madhya pradesh power transmission company …sldcmpindia.com/uploads/meeting/minutes of 71st occm of...
TRANSCRIPT
MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED
STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR Telephone: (0761) 2970089 Fax: (0761) 2664343/2970119 e-mail [email protected]
Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur 482008, CIN-U40109MP2001SGC014880, Email-mdtransco.nic.co.in
No.07-05/SG-9B-II/2886 Jabalpur, dated:30.10.2019
To
As per distribution list
Sub: Minutes of 71st meeting of Operation and Coordination Committee of MP. …
The Minutes of 71st meeting of the Operation and Coordination Committee of MP held on
20th September 2019 at Conference Hall, SLDC, MPPTCL, Jabalpur has been uploaded on
the website of SLDC ‘www.sldcmpindia.com’ and can be downloaded.
(R.A. Sharma) Member Secretary, OCC SLDC, MPPTCL, Jabalpur
Distribution List 1. The Chief Engineer (Works), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur, email-
[email protected]. 2. The Chief Engineer (T&C), MP Power Transmission Co. Limited, Jabalpur. Fax No- 0761-2665593, 2702710 Email-
[email protected] 3. The Chief Engineer (Transmission-East Zone), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur. Email-
[email protected]. 4. The Chief Engineer (Transmission-West Zone), MP Power Transmission Co. Limited, Indore. 5. The Chief Engineer (Transmission-Central Zone), MP Power Transmission Co. Limited, Bijlee Nagar, Govindpura,
Bhopal, email- [email protected]. 6. The Chief Engineer (Plg & Des), MP Power Transmission Co. Limited, Jabalpur, Fax No- 0761-2660908 Email-
[email protected] 7. The Chief Engineer (Procurement.), MP Power Transmission Co. Limited, Jabalpur, .Fax No- 0761-2660908 Email –
[email protected] 8. The Chief Engineer(EHT:Const.), MP Power Transmission Co. Limited, Jabalpur. Fax-0761-2661618, E-mail-
[email protected]. 9. The Chief Engineer(EHT:Maint&insp.), MP Power Transmission Co. Limited, Jabalpur. Fax-0761-2665593, E-mail-
[email protected]. 10. The Executive Director (O & M:Gen), MP Power Generating Company Limited, Jabalpur. Fax No- 0761-2664749,
Email- [email protected], Email- [email protected] 11. The Chief Engineer (O&M:Hydel), MP Power Generating Co. Ltd, Jabalpur, Fax No-0761-2664749. 12. The General Manager(PM), MPPMCL, Jabalpur Email – [email protected] [email protected] 13. The Superintending Engineer (GCC), MPPGCL, Jabalpur Email – [email protected] [email protected]. 14. The General Manger (DCC-EZ), DISCOM Control Centre, MP Poorva Kshetra Vidyut Vitaran Co.Limited, Jabalpur,
Fax No- 0761-2668503, Email – [email protected]. 15. The Dy. General Manager (DCC –CZ), DISCOM Control Centre, MP Madhya Kshetra Vidyut Vitaran Co. Limited,
Bhopal, Fax No-0755-2580611,Email- [email protected]. 16. The Executive Engineer (DCC-WZ), DISCOM Control Centre, MP Paschim Kshetra Vidyut Vitaran Co. Limited, Near
Polo Ground, Jail Road, Indore, Fax No- 0731-2421554, Email- [email protected]. 17. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Indore, Fax No- 0731-2874515, Email –
[email protected]. 18. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Bhopal, Fax No- 0755-2885220, Email –
[email protected] 19. The General Manger(RO), MPPMCL, In front of Bhojpur Club, E-4, Arera Colony,Bhopal, Fax No-0755-2423046,
[email protected] 20. The Chief Engineer (PM&C), Narmada Hydroelectric Development Corpn. Ltd, NHDC Parisar, Shamla Hills, Bhopal –
462013., Fax No- 0755-4030130,Email – [email protected] [email protected] 21. The Chief Electrical Distribution Engineer, West Central Railway (WCR), General Manager’s Office, Electrical
Department, Jabalpur-482001 (MP), Fax: 0761-2627629, Email- [email protected], [email protected], M-9752415312, Mr.Satyendra Kumar (Dy.CE), Mob.9752415301 (CEDE, WCR).
22. The General Manager, Indira Sagar Power Station, NHDC Office complex, PO : Narmada Nagar, Distt : Khandwa (MP) – 450 119, Fax No- 07323-284080, Email – [email protected]
23. The General Manager, Omkareshwar Power Station, Prashsnik Bhawan, Urja Vihar, Sidhwarkut, Distt : Khandwa (MP) – 450 554, FaxNo-07280-271703, Email- [email protected], [email protected], [email protected].
24. The Director (Projects), BLA Power Limited, At : Niwari, PO: Khorsipan, Tah : Gadarwara, Distt ; Narsinghpur 487 551, Fax No. 07791-243667 / 243669, Email – [email protected]
25. The Sr. Vice President, Jaiprakash Power Ventures Ltd., Village Sirchopi Subpost Office-Agasod, Post Office-Bina- 470113 Distt- Sagar, Fax No. 07580-277200, Email – [email protected] [email protected],
26. The Chief Executive Officer, Kalpataru Satpura Transco Pvt. Ltd., Satpura Colony, Betul Road, Old Itarsi, Distt. Hoshangabad, Email – [email protected]
27. M/s Ujaas Energy Ltd. 701, NRK Business park, Vijay Nagar Sqaure, Indore – 452010, Email id :[email protected] 28. M/s Suzlon Global Services Ltd., 1090, Scheme no. 114, Park-2, Ring Road, Universal Hospital Row,
Email- [email protected], Indore – 452010, [email protected]
The 71st meeting of Operation & Coordination Committee of MP was held on 20th September 2019 at
11:00 AM at Conference Hall, SLDC, MPPTCL, Nayagaon, Jabalpur. The list of participants is enclosed at
Annexure -1.0.
Shri K.K.Parbhakar, C.E.(SLDC) & Chairman OCC welcomed all the guests & participants to 71st
OCCM of MP. Chairman OCC stated that 50% of maximum demand of the state is being met by RE and Hydel
as Hydel is about 2800-2900 MW, hence thermal units are under backing down. During the last months the
Grid operations and system was smooth but the upcoming months might be crucial as there may be shortfall
of about 600-700MW for the demand forecasted by Discoms, even after purchasing from all the availability
sources. During peak hours, SLDC & MPPMCL is planning to manage the shortfall and met the demand by
power purchase from open access & other sources.
Another challenge is the shortage of coal in thermal units of MPPGCL, seeing to their coal
shortage/supply pattern of last months and it is an area of concern as during peak period it will not be feasible
to stop the unit due to coal shortage. Hence MPPGCL is requested to kindly resolve the coal shortage problem
and ensure the required coal supply and maintain adequate coal stocks during the peak season and
approximately 3800MW power will be required to mitigate the forecasted Demand from the month of
November 2019 onwards. Representative from MPPGCL informed the committee that the coal companies
have restricted the coal supply due to pending bill. Further Chairman OCC stated that MPPGCL shall take up
the matter with Govt. and ensure to maintain the adequate coal stock.
Chairman OCC informed the committee that SLDC has to submit a Detailed Operating Procedure for
backing down of SSGS units in line with CERC guidelines after discussing/providing copy of the procedure to
all the entities. Where in Discom have to pay compensation to generating companies if the generators are
taken ON BAR below normative PLF. It will be implemented after the approval by the commission. Thereafter
he requested Shri. R.A.Sharma, Addl. CE, SLDC & Member Secretary OCCM to take up the agenda points.
ShriR.A.Sharma, Addl. CE, SLDC stated that Chairman OCCM has discussed the complete gist in his
opening remarks, especially regarding the demand and supply management in MP Grid. He shown his
concern about the voltage management in the ensuing Rabi season. He also mentioned his concern to identify
the pockets in advance where load management will be required as load diversion will also be required from
Discom sides for the critical pockets during rabi season. The load diversion shall also be planned in advance
to maintain uninterrupted 24X7 supply. Thereafter he requested the guests & participants for introduction.
Thereafter the agenda points were taken up, which are narrated here under :-
ITEM NO. 1 : CONFIRMATION OF MINUTES : Minutes of 70th meeting of Operation & Coordination Committee of MP held on 09th July 2019 at Conference Hall, SLDC, MPPTCL, Nayagaon, Jabalpur were forwarded to the committee members vide No. 07-05/SG-9B-II/2432 Jabalpur dated 12.09.2019. No comments have been received. Committee confirms the minutes.
MINUTES FOR 71st MEETING OF OPERATION & COORDINATION COMMITTEE OF MP HELD ON 20th SEPTEMBER 2019 AT 11:00 AM AT Conference Hall, SLDC, MPPTCL,
Nayagaon, Jabalpur.
Minutes of 71st OCCM of MP 1
ITEM NO.2: REVIEW OF SYSTEM OPERATION DURING THE MONTHS JUNE 2019 TO JULY 2019. 2.1. Frequency Particulars: The committee was apprised that during JUNE 2019 the system frequency was below 49.90 Hz for 9.87% of time against 7.09% of time during JULY 2019. The system frequency was above 50.05 Hz for 19.79% of time during JUNE 2019 against 24.64 % of time during JULY 2019. The system frequency was within the IEGC range of 49.90-50.05 Hz for 70.34 % of the time during JUNE 2019 against 68.27 % of time during JULY 2019. The average monthly frequency was 50.00 Hz during month of JUNE 2019 and 50.00 Hz during month of JULY 2019.
The detailed frequency particulars for the month of JUNE 2019 and JULY 2019 are enclosed at
Annexure-2.1. The brief detail of frequency profile is given here under:-
Month Average frequency
Minimum Integrated frequency over an hour
Maximum integrated frequency over an hour
Instantaneous Minimum Frequency
Instantaneous Maximum Frequency
JUNE 2019 50.00 Hz 49.80 Hz 50.23 Hz 49.63 Hz 50.31 Hz
JULY 2019 50.01 Hz 49.83 Hz 50.16 Hz 49.64 Hz 50.32 Hz
2.2 Operational Matters
2.2.1 Operational Discipline: The committee was apprised that system operated in terms of frequency
profile for the months JUNE 2019 & JULY 2019 is as given below for discussion by the committee:
Month % of time Frequency Below 49.90 Hz
% of time Frequency above 50.05 Hz
% of time frequency within the permissible range of 49.90-50.05 Hz.
Average monthly frequency
JUNE 2019 9.87% 19.79% 70.34% 50.00 Hz
JULY 2019 7.09% 24.64% 68.27% 50.00 Hz
2.2.2 Voltage Profile: The committee was apprised that during the months JUNE 2019 & JULY 2019 the maximum and minimum voltage as recorded at following important 400 KV s/s in MP Grid: -
Sr. No.
Name of 400 KV
Substation
JUNE 2019 JULY 2019 Max. Voltage Min. Voltage Max. Voltage Min. Voltage
Observed Observed Observed Observed
Voltage KV
Date Voltage KV Date Voltage
KV Date Voltage KV Date
1 Indore 416 02-06-19 399 19-06-19 416 06-07-19 400 20-07-19 2 Bhopal 418 02-06-19 399 12-06-19 417 07-07-19 398 23-07-19 3 Nagda 419 13-06-19 402 07-06-19 420 28-07-19 403 20-07-19 4 Satpura 420 02-06-19 407 07-06-19 421 07-07-19 406 23-07-19 5 SGTPS 420 15-06-19 407 08-06-19 424 31-07-19 407 23-07-19 6 Bina 416 02-06-19 398 23-06-19 416 07-07-19 398 23-07-19 7 Pithampur 420 13-06-19 404 19-06-19 418 28-07-19 404 20-07-19
Minutes of 71st OCCM of MP 2
8 Ashta 423 26-06-19 407 12-06-19 425 07-07-19 406 23-07-19 9 Julwania 419 01-06-19 408 19-06-19 419 01-07-19 412 19-07-19
Committee was informed that the voltage at 400 KV S/s Kirnapur is continuously on higher side and the loading on transformers is also on higher side since the commissioning and charging of substation. Further Chairman OCC stated that P&D, MPPTCL shall explore possibility and propose a plan for installing suitable capacity reactor for maintaining voltage at 400KV S/s Kirnapur. 2.2.3 Status of Capacitor Banks in sub-transmission system: The committee was apprised about the updated information of the status of capacitor banks in sub-transmission system as on 31th JULY 2019 as submitted by DISCOMs is detailed below:-
. East & Central Discoms were requested to kindly ensure to provide the desired information within stipulated time. Further the coordination with East Discom Control room is not proper in all respects, hence East Discom shall ensure to provide the required data. Member Secretary OCC stated that during ensuing rabi there will be low voltage problem in some pockets, hence Discoms shall ensure the healthiness and availability of capacitor banks. 2.2.4 Status of Shunt Capacitor Banks installed at various EHV Transmission Substation: The committee was apprised about the updated information of the status of installed capacitor banks (in MVAR) in EHV transmission system as on 31.07.2019 as submitted by MPPTCL is given below:-
Voltage Class
Capacitor bank installed as on
31.05.19(MVAR)
Capacity Added after Last OCC
Meeting (MVAR)
Capacitor banks already covered under ADB T-V
TOTAL CAPACITY AS ON 31.05.19
(MVAR)
Capacitor Bank Installed but
defective & are not repairable (No &
MVAR) 220 KV 100.00 0.00 - 100.00
All in Service 132 KV 1238.00 0.00 - 1238.00
DISC
OM
Capacitor bank installed in good condition (No)
Capacitor Banks healthy but not in service due to control ckt problem
Capacitor bank installed but defective & are repairable (No)
Requirement of repair against each unit (No)
Requirement against non-repairable capacitor banks
Capacitor banks already covered under ADB T-V
Balance capacitor banks to be covered in other schemes
600 KVAR
1200 KVAR
1500 KVAR
600 KVA
R
1200 KVA
R
1500 KVA
R
600 KVAR
1200 KVAR
1500 KVAR
No of 100 KVAR Units
required
600 KVAR
1200 KVAR
600 KVAR
1200 KVAR
600 KVAR
1500 KVAR
EZ 449 156 75 - - - - - - - - - - - - -
CZ 1 687 826 - - - 1 0 0 3 0 0 0 0 0 0
WZ 613 550 725 10 3 1 23 12 15 207 08 16 - - - 0
Minutes of 71st OCCM of MP 3
33 KV 5339.50 60.00 - 5399.50 Total 6677.50 0.00 - 6737.50
The members has noted.
2.2.5 Status of completion of ongoing Transmission Schemes being executed by MPPTCL: The committee was apprised about the various ongoing Transmission Schemes completed during the financial year 2019-2020 (up to JULY 2019) and plan for completion of various ongoing Transmission Schemes for the Year 2019-2020 is enclosed as Annexure 2.2.5(i) and 2.2.5(ii) respectively.
The members has noted.
2.2.6 U/F and df/dt Relay Operation (i) U/F and df/dt Relay Operation: The committee was apprised that frequency did not touch 49.20 Hz
during JUNE 2019 and JULY 2019. There was no df/dt operation during the same period. MPPTCL informed that under Frequency Plan for all the stages have been implemented and in operation.
(ii) Defective u/f, df/dt relays: The committee was apprised that MPPTCL has informed that all the df/dt and U/F relays are in operation, where the U/F relays are not available, the numerical relays programmed for under frequency operation. All U/F stages are in good/ healthy & working condition. 2.3 Power Cuts / Load restrictions/Differential Load Shedding by DISCOMS & group allocation to
33 KV feeders: (i) The committee was apprised that the details of DISCOM wise Power supply given to various domestic
categories during the period JUNE 2019 and JULY 2019 is enclosed at Annexure 2.3(i).
(ii) Group Allocation to Newly Commissioned existing EHV substations:- The committee was apprised
about the region wise list of 33 KV feeders emanating from various newly commissioned/existing EHV
substations for which groups have not been allocated is given in Annexure 2.3 (ii). The DISCOM wise details
of pending group allocation to 33 KV feeders is given below:-
SN DISCOM Region No of 33 KV feeders for which groups to be allocated
01
EAST
Jabalpur 17 02 Sagar 02 03 Rewa 02 04 Total 21 05
WEST Indore 03
06 Ujjain 04 07 Total 09 08
CENTRAL Bhopal 23
09 Gwalior 00 10 Total 23
TOTAL Grand Total 53
Minutes of 71st OCCM of MP 4
Discoms are requested to furnish the details as per list enclosed at Annexure-2.3(ii) in the meeting. In view of the above it is requested that the order copy for which group have been allocated may
please be submitted to P&D, MPPTCL under intimation to SLDC. The matter has been discussed.
ITEM NO. 3 : OPERATIONAL PLANNNING: 3.1 Generating Units under planned outage and proposed maintenance programme: The annual maintenance /outages of thermal generating units of MPPGCL for FY 2019-2020 as intimated by ED(O&M:Gen.) is NIL for the month OCT-19 to DEC-19. Representative from MPPGCL informed that the maintenance of all the Units has been completed and hence there no outage is required on the Units.
3.2 Proposed shutdown programme of Transmission lines / Transformers: The committee was apprised about the proposed shutdown of transmission elements for the period 01.09.2019 to 31.12.2019 as submitted by T&C, MPPTCL, enclosed as Annexure-3.2.
The matter has been discussed.
3.3 Long Outages of transmission elements and protections: The status submitted by MPPGCL /MPPTCL are given below:-
Sr. No
Line/Transformer/ etc under long Outage
Outage date Reason Response from Utility
1. 20MVA BHEL make X’mer at 132KV S/S Khachrod. 27.03.2019
X’mer was taken under for pre monsoon maintenance and testing work on
27.03.2019. Shutdown is continue
as the tan-delta values of transformer
windings are measured
considerably high.
MPPTCL informed that X’mer is being replaced by 50 MVA X’mer. MPPTCL informed the committee that the transformer will be commissioned by end of Sept-19.
2 20MVA BBL X’mer at 220 KV S/s Rajgarh(Biora). 30.05.2019 X’mer tripped on
differential indication
MPPTCL informed that X’mer is under investigation & testing. Transformer is being replaced by another 20MVA transformer by Sept-2019 end. Chairman OCC stated that Rajgarh is a District Headquarter and load is being managed by only one transformer, hence X’mer shall be replaced on priority so that load can be managed during contingency. Representative from MPPTCL informed the committee that new 50 MVA X’mer is also being commissioned against augmentation of existing transformer.
Minutes of 71st OCCM of MP 5
3 100 MVA 220/33KV X’MER at 220KV S/S Badnagar
21.06.2019 X’mer Tripped on differential trip indication.
Transformer tripped on differential trip indication with 33KV Multhan Discom feeder. MPPTCL informed the committee that the transformer has been charged on 27.08.2019.
4 40 MVA BBL, 132/33KV Transformer at 132KV S/S Sagar
07.07.2019 X’mer tripped on
differential trip indication.
Transformer tripped on Differential trip indications, under investigation and testing. MPPTCL informed the committee that the transformer will be commissioned by end on OCT-19.
5 63 MVA GEC, 132/33KV Transformer at 220KV S/S Mahalgaon, Gwalior
10.07.2019 X’mer tripped on
differential trip indication.
Transformer tripped on Differential trip indications, under investigation and testing. MPPTCL informed the committee that the 63MVA X’mer has been replaced by 50 MVA X’mer and charged on 16.09.2019. Chairman OCC stated that seeing to the loading of Mahalgaon the 50MVA X’mer shall be run separately. Hence MPPTCL shall inform SLDC about the operation of X’mer i.e., it will run in parallel or not.
6 160MVA BHEL X’mer – 2 at 220KV S/s Satna.
14.08.2019
B-Phase bushing & OLTC selector switch failed due to heavy
lightening.
MPPTCL informed the committee that the transformer is on the way and is expected to reach site by 15.10.2019. MPPTCL informed the committee that the X’mer will be commissioned after Diwali.
7 500 MVA, 400/220 KV X’mer at STPS. 19.04.2018
X’mer tripped at 21:55 Hrs. due to LA Burst. Emergency shutdown taken for 15 days from
21.04.18 to 05.05.18 for CPRI oil filtering and
RLA testing work.
In 70th OCCM it was apprised to the committee that as decided, MPPGCL will purchase &provide 315MVA, 400/220KV ICT by Dec-19 against an order of MPPTCL, existing 3 no. feeders will be integrated through GIS& MPPTCL will reroute remaining 3 no. feeders. Thereafter STPS Ubit#6&7 will phase out. MPPGCL informed that extension order for 1 no. 400/200KV, 315 MVA ICT has been placed by CE Procurement MPPTCL, vide order No. 04-01/TR-68/2018/04725-7-Extn./SI/4512 dtd-07/08/2019 to M/s BHEL. The delivery at site is expected upto June 2020. MPPGCL informed the committee that the X’mer will be commissioned as soon as the X’mer is delivered. MPPTCL informed the committee that the X’mer will be delivered by Dec-19.
Minutes of 71st OCCM of MP 6
8 50 MVAR (Make GE) Line Reactor at 400KV Sarni-Asta Ckt-I.
31.03.2018
Under outage since 31.03.18 due to concentration of
Acetylene gas. DGA test of transformer oil of
reactor was carried out by M/s CPRI, Bhopal.
MPPGCL informed that NIT has been uploaded on dtd-20.08.2018 & enquiry has been opened on 19.09.2018 and certain queries on techno commercial issues have been sought from M/s GE(T&D) India(OEM). Price bid opened on 05.12.2018 & order was placed on 01.03.2019. it is expected to bring back the reactor in service after rainy season. MPPGCL informed the committee that the it is expected to commissioned by OCT-19.
The matter has been discussed.
ITEM NO. 4 : OPERATIONAL STATISTICS FOR THE MONTH OF JUNE 2019 AND JULY 2019: The committee was apprised about the details of actual generation, Schedule from Central Sector, demand etc. are given in the following Annexures: Annex. 4.1 Unit wise actual Generation of MPPGCL thermal Units and station wise Generation of
MPPGCL & NHDC Hydel Units. Annex. 4.2 Power Supply Position(Energy Balance Sheet).
POWER SUPPLY POSITION FOR THE MONTH : Jun 19 All Fig in MW
Particulars
Max Dem Met on : 05-Jun-19 AT : 07-
15
Average 01-10 June
Average 11-20 June
Average 21-31 June
Average Monthly
STATE PEAK DEMAND MET 9955 9011 8298 7388 8205
BREAKUP :-
STATE THERMAL (Actual Gen) 2502 2471 2053 2187 2237 STATE THERMAL (RSD) Total MW 0 36 77 37 50
STATE HYDEL 475 296 174 121 197
IPP (STATE) 351 315 340 330 328
CENTRAL SECTOR (Schedule) 3164 2708 2960 3105 2924
CENTRAL SECTOR (Surrender) 302 537 528 510 525
IPP (INTER STATE) 2259 2295 2364 2252 2304
RAILWAY 241 231 227 235 231
RENEWABLE ENERGY 1272 1177 990 752 973
OTHERS -269 -107 -72 -137 -105
Minutes of 71st OCCM of MP 7
BANKING / PURCHASE / SALE 0 -321 -600 -784 -575
DEVIATION -39 -55 -137 -265 -152
DEVIATION (AVERAGE) Between (-871 to 467)
Between (-1063 to 710)
Between (-1338 to 372)
Between (-1338 to 710)
ENERGY SUPPLY STATE (LU) 2213.10
POWER SUPPLY POSITION FOR THE MONTH : July 19 All Fig in MW
Particulars
Max Dem Met on : 19-Jul-19
AT : 07-00
Average 01-10 July
Average 11-20 July
Average 21-31 July
Average Monthly
STATE PEAK DEMAND MET 9845 6543 8235 7988 7601 BREAKUP :-
STATE THERMAL (Actual Gen) 2620 2315 2523 2708 2522 STATE THERMAL (RSD) Total MW 0 96 38 228 124
STATE HYDEL 1243 143 372 276 264
IPP (STATE) 197 185 206 197 196
CENTRAL SECTOR (Schedule) 3011 2273 2906 3063 2757
CENTRAL SECTOR (Surrender) 200 618 319 470 469
IPP (INTER STATE) 2029 1878 1876 1878 1877
RAILWAY 241 231 234 236 234
RENEWABLE ENERGY 567 1002 1179 881 1016
OTHERS -12 -132 -98 -95 -108
BANKING / PURCHASE / SALE -548 -1273 -969 -888 -1038
DEVIATION 496 -79 28 -38 -30
DEVIATION (AVERAGE) Between (-1026 to 917)
Between (-899 to 943)
Between (-690 to 871)
Between (-1026 to 943)
ENERGY SUPPLY STATE (LU) 2125.58
Annex. 4.3 Hourly Average of Availability and Demand.
Annex. 4.4 Hourly average schedule Vs Drawal of DISCOMs.
The members has noted.
Minutes of 71st OCCM of MP 8
ITEM NO. 5 : SYSTEM DISTURBANCE IN MP DURING OF JUNE 2019 AND JULY 2019: The committee was apprised about the Grid Disturbances and Grid Incidents in MP during these months are given in Annexure 5. The members has noted.
ITEM NO. 6.0 : IMPORTANT OPERATIONAL ISSUES:- 6.1 STATUS OF COMPLETION OF ONGOING SCHEMES FOR COMMISSIONING OF REACTORS / TRANSMISSION ELEMENTS:- The committee was apprised about the present status
regarding schedule and commissioning of reactors / transmission elements is as below:-
S.No. 400 KV S/s Size MVAR Implementing Agency
Expected Date of Commissioning as intimated in last OCC
1. Line Reactor on 400 kV Sapura–ISP line at STPS
50 MVAR MPPGCL
In 66th OCC MPPGCL informed that the price bid has to be opened and the reactor will be commissioned by June 2019. MPPGCL informed the committee that the reactor is expected to be installed by June-2020.
