Magnet & services projectsP. Tropea

9 Nov 2011 – CMS upgrade workshop

Page 2: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Contents

CONSOLIDATION•Magnet infrastructure •Water & Fluorocarbon cooling•General servicesUPGRADE

•Pixel phase I CO2 cooling

•RE4 cooling

2

Page 3: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Magnet (courtesy B. Cure)

Magnet operation in 2011 (since Feb restart till Oct 2011):•84.8% of total time at 3.8T•11.6% of total time with planned magnet stops•3.6% of total time with unexpected magnet stops100% available for physics at LHC. Three faults, both recovered in 4 days:•faulty valve position controller•mismatch of cryo parameters (operator mistake), following intervention on cryoplant during the July TS and the following power cut•Switch off of all magnet power converters (procedural problem)

Increase reliability & redundancy of services to reduce failure impact & limit the magnet

cycling, in order to maintain expected magnet availability and lifetime!

3

Page 4: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Magnet cryo & cooling (courtesy B. Cure)

Cryo compressors: standard revision demands several months with magnet off. Any failure would imply long waiting time, since compressors are not off-the-shelf components. Low efficiency (still within specs) due to the non optimal lubricant separation system

2 new compressors to be installed in order to guarantee full redundancy: scheduled for LS1, critical parts already ordered (rotor, casing, bearings, motors)

Issue with lubrication separation system addressed (common issue with LHC machine cryoplants) : helium dryer (+ purifier, to be confirmed) to be installed during LS1

Busbar cooling: coupled through buffer tank to Yoke and Endcap cooling (possible stoppage during maintenance operation on the latters). Requirements on EDMS 1149889, project launched with EN/CV for LS1

4

Page 5: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Magnet safety & control system, power (courtesy B. Cure)

5

Page 6: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Water cooling: consolidation

Consultation with EN/CV in October, agreement to plan all activities and finalize studies by beginning of 2012.

Operation improvements•Additional monitoring & verification of DSS cabled alarms•Action matrix on humidity level alarms to be updated (stop of rack circuit incident on August 3rd)•Backup chiller during maintenance/major incidents?

Ecal cooling system•Slow response of T regulation to changes of load or primary cooling T•Too high sensitivity to small flow/temperature changes on CMS side•Review with CMS and CV people to be organized asap

6

Page 7: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Water cooling: leak risk mitigation

Since Jan 2010: 24 leaks (all detected by inspections, except one spotted by leak detection cable). Rack circuit is the most critical (19 leaks), followed by the Muon circuit.

1.Modify critical racks (Tracker) to make connections accessible: on-going study 2.Improve leak detection system:

• calibration of leak sensors to retrieve leak position

• graphic interface to have a faster feedback (DSS team, cooling team, Sensors 4CMS team)

7

Page 8: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Fluorocarbon circuits: “go cold” &

reliabilityTracker cooling working group (Chair: A. Onnela,

members: Tracker, EN/CV/DC, PH/DT) is in charge for evaluation of main interventions towards long term improvements on cooling system and implications of running at much lower temperatures after LS1

- Performance test: to assess the capacity of the system to cope with low T and demanded power, including Pix CO2 plant (ETS 2011/2012)

- Dryness of cooling cabinets & environment for Tk maintenance

- Pneumatic cabinet revamp to increase reliability- Backup chiller full commissioning for Thermal Screen

and Preshower plants- Additional monitoring instrumentation (vibration, fast

pressure transducers, etc.)

8

Page 9: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

General services

Gas nitrogen for detector dryness•Additional N2 gas flow needed.

•Full picture on EDMS 1137136. To be completed with updated Tracker needs once humidity issues assessed

SHL5 Pixels lab•Climatic chamber: T and RH regulation ranges defined, structure being prepared and HVAC works to be done in 2012

UXC55 Temperature/Humidity control•Cavern temperature above 20°C all year long•Huge sensitivity of RPC to ambient temperature•Additional load to the cavern from ECAL cables•Need for understanding present system limits and possible cures, project launched with EN/CVRack cooling turbines-Mandatory to replace all turbine motors in magnetic field in LS1-Considering replacement of turbine motors in USC as well

9

Page 10: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Pixels phase I CO2(see talk by H. Postema for further details)

On-detector cooling design ongoing- Definition of cooling loops length (PSI, FNAL)- Thermal performance tests and simulations (PSI, FNAL,

CERN)

Conceptual design mostly ready for cooling plant- Components being selected (CERN/Lyon)- 3D modeling started (Lyon)- Control system studies started (CERN)

Qualification of copper pipes- Resistance to high pressure approved by CERN safety

(failing @ 240 bar)- Full scale mock-up for flow regime investigation ready,

tests to start in few weeks (CERN)

Installation studies- Two possible locations: USC or UXC- Radiation protection studies ongoing

10

Page 11: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

RE4 cooling manifold (courtesy D. Loveless)

• RE Proposal– Design Xmas towers in accessible location– Run laterals from the towers to the

chambers• Use hoses, not copper pipe• RE chambers have pigtails, connect via O-rings

– Design should take 3-4 weeks– Production of stainless piping can be done

by local firm

• CSC Connections exist– Purchase fittings

11

Main issues to be addressed: integration, coordination of installation works and commissioningSame design to be considered for YE1 possible consolidation…

Page 12: Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop

9 November 2011P. Tropea

Summary

• Infrastructure consolidation, even if not so fancy, is mandatory to guarantee a good data taking reliability

• A number of projects are well defined and already in the pipeline for LS1

• Some other projects need time and resources to advance: N2 plant…

• Consolidation projects strongly influence also upgrade (see primary circuit for Pix CO2 plant)

• Cooling for upgrade is in good shape: projects are progressing and resources are well allocated

12