Work Related Issues. The work specification shall clearly state who is responsible for monitoring and following up each
individual repair work. Instructions for testing, approval criteria and commissioning should be clearly
explained for each individual work specification.
TECHNICAL MANUAL
Ch. 06 DRY DOCKING
Rev. No: 1
Date 20-Feb-15
Page 13 of 13
Uncontrolled when Printed
During all stages of the repair work, Environmental Protection related issues must be identified and
discussed within the Safety Committee.
6.15.6. Control of Contractors Procedure When any Contractors arrive onboard, at dry-dock or any other time, the person in charge shall be
directed to the Master/Chief Engineer or designated senior officer.
After agreeing the work required they would meet the ships officer responsible for the work.
This officer will discuss specific work details and brief the person in charge on safety requirements
including:-
1. Vessels emergency procedures
2. Means of safe access to place of work
3. Vessels safety and operational requirements
4. Authorisation of work starting
The person in charge of the contractors will acknowledge his understanding of the above and that
the safety arrangements provided are satisfactory. When required, he will sign the appropriate
section of the permit to work.
Contractors will normally provide qualified and experienced personnel to supervise the work
contracted for and provide protective clothing and equipment for the workforce as required.
In the event of the contractor not providing adequate supervision, or if language difficulties exist, a
member of the ships staff will be appointed to oversee work.
Throughout contractor operations a responsible officer will periodically monitor their progress and
compliance with safety requirements.
Assistance of ships staff will be made available when the operation of vessels equipment or
machinery is required.
On completion of contractor operations the following shall be checked by the person in charge of the
contractors together with the ships officer responsible;
5. All work has been completed or suitably terminated.
6. All contractor personnel, equipment and materials have been removed.
7. When the permit to work system has been used the person in charge of the contractors will
complete the relevant section of the form.
8. In all cases the Master / Chief Engineer will be informed when the work has been completed.