2. Bus Reactor at SSTPS 125 MVAR MPPGCL
Work will be carried out under PSDF as intimated by MPPGCL in 62nd OCC in 66th OCC MPPGCL informed the committee that the drawing has been approved and reactor is expected to be commissioned by March 2019. In 68th OCC, MPPGCL informed the committee that reactor will be commissioned by October 2019. MPPGCL was apprised that considering commissioning of unit 3 and 4 at SSTPS stage II, early commissioning of 125 MVA reactor is required to ensure secure operation of grid. MPPGCL informed the committee that the reactor is on foundation, the remaining work is in progress.
6.2 FREQUENT TRIPPING OF 220 KV SATNA (PG)-KOTAR LINE IN FIRST TIME CHARGING:- The committee was apprised that 220 KV Satna (PG)- Kotar line was first time charged at
00:00 hrs on 23.08.2019 after FTC approval of WRLDC, consequent upon bunching of 220 KV Satna-Satna
(PG)-IV Circuit with 220 KV Satna-Kotar Circuit-II. However, line did not hold and declared faulty. The work
permit has been issued to AE (TLM) with instructions to perform patrolling. This line was again charged three
times as detailed below after receiving clearance on basis of patrolling done by EHT(Maint) team, but line did
not hold: 1. 15:43 hrs 23.08.2019
2. 18:40 hrs 24.08.2019 (As reported at location No.104 & 122 top phase conductor found flagged over).
3. 17:18 hrs 25.08.2019 (As reported at location No. 67 & 64 disc insulators were found flagged over).
Thereafter the line was charged multiple times but did not hold.
Minutes of 71st OCCM of MP 9
The frequent failure of charging the line is not desirable for system safety point of view, as Satna is an
important node. The frequent charging of faulty line may lead to system disturbance. The WRLDC has also
viewed seriously regarding repeated tripping of line. The line was finally charged on dtd-09.09.2019 at hrs
after multiple trial charging.
Representative from EHT-M informed the committee the after each tripping inspection of line was
done as per the distance indicated in the relay indication and as no discrepancy/fault was detected on visual
inspection then only the trial charging of the line was taken. Later after 4th tripping the complete inspection was
done and the string between Loc No. 141,142 & 143 was replaced and thereafter the line was successfully
charged.
The matter was discussed in the meeting.
6.3 DELAY IN SUBMISSION OF OPERATIONAL DATA BY DCC, JABALPUR AND NON-FUNCTIONING ROUND THE CLOCK:- The committee was apprised that in the subject matter, it is
mentioned that during recent past difficulties are being faced to get forecasted demand of East Discom from
DCC Control Room which creates operational difficulties. In case of non-availability of accurate forecast
demand, it is very difficult for SLDC to manage the grid in real time and it is also difficult to plan the schedule
of availabilities. It is observed that the accurate data from Discom are not being furnished timely. It has also
been pointed out that supply hours of East Discom should have provided regularly within stipulated time so
that same may be incorporated in consolidated DPR. However, in spite of regular reminders no action has
been taken so far. The representative of East Discom was requested that DCC Control Room may be advised suitably to
provide desired operational data timely without fail for smooth operation of grid.
6.4 TRIPPING REPORT OF INCIDENCE TOOK PLACE ON DTD 26.06.2019 AND 27.06.2019 AT 400 KV SUB STATION ASTHA:- The committee was apprised that on dtd 26.06.2019 at 13:16 hrs.
315 MVA transformer No.II tripped without any indication at 400 KV substation Astha and the same was taken
into service at 17:22 hrs on 26.06.2019. However, at 17:46 hrs on dtd 26.06.2019, 315 MVA transformer No I
& II again tripped. The transformer No II & I was normalized at 18:14 hrs and 18:42 hrs respectively on the
same day. On dtd 27.06.2019 at 17:24 Hrs., 315 MVA transformer No I & II tripped from 220 KV side without
any indication. The transformers were normalized subsequently on the same day. The frequent tripping of 315
MVA ICT No. I & II is dangerous to system security and healthy system operation, which requires thorough
investigations to rectify the cause. The T&C department may kindly comment on the matter so that the same
may be discussed.
MPPTCL informed the committee that the tripping occurred due to DC leakage and the DC leakage
has been attended.
The matter was discussed in the meeting.
6.5 COLLAPSE / DAMAGE OF TOWERS AND RESTORATION THEREOF:- The committee was
apprised that the 400 KV Pithampur- SSTPS Ckt No. I & II tripped at 15:26 hrs on 02.06.2019. It is reported that
24 nos towers are found collapsed / damaged at different locations. It is desired that 400 KV Pithampur – SSTPS
Minutes of 71st OCCM of MP 10
Ckt – I & II may be restored before ensuing rabi season positively. Similarly, one tower of 220 KV Narsinghpur-
Jabalpur Ckt No. I & II damaged at 19:17 hrs on dtd 13.06.2019. It is requested that restoration plan of tower collapsed/ damaged may please be provided so that the
same may be apprised to WRLDC.
In the above context, it is also indicated that due to outage of 220 KV Narsinghpur Ckt - I&II, long outages in
Narsinghpur-Pipariya Corridor is not being permitted. Therefore a few work of tower shifting work is held up.
Therefore, it is also requested that damaged tower of 220 KV Narsinghpur-Jabalpur Ckt No I & II may be
restored on top priority basis.
Representative from EHT-M informed that 7 no. tower is under submerged condition hence tower
erection is interrupted. Further the line on those 7 locations is being diverted and line is being shifted on ERS.
The tower erection work for 220 KV Narsinghpur – Jabalpur Ckt – 1 & 2 is completed and line stringing
work is under progress and the work is slowed down due to crossing of National Highway and also crossing of
33KV & 11KV Discom feeders which requires Discom consent for S/D.
The matter was discussed in the meeting.
6.6 PROTECTION AUDIT IN MP :- The committee was apprised that as per the recommendations of
Enquiry committee on Grid Disturbance of 30.06.2012, Protection Audit of all the substations is required to be
carried out once in 5 year and the Protection Audit of newly commissioned substations be carried out within
one year of its commissioning.
In 38th meeting of WRPC held on 28.06.2019, it was decided that Second Phase of Third Party Protection
Audit has become due for the substations of Western Grid and requested all the constituents to carry out the
Protection Audit of substations at the earliest in compliance to CERC directives. In the meeting MP-SLDC has
been entrusted with the responsibility of carrying out Protection Audit in the state of Madhya Pradesh. Thus,
the MP-SLDC has planned to carry out Protection Audit of 220 KV Substations and Generating Stations by
constituting the teams from various entities of the state grid in a phase manner.
Thus, in order to comply with the directives of CERC, MP-SLDC has constituted 5 no. teams for carrying
out Protection Audit of some of the 220 KV Substations/Generating Stations. Each team has been assigned 3
nos. of substations. The name of the substation and date on which Protection Audit is proposed to be carried
out along with the team member details is enclosed as Annexure – 6.6. Further the format for protection audit
has been e-mailed to the site offices of MPPTCL & MPPGCL where the protection is proposed to be
conducted. Hence the concerned officials are requested to kindly ensure the availability of the data in the
prescribed format to the protection audit team, so that the same may be verified and data may be
authenticated during the protection audit.
The matter was discussed in the meeting.
6.7 FREQUENT TRIPPING OF 132 KV VSTPS – WAIDHAN CKT – I AND 132 KV VSTPS – WAIDHAN – MORWA CKT – II:- The committee was apprised that 132 KV VSTPS –
Waidhan Ckt – I & 132 KV VSTPS – Waidhan – Morwa Ckt – II is tripping frequently as detailed below:-
NAME OF ELEMENT JUNE 2019 JULY 2019
Minutes of 71st OCCM of MP 11
132 KV VSTPS – WAIDHAN CKT – I
18.49/08.06.19 10.32/02.07.19 06.12/14.06.19 15.32/06.07.19 02.38/22.06.19 14.44/18.07.19 02.38/25.06.19 15.18/18.07.19 16.28/30.06.19 10.57/19.07.19
12.44/21.07.19
19.13/24.07.19
132 KV VSTPS – WAIDHAN – MORWA CKT – II
23.17/12.06.19 10.32/02.07.19 16.28/30.06.19 15.32/06.07.19
12.44/21.07.19
19.13/24.07.19
It is to intimate that the above mentioned circuits are inter-state circuits and frequent tripping of these
circuits causes interruption Waidhan, Morwa & Rajmilan substations. MPPTCL is requested to kindly
investigate the reason for frequent tripping of these circuits and address the issue so that the tripping of these
circuits is not repeated in future.
EHT-M was requested to investigate and inspect the lines so that the above tripping can be avoided.
Further P&D, MPPTCL was requested to explore the possibility for commissioning of 220 KV S/s in Morwa or
Waidhan area so that the interruption in these areas can be avoided. The matter was discussed in the
meeting.
The matter was discussed in the meeting.
6.8 FREQUENT VARIATION IN SCHEDULING OF SSTPP UNIT BY MPPMCL:- The
committee was apprised that ED(O&M) generation, MPPGCL, Jabalpur has intimated vide letter no: 1500 dtd-
26.08.2019 that it has been seen that there is frequent backing down/up of scheduling is being given to
SSTPS Units without giving reasonable time to stabilize the unit on particular load. There is cases where after
ramp down upto TMM in a particular block the unit again schedule for ramped up in next block and vice-versa.
The MPPGCL has mentioned that thermal units are not designed to vary load such frequently as the thermal
units take time to stabilize the machine and to maintain the desired differential expansion and overall
expansion with other parameter of unit after ramp-up and ramp-down for safe operation. The MPPGCL has
requested to give 4 time block to run the machine on the same load.
The matter was discussed in the meeting along with the presentation of MPPGCL, enclosed as
Annexure-6.8.
MPPGCL stated that the generators are designed for base load and not for cyclic load. Hence it is
requested to kindly provide adequate time for Ramp Up/Down to avoid wear & tear of the machine and to
avoid Unit outage.
MPPMCL informed that frequent load variations are being done on the machines which are up on the
MOD list and not on all the machines.
Member Secretary OCC stated that MPPMCL provides the schedule following the Grid Code and
MPPGCL shall abide to it. Further he also stated that seeing to the IEGC clause quoted by MPPGCL the any
relaxation in operation of machine shall be entertained/discussed only if MPPGCL provides a letter from the
Minutes of 71st OCCM of MP 12
competent authority that the Machine is not designed for frequent load variations and is not safe & feasible for
such frequent operation which will be safe for the Machine & for grid operation.
The matter was discussed in the meeting.
6.9 REVIEW AND UPDATING LOAD DROPPING SCHEME/ SYSTEM PROTECTION SCHEMS (SPS) AT SUBSTATIONS IN M.P TO HANDLE EMERGENCY CONDITION: - The committee was apprised that considering the integration of new transmission elements in the grid it is to
bring to the notice that the existing load drop scheme shall also be reviewed and updated timely as per the
updated network. It is also to bring to the notice that at 132 KV S/s Chambal on dtd- 28.05.2019 at 13:04 Hrs.
132 KV Chambal – North Zone Ckt – I & II tripped as Y-Phase conductor of ckt – II snapped resulting in
overloading & tripping of 132 KV Indore SZ – Satsai Ckt & 132 Kv Indore SZ – E.Complex ckt even after
operation of load drop scheme. Hence it can be gathered that after up gradation of 132 KV North Zone S/s to
220 KV S/s North Zone the load drop scheme has not been revise accordingly. It is also to intimate that the
load drop scheme shall also be reviewed according to the increasing 33 KV load. MPPTCL is requested to review the existing load drop scheme (SPS) and to implement new load drop
scheme as per requirement as per undated network and submit to SLDC. In view of the above it is requested that the complete details of all SPS commissioned in MP by
MPPTCL along with load shed quantum, may be submitted to SLDC so that the copy of the same could be
placed in Control room of SLDC and concerned substation / power station for reference & record and the
same can also be submitted to WRLDC. It was informed to the committee that the details have been received from Khandwa Circle only and
MPPTCL was requested to submit the load dropping details of remaining circles.
The matter was discussed in the meeting.
6.10 WRLDC TRIPPING PORTAL:- The committee was apprised that as intimated by WRLDC in
529th WR-OCCM, that WRLDC has started a tripping portal from 01.06.2019 for uploading FIR, DR/EL and
other details related to the tripping of all 400KV elements, important grid elements, inter-state/inter-regional
links and lines connected to PGCIL. Further details major Grid Disturbance resulting in significant load
loss/generation loss is also required to be uploaded on the WR-Portal and as per IEGC 54.2(r), utilities need
to submit the data within 24 hours of the event. The link
(https://portal.wrldc.in/Trippingnew/Account/Login.aspx) , common user ID & password for the entities of MP
has been shared with all the entities vide this office letter No.07-05/RPC-51/ 18.06.2019.
As advised in 529th WR-OCCM, all Utilities are requested to use and submit the data through the
WRLDC tripping portal. Therefore, entities are requested to use and upload the FIR, DR/EL and other details
related to the tripping of elements mentioned above, in the Tripping Monitoring System of WRLDC within
stipulated time.
The matter was discussed in the meeting.
Minutes of 71st OCCM of MP 13
6.11 PROTECTION COORDINATION DURING INTEGRATION OF NEW INTRA-STATE ELEMENTS:- The committee was apprised that in compliance to the IEGC & WRLDC operating procedure
the protection coordination of the existing elements & adjacent substations shall be prior to integration of new
intra state elements. All the concerned entities were requested to ensure/review the protection coordination of
adjacent substations/elements and confirm the same along with the first time charging documents for intra
state elements also.
The matter was discussed in the meeting.
6.12 AVAILING SHUT DOWN ON NON-ISTS ELEMENTS (ELEMENTS FOR WHICH ONLY APPROVAL OF MP-SLDC IS REQUIRED) AND OUTAGE MODULE THEREOF:- The committee was apprised that the parallel run of the ABT, OA & MIS system is in progress and the outage
module has already been initiated (link:- http://223.31.122.117:8080/EltrixPortal/login.jsp). Further it is to
inform that the User ID and Password for all the circles/generating stations/EHT-M/EHT-C along with user
manual of the outage module has already been provided vide this office e-mail dtd-14.01.2019. Also vide this
office letter no. No No.07-05/174-B/Kalki/131 dtd-15.01.2019 all the concerned entities/authorities were
requested to communicate the User ID/Password & issue necessary directives to the respective authorities to
initiate the use of web based outage module.
In view of the reliability and safe & secure grid operation entities are requested to follow the outage
procedure and submit the outage request well in advance i.e., on D-3 basis by 17:00 Hrs. only the emergency
shut down request shall be made on D-1 day or in real time.
In view of the above all the concerned entities are again requested to submit/process the outage,
tripping, generator outage, generator start/stop, new element charging request through web based outage
module in addition to the existing practice. It is also to mention that from 01.04.2019 it will be mandatory to
process the outage request through outage module only, hence all the entities shall approach for approval of
shut down through outage module. It is also to mention that WRLDC has developed a separate portal for WR-
OCCM approval of outage of ISTS elements. Further outage on ISTS elements for integration of new element
shall be availed only after completion of FTC formalities and the outage request for ISTS elements shall be
provided well in advance i.e., one month prior as it requires WRPC approval which is provided in WRPC-
OCCM.
The matter was discussed in the meeting.
6.13 MAPPING OF FEEDERS:- The committee was apprised that it has been requested to initiate the
process of mapping of AUFLS feeders in SCADA system, however no any progress in this regard noticed so
far. In 8th NPC, it has been decided that WRPC would submit the details / progress of feeder mapping to NPC
Secretariat on regular basis (quarterly).
The representative of MPPTCL was requested that quarterly details/ progress of mapping of feeders
may kindly be furnished so that same may be communicated to WRPC for onward communication.
The matter was discussed in the meeting.
Minutes of 71st OCCM of MP 14
6.14 INSPECTION OF RELAYS OF AUTOMATIC UNDER FREQUENCY LOAD SHEDDING AND CERTIFICATION THEREOF: - The committee was apprised that it is desired that
for safe & secure operation of integrated system, the under frequency relay should be connected in the system
in healthy condition. Accordingly, WRPC is pressing hard to provide the self-certified status of healthiness of
relays of Automatic Under Frequency Load Shedding (AUFLS) and periodic checking of the same. Vide this
office various correspondence. The CE (T&C) and also SE(T&Cs) were requested to provide status of
healthiness of relays of Automatic Under Frequency Load Shedding on priority basis to SLDC, so that same
may be communicated to WRPC. Inspite of repeated request vide various correspondence, moreover the
matter had been raised in OCC meeting of MP in time to time, however the desired information are still
awaited from utilities. It is therefore desired that the above matter may be treated as urgent and status of healthiness of
Automatic Under Frequency Relays may be provided to SLDC and also the under frequency may be tested
periodically. In this context it is also mentioned that time to time WRPC official as well as SLDC official shall
visit the sub-stations to ascertain the healthiness of under frequency relay.
The matter was discussed in the meeting.
6.15 PROVISION OF SYNCHRONIZATION FACILITY AT EHV SUB-STATIONS OF MPPTCL
AND AT ALL POWER HOUSE: - The committee was apprised that as per Grid Code, the synchronization
facility should be available at all the Power Stations, 400 KV Sub-stations, 220 KV Sub-stations and 132 KV
sub-stations in the path of black start. In 60TH OCC meeting MPPTCL representative informed the committee
that order for 69 no. synchronization trolleys has been placed and 1 no. synchronization trolley has been
delivered for checking and testing purpose at 220KV S/S Barwaha. In subsequent meetings this issue has
been discussed. However, no any fruitful progress has been observed so far. In the above context it is
indicated that at Manikheda HPS and Rajghat HPS synchronization facility is not available. It is felt that every
Hydel Power station should be equipped with synchronization facilities invariably for system reliability and
Crises Management. Also at Manikheda HPS & Rajghat HPS single bus system exists, hence MPPGCL is
requested to explore the possibility for commissioning of Double Main Transfer Bus system. Thus, MPPGCL is
requested to provide synchronization facility at Manikheda HPS and Rajghat HPS and MPPGCL may kindly
provide status of making synchronization facility in aforesaid HPS. The matter was discussed in the meeting.
6.16 DELAY IN SUBMISSION OF DOCUMENTS FOR FIRST TIME CHARGING OF ELEMENTS:- The committee was apprised that as per procedure laid down by NLDC for integration of new
EHV elements into the grid and issuance of certification thereof vide letter dtd-26.05.2014, wherein it is
indicated that all transmission licensees intending to commission any transmission element belonging to them
and which is a part of a interstate transmission system shall submit FTC document for approval of RLDC.
Further WRLDC vide e-mail dtd-02.01.2019 intimated the launch of FTC Software along with the user manual. In view of the above it is to inform that, after registration the separate user id & password of MPPTCL
& MPPGCL provided by WRLDC was forwarded to respective entities so that they can upload FTC documents
Minutes of 71st OCCM of MP 15
through this new FTC portal (link-http://ftc.wrldc.in:8080/ftc_wrldc/). Hence all the respective entities are
requested to apply for integration of any transmission element belonging to them and which is a part of a
interstate transmission system through this FTC portal within the specified time limit (i.e., 10 days prior to
anticipated date of first time charging). It is requested that licensee / utilities shall strictly adhere with time
schedule for documentation of first time charging of new transmission elements of all interstate line and all
EHV elements 400kv and above. It may also be ensured that FTC formalities should have completed before
availing outage for integration of element. The authority submitted FTC document should ensure compliance
of protection/ metering/Telemetry issue in coordination with T&C official. It is also desired that all necessary
data should have made available to all adjacent s/s for relay coordination well before targeted date. The
authority submitted FTC document should ensure all formalities have been completed otherwise it would be
difficult to obtain clearance from WRLDC. In general, non-attachment of requisite papers/ SLD/ document of
standing committee approval or approval of competent authority for intrastate elements /approval of Electrical
inspector /noncompliance of relay coordination of adjacent s/s / providing information incorrectly caused delay
in obtaining FTC approval. Therefore, it is desired that FTC document completed in all respect may be
provided in stipulated time schedule so that FTC formalities could be completed within targeted date of
charging.
The matter was discussed in the meeting.
SA-1 :-DETAILED OPERATING PROCEDURE FOR BACKING DOWN, PART LOAD OPERATION, AND MULTIPLE START/STOP OF UNITS-COMPENSATION THEREOF:
The committee was apprised that as per clause no. 8.8(6) of MPEGC-2019, a Detailed Operating Procedure for backing down of coal based thermal units of the State Sector Generating Stations having 100% installed capacity tied up with MP Power Management Company Ltd. (MPPMCL)/Discoms of MP, and mechanism for compensation for degradation of heat rate, aux consumption and secondary fuel oil consumption due to Part load Operation and multiple start/stop of units, has been prepared by SLDC. The DOP had been circulated to all the members of OCCM on 13/09/2019 at approx.15.30 hrs. The concerned State entities were requested to go through the procedure and offer any suggestion, modification, clarification, if any.
Shri.S.S.Patel, SE(OA & ABT), SLDC informed the committee that the DOP has been drafted by
SLDC in accordance with MPEGC in line with CERC guidelines which shall be approved by MPERC. The
committee members were appraised about the procedure through a detailed power point presentation during
the meeting. Some of the important points discussed are given here under : -
1. Regulatory requirement.
2. Methodology for revival of generating station or unit(s) from RSD.
3. Mechanism for Compensation for Degradation of Heat Rate, Aux Consumption and Secondary
Fuel Oil Consumption, due to Part Load Operation and Multiple Start/Stop of Units.
4. Compensation for degradation of Heat Rate (SHR) and Auxiliary Energy Consumption (AUX).
5. Calculation of compensation, billing & submission of data by generator.
6. Issuance of compensation statement.
7. The committee was also apprised that the Procedure shall be reviewed after one year of its
approval and implementation based on feedback received from MP Genco, Discoms, SLDC and
MPPMCL.
Minutes of 71st OCCM of MP 16
Further a copy of presentation given during the meeting is enclosed as Annexure-6.17. The generator
has unanimously appreciated the Draft Proposal.
Representative from MPPGCL stated that the comments will be provided to SLDC after study of the
procedure.
During the discussion on the Compensation Mechanism, representative of Jaypee Bina stated that the
effective generation mentioned for calculation of Average Unit Loading (AUL) shall be scheduled generation
i.e. total of schedule under Long Term Contracts and bilateral transactions.
The representative of SLDC clarified that as per Clause-8.8.1 of MPEGC-2019, Compensation
Mechanism for Technical Minimum schedule for operation of Thermal Generating Station is applicable for
those SSGS whose 100% installed capacity is tied up / contracted with MPPMCL / Discoms of MP through a
Long Term Power Purchase Agreement. Thus no capacity is available for generator for trading power under
bilateral transaction, therefore the suggestion of representative of Jaypee Bina is not as per guidelines
contained in MPEGC-2019.
Representative from MPPMCL advised some typographic changes in the draft DOP, SLDC agreed to
look into the same and to incorporate feasible corrections in the DOP, if any.
SA-2 :- EXPERIENCE OF SOLVER PROGRAMME AND IMPLEMENTATION OF PILOT PROJECT OF RRAS IN THE STATE OF MP:-
The MP OCC committee was also apprised that in the 4th meeting of the FOR Sub Group Standing
Technical Committee on Reserves and Ancillary Services at State level held at Maharashtra SLDC, Kalwa,
Mumbai on dated 30.08.2019, MP had given a demonstration of "Solver Programme" for determination of best
economic despatch for all the 96 blocks of a day. In the programme, ramping up and ramping down values of
power plants/units are also considered. The Committee opined to go ahead for implementation of Pilot Project
on the same. For this , sub Committee has asked MPERC to issue a Suo-Motu order for implementation of
Pilot Project with uses of Solver Programme. MP is ready to share the experiences and extend any help in the
matter for any SLDC interested in learning economic load dispatching with the help of Solver Programme of
Excel.
The members of committee were apprised that we can deduce the final schedule which should have
been given in order to make the operation most economical. Then we have deduced the difference in original
schedule and Recommended schedule by Solver. Similarly, cost benefit calculations were done after running
solver for all 96 blocks of a day, and committee was apprised the same.In this way by using solver solution
only, we can prepare a day ahead or real-time basis power schedules. Similarly, solver solution can also be
used for analyzing the present-day scheduling procedure being followed. Improvement in that can also save a
lot of money.
The matter was discussed.
SA-3 :-2X50MVAR, 400KV BUS REACTOR AT 220 KV S/S PITHAMPUR:- The committee was apprised that initially 50MVAR, 400KV Bus reactor was commissioned at 400 KV
S/s Pithampur, thereafter one more 50MVAR capacity of bus reactor have been added. It is observed that
Minutes of 71st OCCM of MP 17
both bus reactors are being operated through one breaker. It was pointed out that why two separate breakers
have not been provided for each 50 MVAR Bus Reactor looking to its operational ease.
The MPPTCL representative has informed that there is no provision for separate breaker for both
reactors , however provisioning could be made for the same and this matter would be taken up with
authorities.
ITEM NO. 7: BLACK-START MOCK DRILL OF HYDEL POWER STATIONS : Black Start mock drill of Hydel stations of MPPGCL:- During 2019-2020 the proposed / tentative dates for
conducting black start mock drill at various Hydel power station of MP is detailed as mentioned below:-
S.NO. NAME OF HPS PROPOSED/TENTATIVE
DATE OF MOCK DRILL
1 TONS HPS 06.11.2019
2 BARGI HPS 28.11.2019
3 PENCH HPS 04.12.2019
All the concerned entities were requested to review the proposed tentative dates for conducting
black start mock drill and confirm the readiness in the meeting. It is also requested that the generators shall
intimate the Unit No. and the Bus No. on which the mock drill is to be conducted.
