maintenance and engineering procedures and tools at soreq applied research accelerator facility
DESCRIPTION
Maintenance and Engineering Procedures and Tools at Soreq Applied Research Accelerator Facility. I. Gertz , Y. Buzaglo, A. Grin, R. Michael, R. Raizman, L. Weissman, A. Nagler Soreq NRC, Yavne, Israel WAO 2007 September 26 th , 2007. Accelerator Building and Infrastructure. Cryogenics. RF. - PowerPoint PPT PresentationTRANSCRIPT
Maintenance and Maintenance and Engineering Procedures Engineering Procedures
and Tools at Soreq and Tools at Soreq Applied Research Applied Research
Accelerator FacilityAccelerator Facility
I. Gertz, Y. Buzaglo, A. Grin, R. Michael, R. Raizman, L. Weissman, A. Nagler
Soreq NRC, Yavne, Israel
WAO 2007September 26th, 2007
226/9/2007
SARAFSARAF
Accelerator Building and Infrastructure Cryogenics RF
326/9/2007
SARAF Building and SARAF Building and InfrastructureInfrastructure
Building CHW HVAC
Comp. Air Communication Safety
Electrical Supply and Distribution Control Systems
426/9/2007
Senior Engineering Team (SET)Senior Engineering Team (SET)SET Members: o Electrical Engineer (Control Systems, Infrastructure, RF)o Mechanical Engineer (Cryogenics, Vacuum)
o Physicist (Accelerator, Diagnostics, Beam lines)
o Industrial Engineer (Maintenance Management, Documentation)
o Safety Specialist (“online” safety, procedures for present and future)
o Two accompanying part time technicians
Responsibilities:o Operation
o Systems Commissioning and Acceptance
o Maintenance
o Engineering and Technical Office
o Training
526/9/2007
OperationOperation
Most infrastructure systems were accepted and serve accelerator installation and commissioning purposes
SET members ware trained up to supervisor level to operate the infrastructure systems
626/9/2007
Accelerator Systems Commissioning Accelerator Systems Commissioning and Acceptance (1)and Acceptance (1) SET members are participating and assisting in
accelerator installation, commissioning and acceptance tests
Effort is lead by the accelerator contractor personnel and is under their responsibility
726/9/2007
Accelerator Systems Commissioning Accelerator Systems Commissioning and Acceptance (2)and Acceptance (2)
Emphasis is on thorough learning and understanding of all systems and components
SET members spend about 40% of their time on these tasks
826/9/2007
Engineering and Technical OfficeEngineering and Technical Office
Engineering tasks and Technical Office responsibilities are entwined
Engineering R&D of accelerator supplementary systems (Control, Diagnostics,
infrastructure) Writing maintenance and operating procedures
Technical Office Documentation of engineering tasks Updating of documentation and drawings Archiving of engineering data Maintenance schedule Coordination among SARAF and external contractors and suppliers Purchasing of spare parts and stock management
926/9/2007
MaintenanceMaintenance
Maintenance procedures concern operational and mechanical systems conditions
Currently, maintenance is mainly performed on The building Infrastructure systems Cryogenics Part of the accelerator vacuum and RF
The maintenance works are divided into: Breakdown Maintenance (BM) Preventive Maintenance (PM) Predictive Maintenance (PdM)
1026/9/2007
Breakdown Maintenance (BM)Breakdown Maintenance (BM) Most of the systems are still in their warranty periods, so
they are usually repaired by the system contractor In urgent cases, breakdown maintenance is performed by
SET members The procedure for BM is
1. BM is requested in the commissioning logbook (if encountered during shifts) or in a PM form (if encountered during PM)
2. The BM Request is accepted and checked by the relevant SET member
3. A BM form is issued
4. BM is performed according to the procedures
3. A BM technical report is prepared
4. The BM technical report is checked and approved by the SET head
5. The data base of the Computerized Maintenance Management System (CMMS) is updated
6. The approved report is logged and stored in the BM archive
1126/9/2007
Preventive Maintenance (PM)Preventive Maintenance (PM)
For accepted systems PM procedures have been written and scheduled by the technical office
The procedures are based on the system contractor requests and maintenance timetables (with small deviations)
PM is performed either by SET members, the system contractor or other external contractors
The procedure for PM is 1. A PM procedure form is issued by the technical office
2. PM is performed and reported on the form
3. The PM report is checked and approved by the SET head
4. The data base of the CMMS is updated
5. The approved report is logged and stored in the PM archive
1226/9/2007
Predictive Maintenance (PdM)Predictive Maintenance (PdM) Predictive Maintenance (PdM) is an integral part of preventive maintenance Measurements of systems parameters are performed routinely to observe
patterns and predict equipment breakdowns or malfunctions Typical measurements and operations include
Thermal imaging of electrical cabinets Electric current measurements of motors and other equipment Pressure and flow measurements of process cooling water systems Gas and water analysis in relevant systems
1326/9/2007
Computerized Maintenance Computerized Maintenance Management System (CMMS)Management System (CMMS)
For the abovementioned tasks we developed a Computerized Maintenance Management System (CMMS), which enables SET members to schedule and structure maintenance tasks
The SARAF CMMS is a Microsoft Access based maintenance database management system which includes
1. Assets Management
2. Preventive Maintenance Scheduling and Management
3. Report Generation
1426/9/2007
CMMS – Asset ManagementCMMS – Asset ManagementComponent Data ScreenComponent Data Screen
1526/9/2007
CMMS – Asset ManagementCMMS – Asset ManagementService Providers ScreenService Providers Screen
1626/9/2007
CMMS - PM Scheduling and ManagementCMMS - PM Scheduling and Management
Weekly
Monthly
Quarterly
Semi-annual
1726/9/2007
CMMS – Reports GenerationCMMS – Reports GenerationThe 2007 Annual BM reportThe 2007 Annual BM report
1826/9/2007
Workload during commissioningWorkload during commissioning
20%
40%
20%
20%Operating
Systems Commissioning andAcceptance
Maintenance
Engineering
1926/9/2007
ConclusionsConclusions Development and assimilation of maintenance and
engineering systems during accelerator installation and commissioning presents a big challenge for SARAF Senior Engineering Team.
Currently, the biggest effort is the accelerator installation and commissioning, so maintenance and engineering receive a smaller share of the workload
It is unequivocal that after the accelerator systems will be accepted, the maintenance load will grow accordingly. Therefore major SET tasks are: Verified written procedures
A CMMS including all of the accepted systems Appropriate training of SET members Development of a maintenance culture
Thank YouThank You
2126/9/2007
Breakdown Maintenance ReportBreakdown Maintenance Report
2226/9/2007
Printed request for PM procedurePrinted request for PM procedure