ITEM NO. 08: AVAILABILITY BASED TARIFF (ABT) RELATED ISSUES: 8.1 TESTING & CALIBRATION OF METERS AND NON-RECEIPT OF TIMELY JMR DATA:
1. SLDC representative requested CE(T&C) office to apprise about the status of testing / calibration of
interface meters as per Regulations 10 and 18 of Central Electricity Authority (Installation and operation
of meter) Regulation 2010 to the committee. CE(T&C) office representative informed that proposal for
placing order for testing / calibration of all interface meters is under process.
2. SLDC representative informed that inspite of repeated requests made by SLDC in the previous OCCMs
for issuing instructions to all circle office for furnishing the JMR data in standard format by 7th of every
month, the JMR data was received by SLDC after 10th of September 2019. He again requested the
CE(T&C) office for issuing instructions to field offices for furnishing the JMR data by 7th of every month.
CE(T&C) office has assured that instructions will be issued to all circle offices for furnishing the JMR
data in standard format by 7th of every month at email id - [email protected].
8.2 NON RECEIPT OF ABT METER DATA OF RAILWAY TSS THROUGH AMR SYSTEM:- SLDC representative informed that ABT meter data of following TSS of Railways is not being
received through AMR system.
1. Railway TSS Mansakra.
2. Railway TSS Khirkiya
3. Railway TSS Bhitoni.
4. Railway TSS Narsinghpur.
5. Railway TSS Mungaoli.
Minutes of 71st OCCM of MP 18
Railway representative informed that Mansakra & Khirkiya TSS end problem regarding downloading of
meter data shall be resolved within one week and meter data will be received by SLDC through AMR. SLDC
requested the Railways to coordinate with M/s Secure Meters Ltd. and MPPTCL for resolving the problems
related with downloading of meter data of remaining TSS through AMR installed at SLDC. Railways assured
for the same.
8.3 AMR FACILITY FOR THE ABT METERS INSTALLED AT MPPGCL :
SLDC representative informed that MPPGCL has provided AMR facility on 107 Nos ABT meters
installed at the interface points and all the meters were successfully integrated with AMR server. He also
informed that every month data of around 35-40 Nos. meters do not received through AMR to SLDC.
MPPGCL requested to take up the matter with site officials and M/s Secure Meters Ltd. to resolve the
problems related with non readability of meters which were integrated successfully and provide AMC of AMR
facility to M/s Secure Meters Ltd. so that complete data is received by SLDC. MPPGCL representative
intimated that matter is being taken up with M/s Secure Meters Ltd for providing AMC of AMR system.
SLDC representative informed that 15 minutes blockwise data recorded in the meter no. XD435287
installed at GT of SSTPS PH-II unit-III do not match with midnight data i.e monthly injection data. The issue
was informed to CE, SSTPP and ED(O&M:Gen), Jabalpur vide letter No.07-05/SG-11/SEM/347 on date
14.02.2019, however, no action is taken so far by MPPGCL. The same problem is also observed in the meter
no. XD435284 installed at GT of SSTPS PH-II unit-IV. MPPGCL representative intimated that matter has been
taken up with M/s Secure Meters Ltd. and with M/s L&T for resolving the problem.
8.4 TIME DRIFT IN ABT METER INSTALLED AT THE POOLING STATIONS OF WIND AND SOLAR GENERATING STATIONS AND SLIDING WINDOW PROBLEM:- SLDC
representative stated that as already informed in previous OCCMs, the following ABT meters installed at
Pooling Stations of Solar Power Projects has time drift and thus not recording the correct data. He also
informed that SLDC has already requested to Generators with copy to concerned licensee vide letter no. 2353
dated 31/08/2019 for time synchronization of the ABT meters with GPS so that correct DSM account of these
Wind and Solar Projects is issued by SLDC.
Sr.No. FEEDER NAME LOCATION NAME Location VOLTAGE LEVEL
Meter No
1. 33 KV UJAS -2
ICHHAWAR
132KV S/S
ICHHAWAR Grid S/s End 33 MPC59975
2. 33KV
BHADRESH_SUSNER 132KV S/S SUSNER Grid S/s End 33 XB593639
3. UJAAS-1 AGAR 132KV S/S AGAR Grid S/s End 33 MPC59595
4. UJAAS-2 AGAR 132KV S/S AGAR Grid S/s End 33 MPC59596
Minutes of 71st OCCM of MP 19
5. 33 KV UJAAS 1 BERCHHA 132KV S/S BERCHHA Grid S/s End 33 XB571652
6. 33 KV UJAAS 1 SUSNER 132KV S/S SUSNER Grid S/s End 33 XB571653
SLDC representative further informed that ABT meters installed at the following Wind and Solar
Generating Stations are recording the 15 minutes block wise data on sliding window principal thus block wise
data do not match with midnight data. These meters need immediate replacement.
Sr.No. Feeder Name Substation ABT Meter No. QCA NAME
1 33KV SUZLON-I SAILANA 132 KV S/S SAILANA
XE479853
REConnect Energy Solution Pvt Ltd
2 33KV SUZLON-II SAILANA 132 KV S/S SAILANA
XE479854
REConnect Energy Solution Pvt Ltd
3
33KV SUZLON-III SAILANA 132 KV S/S SAILANA
XE479855
REConnect Energy Solution Pvt Ltd
4 33KV SUZLON-I RATLAM 132KV S/S JAORA
XE479856
REConnect Energy Solution Pvt Ltd
5
33KV SUZLON- IV RATLAM 132KV S/S JAORA
XE479859
REConnect Energy Solution Pvt Ltd
6 33KV SUZLON- V RATLAM 132KV S/S JAORA
XE479860
REConnect Energy Solution Pvt Ltd
7 33KV SUZLON-IV AGAR 132KV S/S AGAR
XE479864
REConnect Energy Solution Pvt Ltd
8 33KV SUZLON-V (SUSNER-
III)
132KV S/S SUSNER
XE479867
REConnect Energy Solution Pvt Ltd
9 33KV SUZLON-III (AGAR- I), 132KV S/S AGAR
XE479863
REConnect Energy Solution Pvt Ltd
10 33KV SUZLON BEHAPUR
DALODA-I
220 KV S/s DALODA
XE479862
REConnect Energy Solution Pvt Ltd
11 33KV SUZLON BEHPUR
DALODA-II
220 KV S/s DALODA
XE479861
REConnect Energy Solution Pvt Ltd
12 33KV SUZLON I (SUSNER-
I),
132KV S/S SUSNER
XE479866
REConnect Energy Solution Pvt Ltd
Minutes of 71st OCCM of MP 20
13 33KV SUZLON I (SUSNER-
II),
132KV S/S SUSNER
XE479865
REConnect Energy Solution Pvt Ltd
14 33KV AVP POWER INFRA
PVT LTD.,
132KV S/S
SONKATCH
XD595991
XD595994
REConnect Energy Solution Pvt Ltd
15 33KV BADONI POWER PVT.
LTD.
132KV S/S MAXI
XD522128
XD558031
REConnect Energy Solution Pvt Ltd
16 33 KV M P Wind Farm,
Nagda Hill 220 KVS/SDewas XE525393 Manikaran Analytics Ltd.
17 33 KV Suzlon Gujrat Wind
Park , Barod 220 KV S/S Barod
XD595984
XD595980 Manikaran Analytics Ltd.
SLDC representative requested to DDCs, Indore & Bhopal to take-up the issue with concerned officials for
time synchronization and replacement of ABT meters. DCCs Indore & Bhopal assured to take up the issue
with concerned officials of Discoms.
ITEM NO. 9: SCADA and E&T RELATED ISSUES:
9.1 ARRANGENEMENT OF TELEMETRY OF IMPORTANT 220KV SUB STATIONS & 132KV S/S HAVING INJECTION FROM RENEWABLES/CAPTIVE POWER PLANTS OR HAVING INTERDISCOM FEEDERS /TRACTION FEEDERS:-
It was informed during the meeting that integration of telemetry of Four Substations (132 KV
Udaipura, 132 KV Nowgaon, 132 KV Khandwa & 132 KV VFJ) with SLDC SCADA is pending.
MPPTCL informed that procurement of RTUs is under progress & telemetry integration of all
substations shall be done shortly.
SLDC informed that 220 KV Sheopurkalan S/s is scheduled to be charged shortly & telemetry of this
substation is not provided to SLDC. MPPTCL informed that the all the required hardware materials have been
received & its telemetry integration shall be done shortly.
Further, SLDC informed that telemetry of Birsingpur HPS and Zinna HPS is also not available and
same needs to be provided by MPPGCL. MPPGCL informed that order for RTU & cables have been placed &
its delivery is expected soon.
SLDC informed that MPERC regularly monitors & enquires about the reason of RTUs pending for
integration & thus SLDC requested MPPTCL & MPPGCL to take up this matter on topmost priority.
9.2 TELEMETRY OF BUS VOLTAGE IN DFE RTUS :- SLDC informed that in substations having DFE RTUs, the telemetry of Bus voltage is extended through MFM provided for transformer telemetry. This results in wrong Bus Voltage in case of outage of transformer. The matter was discussed in 69th & 70th OCC meeting in which T&C representatives agreed to arrange to provide separate telemetry of Bus voltage. The matter was also pursued by SLDC vide UO dtd.13.09.19 & 20.03.19. However no progress in the matter was observed.
Minutes of 71st OCCM of MP 21
MPPTCL (T&C) informed that instructions in the matter have already been issued to field offices for providing telemetry of Bus voltage.
9.3 PROVIDING TELEMETRY OF ISOLATORS OF 400 KV SUBSTATIONS:- SLDC
informed that telemetry of isolators is required for real time grid monitoring as well as for better functioning of
EMS system. NLDC & WRLDC are constantly requesting to provide the telemetry of isolators of 400 KV, 220
KV substations & Generating Stations; and reason for non-integration of telemetry of isolator status.
The matter was pursued with MPPTCL vide this office UO dtd. 11.09.19 & 20.03.19. CE(T&C) vide UO
note dtd. 15.05.19 informed that suitable arrangements for integration of telemetry of isolators is being made &
it shall be integrated to SCADA RTU through CMR. However no progress in the matter was observed.
MPPTCL informed that there is no provision of integration of telemetry of isolators in the existing Transco
SCADA project & filed offices are instructed to work out the requirement regarding additional hardware and
CMRs. On receipt of the same action for procurement and additional work order shall be issued by concern
departments.
SLDC further informed that matter regarding providing telemetry of isolators of Generating Stations
was pursued with MPPGCL vide this office UO dtd.12.09.19 & also discussed in 70th OCCM in which
MPPGCL informed that telemetry of isolator status will be extended to SLDC SCADA system. Further the
matter was also taken up by ED(O&M:Gen) with all the MPPGCL generating stations vide letter dtd.12.07.19.
However no significant progress in the matter was observed. MPPGCL informed that telemetry integration of
isolators shall be done on top most priority wherever possible and in places where RTUs are under
replacement, provision of isolators shall be made while procurement of new RTUs.
SLDC also requested ISP to provide telemetry of isolators in response to which ISP informed that
isolator signals are already available in ISP SCADA system from where telemetry to SLDC is proposed to be
provided through IEC gateway. Accordingly, while commissioning of telemetry through ISP SCADA, the
isolators status shall be provided to SLDC.
SLDC pursued the matter with JP Bina to provide the telemetry of isolators in which JP Bina informed
that their SCADA upgradation is being carried out & the telemetry of isolators will be extended to SLDC after
completion of upgradation of their SCADA.
9.4 UPGRADATION OF EXISTING RTUS & DISCREPANCY IN TELEMETRERED VALUES RECEIVED FROM DIFFERENT EHV S/S & POWER STATIONS:- SLDC informed that the telemetry discrepancies pertaining to MPPGCL generating stations is detailed below :-
1. Satpura TPS :-
Sr.No. Description Unit Pending since
MPPGCL response in meeting dtd.30.10.18
MPPGCL response in 70th OCC
1 400 KV Satpura -Itarsi
MW 6 months - MPPGCL informed that shutdown will be required for transducer replacement. Shutdown approval was provided by SLDC & shutdown on 400 KV Satpura-Itarsi , However the discrepancies still exists & status of transducer replacement is not
2 400 KV Satpura-Koradi
MW 6 months -
3 400 KV Satpura-Seoni
MW 6 months -
Minutes of 71st OCCM of MP 22
provided by MPPGCL. 4. Gen-7 GT MVAR More than 1
year - MPPGCL informed that the unit is to be
dismantled, so procurement of transducer is not possible. SLDC requested MPPGCL to utilize the spare transducers, if any, for replacement. SLDC informed that transducers may also be arranged from MPPTCL wherein some RTU having same transducres is replaced with Dongfeng RTUS. However no progress in the matter has been observed.
5. 400 KV Astha 1 & 2
Line Reactor
Commissioning
MPPGCL informed that signals of reactor are configured in database of Satpura SCADA system but values are not being conveyed to SLDC. NIT has been issued for configuration of point & it shall be completed within one month.
MPPGCL informed that engineer of service provider will visit the site & it will be configured at the earliest. However despite continuous pursuance, the telemetry is still not available to SLDC.
6. Gen-8,9 Generating Transformer
MW,MVAR
One week
2. SGTPS :-
Sr.No. Description Unit Pending since
MPPGCL response in meeting dtd.30.10.18
MPPGCL response in 70th OCC
1. STN TR 1 (220 KV)
CB More than one year
MPPGCL informed that cabling work of breaker upto RTU panel is required to be done & shall be done within one month.
MPPGCL informed that no work has been done. MPPGCL is requested to provide current progress in the matter.
2. 220/33 KV Transformer
MW/MVAR
More than one year
MPPGCL informed that it shall be provided within one month.
MPPGCL informed that all the discrepancies will be rectified after procurement of transducers. MPPGCL is requested to provide the current progress in the matter. No response from MPPGCL in the matter from MPPGCL has been observed.
3. 400 KV Bus 1
Freq More than ten months
MPPGCL informed that corrective action including testing of transducer/arrangement of new transducer shall be completed within a month.
4. 220 KV Bus 2 Voltage More than ten months
MPPGCL informed that procurement of transducer is under process & it shall be commissioned by March-19. SLDC informed that recently RTU of Rajghat & Devlond has been replaced, so transducers can be arranged from Rajghat & Devlond till procurement of new transducers.
Minutes of 71st OCCM of MP 23
3. Gandhi Sagar HPS :-
Sr.No. Description Unit Pending since
MPPGCL response in meeting dtd.30.10.18
MPPGCL response in 70th OCC
1. 33 KV Rajasthan(Kuakheda) feeder
MW/MVAR
Commissioning
SLDC informed that the telemetry of this feeder is of utmost importance as it is an inter-regional feeder. MPPGCL informed that they will arrange for the telemetry of this feeder on priority.
MPPGCL informed that these discrepancies shall be rectified after upgradation of RTUs.
2. 132 KV Bus 1 Voltage 2 months Wrong Values No response from MPPGCL
3. 132 KV Bus 2 Voltage 2 months Wrong Values No response from MPPGCL
4. Rajghat HPS :-
SLDC informed that all above issues are pending since long time creating problem in grid
management. In response, MPPGCL informed that a separate meeting shall be conducted at SLDC with officers from Power Stations and SLDC, so that exact problems may be identified. SLDC requested MPPGCL to arrange the meeting on top most priority.
SLDC informed the list of telemetry discrepancies pertaining to MPPTCL/IPP substations is detailed below:-
(a) Transmission/ other Generating Substations :- Sl
No. Name of Substation Name of feeders/transformers
01 0 ISP
1.Telemetry of 125 MVAR Bus Reactor not available. 2.Telemetered values of 400 KV Nagda MW & MVAR is 10 times of actual value. 3. Telemetered values of 400 KV Indore-1 MW. 4. MVAR values of all generators
Non-current data of generators in OFF condition.
Digital telemetry including CB status, RGMO/FGMO & SOE is not available.
02 400 KV Bhopal 1. Wrong CB status 400 KV Damoh-1 Main CB 2. Wrong CB status of 400 KV Bina-1 Tie CB 3. Wrong CB status of 220 KV Bus Tie.
03 220 KV Rajgarh Biaora 220 KV TBC CB status
Sr.No.
Description Unit Pending since
MPPGCL response in meeting dtd.30.10.18
MPPGCL response in 70th OCC
1. Gen-3 CB Commissioning of new RTU
MPPGCL informed that it shall be rectified at the earliest.
Minutes of 71st OCCM of MP 24
04 400 KV Chhegaon Wrong CB status of :- 400 KV Transfer Bus Coupler 160 MVA Xmer-3
05 400 KV Julwaniya This problem is persisting since last 8 months. No
action in the matter has been taken. 1.All 132 KV CB status showing open. 1.CB of 220KV Sendhwa feeders is not available.
06 400 KV Katni Wrong CB status of 400 KV Damoh-1 & 125 MVAR Bus Reactor
07 220 KV Nimrani Telemetry of 33 KV Maral is to be provided
08 220 KV Indore East CB status of 220 KV Dewas
09 220 KV Sabalgarh
Faulty CB status of 220 KV Bus Coupler
10 220 KV Kotar Faulty CB status of 220 KV Satna PG
11 220 KV Satna Faulty CB status of 132 KV Kymore
12 220 KV Panagar Faulty CB status of 220 KV Sukha
13 220 KV Ujjain Faulty CB status of 132 KV Bus Coupler
ISP informed that case for addition of IEC gateway in ISP SCADA/EMS shall be completed by Nov-19.
MPPTCL informed to look into the matter and expedite the resolution of above discrepancy by next fifteen days. The list of discrepancy discussed is enclose as Annexure-9.4.
9.5 EXTENSION OF RGMO/FGMO SIGNAL TO SLDC/WRLDC :- SLDC informed that extension of RGMO/FGMO signal of following generating units is still pending:-
S.No. Name of Generating Station
Unit.No. MPPGCL response in last OCC
1 SGTPS 1,2,3,4 MPPGCL informed in last three OCC meetings that it is under tendering process & telemetry integration of RGMO/FGMO signal shall be completed within 3-4 months. However no progress in the matter has been observed even after lapse of 8 month period.
2 BARGI HPS 1,2 MPPGCL informed in last three OCC meetings that integration of RGMO/FGMO signal shall be done during AOH of units in 2019. However the AOH of Bargi HPS units has been done but the integration of RGMO/FGMO signal is still pending.
Minutes of 71st OCCM of MP 25
WRONG RGMO/FGMO SIGNAL STATUS :- S.No. Name of Generating
Station
Unit.No. Remarks
1 TONS 1,2,3 Incorrect RGMO/FGMO status of Tons HPS units is
being frequently observed. The matter was discussed
in OCC in which MPPGCL informed that problem is
due to requirement of manual intervention for ON
operation status of RGMO/FGMO. SLDC requested
MPPGCL to arrange for automatic operation of
RGMO/FGMO signal status through its OEM,
however no response from MPPGCL in the matter
has been observed.
2 ISP All units RGMO/FGMO signal is not available. The matter has
been pursued by SLDC, however the RGMO/FGMO
signal is still not available.
MPPGCL informed that they will arrange for resolution of wrong RGMO/FGMO status. 9.6(a) NON AVAILABILITY/ UNRELIABLE TELEMETRY OF HYDEL POWER STATIONS :-SLDC informed that the telemetry of Hydel Power Stations is very unreliable & frequent long outage with abnormal delay in restoration of same is observed. The RTU availability of MPPGCL HPS is as detailed here under :-
RTU AVAILABILITY JULY AVAILABILITY AUGUST
RAJGHAT HPS 90 81
BARGI HPS 86 85
MADIKHEDA HPS 84 80
GANDHI SAGAR HPS 87 99
PENC HPS 98 99
DEOLOND HPS 84 79
TONS HPS 82 80
SLDC informed that in hydel power stations, skilled manpower is not available for attending the telemetry
issues & considerable time is taken for restoration of telemetry.
SLDC further informed that the matter regarding arrangement of RTU/PLCC spares, measuring
instruments & adequate trained manpower at MPPGCL stations has been discussed in last various OCC
meetings. However MPPGCL has not taken any actions regarding this matter.
Minutes of 71st OCCM of MP 26
MPPGCL was thus again requested to take following measures to ensure round the clock availability of
real time data to SLDC:-
1. Arrangement of essential spares at power stations and one set of all spares at centralized location with
intimation to all power stations
2. Arrangement of training to persons looking after telemetry work.
3. Arrangement of measuring instruments like level meters wherever not available.
4. Ensuring availability of RTU configuration at all power stations.
MPPGCL agreed to look into the matter. Further, it was decided that the matter shall be discussed in the
proposed meeting with MPPGCL filed officers.
9.6(b) NON AVAILABILITY/ UNRELIABLE VOICE COMMUNICATION BETWEEN SLDC TO THERMAL/ HYDEL POWER STATIONS :- SLDC informed that despite constant pursuance
most of the PLCC voice communication of various power stations to SLDC is out since long time. The details
of outage are here as under:-
Sr.No Name of HPS/TPS
2 wire PLCC channel
MPPGCL response in meeting dtd.30.10.18
Remark
1.
Bansagar- IV
PLCC voice
communication is
not established
Mr.Vinay, AE, Tons HPS informed
that he will visit Bansagar-IV for
restoration of voice communication
of Bansagar-IV at the earliest.
Restoration of PLCC
channel is still
pending.NO action in
the matter is initiated by
MPPGCL.
2.
Madikheda
PLCC voice
channel is not
working since last
two and half years.
Restoration of PLCC
channel is still pending.
In last two OCCM,
MPPTCL was requested
to arrange for extension
of voice channel utilizing
Mahalgaon wideband
node in coordination with
Madikheda HPS.
3
Birsinghpur HPS
/TPS
PLCC voice
channel is not
working since long
time due to faulty
PLCC exchange at
Birsinghpur.
AE Birsinghpur informed that
presently voice communication
between SLDC to thermal power
house is proper & the
commissioning of EPAX at site is
under progress. AE Birsinghpur
Restoration of voice
channel is still pending.
Minutes of 71st OCCM of MP 27
assured that the voice channel of
Birsinghpur HPS shall be restored
within one month.
4.
Satpura TPS
PLCC voice
channel is not
working since last
one and half
years.
AE Satpura informed that faulty
card shall be repaired at the
earliest.
Repair/replacement of
Exchange & Card of
PLCC equipment at
Satpura TPS side is still
pending.
SLDC informed that matter regarding Non Availability/ Unreliable voice communication Between SLDC to
Thermal/ Hydel Power Stations was discussed in last various OCC meeting & special meeting on 30.10.18,
however 2 wire voice facility extension of Singhaji 1 & 2 TPS, Madikheda HPS is still pending.
MPPGCL agreed to arrange for the same. Further, it was decided that the matter shall be discussed in
the proposed meeting with MPPGCL filed officers.
9.6(c) REPLACEMENT OF RTUS IN THERMAL POWER STATIONS:- SLDC informed that
large no. of discrepancies pertaining to MPPGCL Thermal Power Station are pending since long time. The
various discrepancies are due to non-availability of desired spares, non renewal of AMC contract of RTUs,
Modems, PLCC equipments. The replacement of RTUS in thermal power stations is required to be arranged
to ensure round the clock availability of telemetry. SLDC informed that it was requested earlier to arrange the
replacement of RTUs. However, no feedback in the matter is provided to SLDC. SLDC has also pursued the
matter vide UO dtd.12.09.19. MPPGCL was thus again requested to arrange for replacement of RTUs in
Thermal Power Stations. MPPGCL informed that they will look into the matter and initiate action as soon as
possible.
9.7 DUAL DATA CHANNEL CONNECTIVITY FOR POWER STATIONS:-SLDC informed
that presently most of the Power Stations to SLDC/Backup SLDC only single channel is established. Looking
the data availability of Power Stations and recently implemented CERC new DSM regulation w.e.f. 1st January,
2019 it is required that each Power Station shall have dual data channel to avoid any outage/discrepancy in
real time data of Generation Station. Therefore to reduce outage due to single data channel failure, MPPGCL
& NHDC were requested to arrange / ensure dual data channel from each Power Stations so that continuity of
real time data to SLDC/Backup SLDC SCADA all the time may be achieved. MPPGCL representative
informed that the matter shall be discussed in proposed separate meeting with MPPGCL field officers. 9.8 NON AVAILABLITY & WRONG TIME STAMPING OF SOE AT SLDC SCADA:- SLDC
informed that on some instances, it has been observed that the SOE was not received or wrong time stamping
of SOE was received in SLDC SCADA system. The matter was taken up with field for verification for proper
configuration /connections of SOE data in RTUs & after long pursuance, the matter was investigated and it
was found that the settings “inf code 2” & “inf code 4” were not correct in Dongfeng make RTUs. These
Minutes of 71st OCCM of MP 28
settings have now verified and changed in some of the RTUs and SOE with correct time stamping from RTUS
where settings were modified is now receipt in SLDC SCADA/EMS system.
Further SLDC informed that the SOE verification of all RTUs is being done & out of 175 RTUs, SOE
verification of 165 RTUs has been done & requested MPPTCL to expedite the SOE verification of balance
RTUs at the earliest. MPPTCL informed that they have instructed all the field offices to coordinate with SLDC
for SOE verification. List of SOE verification pending is enclosed as Annexure-9.8.
9.9. UTILIZATION OF W.B NODE AT BIRSINGHPUR TPS :- SLDC informed that despite
constant pursuance utilization of node at Birsingpur TPS is still pending since last two years due to pending
work of laying of cable form W.B node location to PLCC room, Exchange room and RTU. It was informed by
SLDC that complete scheme to extend wideband facility upto RTU was prepared by SLDC and forwarded to
SGTPS around two years back. The matter is pursued by SLDC constantly. However, required converter and
laying of fiber optic cable is still pending. MPPGCL informed that the procurement of optical cable & modem is
under tendering process & it will be completed by end of October-19. 9.10 MAINTENANCE OF OPGW NETWORK :- SLDC informed that under the MP portion of Master
Telecom project executed by PGCIL,36 No. of wideband nodes has commissioned. As per agreement
between MPPTCL and PGCIL, the subsequent maintenance of these links is to be looked after by MPPTCL.
While execution of the project, it was informed by PGCIL that the AMC of the terminal equipments is covered
under the equipments contract. However, modalities for AMC payment is to be finalised by MPPTCL with
PGCIL. Further, separate arrangement towards maintenance of OPGW cable (upto FODP) involving OPGW
restoration, OPGW LILO work, OTDR testing, OPGW shifting during line diversion etc is to be made by
MPPTCL, the details for which has already been forwarded by SLDC. SLDC further informed that as per order
of CERC, the expenditure towards maintenance under the project shall be done by MPPTCL. SLDC further informed that some of the nodes installed under agreement between MPPTCL and
PGCIL is not utilized properly. The telemetry of 132KV Pichore is shifted to PLCC in place of restoration of
problem in wideband node. Similarly, as per the permission provided by MPPTCL for Chindwara repeater
station, PGCIL to arrange shifting of equipments from Chindwara to Daloda. However, the same is not done
by PGCIL. MPPTCL agreed to take up the matter with PGCIL.
Further, MPPTCL (T&C) informed that the matter regarding maintenance issues shall be taken up in a
separate meeting with all the other departments of MPPTCL.
9.11 LONG OUTAGE OF RTUS, PROBLEM IN DATA AND VOICE CHANNELS & INTERMITTENT TELEMETRY DUE TO NOISE IN COMMUNICATION CHANNEL :- The long outage of telemetry & substations having intermittent telemetry due to heavy noise in communication channel was discussed in detail:-
Sl No. Name of Sub Station Out from /Remark
01 220 KV Narsinghpur
Out since last 3 months due to outage in 220 02 220 KV Chichli
Minutes of 71st OCCM of MP 29
03 132 KV Gadarwara KV Jabalpur-Narsinghpur Ckt 1 & 2
04 132 KV Pondar
05 BLA TPS
06 220 KV Chhatarpur Out since 1 month
08 220KV Shahdol Very intermittent
09 220 KV Anuppur Very intermittent
10 220KV Sidhi Very intermittent
11 132 KV Waidhan S/s Very intermittent
SLDC requested MPPTCL & MPPGCL to sort out rectification of above RTU/data channel on top most priority. 9.12 TELEMETRY OF RAILWAY TSS SUB STATIONS: -
SLDC informed that the telemetry of existing 38 Nos railway Traction Sub Stations & upcoming 25
new railway TSS is required to be provided by railway for monitoring of drawal by each TSS and also
monitoring of demand of railway in MP.
SLDC further informed that testing of telemetry for 1 Railway TSS has been done in SLDC SCADA,
however it is currently offline since testing. Railways informed that telemetry integration of 24 Railway TSS
shall be done within a month.
9.13 ENSURING AVAILABILITY OF AIR CONDITIONER AT WIDE BAND NODES:- SLDC informed that availability of air conditioner is essentially required in wide band communication rooms.
Accordingly, SLDC is taking up the matter continuously for ensuring proper functioning of air conditioners in
wideband communication rooms. In last two OCCM, it was also informed regarding non-availability of air
conditioner at 220 KV Betul. MPPTCL informed that air conditioner has been installed in 220 KV Bhopal &
civil work in 220 KV S/s Betul is under progress and the installation of air conditioner shall be done shortly.
MPPTCL & MPPGCL were also requested to ensure availability & running condition of Air Conditioner
at following wide band nodes already commissioned :-
MPPTCL Substations MPPGCL Substations
220 KV S/s Satna
220 KV S/s Katni
400 KV S/s Bhopal
400 KV S/s Bina
220 KV S/s Jabalpur
Birsinghpur TPH
Gandhi Sagar HPS
Pench HPS
Minutes of 71st OCCM of MP 30
220 KV S/s Itarsi
400 KV S/s Indore
220 KV Chhindwara
220 KV Ratlam
220 KV Shivpuri
220 KV Indore (SZ)
220 KV Shujalpur
220 KV Neemuch
220 KV Gwalior
220 KV Bina
400 KV Pithampur
220 KV Barwaha
220 KV Seoni
220 KV Damoh
400 KV Nagda
400 KV Chhegaon
220 KV Bhopal
220 KV Rajgarh
220 KV Malanpur
220 KV Pithampur
Indore chambal
Indore SubLDC
132 KV Pichhore
220 KV Betul
MPPTCL assured to look into the matter on priority.
ITEM NO 10 : DATE AND VENUE OF NEXT OCC MEETING :
The matter was discussed and it is decided that next OCCM will be conducted in first fortnight of month of November 2019 , date and venue shall be decided later.
***********
Minutes of 71st OCCM of MP 31
Minutes of 71st OCCM of MP 32
Minutes of 71st OCCM of MP 33
Minutes of 71st OCCM of MP 34
Annexure-2.1
S. No. Particulars
1
1.1 Maximum Frequency 50.23 HzBetween 09.00 hrs & 10.00 Hrs on 16.06.19
50.16 HzBetween 13.00 hrs & 14.00 Hrs on 07.07.19
1.2 Minimum Frequency 49.8 HzBetween 22.00 hrs & 23.00 Hrs on 10.06.19
49.83 HzBetween 00.00 hrs & 01.00 Hrs on 04.07.19
1.3 Average Frequency 50 Hz 50.01 Hz
2
2.1 Maximum Frequency 50.31 HzAT 09.49.20 HRS ON 16.06.19
50.32 HzAT 15.50:50 HRS ON 15.07.19
2.2 Minimum Frequency 49.63 HzAT 22.10:50 HRS ON 11.06.19
49.64 HzAT 00.06:50. HRS ON 04.07.19
3 Percentage of time when frequency was :-
%age of time when frequency was Jun-18 Jul-19
3.1 Below 48.5 Hz 0.00 0
3.2 Between 48.50 Hz and 48.8 Hz 0.00 0
3.3 Between 48.80 Hz and 49.2 Hz 0.00 0
3.4 Between 49.20 Hz and 49.5 Hz 0.00 0
3.5 Between 49.50 Hz and 49.7 Hz 0.00 0
3.6 Between 49.70 Hz and 49.9 Hz 9.87 7.09
3.7 Between 49.9 Hz and 50.05 Hz 70.34 68.27
3.8 Between 50.05 Hz AND 51.5 Hz 19.79 24.64
3.9 Above 51.5 Hz 0.00 0.00
4 No. of times frquency touched 48.80 Hz 0 0
4.1 No. of times frquency touched 48.60 Hz 0 0
4.2 No. of times frquency touched 51.0 Hz 0 0
FREQUENCY PARTICULARS
INTEGRATED OVER AN-HOUR
INSTANTANEOUS FREQUENCY
Jun-18 Jul-19
Minutes of 71st OCCM of MP 35
I S.
No. NAME OF THE TRANSMISSION LINE / (FINANCED BY)
TYPE OF CIRCUITS
ROUTE LENGTH
CIRCUIT KMS.
MONTH OF COMPLETI
ON
DATE OF COMMI-SSIONING
1 2 3 4 5 6 7
A. 400 KV TRANSMISSION LINES
1 Nill
B. 220 KV TRANSMISSION LINES
1220kV DCDS line from Betul 220kV S/s - Gudgaon 220kV S/s (2x46.771) (GEC)
DCDS 46.77 93.542 June'2019Test charged
on 12.06.2019
22nd Ckt of 220kv Satna - Chhatarpur line (152) (JICA-I)
2nd ckt 160.00 160 Aug'2019charged on 29.08.2019
C. 132 KV TRANSMISSION LINES
1132 KV 2 phase 2 wire DCSS line for PS to 132/25 KV 5 MVA RTS at Sausar from 132 KV S/s Boregaon (RTS)
DCSS 17.413 17.413 May'2019charged on 25.05.2019
2132 KV Shyampur - Pilukhedi DCSS line (1x22.834) (UBI)
DCSS 22.83 22.834 June'2019charged on 28.06.2019
3
2nd ckt of 132 KV Sheopur- Baroda line & LILO of its both ckt at 220 KV S/s Sheopur for 132 KV interconnection of 132 KV S/s Sheopur & 220 KV S/s Sheopur. (2nd ckt- 34 cktkm+2x1+4x5) (UBI)
DCDS 5.13 5.131 June'20195.131 cktkm charged on 29.06.2019
4132 kv DCSS Karakbel - Belkheda (1x24.93) (ADB-III)
DCSS 24.93 24.93 June'2019charged on 30.06.2019
5
LILO of 2ND CIRCUIT OF 132KV Gwalior- Pichhore at 132Kv S/s Dabra (2X0.108) (ADB-III) (balance work) (Note: LILO at Chinour 27.364 cktkm charged on 04.08.2017)(ADB-III)
DCDS 0.11 0.216 June'2019comm on
03.06.2019
6132 KV line 2 phase 2 wire Nainpur - RTS Nainpur line (4.176) (CCW)
DCSS 4.176 4.176 June'2019 12.06.2019
7
LILO of 132kV Betul - Gudgaon at 220kV S/s Gudgaon (2x9.825)(132kV interconnector between Gudgaon 220 kV S/s & Gudgaon 132kV S/s (Note:LILO 1st ckt(2x5.092) charged on 24.01.2019)(2nd ckt 2x4.733) (GEC)
DCDS 4.73 9.466 June'20192nd ckt
charged on 20.06.2019
8 LILO of Satna 220kV-Kymore 132kV DCSS line for Uchehara (2x1.8) (JICA-II) DCDS 1.8 3.60 July'2019
comm on 18.07.2019
9132Kv DCSS line from GWSTPP to upcoming Make up Water Pump House river Narmada (Line-II)(1x24.515) (CCW)
DCSS 24.52 24.515 July'2019comm on
11.07.2019
10
LILO of Both circuit of 132 kv DCDS Gwalior(Mahalgaon) - Dabra/Karera line at 220 KV S/s Gwalior II) (2x2x5.95+2x1.278) (Transco/UBI)
DCDS 7.26 26.472 Aug'2019charged on 29.08.2019
11
2nd ckt of 132 KV Sheopur- Baroda line & LILO of its both ckt at 220 KV S/s Sheopur for 132 KV interconnection of 132 KV S/s Sheopur & 220 KV S/s Sheopur. (2nd ckt- 33.410 cktkm +1x1.896 +3x3.235) (Note- 5.131 cktkm charged on 29.06.2019) (UBI)
2nd ckt+DCDS
38.54 45.011 Aug'2019charged on 24.08.2019
12132Kv DCSS 2 phase 2wire line from 132Kv s/s Prithvipur to RTS Niwadi for p/s to RTS Niwadi (1x22.712) (RTS)
DCSS 22.71 22.712 Aug'2019charged on 09.08.2019
ANNEXURE - 2.2.5.i
M.P POWER TRANSMISSION COMPANY LIMITED
TRANSMISSION WORKS COMPLETED DURING 2019-20 (UP TO 31.08.2019)
EHV TRANSMISSION LINES
Minutes of 71st OCCM of MP 36
1 2 3 4 5 6 7
II.
S. No.
NAME OF SUBSTATION / (DISTRICT) / (FINANCED BY)
VOLTAGE RATIO
(KV)
No.OF X-mer &
Cap.(MVA)
EFFECTIVE CAPACITY
MVA
MONTH OF COMPL-ETION
DATE OF COMMI-
SSIONING
A. 400 KV SUBSTATIONS
1 Nill
B. 220 KV SUBSTATIONS
a. 220 KV NEW SUBSTATIONS
1 Nill
C. 132 KV SUBSTATIONS
a. 132KV NEW SUBSTATIONS
1 Bada malehra 132kv s/s 1x40MVA (ADB-III) 132/33 kV 1x40 40 May'2019charged on 30.05.2019
2 Pilukhedi 132kV S/s with 1x50 MVA (UBI) 132/33 kV 1x50 50 June'2019charged on 28.06.2019
3Karakbel 132kv s/s1x40 MVA (Dist. Narsinghpur) (ADB-III)
132/33 kV 1x40 40 July'2019comm on
25.07.2019
4Belkheda 132kv s/s 1x40 MVA (Dist- Jabalpur)(ADB-III)
132/33 kV 1x40 40 July'2019comm on
04.07.2019
EHV SUB - STATIONS
Minutes of 71st OCCM of MP 37
Annexure-2.2.5.ii
S. No. NAME OF THE TRANSMISSION LINECKT.KMS.
PROGRESS IN % (Aug'2019)
A. 400 KV TRANSMISSION LINES
1 400 kV DCDS line from Nagda 400 kV S/s to Mandsaur 400 kV S/s 137.32 58
2400 kV DCDS line for LILO of one ckt of Satna(PGCIL) - Bina(PGCIL) 400 kV at Sagar 400 kV S/s
56 85
3 400 kV DCDS line from Ashta 400 kV S/s to Ujjain 400 kV S/s 179.474 424 400 kV DCDS line from Indore (PGCIL) 765 kV S/s to Ujjain 400 kV S/s 84.528 85
5 400 kV DCDS line from Nagda 400 kV S/s to Ujjain 400 kV S/s 53.2 56
6 LILO of one ckt of 400 KV Khandwa - Rajgarh PGCIL line at Chhegaon 400 kV S/s 3.78 8
B. 220 KV TRANSMISSION LINES
1LILO of one Ckt of 220kv DCDS Ashta - Dewas line at 220kv S/S Chapda (DCDS) (2x32.782)
66 51
2 220Kv DCDS line from Pithampur-Depalpur line (2X31) 62 71
3220Kv FCFS line for LILO of both Ckt. Of Badnagar -Ratlam D/C line at 400Kv S/s Badnawar (2x1.453+4x6.161)
27.55 95
4 220Kv DCDS Julwaniya- Kukshi (2X58) 116 21
5 220Kv DCSS Shujalpur- Narsinghgarh line (1X43.6) 44 42
6 LILO of one circuit of Bhopal-Hoshangabad DC line at 220kV S/s Adampur 5.84 28
7Part (b).LILO of 220kV Sarni - Pandhurna at 220kV S/s Betul (2x38.864) (Note: Betul220 & Betul400 I/C line 3.76 cktkm. charged on 21.07.2017)
77.728 60
8 220kV DCDS line from Kanwan 220kV S/s - Dhar 220kV S/s 62.78 90
9LILO of both ckt Nagda - Neemuch 220kV line at 400Kv S/s Mandsore(Sitamau) (2x22.787+4x2.229+2x23.323)
101.136 53
10220kV DCDS line from Mandsaure(Sitamau) 400kV S/s - Maruti Shakti Pool 220kV S/s
92.294 51
11 220kV DCDS line from Neemuch 220kV S/s to Ratangarh 400kV S/s 85.016 76
12 2nd circuiting of Ratlam switching - Daloda 220kV DCSS line 72 84
13 LILO of Ratlam - Daloda 220kV line at 220Kv S/s Jaora (2x3.51) 7.02 69
14 LILO of both ckt of Ujjain - Badod 220 kV line at Ujjain 400 Kv S/s (2x6.4+2x5.691) 24.182 57
15 LILO of both ckt of Ujjain - Nagda 220 kV line at Ujjain 400 Kv S/s (2x2x11.766) 47.064 56
16 220kV DCDS line from Ujjain 400kV S/s to Susner (Nalkheda) 220kV S/s 156.00 717 220kV DCDS line from Badod 220kV S/s to Susner (Nalkheda) 220kV S/s 104.55 1818 220kV DCDS line from Rajgarh(B) 220kV S/s to Susner (Nalkheda) 220kV S/s 124.00 719 220 kV Sabalgarh - Sheopur line (2x110) 220 61
20 220kV Chhatarpur-Tikamgarh DCSS line 110 8
21 Rewa RUMS-Rewa 53.416 0
22 Rewa Rums-Sidhi 114.998 6
220Kv DCDS line from 220kV Pooling S/s RUMS at Goojarkhedi, Suwasara (For interconnection of Solar PV Plant of RUMS) (2X43.426)
86.852
b) Tap point to 400 kV S/s Sitamau (2x34.613) 69.226 93
24220kV DCDS Badwar (220kV Pooling S/s) - 400kV Grid S/s PGCIL line) (2X1.134) (ckt-I charged on 28.03.2019)
2.268100%
2nd ckt comm on 04.07.2019
132 KV TRANSMISSION LINES
1 132kv DCSS Gautampur -Depalpur line (1x19) 19 98
2 132kv Nagda(220kv)- Kachrod-Jaora DCSS line (1x64) 64 56
3 132 kv DCSS line between 132Kv S/s Nasrullaganj & 220KV Itarsi s/s (1x53.209) 53.209 82
4 LILO of S/C ckt of 132 KV Seoni-Lakhnadon line at 220kv S/S Seoni (2x20) 40 88
5 132 kv DCSS Guna-Eshagarh line (1x72) 72 41
6LILO of one circuit of 132 kv Neemuch220 - Ratangarh DCDS line at 132 KV S/s Morwan (2x1)
2 52
7 132 kv Sirmour - Katra DCDS line (2x37.67) 75.34 76
8 LILO of 132 kv Jaora - Khachrod line at Bhesola 132 KV S/s (2x0.729) 1.458 100
23
EHV TRANSMISSION WORKS UNDER PROGRESS AS ON 31.08.2019
Minutes of 71st OCCM of MP 38
9 132 kV DCSS line from 132kV Mandla - Bichhiya (1x43.54) 43.54 3
10 132 kV DCSS line from 132kV Dindori - Gorakhpur 132kv S/s (1x49.4) 49.4 7
Minutes of 71st OCCM of MP 39
11 132 KV Gourjhamar - Deori DCSS line (1x27.493) 27.493 66
12132kV DCDS line from 400 kV Ujjain to 132KV Vikram Udyogpuri (Narwar) (2x21.43)
42.86 95
13 133 KV Datiya- Bhitarwar DCSS line (1x35.296) 35.296 84
14 132 kv DCSS Khurai- Khimlasa line (1x20.937) 20.937 99
15 132 kv DCSS Panagar - Patan line (1x22.749) 22.749 32
16132 kv DCSS Badnagar - Chhayan Line (1x28.26) ADB-III (Part line 20.969 ckt charged on 05.11.2018 by tapping arrangement)
28.26 95
17 132 kv DCSS Dhar - Teesgaon line (1x15.35) 15.35 95
18 LILO of 132 kv Ratlam - Meghnagar line at 132Kv S/s Petlawad (2x7.4) 14.8 77
19 132 kv DCSS Narsinghpur - Devnagar (1x23) 23 94
20 132 kv DCDS Narsinghpur - Karakbel line (2x23) 46 89
21 LILO of 132 kv Bhikangaon Khargone line at Biston 132 KV S/s (2x18.997) 38 96
22132kV DCSS line Chichli - Palohabada (1x25.606) (Note:charged Part line 10.776 on 28.03.2019)
25.606 97
23LILO of 132 kv Satna-Maihar line at Satna-II S/s (2x11.047)(ADB-III Saving) (Part line 0.50 CktKm charged on 05.12.2018)
22.094 29
24 132kv DCDS line Guna-Bhonra (2x21.394) 21 84
25 132kV DCDS line from Sendhwa 220 kV S/s - Pansemal 132kV line 95.69 70
26 2nd ckt of 132kV Rajgarh(Dhar)220 kV S/s - Jhabua 132kV line 68.8 86
27LILO of both ckt of 132kV Neemuch - Mandsore at Mandsore(Sitamau) 400 kV S/s (2x71.464)
142.928 49
282nd Circuiting of Sidhi 220 Mauganj 132 kV DCSS line (new line 6 km involved)(2x8.285+ 35.922 ckm 2nd ckt) (Note:35.922 charged on 27.03.2019)
52 33
29 LILO of both ckt. of 132kV Neemuch - Ratangarh DCDS line at 220kV S/s Ratangarh (2x3.094)(132kV interconnector between Ratangarh 400 kV S/s & Ratangarh 132kV S/s
6.188 11
30 2nd circuiting of Sabalgarh - Vijaypur 132KV DCSS line (31.39) 31.39 79
31 2nd circuiting of Ashta - Ichhawar 132KV DCSS line (34.64) 34.64 27
32 2nd circuiting of Nalkheda - Moman Badodiya 132KV DCSS line (28.34) 28.34 78
33 LILO of both ckt of Ujjain - Tarana 132KV line at Ujjain 400 KV S/s (4x0.198) 0.792 39
34 LILO of Susner - Jeerapur 132kV line at Susner (Nalkheda) 34.922 12
35 2nd Circuiting of Susner - Jeerapur 132 kV DCSS line (30.256) 30.256 35
36LILO of both ckt of Ujjain 220 KV - Agar 132kV line at Makdon 132KV S/s (2x2x30.052)
120.208 23
37 2nd circuiting of Agar-Susner 132kV DCSS line 31.603 6038 2nd circuiting of Tarana-Makdon 132kV DCSS line 23.05 6939 132kV DCDS Alot-Zarda line 49.92 44
40LILO of one circuit of Susner 132 KV - Agar 132KV line at Susner (Nalkheda) 220kV (2x18)
34 6
41 2nd ckt of 132 KV shahdol 220 - Dindori132 line (2nd ckt-61.71) 61.71 35
42 2nd ckt of 132 KV Gorabazar 220 - Maneri 132 line (2nd ckt-21.175) 21.75 70
43132kV Julwaniya400 - Shahpura DCSS line (2nd ckt-28 + 1x47.008) (Note:1x47.008 charged on 29.03.2019)
74.866 99
442nd ckt of 220 KV Mandideep to 132 KV Mandideep line & LILO for HEG (2nd ckt-6.5 + 2x2.5)
11.5 50
45 2nd ckt of 132 KV Birsingpur - Umariya line (2nd ckt-35.50) 35.5 78
46 Julwania 400kV-Pati(Silawad) 132kV DCSS line 40.69 747 Panagar 220kV-Dheemarkheda 132kV DCSS line 62.50 3148 132kV Prithvipur-Orchha DCSS line 33.50 2549 132kV Udaipura-Tendukheda DCSS line 36.78 5650 132 kV Gohad - Gormi DCSS line (1x21.187) 21.187 3
51 132kV Narsinghgarh-Suthaliya DCSSline 29.05 3152 Mugaliyachhap 220 kV - Mahawadia 132KV DCDS line(2x7.661) 15.32 153 132kV Sirmour-Atraila DCDSline 70.50 554 132kV Sidhi-Sinhawal DCSS line 58.47 755 132kV Manera-Mandla DCSS line 77.59 3
Minutes of 71st OCCM of MP 40
56132Kv DCSS 2 phase 2wire line from 220Kv s/s KOtar for PS to RTS kaima1x26.938)
26.938 63
57 132kV DCSS Sirmore - RTS Dabhaura line (1x56.1) 56.1 93
58132Kv DCSS 2 phase 2wire line from 132Kv s/s Beohari for PS to RTS Beohari (1x20.278)
20.278 97
59132Kv DCSS 2 phase 2wire line from 220Kv s/s Sidhi for PS to RTS Marwasgram(1x51.341)
51.341 78
60132Kv DCSS 2 phase 2wire line from 132Kv s/s Dongrital for PS to RTS Gajra Bahara (1x17.435)
17.435 25
61132kV 2Phase 2Wire Lalbarra-Samnapur RTS line. (Earlier 132kV 2 Phase 2 wire Kirnapur-RTS Hatta Road line ) 18.643 31
62132Kv DCSS 2 phase 2wire line from 132 Kv s/s Nowgaon for PS to RTS Harpalpur (1x49.851)
49.851 84
63 132 KV line from Seoni 220 KV S/s - Nainpur 132 KV S/s 82.659 97
64 132Kv DCSS 2 phase 2wire line NainpurRTs - Ghansor line (1x34.413) 34.413 19
65 132Kv 2ph 2 wire DCSS Neemuch - RTS Neemuch line 12.188 59
66132 KV 2 phase 2wire DCSS line from 132 KV S/s Malhargarh to RTS Sindpan (earliar 132 KV 2 phase 2wire DCSS Mandsore - RTS Mandsore (Sindpan) line)
14.86 55
67 132Kv 2ph 2 wire line from 220KV S/s - Mandla - RTS Mandla Fort 8.102 39
S.No.
NAME OF THE SUBSTATIONEFFECTIVE CAPACITY
MVA
A. 400 KV SUBSTATIONS
1Badnawar 400 KV sub-station with 2x315MVA 400/220 KV X-mer (1x315MVA charged on 07.03.2019 & 1x125MVAR Bus reactor charged on 11.03.2019)
630 85
2 Mandsore 400 KV sub-station with 2x315MVA 400/220 KV X-mer + 2x160 MVA 630 24
3 Sagar 400 KV sub-station with 2x315MVA 400/220 KV X-mer 630
78%2nd unit 315 MVA
charged on 25.08.2019 from
220 kv side
4 Ujjain 400 KV sub-station with 2x315MVA 400/220 KV X-mer+ 2x160 630 49
B. a 220 KV SUBSTATIONS
1 Gorabazar 220/132kv with 1x160MVA + 40MVA 160 10
2 Chapda 220 Kv S/s (Upgradation) with 1x160MVA 160 40
3 Upgradation of Depalpur 132Kv S/s to 220kv with 1x160MVA 160 60
4 Adampur 220/33kv S/s 2x50MVA 100 54
5 Kukshi 220 Kv S/s Upgradation)with 1x160MVA 160 45
6 Sailana 220/132kV S/s (2x160MVA + 1x63) (Note:63 MVA charged on 12.03.2019)
320 65
7 Jaora 220/132kV S/s (Upgradation) (2x160MVA + 1x40) (Note:40 MVA X-mer charged on 17.02.2019)
320
79%1st 160 MVA charged on
14.08.2019 from 132 KV side
8Gudgaon 220/132kV S/s (1x160MVA + 1x63) (Note:63 MVA charged on 24.01.2019)
160 70
9 Ratangarh 220/132kV S/s (2x160MVA + 1x63) 320 46
10 Nalkheda 220/132kV S/s (2x160MVA + 1x63) 320 4
11 North Zone Substation at Indore to 220kV (Upgradation ) 320 77
12 Sheopurkala 220kv S/s with 2x160MVA+ 1x63MVA 320
38%63 Mva charged on
30.06.2019 & CB charged on 10.07.2019
13 Upgradation of 220 kV S/s at Udaipura 160 7
Minutes of 71st OCCM of MP 41
14 33/220kV Pooling Sub-station at Ramnagar 3x100 (1st & 2nd X-mer charged) 300100%
3rd charged on 25.04.2019
15 33/220kV Pooling Sub-station at Badwar (3x100) (1st charged) 300
1st 100 MVA charged on
29.03.2019 & 2nd on 04.07.2019
C. 132 KV SUBSTATIONS
(a) NEW SUBSTATIONS
1 Biston 132kv s/s1x40 MVA 40 60
2 Khimlasa 132kv s/s 1x40 MVA 40 59
3 Narsinghgarh 132kv s/s with 1x40 MVA 40 23
4 Devnagar 132kv s/s 1x40 MVA (Dist- Narsighpur) (ADB-III) 40
100%charged on
30.03.2019 from 33 KV
5 Bhesola 132kV S/s with 1x50 MVA 50 52
6 Deori 132kV S/s with 1x50 MVA 50 57
7 Vikram Udyogpuri 132kV S/s with 1x63 MVA 63 58
8 Bhitarwar 132kV S/s with 1x50 MVA 50 59
9 Morwan 132kV S/s with 1x40 MVA 40 58
10 Orchha 132kV S/s with 1x50 MVA 50 7
11 Madwas 132kV S/s with 1x50 MVA 50 1
12 Unchehera 132kV S/s with 1x50 MVA 50 39
13 Tendukheda 132kV S/s with 1x50 MVA 50 3
Minutes of 71st OCCM of MP 42
Annexure-2.3(i)
Jun-19 Jul-19 Jun-19 Jul-19
Commissinary HQ 23:50 23:52 23:43 23:42
District HQ 23:49 23:49 23:42 23:44
Tehsil HQ 23:45 23:49 23:38 23:34
Rural -Mixed 23:39 23:42 23:28 23:13
Rural -DLF 23:40 23:42 23:27 23:17
Rural -Irrigation 9:54 9:57 9:55 9:53
Jun-19 Jul-19 Jun-19 Jul-19
Commissinary HQ 23:51 23:53 23:48 23:48
District HQ 23:50 23:51 23:48 23:48
Tehsil HQ 23:44 23:47 23:43 23:44
Rural -3Phase - - 23:34 23:29
Rural -1Phase 23:37 23:41 23:35 23:34
Total Rural 9:49 9:49 9:53 9:53
Discoms wise Average Supply Hours
PARTICULARS
PARTICULARS
West Zone MP
East Zone Central Zone
Minutes of 71st OCCM of MP 43
Annexure-2.3.ii
LIST OF 33KV FEEDERS UNDER MPPKVVCL, JABALPUR (For which group to be allocated)
JABALPUR REGION
Name of EHV Substation
Name of 33KV feeder
Date of commission-ing of feeder
bay
Date of commission
-ing of feeder
220KV 220 KV Panagar
33 KV Industrial Sihora
31.12.2014 10.05.2018
220 KV Chichli 33 KV Imaliya-II 24.02.2018 23.01.2019
132KV
132 KV Marotal 33 KV Discom bay 28.02.2018 -
132 KV Ponder 33 KV Belkheda 33 KV Salichouka 33 KV NSPL
06.12.2018 07.12.2018 19.01.2018
06.12.2018 07.12.2018 19.01.2018
132 KV Barhi
33 KV Barhi 33 KV Kuwa 33 KV Pipariya 33 KV Gertalai
20.01.2018 20.01.2018 20.01.2018 20.01.2018
20.01.2018 20.01.2018 20.03.2018 20.03.2018
132 KV Palohabada
33 KV Bilthari 33 KV Sadumar
01.04.2019 02.04.2019
01.04.2019 02.04.2019
132 KV Narsinghpur
33 KV Nagar Palika 28.02.2018
02.11.2018
132 KV Karapgaon
33 KV Karapgaon 33 KV Bansadehi 33 KV Kareli 33 KV Aamgaon
29.12.2017 29.12.2017 29.12.2017 29.12.2017
24.02.2018 27.01.2018 27.01.2018 28.01.2018
REWA REGION
Name of EHV Substation
Name of 33KV feeder
Date of commission-ing of feeder
bay
Date of commission-ing of feeder
220KV Nil
132KV
132 KV Mauganj 33KV Discom Bay-I (Dhera) 33KV Discom Bay-II (Khatkhari)
31.03.2018 31.03.2018
31.03.2018 31.03.2018
SAGAR REGION
Name of EHV Substation
Name of 33KV feeder
Date of commission-ing of feeder
bay
Date of commission-ing of feeder
220KV 220 KV Chhatarpur
33KV Dharari 09.09.2018 29.09.2018
132KV 132 KV Rahatgarh
33KV Sehora
03.10.2017 14.03.2018
Minutes of 71st OCCM of MP 44
LIST OF 33KV FEEDERS UNDER MPPKVVCL, INDORE (For which group to be allocated)
INDORE REGION
UJJAIN REGION
LIST OF 33KV FEEDERS UNDER MPPKVVCL, BHOPAL (For which group to be allocated)
BHOPAL REGION
Name of EHV Substation
Name of 33KV feeder
Date of charging of feeder bay
Date of charging of feeder
220 KV 220 KV Ganjbasoda
33 KV Simcon-I 33 KV Simcon-II
03.11.2016 31.08.2017
03.11.2016 09.09.2017
220 KV Pipariya 33 KV Food Park (AKVN)
19.06.2017 25.06.2017
220 KV Rajgarh 33 KV WRD 07.12.2018 09.01.2018
132 KV
132 KV Tamot 33 KV Obedullaganj 33 KV AKVN-1 33 KV AKVN-2
05.05.2016 05.10.2016 05.10.2016
02.02.2017 05.10.2016 05.10.2016
132 KV Lateri 33 KV Aligarh Kotra
33 KV Madankhedi 33 KV Anantpura
28.08.2017 27.06.2017 15.06.2017
20.12.2017 05.01.2018 22.05.2018
132 KV Salamatpur 33 KV Dewanganj 33 KV Aamkheda 33 KV Salamatpur Industrial
04.12.2017 04.12.2014 25.11.2017
04.12.2017 04.12.2017 10.01.2019
132 KV Udaipura 33 KV Thaladigawan 33 KV Boras 33 KV Udaipura
26.04.2018 04.06.2018 04.06.2018
04.06.2018 06.06.2018 07.01.2019
132 KV Ayodhya Nagar 33 KV Maholi 30.10.2018 30.10.2018
132 KV Nasrullaganj 33 KV Kankariya
15.05.2004
15.09.2017
132 KV Gopalpur 33 KV AE PHE
26.02.2015
26.02.2015
Name of EHV Substation
Name of 33KV feeder Date of commissioning of feeder bay
Date of commissioning
of feeder
220KV 220KV Pithampur (Sec-III)
33KV SRF 03.09.2013 03.09.2013
132KV
132KV Chandrawatiganj
33KV Chandrawatiganj
27.04.2015
27.04.2015
132KV Electronic
33KV AKVN (Namkeen Cluster)
31.03.2016
31.03.2016
Name of EHV Substation
Name of 33KV feeder Date of commissioning of feeder bay
Date of Charging of feeder
220KV 220KV Barnagar 33KV Bangred 23.10.2017 20.10.2018
132KV
132KV Agar
33KV Agar Town-II
03.12.2012
24.05.2018
132KV Arniyakalan
33KV Designco Manufacture & Exporter (5MW Solar Power Plant)
01.05.2018
01.05.2018
132KV Agrod
33KV Madhopur 30.06.2018 26.07.2018
Minutes of 71st OCCM of MP 45
132 KV Sironj 33 KV Bhairo Baba
14.09.2012
08.10.2018
132 KV Runaha 33 KV Sawansi 31.03.2015 14.10.2018
132 KV Khirkiya 33 KV Killod 07.12.2017 10.01.2018
132 KV Bilquisganj 33 KV Uljhawan 07.01.2018 20.07.2018
Minutes of 71st OCCM of MP 46
ANNEXURE-3.2
Date Time Date Time
1 400 315MVA Transformer-III at 400KV S/s Bhopal 18-Sep-19 08:00 18-Sep-19 18:00 DailyFor Transformer & bay equipment maintenance and testing work
2 400 315MVA Transformer-III at 400KV S/s Bhopal 19-Sep-19 08:00 19-Sep-19 18:00 DailyFor Transformer & bay equipment maintenance and testing work
3 400315MVA CGL Transformer-I at 400KV S/s Chhegaon
16-Sep-19 10:00 17-Sep-19 18:00 ContinueFor Transformer & bay equipment maintenance and testing work
4 400315MVA BHEL Transformer-II at 400KV S/s Chhegaon
18-Sep-19 10:00 19-Sep-19 18:00 ContinueFor Transformer & bay equipment maintenance and testing work
5 400315MVA CGL Transformer at at 400KV S/s Julwaniya
24-Sep-19 10:00 25-Sep-19 18:00 ContinueFor Transformer & bay equipment maintenance and testing work
6 400315MVA EMCO Transformer at 400KV S/s Julwaniya
27-Sep-19 10:00 28-Sep-19 18:00 ContinueFor Transformer & bay equipment maintenance and testing work
7 400 315MVA TELK Transformer-IV at 400KV S/s Nagda 24-Sep-19 08:00 25-Sep-19 18:00 ContinueAdditional PI structure installation and post monsoon mainteance work
8 400 315MVA ICT- II at 400KV S/s Indore 23-Sep-19 09:00 25-Sep-19 18:00 ContinueFor replacement of 33 KV CTs , Transformer will be kept OFF
9 400 315MVA ICT-I at 400KV S/s Pithampur 23-Sep-19 08:00 24-Sep-19 18:00 ContinueFor Transformer & bay equipment maintenance and testing work
10 400 315MVA ICT-II at 400KV S/s Pithampur 25-Sep-19 08:00 26-Sep-19 18:00 ContinueFor Transformer & bay equipment maintenance and testing work
11 400 315MVA BHEL Transformer at 400KV S/s Katni 19-Sep-19 9:00 20-Sep-19 17:00 ContinueFor Transformer & bay equipment maintenance and testing work
12 400 315MVA TELK Transformer at 400KV S/s Katni 23-Sep-19 9:00 24-Sep-19 17:00 ContinueFor Transformer & bay equipment maintenance and testing work
13 400 315MVA BHEL Transformer-I at 400KV S/s Nagda 01-Oct-19 08:00 01-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
14 400 315MVA CGL Transformer-III at 400KV S/s Bina 01-Oct-19 08:00 01-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
15 400 315MVA Transformer-II at 400KV S/s Bhopal 03-Oct-19 08:00 03-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
16 400 315MVA Transformer-I at 400KV S/s Pithampur 03-Oct-19 08:00 04-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
17 400 315MVA EMCO Transformer-I at 400KV S/s Bina 03-Oct-19 08:00 04-Oct-19 17:00 ContinueFor Post Monsoon maintenace work & Testing work
18 400315MVA CGL Transformer-I at 400KV S/s Julwaniya
03-Oct-19 09:00 03-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
19 400 315MVA Transformer-II at 400KV S/s Bhopal 04-Oct-19 08:00 04-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
20 400315MVA CGL Transformer-I at 400KV S/s Julwaniya
04-Oct-19 09:00 04-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
21 400 315MVA Transformer-II at 400KV S/s Pithampur 05-Oct-19 08:00 06-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
22 400 315MVA BHEL Transformer-II at 400KV S/s Bina 05-Oct-19 08:00 05-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
23 400 315MVA Transformer-I at 400KV S/s Bhopal 10-Oct-19 08:00 10-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
24 400 3*105MVA Transformer-II at 400KV S/s Indore 10-Oct-19 09:00 11-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
25 400 315MVA CGL Transformer-I at 400KV S/s Ashta 10-Oct-19 9:00 10-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
26 400315MVA EMCO Transformer-II at-400KV S/s Julwaniya
10-Oct-19 09:00 10-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
27 400 315MVA Transformer-I at 400KV S/s Bhopal 11-Oct-19 08:00 11-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
28 400 315MVA BHEL Transformer-II at 400KV S/s Nagda 11-Oct-19 08:00 11-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
29 400 315MVA CGL Transformer-I at 400KV S/s Ashta 11-Oct-19 9:00 11-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
30 400315MVA EMCO Transformer-II at-400KV S/s Julwaniya
11-Oct-19 09:00 11-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
31 400315MVA BHEL Transformer-III at 400KV S/s Nagda
14-Oct-19 08:00 14-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
32 400 315MVA Transformer-III at 400KV S/s Indore 14-Oct-19 09:00 15-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
33 400 315MVA CGL Transformer-II at 400KV S/s Ashta 14-Oct-19 9:00 14-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
34 400100MVA BHEL Transformer-I at 400KV S/s Kirnapur
15-Oct-19 10:00 16-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
35 400 315MVA Transformer-IV at 400KV S/s Bhopal 15-Oct-19 08:00 15-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
36 400 315MVA CGL Transformer-II at 400KV S/s Ashta 15-Oct-19 9:00 15-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
37 400 315MVA ICT-I at 400KV S/s Badnawar 15-Oct-19 09:00 15-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
38 400 315MVA Transformer-IV at 400KV S/s Bhopal 16-Oct-19 08:00 16-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
39 400 315MVA Transformer-IV at 400KV S/s Indore 17-Oct-19 09:00 18-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
40 400100MVA BHEL Transformer-II at 400KV S/s Kirnapur
18-Oct-19 10:00 19-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
41 400 315MVA Transformer-I at 400KV S/s Indore 20-Oct-19 09:00 21-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
42 400 315MVA Transformer-I at 400KV S/s Indore 01-Nov-19 09:00 02-Nov-19 18:00 Continue Post Mansoon Maintenance & Testing work
A- 400 KV TRANSFORMERS
71st OCCM : PROPOSED SHUTDOWN OF TRANSMISSION ELEMENTS FOR THE PERIOD 01-09-19 TO 31-12-19 (TO BE APPROVED BY SLDC JABALPUR)
Sr- No
KV Line / Transformer / Reactor / Bay
From To Basis(Daily/
Continue)Reason
Minutes of 71st OCCM of MP 47
Date Time Date Time
Sr- No
KV Line / Transformer / Reactor / Bay
From To Basis(Daily/
Continue)Reason
43 400 3*105MVA Transformer-II at 400KV S/s Indore 04-Nov-19 09:00 05-Nov-19 18:00 Continue Post Mansoon Maintenance & Testing work
44 400 315MVA Transformer-III at 400KV S/s Indore 06-Nov-19 09:00 07-Nov-19 18:00 Continue Post Mansoon Maintenance & Testing work
45 400 315MVA Transformer-IV at 400KV S/s Indore 13-Nov-19 09:00 14-Nov-19 18:00 Continue Post Mansoon Maintenance & Testing work
46 400 315MVA Transformer-I at 400KV S/s Pithampur 04-Nov-19 08:00 05-Nov-19 17:00 Continue Post Mansoon Maintenance & Testing work
47 400 315MVA Transformer-II at 400KV S/s Pithampur 06-Nov-19 08:00 07-Nov-19 17:00 Continue Post Mansoon Maintenance & Testing work
1 400 50MVAR CGL Bus Reactor at 400KV S/s Julwaniya 30-Sep-19 10:00 30-Sep-19 18:00 DailyFor Reactor & bay equipment maintenance and testing work
2 400 2X50 MVAR BUS Reactor at 400KV S/s Pithampur 27-Sep-19 08:00 27-Sep-19 16:00 DailyFor Reactor & bay equipment maintenance and testing work
3 400 125MVAR BHEL Reactor at 400KV S/s Katni 14-Sep-19 9:00 14-Sep-19 17:00 DailyFor Reactor & bay equipment maintenance and testing work
4 400 50MVAR GCL Bus-Reactor at 400KV S/s Julwaniya 01-Oct-19 09:00 01-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
5 400 125MVAR Reactor at 400KV S/s Badnawar 04-Oct-19 09:00 04-Oct-19 17.:00 DailyFor Post Monsoon maintenace work & Testing work
6 400 50MVAR CGL Bus-Reactor at-400kV S/s Chhegaon 10-Oct-19 10:00 11-Oct-19 18:00 ContinueFor Post Monsoon maintenace work & Testing work
7 4002X50 MVAR BUS REACTOR at 400KV S/s Pithampur
18-Oct-19 08:00 18-Oct-19 16:00 DailyFor Post Monsoon maintenace work & Testing work
8 400 400KV CGL Bus Reactor at 400KV S/s Ashta 21-Oct-19 9:00 21-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
9 400 400KV BHEL Line Reactor- I at 400KV S/s Ashta 22-Oct-19 9:00 22-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
10 400 400KV BHEL Line Reactor-I at 400KV S/s Bina 22-Oct-19 08:00 22-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
11 400 400KV BHEL Line Reactor-II at 400KV S/s Bina 23-Oct-19 08:00 23-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
12 400 400KV BHEL Line Reactor- II at 400KV S/s Ashta 30-Oct-19 9:00 30-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
13 400 2X50 MVAR Bus Reactor at 400KV S/s Pithampur 08-Nov-19 08:00 08-Nov-19 17:00 Daily Post Mansoon Maintenance & Testing work
14 400125MVAR Line Reactor (SSTPS-IV) at 400KV S/s Pithampur
13-Nov-19 08:00 13-Nov-19 17:00 Daily Post Mansoon Maintenance & Testing work
15 400125MVAR Line Reactor (SSTPS-III) at 400KV S/s Pithampur
14-Nov-19 08:00 14-Nov-19 17:00 Daily Post Mansoon Maintenance & Testing work
1 400 400KV Birsinghpur-Katni-I 04-Sep-19 09:00 04-Sep-19 18:00 Daily For line maintenance work
2 400 400KV Birsinghpur-Katni-II 09-Sep-19 09:00 09-Sep-19 18:00 Daily For line maintenance work
3 400 400KV MTPH-Julwania 03-Sep-19 08:00 03-Sep-19 18:00 Daily For line maintenance work
4 400 400KV ISP-Indore-I 11-Sep-19 10:00 11-Sep-19 17:00 Daily For line maintenance work
5 400 400KV ISP-Indore-I 12-Sep-19 10:00 12-Sep-19 17:00 Daily For line maintenance work
6 400 400KV ISP-Indore-II 04-Sep-19 10:00 04-Sep-19 17:00 Daily For line maintenance work
7 400 400KV ISP-Indore-II 05-Sep-19 10:00 05-Sep-19 17:00 Daily For line maintenance work
8 400 400KV ISP-Indore-II 06-Sep-19 10:00 06-Sep-19 17:00 Daily For line maintenance work
9 400 400KV MTPH-Chhegaon 13-Sep-19 09:00 13-Sep-19 16:00 0.29166667 For line maintenance work
10 400 400KV Chhegaon-Julwaniya 23-Sep-19 10:00 23-Sep-19 18:00 DailyFor bay equipment maintenance and testing work
11 400 400KV Nagda-Indore 21-Sep-19 08:00 21-Sep-19 18:00 Daily For line maintenance work
12 400 400KV Malwa TPH - Julwania 01-Oct-19 08:00 01-Oct-19 18:00 Daily For line maintenance work
13 400 400KV Katni-Birsingpur-I 03-Oct-19 09:00 03-Oct-19 18:00 Daily For line maintenance work
14 400 400KV Malwa TPH - Chhegaon 03-Oct-19 09:00 03-Oct-19 17:00 Daily For line maintenance work
15 400 400KV ISP- Indore-I 04-Oct-19 10:00 04-Oct-19 17:00 Daily For line maintenance work
16 400 400KV ISP- Indore-I 05-Oct-19 10:00 05-Oct-19 17:00 Daily For line maintenance work
17 400 400KV ISP- Indore-I 06-Oct-19 10:00 06-Oct-19 17:00 Daily For line maintenance work
18 400 400KV ISP- Indore -II 11-Oct-19 10:00 11-Oct-19 17:00 Daily For line maintenance work
19 400 400KV Main Bus No- I at 400KV S/s Katni 14-Oct-19 9:00 14-Oct-19 17:00 Daily For post Monsoon maintenace work
20 400 400KV Katni-Birsingpur-II 14-Oct-19 09:00 14-Oct-19 18:00 Daily For line maintenance work
21 400 400KV ISP- Indore -II 14-Oct-19 10:00 14-Oct-19 17:00 Daily For line maintenance work
22 400 400KV Sarni-ISP 15-Oct-19 07:00 15-Oct-19 19:00 Daily For line maintenance work
23 400 400KV Main Bus No- II at 400KV S/s Katni 15-Oct-19 9:00 15-Oct-19 17:00 Daily For post Monsoon maintenace work
B- 400 KV REACTORS
C- 400 KV FEEDER & BAYS OF 400 KV- S/S-
Minutes of 71st OCCM of MP 48
Date Time Date Time
Sr- No
KV Line / Transformer / Reactor / Bay
From To Basis(Daily/
Continue)Reason
24 400 400KV Chhegaon - Julwania 17-Oct-19 09:00 17-Oct-19 17:00 Daily For line maintenance work
25 400 400KV TBC at 400KV S/s Julwaniya 18-Oct-19 09:00 18-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
26 400 400KV Bus Tie at 400KV S/s Julwaniya 21-Oct-19 09:00 21-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
27 400 400KV Ashta - Satpura-I 22-Oct-19 09:00 22-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
28 400 400KV Nagda - Indore 22-Oct-19 08:00 22-Oct-19 18:00 Daily For line maintenance work
29 400 400KV Ashta - Satpura-I 23-Oct-19 09:00 23-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
30 400 400KV Ashta - Satpura-II 30-Oct-19 09:00 30-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
31 400 400KV Ashta - Satpura-II 31-Oct-19 09:00 31-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
32 400 400KV Birsinghpur-Katni-I 11-Nov-19 09:00 11-Nov-19 18:00 Daily For line maintenance work
33 400 400KV Birsinghpur-Katni-II 04-Nov-19 09:00 04-Nov-19 18:00 Daily For line maintenance work
34 400 400KV Sarni-ISP 15-Nov-19 07:00 15-Nov-19 19:00 Daily For line maintenance work
35 400 400KV MTPH-Chhegaon 08-Nov-19 10:00 08-Nov-19 17:00 Daily For line maintenance work
36 400 400KV MTPH-Julwania 11-Nov-19 10:00 11-Nov-19 17:00 Daily For line maintenance work
37 400 400KV Indore-Nagda 13-Nov-19 10:00 13-Nov-19 17:00 Daily For line maintenance work
38 400 400KV Indore-Nagda 14-Nov-19 10:00 14-Nov-19 17:00 Daily For line maintenance work
39 400 400KV Indore-Nagda 15-Nov-19 10:00 15-Nov-19 17:00 Daily For line maintenance work
1 220 160MVA Transformer-I at 220KV S/s Mahalgaon 10-Sep-19 10:00 10-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
2 220 160MVA Transformer-I at 220KV S/s Mahalgaon 30-Sep-19 10:00 30-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
3 220 3x40 MVA Transformer at 220KV S/s Mahalgaon 03-Sep-19 10:00 03-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
4 220 160MVA Transformer-I at 220KV S/s Gwalior-II 04-Sep-19 10:00 04-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
5 220 160MVA Transformer-II at 220KV S/s Gwalior-II 05-Sep-19 10:00 05-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
6 220 160MVA Transformer-I at 220KV S/s Malanpur 18-Sep-19 09:00 18-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
7 220 160MVA Transformer-I at 220KV s/s Mehgaon 11-Sep-19 09:00 11-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
8 220 160MVA Transformer-II at 220KV s/s Mehgaon 12-Sep-19 09:00 12-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
9 220 160MVA Transformer-I at 220KV S/S Datia 28-Sep-19 09:00 28-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
10 220 160MVA Transformer-II at 220KV S/S Datia 30-Sep-19 09:00 30-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
11 2203x40MVA MITSUBISHI Transformer at 220KV S/s Barwaha
06-Sep-19 10:00 06-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
12 220 160MVA NGEF Transformer at 220KV S/s Barwaha 07-Sep-19 10:00 07-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
13 220 160MVA BBL Transformer at 220KV S/s Barwaha 08-Sep-19 10:00 08-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
14 220 160MVA CGL Transformer at 220KV S/s Nimrani 10-Sep-19 10:00 10-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
15 220 160MVA BHEL Transformer at 220KV S/s Nimrani 12-Sep-19 10:00 12-Sep-19 17:00 DailyFor Transformer & bay equipment maintenance and testing work
16 220 220KV Mahalgaon-Bina 25-Sep-19 10:00 25-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
17 220 220KV Mahalgaon-Datia 27-Sep-19 10:00 27-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
18 220 220KV Gwalior II -PGCIL-I 11-Sep-19 10:00 11-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
19 220 220KV Gwalior II-PGCIL-II 12-Sep-19 10:00 12-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
20 220 220KV Malanpur-Morena-I 13-Sep-19 10:00 13-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
21 220 220KV Malanpur-Morena-II 16-Sep-19 10:00 16-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
22 220 220KV Datia- Bina 16-Sep-19 09:00 16-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
23 220 220KV Bina (PGCIL)-Shivpuri 03-Sep-19 09:00 03-Sep-19 17:00 Daily For line maintenance work
24 220 220KV Shivpuri-Bina MPPTCL 09-Sep-19 09:00 09-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
25 220 220KV Shvipuri-Sabalgarh-I 16-Sep-19 09:00 16-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
26 220 220KV Shivpuri-Sabalgarh-II 23-Sep-19 09:00 23-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
27 220 220KV Damoh (PGCIL)-Tikamgarh-I 11-Sep-19 09:00 11-Sep-19 18:00 Daily For line maintenance work
D- 220 KV FEEDER & BAYS-
Minutes of 71st OCCM of MP 49
Date Time Date Time
Sr- No
KV Line / Transformer / Reactor / Bay
From To Basis(Daily/
Continue)Reason
28 220 220KV Damoh(PGCIL)-Sagar -I 13-Sep-19 09:00 13-Sep-19 18:00 Daily For line maintenance work
29 220 220KV Damoh(PGCIL)-Sagar -II 19-Sep-19 09:00 19-Sep-19 18:00 Daily For line maintenance work
30 220 220KV Damoh - PGCIL Damoh-I 21-Sep-19 09:00 21-Sep-19 18:00 Daily For line maintenance work
31 220 220KV Damoh - PGCIL Damoh-II 23-Sep-19 09:00 23-Sep-19 18:00 Daily For line maintenance work
32 220 220KV Sagar -Bina -I 09-Sep-19 09:00 09-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
33 220 220KV Sagar -Bina -II 12-Sep-19 09:00 12-Sep-19 17:00 DailyFor bay equipment maintenance and testing work
34 220 220KV Chhindwara-PGCIL-I 16-Sep-19 09:00 16-Sep-19 18:00 DailyFor bay equipment maintenance and testing work
35 220 220KV Chhindwara-PGCIL-II 12-Sep-19 09:00 12-Sep-19 18:00 DailyFor bay equipment maintenance and testing work
36 220 220KV Seoni-PGCIL-I 27-Sep-19 09:00 27-Sep-19 18:00 DailyFor bay equipment maintenance and testing work
37 220 220KV Seoni-PGCIL-II 26-Sep-19 09:00 26-Sep-19 18:00 DailyFor bay equipment maintenance and testing work
38 220 220KV Indore (400)-Indore East 16-Sep-19 09:00 19-Sep-19 18:00 ContinueFor Overhauling of Circuit Breaker, Line will be on TBC
39 220 220KV Indore (400) -Mangliya 11-Sep-19 09:00 11-Sep-19 18:00 Dailyfor replacement of Wave trap , Line will be kept OFF
40 220 220KV Indore (400)-Barwaha-I 12-Sep-19 09:00 12-Sep-19 18:00 Dailyfor replacement of Wave trap ,Line will be kept OFF
41 220 220KV Pithampur Inter connector-I 19-Sep-19 08:00 19-Sep-19 16:00 DailyFor bay equipment maintenance and testing work
42 220 220KV Pithampur Inter connector-II 20-Sep-19 08:00 20-Sep-19 16:00 DailyFor bay equipment maintenance and testing work
43 220 220KV Pithampur(400)-Badnagar 21-Sep-19 08:00 21-Sep-19 16:00 DailyFor bay equipment maintenance and testing work
44 220 220KV Pithampur(400)-Pithampur Sector-I 30-Sep-19 08:00 30-Sep-19 16:00 DailyFor bay equipment maintenance and testing work
45 220 220KV Rewa-Tons-I 02-Sep-19 10:00 02-Sep-19 17:00 Daily For line maintenance work
46 220 220KV Rewa-Tons-II 06-Sep-19 10:00 06-Sep-19 17:00 Daily For line maintenance work
47 220 220KV Kotar-Tons-I 11-Sep-19 10:00 11-Sep-19 17:00 Daily For line maintenance work
48 220 220KV Kotar-Tons-II 16-Sep-19 10:00 16-Sep-19 17:00 Daily For line maintenance work
49 220 220KV Rewa-Birsinghpur 19-Sep-19 10:00 19-Sep-19 17:00 Daily For line maintenance work
50 220 220KV Sidhi-ATPS 22-Sep-19 10:00 22-Sep-19 17:00 Daily For line maintenance work
51 220 220KV Rajgarh-Shujalpur (PGCIL)-I 04-Sep-19 09:00 04-Sep-19 17:00 Daily For line maintenance work
52 220 220KV Rajgarh-Shujalpur (PGCIL)-II 06-Sep-19 09:00 06-Sep-19 17:00 Daily For line maintenance work
53 220 220KV Shujalpur-Shujalpur (PGCIL)-I 23-Sep-19 09:00 23-Sep-19 17:00 Daily For line maintenance work
54 220 220KV Shujalpur-Shujalpur (PGCIL)-II 24-Sep-19 09:00 24-Sep-19 17:00 Daily For line maintenance work
55 220 220KV Rajgarh-I/C-I 24-Sep-19 10:00 24-Sep-19 17:00 Daily For line maintenance work
56 220 220KV Rajgarh-I/C-II 25-Sep-19 10:00 25-Sep-19 17:00 Daily For line maintenance work
57 220 220KV Jaitpura (PGCIL) Hatunia-Indore-I 26-Sep-19 10:00 26-Sep-19 17:00 Daily For line maintenance work
58 220 220KV Jaitpura (PGCIL) Hatunia-Indore-II 27-Sep-19 10:00 27-Sep-19 17:00 Daily For line maintenance work
59 220 220KV Indore (PGCIL) Hatunia-Ujjain-II 28-Sep-19 10:00 28-Sep-19 17:00 Daily For line maintenance work
60 220 220KV Shajapur-Ashta-I 01-Oct-19 09:00 01-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
61 220 160 MVA Xmer-II at 220KV S/s Malanpur 03-Oct-19 09:00 03-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
62 220 160 MVA-I EMCO Shivpuri 03-Oct-19 10:00 03-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
63 220 220KV Indore-Indore East 03-Oct-19 09:00 05-Oct-19 18:00 ContinueFor Overhauling work of 220KV Circuit Breaker, Line will be kept ON through TBC
64 220 220KV Chhegaon-Malwa (SSTPH) -I 03-Oct-19 10:00 03-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
65 220 220KV Rewa-Tons-I 03-Oct-19 10:00 03-Oct-19 17:00 Daily For line maintenance work
66 220 220KV Shajapur-Ashta-II 03-Oct-19 09:00 03-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
67 220 220KV Shujalpur-PGCIL-I 03-Oct-19 09:00 03-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
68 220 100MVA AREVA Transformer at 400KV S/s Ashta 04-Oct-19 09:00 04-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
69 220 220KV Chhegaon-Malwa (SSTPH) -II 04-Oct-19 10:00 04-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
70 220 220KV Dewas-Ashta-I 04-Oct-19 09:00 04-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
71 220 220KV Shujalpur-PGCIL-I I 04-Oct-19 09:00 04-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
Minutes of 71st OCCM of MP 50
Date Time Date Time
Sr- No
KV Line / Transformer / Reactor / Bay
From To Basis(Daily/
Continue)Reason
72 220 160 MVA-II BHEL Shivpuri 05-Oct-19 10:00 05-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
73 220 220KV Chhegaon-Khandwa (PGCIL) -I 05-Oct-19 10:00 05-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
74 220 220KV Dewas-Indore East (Bicholi) 05-Oct-19 09:00 05-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
75 220160MVA BHEL Transformer-I at 220KV S/s Shajapur
05-Oct-19 09:00 05-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
76 220 160MVA X-mer-I At 220KV s/s Mehgaon 07-Oct-19 09:00 07-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
77 220 220KV Rewa-Tons-II 07-Oct-19 10:00 07-Oct-19 17:00 Daily For line maintenance work
78 220 220KV Chhegaon-Khandwa (PGCIL)-II 09-Oct-19 10:00 09-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
79 220 220KV Barwaha-Nimrani 09-Oct-19 10:00 09-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
80 220 160MVA X-mer-II At 220KV s/s Mehgaon 10-Oct-19 09:00 10-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
81 220 220KV Omkareshwar - Khandwa 10-Oct-19 09:00 10-Oct-19 17:00 Daily For line maintenance work
82 220 220KV Barwaha-Itarsi 10-Oct-19 10:00 10-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
83 220 220KV Dewas-Ashta-II 10-Oct-19 09:00 10-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
84 220160MVA BHEL Transformer-II at 220KV S/s Shajapur
10-Oct-19 09:00 10-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
85 220 220KV Barwaha-Handia 11-Oct-19 10:00 11-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
86 220 220KV Kotar-Tons-I 11-Oct-19 10:00 11-Oct-19 17:00 Daily For line maintenance work
87 220 220KV Shajapur-INOX-I 11-Oct-19 09:00 11-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
88 220 220KV Malanpur-Morena-II 14-Oct-19 09:00 14-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
89 220 220KV Datia- Bina 14-Oct-19 09:00 14-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
90 220 220KV Omkareshwar - Chhegaon 14-Oct-19 09:00 14-Oct-19 17:00 Daily For line maintenance work
91 220 220KV Dewas-Indore 14-Oct-19 09:00 14-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
92 220 220KV Shajapur-INOX-II 14-Oct-19 09:00 14-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
93 220 220KV Seoni-Chhindwara-I 15-Oct-19 09:00 15-Oct-19 18:00 Daily For line maintenance work
94 220 220KV Sagar-Bina-I 15-Oct-19 9:00 15-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
95 220 220KV Damoh (PGCIL)-Tikamgarh-I 15-Oct-19 09:00 15-Oct-19 18:00 Daily For line maintenance work
96 220 220KV Bus Couplar at 220KV S/s Barwaha 15-Oct-19 10:00 15-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
97 220 220KV Kotar-Tons-II 15-Oct-19 10:00 15-Oct-19 17:00 Daily For line maintenance work
98 220 160MVA TELK Transformer at 220KV S/s Dewas 15-Oct-19 09:00 15-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
99 220 220KV Mahalgaon-Bina 16-Oct-19 10:00 16-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
100 220 220KV Sagar-Bina-II 16-Oct-19 9:00 16-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
101 220 220KV Damoh(PGCIL)-Sagar-I 16-Oct-19 09:00 16-Oct-19 18:00 Daily For line maintenance work
102 220 160MVA EMCO Transformer at 220KV S/s Dewas 16-Oct-19 09:00 16-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
103 220220KV Transfer Bus Coupler at 220KV S/s Shajapur
16-Oct-19 09:00 16-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
104 220 220KV Seoni-PGCIL-I 17-Oct-19 09:00 17-Oct-19 18:00 Daily For line maintenance work
105 220 160MVA BHEL Transformer at 220KV S/s Dewas 17-Oct-19 09:00 17-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
106 220 220KV Mahalgaon-Datia 18-Oct-19 10:00 18-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
107 220 220KV Datia- Gwalior 18-Oct-19 09:00 18-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
108 220 220KV Seoni-Chhindwara-II 18-Oct-19 09:00 18-Oct-19 18:00 Daily For line maintenance work
109 220 220KV Seoni-PGCIL-II 18-Oct-19 09:00 18-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
110 220 160MVA AREVA Transformer at 400KV S/s Ashta 18-Oct-19 09:00 18-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
111 220 220KV Damoh(PGCIL)-Sagar-II 18-Oct-19 09:00 18-Oct-19 18:00 Daily For line maintenance work
112 220 220KV Chhanera-Khandwa (PGCIL) -I 18-Oct-19 10:00 18-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
113 220 220KV Rewa-Birsinghpur 18-Oct-19 10:00 18-Oct-19 17:00 Daily For line maintenance work
114 220 220KV Transfer Bus Coupler at 220KV S/s Dewas 18-Oct-19 09:00 18-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
115 220 220KV Malanpur-Morena-I 19-Oct-19 09:00 19-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
Minutes of 71st OCCM of MP 51
Date Time Date Time
Sr- No
KV Line / Transformer / Reactor / Bay
From To Basis(Daily/
Continue)Reason
116 220 220KV Bina (PGCIL)-Shivpuri 19-Oct-19 09:00 19-Oct-19 17:00 Daily For line maintenance work
117 220 160MVA BBL Transformer at 400KV S/s Ashta 19-Oct-19 09:00 19-Oct-19 18:00 DailyFor Post Monsoon maintenace work & Testing work
118 220 220KV Damoh-400KV PGCIL Damoh-I 19-Oct-19 09:00 19-Oct-19 18:00 Daily For line maintenance work
119 220 220KV Chhanera-Khandwa (PGCIL) -II 19-Oct-19 10:00 19-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
120 220 220KV Julwaniya-Omkareshwar 19-Oct-19 09:00 19-Oct-19 18:00 DailyFor bay equipment maintenance and testing work
121 220 220KV Bus Tie at 220KV S/s Dewas 19-Oct-19 09:00 19-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
122 220 160 MVA X-Mer-I at 220KV S/S Datia 21-Oct-19 09:00 21-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
123 220 220KV Damoh-400KV PGCIL Damoh-II 21-Oct-19 09:00 21-Oct-19 18:00 Daily For line maintenance work
124 220 220KV Nimrani-Chhegaon-I 21-Oct-19 10:00 21-Oct-19 17:00 DailyFor bay equipment maintenance and testing work
125 220 220KV Nepanagar-Khandwa (PGCIL) 22-Oct-19 10:00 22-Oct-19 18:00 DailyFor commissioning of 220KV CVT & bay maintenance work.
126 220 220KV Sidhi-ATPS 22-Oct-19 10:00 22-Oct-19 17:00 Daily For line maintenance work
127 220 220KV Indore (PGCIL) Hatunia-Ujjain-I 22-Oct-19 10:00 22-Oct-19 17:00 Daily For line maintenance work
128 220 160 MVA X-Mer-II at 220KV S/S Datia 23-Oct-19 09:00 23-Oct-19 17:00 DailyFor Post Monsoon maintenace work & Testing work
129 220 220KV Indore (PGCIL) Hatunia-Ujjain-I 23-Oct-19 10:00 23-Oct-19 17:00 Daily For line maintenance work
130 220 220KV Indore (PGCIL) Hatunia-Ujjain-II 24-Oct-19 10:00 24-Oct-19 17:00 Daily For line maintenance work
131 220 220KV Indore (PGCIL) Hatunia-Ujjain-II 25-Oct-19 10:00 25-Oct-19 17:00 Daily For line maintenance work
132 220 220KV Jaitpura (PGCIL) Hatunia-Indore-I 26-Oct-19 10:00 26-Oct-19 17:00 Daily For line maintenance work
133 220 220KV Jaitpura (PGCIL) Hatunia-Indore-II 28-Oct-19 10:00 28-Oct-19 17:00 Daily For line maintenance work
134220 KV
220 KV BHANPURA MODAK Feeder 14-Oct-19 10:00 14-Oct-19 17:00 Daily For commissioning of second DPR at 220KV S/S Bhanpura
135220 KV
220 kv BHANPURA RANPUR Feeder 15-Oct-19 10:00 15-Oct-19 17:00 Daily For commissioning of second DPR at 220KV S/S Bhanpura
136 220 220KV Seoni-Chhindwara-I 13-Nov-19 09:00 13-Nov-19 18:00 Daily For line maintenance work
137 220 220KV Seoni-Chhindwara-II 20-Nov-19 09:00 20-Nov-19 18:00 Daily For line maintenance work
138 220 220KV Seoni-Interconnector-I 15-Nov-19 09:00 15-Nov-19 18:00 Daily For line maintenance work
139 220 220KV Seoni-Interconnector-II 25-Nov-19 09:00 25-Nov-19 18:00 Daily For line maintenance work
140 220 220KV Ashta - Bhopal 05-Nov-19 09:00 05-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
141 220 220KV Ashta - Mugaliyachhap 06-Nov-19 09:00 06-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
142 220 220KV Ashta - Shajapur-I 07-Nov-19 09:00 07-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
143 220 220KV Ashta - Shajapur-II 08-Nov-19 09:00 08-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
144 220 220KV Ashta - Dewas-I 13-Nov-19 09:00 13-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
145 220 220KV Ashta - Dewas-II 14-Nov-19 09:00 14-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
146 220 220KV Ashta - Jetpura (Indore)-I 15-Nov-19 09:00 15-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
147 220 220KV Ashta - Jetpura (Indore)-II 16-Nov-19 09:00 16-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
148 220 220KV Bus Transfer Bay at 400KV S/s Ashta 18-Nov-19 09:00 18-Nov-19 18:00 DAILYPOST MONSOON MAINTENANCE & RELAY TESTING WORK
149 220 220KV Bus Tie Bay at 400KV S/s Ashta 19-Nov-19 09:00 19-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
150 220 22OKV MAIN BUS NO. -I at 400KV S/s Ashta 21-Nov-19 09:00 21-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
151 220 22OKV MAIN BUS NO. -I at 400KV S/s Ashta 22-Nov-19 09:00 22-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
152 220 22OKV MAIN BUS NO. -I at 400KV S/s Ashta 23-Nov-19 09:00 23-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
153 220 22OKV MAIN BUS NO. -I at 400KV S/s Ashta 25-Nov-19 09:00 25-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
154 220 22OKV MAIN BUS NO. -I at 400KV S/s Ashta 26-Nov-19 09:00 26-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
155 220 22OKV MAIN BUS NO. -I at 400KV S/s Ashta 27-Nov-19 09:00 27-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
156 220 220KV AUX Bus at 400KV S/s Ashta 28-Nov-19 09:00 28-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
157 220 220KV AUX Bus at 400KV S/s Ashta 29-Nov-19 09:00 29-Nov-19 18:00 DAILY POST MONSOON MAINTENANCE
158 220 220KV Rewa-Tons-I 02-Nov-19 10:00 02-Nov-19 17:00 Daily For line maintenance work
159 220 220KV Rewa-Tons-II 05-Nov-19 10:00 05-Nov-19 17:00 Daily For line maintenance work
Minutes of 71st OCCM of MP 52
Date Time Date Time
Sr- No
KV Line / Transformer / Reactor / Bay
From To Basis(Daily/
Continue)Reason
160 220 220KV Kotar-Tons-I 08-Nov-19 10:00 08-Nov-19 17:00 Daily For line maintenance work
161 220 220KV Kotar-Tons-II 14-Nov-19 10:00 14-Nov-19 17:00 Daily For line maintenance work
162 220 220KV Rewa-Birsinghpur 19-Nov-19 10:00 19-Nov-19 17:00 Daily For line maintenance work
163 220 220KV Sidhi-ATPS 23-Nov-19 10:00 23-Nov-19 17:00 Daily For line maintenance work
164 220 220KV Indore(400)-Indore east 18-Nov-19 09:00 21-Nov-19 18:00 ContinueFor Overhauling of Circuit Breaker ,Line will be on TBC
165 220 220KV Indore(400)-Mangliya 15-Nov-19 09:00 15-Nov-19 18:00 ContinueFor Replacement of Wave trap ,Line will be OFF
166 220 220KV Indore(400)-Barwaha-I 16-Nov-19 09:00 16-Nov-19 18:00 ContinueFor Replacement of Wave trap ,Line will be OFF
167 220 220KV Sagar-Bina-I 13-Nov-19 09:00 13-Nov-19 17:00 Continue Maintatance & testing work.
168 220 220KV Sagar-Bina-II 14-Nov-19 09:00 14-Nov-19 17:00 Continue Maintatance & testing work.
169 220 220KV Damoh (PGCIL)-Tikamgarh-I 13-Nov-19 09:00 13-Nov-19 18:00 Daily For line maintenance work
170 220 220KV Damoh(PGCIL)-Sagar -I 16-Nov-19 09:00 16-Nov-19 18:00 Daily For line maintenance work
171 220 220KV Damoh(PGCIL)-Sagar -II 18-Nov-19 09:00 18-Nov-19 18:00 Daily For line maintenance work
172 220 220KV Damoh-Interconnector-I 20-Nov-19 09:00 20-Nov-19 18:00 Daily For line maintenance work
173 220 220KV Damoh-Interconnector-II 22-Nov-19 09:00 22-Nov-19 18:00 Daily For line maintenance work
174 220 220KV Bina (PGCIL)-Shivpuri 07-Nov-19 09:00 07-Nov-19 17:00 Daily For line maintenance work
175 220 220KV Mahalgaon- Bina 20-Nov-19 10:00 20-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
176 220 220KV Mahalgaon- Datia 21-Nov-19 10:00 21-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
177 220 220KV Shivpuri-Sabalgarh-I 25-Nov-19 10:00 25-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
178 220 220KV Shivpuri-Sabalgarh-II 27-Nov-19 10:00 27-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
179 220 160MVA X-mer-I At 220KV s/s Mehgaon 07-Nov-19 09:00 07-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
180 220 160MVA X-mer-II At 220KV s/s Mehgaon 13-Nov-19 09:00 13-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
181 220 220KV Datia- Bina 16-Nov-19 09:00 16-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
182 220 220KV Datia- Gwalior 21-Nov-19 10:00 21-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
183 220 160MVA X-Mer-I at 220 KV S/S Datia 23-Nov-19 09:00 23-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
184 220 160MVA X-Mer-II at 220 KV S/S Datia 26-Nov-19 09:00 26-Nov-19 17:00 Daily Post Mansoon Testing & Maintenance work
185 220 220KV Barwaha-Omkareshwar 09-Nov-19 10:00 09-Nov-19 17:00 Daily Post monsoon maintenance.
Minutes of 71st OCCM of MP 53
Date Time Date Time
Sr- No
KV Line / Transformer / Reactor / Bay
From To Basis(Daily/
Continue)Reason
186 220 220KV Nimrani-Chhegaon-II 10-Nov-19 10:00 10-Nov-19 17:00 Daily Post monsoon maintenance.
187 220 220KV Nimrani-Maheshwar-II 11-Nov-19 10:00 11-Nov-19 17:00 Daily Post monsoon maintenance.
188 220 220KV Bus Coupler at 220KV S/s Nimrani 15-Nov-19 10:00 15-Nov-19 17:00 Daily Post monsoon maintenance.
189 220 220KV Rajgarh-Shujalpur(PGCIL)-I 14-Nov-19 09:00 14-Nov-19 17:00 Daily For line maintenance work
190 220 220KV Rajgarh-Shujalpur(PGCIL)-II 15-Nov-19 09:00 15-Nov-19 17:00 Daily For line maintenance work
191 220 220KV Shujalpur-Shujalpur (PGCIL)-I 20-Nov-19 09:00 20-Nov-19 17:00 Daily For line maintenance work
192 220 220KV Shujalpur-Shujalpur (PGCIL)-II 21-Nov-19 09:00 21-Nov-19 17:00 Daily For line maintenance work
193 220 220KV Khandwa (PGCIL)- Nepa 16-Nov-19 10:00 16-Nov-19 17:00 Daily For line maintenance work
194 220 220KV Sant Singaji-Chhegaon-I 18-Nov-19 10:00 18-Nov-19 17:00 Daily For line maintenance work
195 220 220KV Sant Singaji-Chhegaon-I 23-Nov-19 10:00 23-Nov-19 17:00 Daily For line maintenance work
196 220 220KV Omkareshwar(OSP) - Khandwa (PGCIL) 27-Nov-19 10:00 27-Nov-19 17:00 Daily For line maintenance work
197 220 220KV Omkareshwar - Chhegaon 28-Nov-19 10:00 28-Nov-19 17:00 Daily For line maintenance work
198 220 220KV Jaitpura (PGCIL) Hatunia-Indore-I 19-Nov-19 10:00 19-Nov-19 17:00 Daily For line maintenance work
199 220 220KV Jaitpura (PGCIL) Hatunia-Indore-II 20-Nov-19 10:00 20-Nov-19 17:00 Daily For line maintenance work
200 220 220KV Indore (PGCIL) Hatunia-Ujjain-I 25-Nov-19 10:00 25-Nov-19 17:00 Daily For line maintenance work
201 220 220KV Indore (PGCIL) Hatunia-Ujjain-II 26-Nov-19 10:00 26-Nov-19 17:00 Daily For line maintenance work
202 220 220KV ICT-I at 220KV Sukha 04-Dec-19 9:00 05-Dec-19 17:00 Daily For maintenance & Testing work
203 220 220KV ICT-II at 220KV Sukha 09-Dec-19 9:00 10-Dec-19 17:00 Daily For maintenance & Testing work
204 220 220KV Pandhurna-Kamleshwar 10-Dec-19 09:00 10-Dec-19 00:00 Daily For maintenance & Testing work
205 220 220KV Chhindwara-PGCIL-I 12-Dec-19 09:00 12-Dec-19 17:00 Daily For maintenance & Testing work
206 220 220KV Chhindwara-PGCIL-II 13-Dec-19 09:00 13-Dec-19 17:00 Daily For maintenance & Testing work
207 220 220KV Seoni-PGCIL-I 10-Dec-19 09:00 10-Dec-19 18:00 Daily For maintenance & Testing work
208 220 220KV Seoni-PGCIL-II 12-Dec-19 09:00 12-Dec-19 18:00 Daily For maintenance & Testing work
209 220 220KV Mahalgaon-PGCIL-I 11-Dec-19 10:00 11-Dec-19 17:00 Daily For maintenance & Testing work
210 220 220KV Mahalgaon-PGCIL-II 12-Dec-19 10:00 12-Dec-19 17:00 Daily For maintenance & Testing work
211 220 220KV Mahalgaon-Bina 18-Dec-19 10:00 18-Dec-19 17:00 Daily For maintenance & Testing work
212 220 220KV Mahalgaon-Datia 19-Dec-19 10:00 19-Dec-19 17:00 Daily For maintenance & Testing work
213 220 220KV Mehgaon --Adani 03-Dec-19 09:00 03-Dec-19 17:00 Daily For maintenance & Testing work
214 220 220KV Mehgaon-Auraiya 07-Dec-19 09:00 07-Dec-19 17:00 Daily For maintenance & Testing work
215 220 160MVA Transformer-I at 220KV s/s Mehgaon 10-Dec-19 09:00 10-Dec-19 17:00 Daily For maintenance & Testing work
216 220 160MVA Transformer-II at 220KV s/s Mehgaon 16-Dec-19 09:00 16-Dec-19 17:00 Daily For maintenance & Testing work
217 220 220KV Datia- Bina 20-Dec-19 09:00 20-Dec-19 17:00 Daily For maintenance & Testing work
218 220 220KV Datia- Gwalior 24-Dec-19 10:00 24-Dec-19 17:00 Daily For maintenance & Testing work
219 220 160 MVA Transformer-I at 220 KV S/S Datia 27-Dec-19 09:00 27-Dec-19 17:00 Daily For maintenance & Testing work
220 220 160 MVA Transformer-II at 220 KV S/S Datia 30-Dec-19 09:00 30-Dec-19 17:00 Daily For maintenance & Testing work
221 220 220 KV Bus Tie at 220 KV S/s Shivpuri 16-Dec-19 10:00 16-Dec-19 17:00 Daily For maintenance & Testing work
222 220 220KV Sagar- PGCIL Damoh-I 19-Dec-19 09:00 19-Dec-19 17:00 Daily For maintenance & Testing work
223 220 220KV Sagar- PGCIL Damoh-II 23-Dec-19 09:00 23-Dec-19 17:00 Daily For maintenance & Testing work
224 220 220KV Damoh- PGCIL Damoh-I 26-Dec-19 09:00 26-Dec-19 17:00 Daily For maintenance & Testing work
225 220 220KV Damoh- PGCIL Damoh-II 30-Dec-19 09:00 30-Dec-19 17:00 Daily For maintenance & Testing work
226 220 Barwaha-Indore-I (at-220KV S/s Barwaha) 09-Dec-19 10:00 09-Dec-19 17:00 DailyFor bay equipment maintenance & Testing work
227 220 Barwaha-Indore-II (at-220KV S/s Barwaha) 10-Dec-19 10:00 10-Dec-19 17:00 DailyFor bay equipment maintenance & Testing work
228 220 Nimrani-Maheshwar-I (at-220KV S/s Nimrani) 11-Dec-19 10:00 11-Dec-19 17:00 DailyFor bay equipment maintenance & Testing work
229 220 Nimrani-Julwaniya (at-220KV S/s Nimrani) 15-Dec-19 10:00 15-Dec-19 17:00 DailyFor bay equipment maintenance & Testing work
Minutes of 71st OCCM of MP 54
A. ThermalStn. Name UNIT No. Capacity
MW June-19 July-195 210 145.89 95.30
PH III 210 145.89 95.30TOT 210 145.89 95.30
6 200 50.73 89.397 210 0.00 56.12
PH II 410 50.73 145.518 210 106.69 96.289 210 72.12 99.93
PH III 420 178.81 196.2110 250 0.00 135.9711 250 163.67 23.49
PH IV 500 163.67 159.46TOT 1330 393.21 501.17
1 210 33.41 62.242 210 66.44 51.70
PH I 420 99.85 113.943 210 109.44 100.144 210 77.49 93.07
PH II 420 186.92 193.215 500 315.16 297.03
PH III 500 315.16 297.03TOT 1340 601.94 604.18
1 600 46.38 29.192 600 248.97 258.18
PH1 1200 295.35 287.373 660 119.65 282.044 660 210.34 291.27
PH II 1320 329.98 573.32
TOT 1860 625.33 860.69
4740 1766.37 2061.33
B. HydelCapacity
MW June-19 July-19115.0 4.63 0.00172.0 0.01 0.0199.0 1.16 6.35
386.0 5.80 6.36193.0 2.90 3.18160.0 0.03 0.00107.0 0.02 0.0090.0 8.72 15.78
315.0 35.70 14.7920.0 0.89 5.1560.0 26.86 30.2530.0 3.02 0.0045.0 0.00 0.0022.5 0.00 0.0020.0 2.75 0.0060.0 0.00 0.00
1186.0 83.76 72.33915.0 82.60 65.97917.5 80.86 69.15
CapacityMW June-19 July-19
Indira Sagar Hydel Project 1000 43.73 80.25Omkareshwar Hydel Project 520 17.74 51.33
Note : 1. Amarkantak Thermal Power Station-II Unit # 4 De-commissioned wef 01-May-2014. 2. Amarkantak Thermal Power Station-II Unit # 3 De-commissioned wef 13-Jan-2015.
TOTAL HYDELMPPGCL HydelMPSEB HYDEL Share
M.P.CHAMBALPENCHM.P.PENCHBARGI
C. NHDC (Ex-Bus)Station Name
B.SGR(DEOLONDH)B.SGR(SILPARA)RAJGHATM.P.RAJGHATB.SGR(JINHA)MADIKHEDA
TONSBIRSINGHPUR
Station NameGANDHISAGARR.P.SAGARJ.SAGARCHAMBAL
Unitwise / Stationwise Genration in MUAnn 4.1
AM
AR
KA
NSA
TPU
RA
SAN
JAY
GA
ND
HI
MPPGCL THERMAL
SSTP
S
Minutes of 71st OCCM of MP 55
S No. Source Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Total30 31 30 31 31 0 0 0 0 0 0 0 153
A.1 Thermal 2278.56 1929.45 1635.59 1915.93 1213.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8973.222 Hydel 125.69 135.30 79.20 66.15 263.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 669.983 Total 2404.26 2064.75 1714.78 1982.08 1477.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9643.20
B.1 Indira Sagar 81.66 94.10 42.03 78.42 507.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 803.572 Omkareshwar 43.59 43.18 17.74 51.33 212.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 368.573 MPPMCL Schedule from Central Sector of WR 1777.61 1845.11 1849.93 1786.51 1529.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8789.004 MPPMCL Schedule from Central Sector ER 31.16 30.60 38.99 34.68 32.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 167.445 Total MPPMCL Schedule from Central Sector (WR+ER) 1808.77 1875.71 1888.92 1821.19 1561.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8956.446 Deviation Energy of (WR+ER) -23.86 1.07 -25.22 -21.74 -103.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -173.437 NET NR ISGS POWER SCH to MP 26.28 60.97 70.71 81.98 41.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 281.438 RUMS SOLAR REWA (Scheduled Energy) 89.06 83.32 82.07 66.59 78.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 399.169 Schedule From Sugen 0.00 0.24 5.07 13.80 2.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.19
10 LANCO Amk 162.90 174.72 166.39 124.22 131.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 759.3811 SASAN 962.78 1016.20 944.63 880.82 794.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4598.8512 ESSAR (STOA against LTA) 0.00 6.16 5.47 4.46 3.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.7213 J P Nigri 315.28 324.01 311.95 162.24 145.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1259.3214 MB Power 215.07 230.68 202.23 179.76 142.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 970.0515 JHABUA Power 70.02 86.00 80.24 77.37 32.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 346.4216 Other Open Access Schedule other than MPPMCL Incl. Seci -188.35 -93.64 -71.91 -76.23 -165.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -595.1317 Himachal Pradesh HYDAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0018 BARH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0019 Schedule from Sardar Sarovar 14.26 11.94 13.14 26.13 398.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 464.2220 SCH to Railway from RGPPL_ebid 176.29 183.11 173.39 180.41 168.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 881.9021 Schedule from SEZ 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0022 Schedule from Rihand+Matatila 3.86 2.81 2.58 6.00 3.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.5023 MTOA / STOA FROM RAJASTHAN 0.00 41.28 41.54 43.06 44.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 170.43
24 Medium Term Power Purchase from CSPDCL through PTC agaisnt PPA CSPDCCL dtd. 18.09.2012
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
25 Medium Term Power Purchase from Balco through PTC agaisnt PPA Balco dtd. 18.09.2012 Including Short term purchase against MTOA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
26 Additional Power Purchase 0.00 0.00 0.00 32.40 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.4427 Energy Exchange 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0028 Banking of Energy -393.14 -468.76 -393.51 -593.40 -564.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -2412.8529 Sale of Power -469.81 -61.02 -40.63 -215.50 -239.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -1026.1030 Total MP Schedule (Including Railway) 2793.28 3473.75 3482.28 2815.30 2580.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15145.3731 Total MP Drawal (Including Railway) 2769.41 3474.82 3457.06 2793.56 2477.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14971.9432 Wheeled Energy of Tawa HEG 0.00 0.00 0.00 0.00 6.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.4833 Wheeled Energy of Wind Farm 10.15 11.63 9.91 13.63 6.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 52.2734 Wheeled Energy of Solar Plant 67.16 64.39 55.62 28.72 35.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 251.6335 Wheeled Energy of Bio-Mass 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0036 Wheeled Energy of Ascent Hydro +SAS Hydel Hatta 1.34 1.27 1.02 2.49 2.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.6237 Export to MSEB (Nepa-Dharni) Wheeling -7.23 -6.99 -5.77 -4.96 -4.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -29.4338 Deviation Energy of MPPGCL Thermal + Infirm Energy of Singajil -30.89 -38.40 -35.05 -25.15 -29.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -159.4139 Energy Purchased by MP from Wind Farm 403.98 579.40 555.30 644.20 490.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2673.1140 Energy Purchased by MP from Solar Plant 163.30 166.07 135.61 109.56 85.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 660.17
41 Firm / Infirm Energy of HEG Mandideep+Hindalco+HEG Tawa +Trimula Ind. purchase by MP +Wheeled enrgy of CPP / IPP
187.15 101.90 86.30 87.04 176.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 639.21
42Purchased from ASN Biomass Katni + RDM Care Ind. Biogas Pariyat + Pragya Energy Pvt. Ltd. Biogas Richhai+ Arya Energy Kotma + Orient Green Power Limited, Gadarawara Bio-Mass+Shaliwahna (CHH+Umariya) + JBP MSW
2.66 2.98 3.06 1.59 0.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.20
43 Deviation Energy of ISP 1.41 1.64 1.70 1.83 2.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.4344 Schedule Energy of BLA Power against LTOA 0.66 4.45 2.27 4.30 1.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.8245 Schedule Energy of JP BINA Power against LTOA 34.61 150.56 147.57 54.21 54.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 441.7946 Import from bargi Left Bank Canal Power House + ISP NVDA 0.59 -0.01 0.00 0.00 1.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.9347 Chambal Complex Excess / less Overshare by MP -1.17 -1.09 1.27 -1.96 -1.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -4.0248 Rajghat Hydel Power Station Excess / Less Overshare by MP -0.03 0.00 -0.02 -0.02 2.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.0749 State Supply (Ex-Power stn. Bus) 6132.61 6714.64 6190.39 5820.86 5506.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30365.1550 AVERAGE DAILY (Ex-Bus) 204.42 216.60 206.35 187.77 177.63 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! 198.4751 MINIMUM DAILY (MP Periphery) 147.90 194.22 166.40 149.59 136.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 136.8952 MAXIMUM DAILY (MP Periphery) 214.82 221.89 221.88 223.94 190.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 223.9453 State Supply (Ex-Power st. Bus):- YEAR : 2018-19 5518.85 5998.45 5155.78 5068.96 5412.65 5474.68 7466.55 7895.66 7889.18 7601.20 6356.67 6508.26 27154.7054 Year ((19-20)-(18-19))*100/Year (18-19) 11.12 11.94 20.07 14.83 1.74 -100.00 -100.00 -100.00 -100.00 -100.00 -100.00 -100.00 11.8255 Unshedule L/S : Year-2019-20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0056 Frequency Correction 2.76 3.66 3.72 2.48 2.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.0557 Restricted Requirement : Year-2019-20 6135.38 6718.30 6194.11 5823.34 5509.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30380.2058 Shedule L/S : Year-2019-20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
ENERGY BALANCE SHEETYear : 2019 - 20
All figures in Million Unit
M.P. Availability
Exchange with other States / Systems
Minutes of 71st OCCM of MP 56
59 Un-Restricted Requirement : Year-2019-20 6135.38 6718.30 6194.11 5823.34 5509.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30380.20
Minutes of 71st OCCM of MP 57
S.NO. Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Yr 19-20
C.1 DEMAND MET 9738 9880 9955 9845 8606 0 0 0 0 0 0 0 99552 LOAD RELIEF 0 0 0 0 0 0 0 0 0 0 0 0 03 LOAD SHEDDING 0 0 0 0 0 0 0 0 0 0 0 0 0D.1 DEMAND MET 9235 9475 9480 9746 8526 0 0 0 0 0 0 0 97462 LOAD RELIEF 0 0 0 0 0 0 0 0 0 0 0 0 03 LOAD SHEDDING 0 0 0 0 0 0 0 0 0 0 0 0 0F. REGISTERED MAXIMUM 9738 9880 9955 9845 8606 0 0 0 0 0 0 0 9955G. COMPUTED MAXIMUM DEMAND 9738 9891 9961 9845 8606 0 0 0 0 0 0 0 9961H. UNRESTRICTED MAXIMUM DEMAND 9738 9891 9955 9845 8606 0 0 0 0 0 0 0 9955I.1. Div. Head Quarters 23:52 23:54 23:48 23:48 23:51 0:00 0:00 0:00 0:00 0:00 0:00 0:00 23:512. District Head Quarters 23:54 23:55 23:48 23:48 23:47 0:00 0:00 0:00 0:00 0:00 0:00 0:00 23:503. Tahsil Head Quarters 23:50 23:53 23:43 23:44 23:48 0:00 0:00 0:00 0:00 0:00 0:00 0:00 23:474. Rural -Mixed 23:36 23:46 23:34 23:29 23:40 0:00 0:00 0:00 0:00 0:00 0:00 0:00 23:375. Rural -DLF 23:40 23:48 23:35 23:34 23:40 0:00 0:00 0:00 0:00 0:00 0:00 0:00 23:396. Rural -Irrigation 9:54 9:57 9:53 9:53 9:53 0:00 0:00 0:00 0:00 0:00 0:00 0:00 9:54J LOAD FACTOR % 87.47 91.35 86.37 79.47 86.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! 86.13
S.N PARTICULARS Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Yr 19-20
A. INTGRATED FREQUENCY1 MAXIMUM 50.21 50.16 50.23 50.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 50.232 MINIMUM 49.81 49.81 49.80 49.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
B. INSTANTANEOUS FREQUENCY1 MAXIMUM 50.29 50.33 50.31 50.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 50.332 MINIMUM 49.65 49.65 49.63 49.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
C. AVG FREQUENCY 50.00 50.00 50.00 50.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40.00D. % TIME WHEN FREQUENCY WAS
1 ABOVE 51.5 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.002 50.05 TO 51.5 Hz 20.14 19.14 19.79 24.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.703 49.9 TO 50.05 Hz 72.76 72.60 70.34 68.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 56.604 49.7 TO 49.9 Hz 7.10 8.26 9.87 7.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.445 49.5 TO 49.7 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.006 49.2 TO 49.5 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.007 48.8 TO 49.2 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.008 48.5 TO 48.8 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.009 BELOW 48.5 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
ENERGY BALANCE SHEET : Demand & Sypply HoursYear : 2019 - 20
MORNING PEAK (MAX)
EVENING PEAK (MAX)
Average Power Supply per day to
FREQUENCY ANALYSIS YEAR 2019-20
Minutes of 71st OCCM of MP 58
THER.Incl Aux
THER. Excl Aux
HYD. ISP OSP
Total IPPs Injecti
on
Total CPPs Injectio
n
Total CSSNet
NR to MP
Sugen Lanco Sasan Essa
rJP
Nigri
RUMS (SOLAR)
REWA TO
MPPMCL
MB Power
Jhabua
Power
SSP
SCH to
Railway
SEZ Banking Sale Pur STOA
Rihand+Matatila-
Rajghat
MTOA / STOA FROM RAJASTHAN
Total SCH UN SCH TOTAL
1:00 50.00 2454 2243 109 114 33 328 940 3768 2788 124 22 240 1256 13 431 0 319 133 19 255 0 -910 -27 0 12 4 58 4739 8508 4742 3 -8 8502 0 0 0 8506 8506
2:00 50.02 2455 2244 104 33 17 325 1009 3731 2799 149 14 248 1264 13 421 0 321 133 19 232 0 -918 -21 0 5 4 58 4740 8471 4613 -127 -8 8337 0 0 0 8339 8339
3:00 50.03 2448 2237 102 11 9 324 1008 3691 2724 154 15 240 1271 13 419 0 318 131 18 212 0 -921 -9 0 5 4 58 4651 8342 4654 4 -7 8339 0 0 0 8340 8340
4:00 50.03 2451 2240 91 18 9 330 974 3661 2682 153 7 244 1310 13 416 0 316 133 18 231 0 -902 0 0 -29 4 58 4653 8313 4630 -23 -7 8283 0 0 0 8285 8285
5:00 50.01 2462 2250 91 14 11 328 946 3640 2661 175 5 240 1285 13 414 0 309 126 18 229 0 -814 0 0 -34 4 58 4687 8327 4641 -46 -7 8274 0 0 0 8278 8278
6:00 49.98 2477 2264 115 63 17 323 889 3671 2625 186 2 235 1284 10 406 18 295 112 17 251 0 -687 -4 0 -39 4 58 4771 8442 4772 1 -8 8435 0 0 0 8443 8443
7:00 50.02 2510 2294 136 36 19 322 931 3739 2732 171 2 237 1293 8 406 20 309 129 17 238 0 -485 -4 0 -57 4 58 5076 8815 4938 -139 -8 8669 0 0 0 8671 8671
8:00 50.08 2455 2243 127 33 13 309 1109 3834 2526 109 0 219 1294 4 404 116 276 103 17 205 0 -346 -4 0 -106 4 58 4878 8712 4696 -182 -8 8522 0 0 0 8523 8523
9:00 50.03 2390 2184 135 26 17 310 1226 3898 2273 56 0 192 1291 1 404 252 216 74 18 236 0 -353 -3 0 -189 4 58 4530 8428 4441 -89 -8 8331 0 0 0 8332 8332
10:00 50.05 2347 2144 134 19 13 309 1294 3912 2166 65 0 180 1273 1 404 344 186 52 18 236 0 -357 0 0 -227 4 58 4402 8315 4353 -50 -8 8257 0 0 0 8258 8258
11:00 50.01 2328 2126 111 4 13 305 1303 3863 2180 57 0 180 1264 1 405 394 177 54 18 245 0 -357 -7 0 -253 4 58 4420 8282 4390 -30 -8 8245 0 0 0 8247 8247
12:00 49.99 2352 2149 119 4 11 306 1266 3854 2172 44 0 187 1239 1 405 411 190 52 17 235 0 -357 -21 0 -257 4 58 4379 8233 4334 -45 -7 8180 0 0 0 8187 8187
13:00 49.98 2403 2196 116 11 11 311 1214 3859 2309 58 0 203 1250 1 405 387 210 68 17 208 0 -387 -9 0 -235 4 58 4547 8406 4608 61 -8 8459 0 0 0 8470 8470
14:00 49.97 2443 2232 109 11 13 314 1083 3761 2404 87 0 218 1242 2 406 336 237 86 17 227 0 -387 -66 0 -205 4 58 4666 8427 4697 31 -8 8451 0 0 0 8461 8461
15:00 49.99 2456 2244 110 19 11 324 1021 3728 2515 74 0 225 1251 3 409 261 256 98 18 232 0 -389 -120 0 -172 4 58 4722 8450 4743 21 -7 8463 0 0 0 8470 8470
16:00 50.00 2457 2245 105 19 21 321 943 3654 2563 100 7 226 1254 4 416 158 270 104 18 249 0 -389 -99 0 -149 4 58 4793 8448 4660 -133 -8 8307 0 0 0 8312 8312
17:00 50.01 2442 2232 98 25 26 328 838 3547 2509 70 10 225 1254 4 418 44 261 110 19 231 0 -389 -69 0 -128 4 58 4629 8176 4595 -34 -8 8134 0 0 0 8139 8139
18:00 50.02 2429 2220 90 26 17 322 762 3437 2398 77 10 215 1255 3 420 5 249 96 19 209 0 -360 -35 0 -125 4 58 4498 7934 4399 -99 -9 7827 0 0 0 7828 7828
19:00 50.01 2457 2246 104 67 22 324 702 3464 2480 90 5 218 1263 3 431 2 245 94 19 236 0 -337 -189 0 -49 4 58 4571 8036 4399 -172 -9 7855 0 0 0 7859 7859
20:00 49.96 2505 2290 140 211 65 367 727 3801 2654 63 15 237 1294 13 441 0 299 139 19 232 0 -594 -191 0 -25 4 58 4658 8459 4707 49 -9 8499 0 0 0 8512 8512
21:00 49.97 2514 2298 130 161 54 368 727 3738 2640 46 17 230 1273 15 444 0 298 137 19 250 0 -582 -124 0 -25 4 58 4699 8437 4667 -32 -9 8396 0 0 0 8406 8406
22:00 50.00 2507 2292 119 151 44 374 755 3734 2611 50 10 226 1275 15 444 0 302 139 19 226 0 -602 -151 0 -26 4 58 4599 8333 4542 -56 -9 8267 0 0 0 8273 8273
23:00 49.98 2506 2290 122 216 67 378 814 3888 2729 53 15 244 1269 16 443 0 318 150 18 205 0 -601 -150 0 -29 4 58 4742 8629 4776 35 -8 8656 0 0 0 8666 8666
24:00 50.00 2494 2279 108 133 50 329 870 3769 2628 53 11 244 1251 15 443 0 307 139 18 235 0 -459 -84 0 11 4 58 4872 8641 4768 -104 -8 8529 0 0 0 8535 8535
Avg. 50.01 2448 2237 114 59 24 328 973 3735 2532 94 7 223 1269 8 419 114 270 108 18 231 0 -537 -58 0 -97 4 58 4663 8399 4615 -48 -8 8342 0 0 0 8347 8347
00 TO 06 HRS.
50.01 2458 2246 102 42 16 327 961 3694 2713 157 11 241 1278 12 418 3 313 128 18 235 0 -859 -10 0 -13 4 58 4707 8401 4675 -31 -8 8362 0 0 0 8365 8365
06 TO 12 HRS.
50.03 2397 2190 127 20 14 310 1188 3850 2341 84 0 199 1276 3 405 256 226 77 18 232 0 -376 -7 0 -182 4 58 4614 8464 4525 -89 -8 8367 0 0 0 8370 8370
12 TO 18 HRS.
50.00 2438 2228 105 18 16 320 977 3664 2449 78 4 219 1251 3 412 198 247 94 18 226 0 -383 -66 0 -169 4 58 4642 8307 4617 -25 -8 8273 0 0 0 8280 8280
06TO 18 HRS.
50.01 2418 2209 116 19 15 315 1082 3757 2395 81 2 209 1263 3 409 227 236 86 18 229 0 -380 -36 0 -175 4 58 4628 8386 4571 -57 -8 8320 0 0 0 8325 8325
18 TO 24 HRS.
49.99 2497 2282 120 156 50 357 766 3732 2624 59 12 233 1271 13 441 0 295 133 19 231 0 -529 -148 0 -24 4 58 4690 8422 4643 -47 -9 8367 0 0 0 8375 8375
Hourly Average Own Generation, Schedule Drawal , Actual Drawal & Demand Month :- June 2019
FIGURES IN MWSchedule from
DEMAND
MET
Load Shedding
UNREST. DEMAND
Export to MS
REST. DEMAN
DHrs. FREQ.
Own Generation
TotAvl.
Act.Drl
Devia -tion
Minutes of 71st OCCM of MP 59
THER.Incl Aux
THER. Excl Aux
HYD. ISP OSP
Total IPPs
Injection
Total CPPs Injectio
n
Total CSSNet
NR to MP
Sugen Lanco Sasan Essa
rJP
Nigri
RUMS (SOLA
R) REWA TO
MPPMCL
MB Power
Jhabua
Power
SSP
SCH to
Railway
SEZ Banking Sale Pur STOA
Rihand+
Matatila-
Rajghat
MTOA / STOA FROM RAJASTHAN
Total SCH UN SCH TOTAL
1:00 50.02 2793 2550 82 172 89 192 899 3984 2581 175 28 161 1161 10 219 0 269 128 38 254 0 -1197 -155 70 -30 8 58 3778 7762 3761 -17 -7 7738 0 0 0 7740 7740
2:00 50.04 2759 2519 77 146 77 190 926 3935 2521 203 24 163 1162 9 213 0 273 114 34 239 0 -1223 -121 70 -44 8 58 3701 7636 3670 -32 -7 7598 0 0 0 7599 7599
3:00 50.03 2762 2521 73 108 64 189 950 3905 2542 208 24 161 1175 7 212 0 272 100 34 209 0 -1256 -93 70 -44 8 58 3686 7591 3686 0 -7 7584 0 0 0 7586 7586
4:00 50.03 2756 2515 74 105 64 186 963 3907 2545 234 19 163 1192 7 209 0 276 102 32 232 0 -1265 -125 70 -66 8 58 3690 7596 3603 -86 -7 7503 0 0 0 7505 7505
5:00 50.01 2740 2501 73 97 66 183 984 3905 2446 195 17 158 1186 7 208 0 254 92 32 232 0 -1120 -120 70 -66 8 58 3656 7561 3615 -41 -7 7514 0 0 0 7516 7516
6:00 49.97 2764 2523 78 79 65 184 939 3868 2375 137 17 153 1176 4 203 13 219 87 31 253 0 -695 -169 70 -71 8 58 3870 7738 3900 29 -7 7760 0 0 0 7770 7770
7:00 50.01 2778 2536 102 97 64 185 979 3964 2463 142 17 157 1182 4 203 25 245 98 31 239 0 -554 -215 70 -80 8 58 4093 8057 4082 -11 -7 8039 0 0 0 8041 8041
8:00 50.07 2768 2527 105 50 53 185 1172 4091 2381 130 17 153 1169 3 203 99 222 91 31 209 0 -553 -125 70 -100 8 58 4066 8157 3822 -245 -7 7906 0 0 0 7906 7906
9:00 50.04 2711 2474 92 22 35 183 1331 4136 2167 93 9 152 1179 3 203 191 172 70 30 239 0 -546 -114 75 -145 8 58 3843 7980 3611 -233 -6 7741 0 0 0 7741 7741
10:00 50.03 2674 2441 86 22 27 180 1404 4159 2092 47 9 150 1156 3 203 254 142 55 31 238 0 -609 -297 31 -160 8 58 3411 7571 3381 -30 -6 7534 0 0 0 7536 7536
11:00 50.03 2658 2425 80 11 29 181 1417 4143 2046 25 7 150 1134 2 203 297 148 55 33 254 0 -608 -338 31 -173 8 58 3331 7474 3209 -121 -6 7347 0 0 0 7349 7349
12:00 50.02 2654 2422 70 22 33 184 1397 4128 1948 39 7 150 1084 2 203 315 151 55 33 237 0 -606 -361 25 -185 8 58 3165 7293 3057 -108 -6 7179 0 0 0 7182 7182
13:00 50.02 2653 2421 68 7 35 186 1355 4073 1960 72 12 150 1083 2 205 304 158 55 34 209 0 -670 -310 29 -186 8 58 3172 7245 3156 -16 -6 7223 0 0 0 7226 7226
14:00 50.01 2660 2427 66 11 33 189 1320 4045 1967 66 12 150 1103 2 206 267 155 59 33 229 0 -669 -287 30 -179 8 58 3209 7255 3157 -52 -6 7197 0 0 0 7200 7200
15:00 49.99 2674 2440 73 48 45 186 1243 4035 2196 69 12 150 1093 3 207 206 182 74 33 231 0 -669 -626 25 -169 8 58 3084 7119 3232 148 -5 7262 0 0 0 7266 7266
16:00 50.01 2681 2447 82 54 53 186 1158 3980 2315 65 14 153 1117 3 209 124 204 82 34 254 0 -668 -528 25 -148 8 58 3321 7301 3315 -6 -6 7289 0 0 0 7294 7294
17:00 49.99 2707 2470 73 54 53 189 1007 3846 2341 81 14 161 1138 3 210 49 243 94 37 234 0 -675 -457 25 -133 8 58 3429 7275 3467 39 -6 7307 0 0 0 7312 7312
18:00 50.00 2742 2503 77 50 55 191 808 3683 2280 67 12 164 1171 3 212 13 213 89 42 209 0 -507 -355 30 -117 8 58 3592 7275 3642 50 -7 7318 0 0 0 7323 7323
19:00 50.00 2837 2590 99 94 65 207 645 3701 2494 90 14 175 1164 6 220 1 247 114 42 237 0 -513 -432 30 -81 8 58 3874 7575 3816 -58 -7 7509 0 0 0 7514 7514
20:00 49.98 2906 2653 142 310 125 240 599 4068 2686 80 26 186 1140 13 223 0 316 165 42 239 0 -921 -370 25 -53 8 58 3863 7932 4037 174 -8 8098 0 0 0 8106 8106
21:00 49.99 2916 2662 119 305 143 244 618 4090 2685 86 31 179 1139 13 223 0 319 173 42 253 0 -882 -407 25 -54 8 58 3892 7982 3880 -12 -8 7962 0 0 0 7970 7970
22:00 50.03 2923 2669 100 256 139 239 682 4084 2641 86 35 183 1136 13 223 0 314 172 42 232 0 -894 -417 25 -54 8 58 3804 7888 3805 1 -8 7881 0 0 0 7883 7883
23:00 50.01 2915 2662 99 263 142 223 768 4156 2658 89 35 179 1149 12 223 0 309 163 42 209 0 -864 -384 25 -47 8 58 3865 8021 3917 52 -7 8066 0 0 0 8069 8069
24:00 50.04 2875 2625 93 193 120 197 822 4049 2564 85 24 167 1142 11 223 1 280 138 42 240 0 -692 -305 25 -45 8 58 3967 8016 3831 -136 -7 7873 0 0 0 7875 7875
Avg. 50.02 2763 2522 87 107 70 196 1016 3997 2371 107 18 161 1147 6 211 90 233 101 36 234 0 -786 -296 44 -101 8 58 3640 7638 3610 -30 -7 7601 0 0 0 7605 7605
00 TO 06 HRS. 50.02 2762 2521 76 118 71 187 944 3917 2502 192 21 160 1175 7 211 2 261 104 33 237 0 -1126 -131 70 -53 8 58 3730 7647 3706 -24 -7 7616 0 0 0 7619 7619
06 TO 12 HRS. 50.03 2707 2471 89 37 40 183 1283 4104 2183 79 11 152 1151 3 203 197 180 71 31 236 0 -579 -242 50 -140 8 58 3652 7755 3527 -125 -6 7624 0 0 0 7626 7626
12 TO 18 HRS. 50.00 2686 2451 73 37 46 188 1148 3944 2176 70 13 155 1117 3 208 160 192 75 35 228 0 -643 -427 28 -155 8 58 3301 7245 3328 27 -6 7266 0 0 0 7270 7270
06TO 18 HRS. 50.02 2697 2461 81 37 43 185 1216 4024 2180 75 12 153 1134 3 206 179 186 73 33 232 0 -611 -334 39 -148 8 58 3476 7500 3428 -49 -6 7445 0 0 0 7448 7448
18 TO 24 HRS. 50.01 2895 2643 109 237 122 225 689 4025 2621 86 28 178 1145 11 223 0 298 154 42 235 0 -794 -386 26 -55 8 58 3878 7902 3881 3 -8 7898 0 0 0 7903 7903
Devia -tion
Export to MS
DEMAND MET
Load Shedding
REST. DEMAN
D
UNREST.
DEMAND
Hourly Average Own Generation, Schedule Drawal , Actual Drawal & Demand Month :- July 2019
FIGURES IN MW
Hrs. FREQ.
Own Generation Schedule from
TotAvl.
Act.Drl
Minutes of 71st OCCM of MP 60
SCH Demand Met
O/U DRL
SCH LS
Unsch LS
Restricted
Demand
Unrestricted
DemandSCH Demand
MetO/U DRL
SCH LS
Unsch LS
Restricted
Demand
Unrestricted
DemandSCH Demand
MetO/U DRL
SCH LS
Unsch LS
Restricted
Demand
Unrestricted
DemandTotal Sch Total
Drawal
1:00 50.00 2819 2850 32 0 0 2851 2851 2779 2895 115 0 0 2896 2896 959 2519 1560 0 0 2520 2520 255 238
2:00 50.02 2808 2714 -94 0 0 2715 2715 2746 2840 94 0 0 2841 2841 873 2536 1663 0 0 2537 2537 232 247
3:00 50.03 2744 2745 1 0 0 2745 2745 2695 2794 99 0 0 2794 2794 869 2564 1696 0 0 2565 2565 212 236
4:00 50.03 2727 2726 -1 0 0 2727 2727 2681 2760 79 0 0 2760 2760 940 2564 1624 0 0 2565 2565 231 233
5:00 50.01 2720 2705 -15 0 0 2706 2706 2651 2741 90 0 0 2742 2742 1040 2589 1549 0 0 2590 2590 229 239
6:00 49.98 2626 2545 -80 0 0 2548 2548 2683 2881 198 0 0 2884 2884 1300 2763 1464 0 0 2766 2766 251 245
7:00 50.02 2688 2613 -75 0 0 2613 2613 2732 2879 147 0 0 2880 2880 1511 2922 1411 0 0 2923 2923 238 254
8:00 50.08 2627 2528 -98 0 0 2528 2528 2674 2746 72 0 0 2746 2746 1254 2997 1743 0 0 2997 2997 205 250
9:00 50.03 2490 2484 -6 0 0 2485 2485 2485 2628 143 0 0 2628 2628 1009 2977 1968 0 0 2978 2978 236 241
10:00 50.05 2524 2514 -10 0 0 2514 2514 2329 2519 190 0 0 2519 2519 891 2982 2091 0 0 2982 2982 236 242
11:00 50.01 2543 2561 18 0 0 2562 2562 2237 2484 247 0 0 2485 2485 865 2965 2100 0 0 2966 2966 245 234
12:00 49.99 2568 2468 -100 0 0 2470 2470 2222 2497 274 0 0 2499 2499 921 2974 2053 0 0 2976 2976 235 242
13:00 49.98 2580 2598 18 0 0 2602 2602 2238 2533 295 0 0 2536 2536 1149 3097 1948 0 0 3101 3101 208 231
14:00 49.97 2559 2568 9 0 0 2571 2571 2334 2567 234 0 0 2571 2571 1339 3079 1740 0 0 3083 3083 227 236
15:00 49.99 2550 2558 8 0 0 2560 2560 2390 2595 205 0 0 2597 2597 1439 3071 1632 0 0 3074 3074 232 239
16:00 50.00 2515 2470 -46 0 0 2471 2471 2472 2610 138 0 0 2612 2612 1549 2986 1437 0 0 2988 2988 249 241
17:00 50.01 2437 2394 -43 0 0 2395 2395 2503 2636 132 0 0 2637 2637 1567 2858 1291 0 0 2860 2860 231 247
18:00 50.02 2375 2253 -122 0 0 2254 2254 2546 2627 81 0 0 2628 2628 1500 2704 1204 0 0 2705 2705 209 242
19:00 50.01 2424 2419 -5 0 0 2420 2420 2568 2616 47 0 0 2617 2617 1560 2571 1011 0 0 2572 2572 236 249
20:00 49.96 2720 2748 28 0 0 2753 2753 2701 2879 178 0 0 2884 2884 1533 2621 1088 0 0 2625 2625 232 250
21:00 49.97 2748 2773 24 0 0 2776 2776 2740 2847 107 0 0 2850 2850 1410 2543 1133 0 0 2546 2546 250 234
22:00 50.00 2736 2730 -6 0 0 2732 2732 2697 2828 131 0 0 2830 2830 1276 2482 1206 0 0 2484 2484 226 227
23:00 49.98 2857 2899 42 0 0 2903 2903 2793 2971 178 0 0 2975 2975 1259 2565 1306 0 0 2568 2568 205 220
24:00 50.00 2880 2853 -28 0 0 2855 2855 2791 2915 124 0 0 2917 2917 1132 2510 1378 0 0 2511 2511 235 252
Avg. 50.01 2636 2613 -23 0 0 2615 2615 2570 2720 150 0 0 2722 2722 1214 2768 1554 0 0 2770 2770 231 240
00 TO 06 HRS. 50.01 2741 2714 -26 0 0 2715 2715 2706 2818 113 0 0 2820 2820 997 2589 1592 0 0 2590 2590 235 240
06 TO 12 HRS. 50.03 2573 2528 -45 0 0 2529 2529 2447 2626 179 0 0 2626 2626 1075 2970 1894 0 0 2970 2970 232 244
12 TO 18 HRS. 50.00 2503 2473 -29 0 0 2475 2475 2414 2595 181 0 0 2597 2597 1424 2966 1542 0 0 2968 2968 226 239
06TO 18 HRS. 50.01 2538 2501 -37 0 0 2502 2502 2430 2610 180 0 0 2612 2612 1249 2968 1718 0 0 2969 2969 229 242
18 TO 24 HRS. 49.99 2728 2737 9 0 0 2740 2740 2715 2843 128 0 0 2845 2845 1362 2549 1187 0 0 2551 2551 231 239
Discomwise Hourly Average Schedule Drawal , Actual Drawal &Over(+)/Under(-) DrawalMonth :- June 2019
FIGURES IN MW
Hrs. FREQ.
EZONE CZONE WZONE Railway
Minutes of 71st OCCM of MP 61
SCH Demand Met
O/U DRL
SCH LS
Unsch LS
Restricted
Demand
Unrestricted
DemandSCH Demand
MetO/U DRL
SCH LS
Unsch LS
Restricted
Demand
Unrestricted
DemandSCH Demand
MetO/U DRL
SCH LS
Unsch LS
Restricted
Demand
Unrestricted
DemandTotal Sch Total
Drawal
1:00 50.02 2629 2563 -66 0 0 2564 2564 2744 2820 76 0 0 2821 2821 2194 2117 -77 0 0 2118 2118 254 238
2:00 50.04 2578 2471 -107 0 0 2471 2471 2694 2784 90 0 0 2784 2784 2157 2100 -57 0 0 2101 2101 239 242
3:00 50.03 2572 2501 -71 0 0 2502 2502 2660 2740 81 0 0 2741 2741 2163 2107 -56 0 0 2108 2108 209 235
4:00 50.03 2583 2493 -90 0 0 2494 2494 2662 2705 43 0 0 2706 2706 2133 2076 -57 0 0 2076 2076 232 230
5:00 50.01 2560 2472 -88 0 0 2473 2473 2638 2695 57 0 0 2696 2696 2180 2119 -61 0 0 2119 2119 232 228
6:00 49.97 2481 2372 -109 0 0 2374 2374 2657 2801 144 0 0 2804 2804 2341 2347 6 0 0 2350 2350 253 241
7:00 50.01 2499 2418 -80 0 0 2419 2419 2779 2874 96 0 0 2875 2875 2542 2497 -46 0 0 2497 2497 239 249
8:00 50.07 2516 2366 -150 0 0 2366 2366 2897 2816 -82 0 0 2816 2816 2524 2480 -44 0 0 2480 2480 209 245
9:00 50.04 2441 2339 -102 0 0 2339 2339 2809 2769 -39 0 0 2770 2770 2451 2394 -56 0 0 2395 2395 239 238
10:00 50.03 2369 2293 -76 0 0 2293 2293 2654 2701 47 0 0 2702 2702 2302 2305 3 0 0 2306 2306 238 235
11:00 50.03 2363 2265 -99 0 0 2265 2265 2606 2622 16 0 0 2623 2623 2272 2230 -42 0 0 2231 2231 254 230
12:00 50.02 2356 2183 -172 0 0 2184 2184 2527 2575 48 0 0 2576 2576 2204 2186 -17 0 0 2187 2187 237 235
13:00 50.02 2335 2227 -108 0 0 2228 2228 2506 2577 71 0 0 2578 2578 2245 2197 -47 0 0 2198 2198 209 221
14:00 50.01 2277 2171 -106 0 0 2172 2172 2511 2585 74 0 0 2586 2586 2251 2218 -33 0 0 2219 2219 229 223
15:00 49.99 2199 2172 -27 0 0 2173 2173 2491 2604 113 0 0 2606 2606 2243 2257 15 0 0 2259 2259 231 228
16:00 50.01 2220 2160 -60 0 0 2161 2161 2542 2608 66 0 0 2610 2610 2348 2288 -60 0 0 2289 2289 254 233
17:00 49.99 2150 2132 -18 0 0 2133 2133 2543 2624 81 0 0 2626 2626 2332 2320 -12 0 0 2321 2321 234 231
18:00 50.00 2168 2104 -64 0 0 2105 2105 2567 2634 67 0 0 2635 2635 2308 2345 38 0 0 2347 2347 209 235
19:00 50.00 2318 2326 8 0 0 2328 2328 2562 2555 -7 0 0 2557 2557 2455 2387 -68 0 0 2389 2389 237 241
20:00 49.98 2607 2622 15 0 0 2624 2624 2664 2780 116 0 0 2783 2783 2467 2439 -28 0 0 2442 2442 239 257
21:00 49.99 2629 2645 15 0 0 2648 2648 2708 2752 44 0 0 2755 2755 2388 2332 -56 0 0 2334 2334 253 234
22:00 50.03 2637 2604 -33 0 0 2605 2605 2684 2767 83 0 0 2767 2767 2341 2283 -57 0 0 2284 2284 232 227
23:00 50.01 2697 2659 -38 0 0 2660 2660 2807 2940 133 0 0 2942 2942 2298 2248 -50 0 0 2249 2249 209 218
24:00 50.04 2675 2604 -71 0 0 2605 2605 2823 2865 42 0 0 2865 2865 2232 2148 -85 0 0 2148 2148 240 256
Avg. 50.02 2453 2382 -71 0 0 2383 2383 2656 2716 61 0 0 2718 2718 2307 2268 -40 0 0 2269 2269 234 235
00 TO 06 HRS. 50.02 2567 2479 -89 0 0 2480 2480 2676 2757 82 0 0 2758 2758 2195 2144 -50 0 0 2145 2145 237 236
06 TO 12 HRS. 50.03 2424 2311 -113 0 0 2311 2311 2712 2726 14 0 0 2727 2727 2383 2349 -34 0 0 2349 2349 236 239
12 TO 18 HRS. 50.00 2225 2161 -64 0 0 2162 2162 2527 2606 79 0 0 2607 2607 2288 2271 -17 0 0 2272 2272 228 229
06TO 18 HRS. 50.02 2324 2236 -89 0 0 2237 2237 2619 2666 47 0 0 2667 2667 2335 2310 -25 0 0 2311 2311 232 234
18 TO 24 HRS. 50.01 2594 2577 -17 0 0 2578 2578 2708 2776 68 0 0 2778 2778 2364 2306 -57 0 0 2308 2308 235 239
Discomwise Hourly Average Schedule Drawal , Actual Drawal &Over(+)/Under(-) DrawalMonth :- July 2019
FIGURES IN MW
Hrs. FREQ.
EZONE CZONE WZONE Railway
Minutes of 71st OCCM of MP 62
Annexure-5
1. System Disturbance on 02.06.2019 at 220kv s/s Sarni: On dated 02.06.19 at 04.30 hrs. M.P system was normal and frequency of National Grid was 50.05 Hz,at 04.33hrs,B Ph. CT of 220kv Sarni-Betulckt failed due to Insulation failure at 220KV S/s Sarni ,leading to the Bus Bar protection operation, resulting into the tripping of following elements :-
220KV Sarni-Betulckt 220KV Sarni-Pandhurnackt 220KV Sarni-STPScktNo 1 &2 160MVA Xmer&100MVA Xmer No any system and areas affected as load managed by other 132kv feeders at
220KV S/s Sarni.There was no load loss and no generation loss.
2. System Disturbance on 13.06.2019 in 220KV S/sJabalpur: On dated 13-06-2019 M.P system was facing Bad weather, heavy thunder storm , rains &lightning and frequency of National Grid was 50.03 Hz, at around 16.00 Hrs, Due to Extreme bad weather conditions one tower of 220kv Jabalpur-Narsinghpurckt 1 & 2 collapsed of loc no 11/1 ,at 16.02hrs subsequently followingelements tripped at 220kv s/s Jabalpur :
220kv Jabalpur-Birsinghpurckt 160 MVA X-mer( BHEL) 160 MVA X-mer( BBL) 160 MVA X-mer( GEC) 3X40 MVA X-mer( MITSU) 132KV Jabalpur-Madhotalckt 132KV Jabalpur-Panagarckt 132KV Jabalpur-TejgarhtapPatanckt
3
4 no of s/s interrupted i.e 220kv Jabalpur s/s, 132kv Maneri s/s , 132kv VFJ s/s & 132kv Vinobabhave s/s affected by the trippingalthough load remain managed in remaining s/s of that region.There was a load loss 232MW and no generation loss. System Normalized by charging 160 MVA X-mer( BHEL) at 16.15 hrs and the other elements gradually. 220kv Jabalpur-Narsinghpurckt 1 & 2 are still out.
3. System Disturbance on 02.06.2019 in SSTPS-Pihampur Area: On dated 02-06-2019 at 15.20 Hrs. M.P system at Indore area was stormy and frequency of National Grid was 50.06 Hz, at 15.26 Hrs, following elements tripped :
400kv SSTPS-Pithampurckt I & II 400kv SSTPS-Pithampurckt III
During the event , 400kv SSTPS-Pithampurckt IV was under shutdown, as SSTPS generation was low at that time , no overloading happened. No any system and areas affected as load remain managed at that region by other ckts.There was no load loss and no generation loss. 24 no of towers collapsed of 400kv SSTPS-Pithampurckt I & II. 400kv SSTPS-Pithampurckt I & II are still out. 400kv SSTPS-Pithampurckt III charged at 18.35 hrs.
4. System Disturbance on 12.06.2019 in Rajgarh area: On dated 12-06-2019 at 20.00 Hrs, frequency of National Grid was 50.07 Hz, MP system was very stormy , 20.03 hrs due to extremely bad weather and stormy conditions, few towers of 400kv Rajgarh-SSP ckt I & II demaged/collapsed at different locations.
There was no load loss and no generation loss. 400kv Rajgarh-SSP ckt I& II are still out.
5. System Disturbance on 26.06.2019 in 220KV S/sBirsinghpur(pali)-On dated 26-06-2019 at 01.50 Hrs. M.P system was normal and frequency of National Grid was 49.98 Hz,
Minutes of 71st OCCM of MP 63
at 01.55 Hrs, 220kv Bus fault occurred at 220KV S/s Birsinghpur ,resulting in the tripping of followingelements :
220kv Birsinghpur-Birsinghpurckt I, II , III , IV 220kv Birsinghpur-Jabalpur ckt I & II 220kv Birsinghpur-Traction ckt I & II 220kv Birsinghpur-Hydelckt 220kv Bus tie 160 MVA x-mer
No any system and areas affected as load remain managed by other 132kv feeders at 220KV S/s Birsinghpur.There was no load loss and no generation loss.
6. System Disturbance on 07.07.2019 at Satna area: On dated 07.07.19 at 18.30 hrs. M.P system was normal with the little stormy weather at satna area and frequency of National Grid was 50.00 Hz,at 18.47 hrs, 220kv Satna(PG)-Chhatarpurckttripped with heavy fault current at Satna(PG) end,ckt didn’t hold at first charge.
On patrolling, a tower at loc no 12 found collapsed.
No any system and areas affected as load managed by other 132kv Bijawar – Chhatarpurckt. There was no load loss and no generation loss.ERS tower installed at the loc no 12 and line charged through it on 15.07.19
Presently the ckt is on ERS tower.
Minutes of 71st OCCM of MP 64
GROUP NAME OF SUBSTATIONPERIOD OF
PROTECTION AUDITTEAM MEMBERS NAME / DESIGNATION DEPARTMENT CONTACT NO. E-MAIL ID
1. Er. Cinderella Felix, Assistant Engineer O/o. CE, SLDC MPPTCL, Jabalpur 9425802661 [email protected]
2. Er. P.S.RAGHAV, Executive Engineer Testing Dn. Bhopal, MPPTCL. 9425804998 [email protected]
3. Er. Rajendra Agrawal, Executive Engineer O/o. CE(Gen), SSTPS, Khandwa 9425808834 [email protected] , [email protected]
4. B.K.Sahu, Manager (Electrical) ISP, NHDC 9424025167/7389806167
[email protected] , [email protected]
1. Er. S.Chakraborty, Executive Engineer O/o. CE, SLDC MPPTCL, Jabalpur 9425805249 [email protected]
2. Er. R.K AGRAWAL, Executive Engineer Testing Dn.-II, Jabalpur. 9425805061 [email protected]
3. Er. Irshad Khan, Executive Engineer O/o. ED(Engg.), Jabalpur 9425806563 [email protected] , [email protected]
4. B.K.Sahu, Manager (Electrical) ISP, NHDC 9424025167/7389806167
[email protected] , [email protected]
1. Er. Shikhar Nema, Assistant Engineer O/o. CE, SLDC MPPTCL, Jabalpur 9425805299 [email protected]
2. Er. C.B.KUSHWAHA, Assistant Engineer Testing Dn., Katni. 9425805293 [email protected] , [email protected]
3. Er. P.K.Shrivastava, Executive Engineer O/o. CE(O&M:Hydel), Jabalpur 9425806636 [email protected]
4. Dhananjay Ram, Assistant Manager (Electrical) OSP, NHDC 9424078528 [email protected] , [email protected]
1. Er. S.Chakraborty, Executive Engineer O/o. CE, SLDC MPPTCL, Jabalpur 9425805249 [email protected]
2. Er. R.K AGRAWAL, Executive Engineer Testing Dn.-II, Jabalpur. 9425805061 [email protected]
3. Er. Harpreet Bumrah, Assistant Engineer O/o. CE(O&M:Gen), Jabalpur 9425808578 [email protected] ,
4. Er. Sailesh Tripathi Plant Engineer, JP Bina 8349997025 [email protected] , [email protected]
1. Er. Shikhar Nema, Assistant Engineer O/o. CE, SLDC MPPTCL, Jabalpur 9425805299 [email protected]
2. Er. R.K AGRAWAL, Executive Engineer Testing Dn.-II, Jabalpur. 9425805061 [email protected]
3. Er. Anshuman Choudhary, Assistant Engineer O/o. CE(Gen), STPA, Sarni 9425611155 [email protected]
4. Er. Arman Ali Senior Engineer, JP Bina 8719899556 [email protected]
Annexure-6.6
22-10-201923-10-201924-10-2019
03-10-201904-10-201905-10-2019
220 KV S/S PITHAMPUR SEC-III220 KV S/S PITHAMPUR SEC-II220 KV S/S DHAR
GROUP-III
15-10-201916-10-201917-10-2019
GROUP-V
GROUP-IV400 KV SGTPS220 KV AMARKANTAK220 KV S/S ANUPPUR
220 KV S/S BINA220 KV S/S GUNA220 KV S/S ASHOKNAGAR
1. 220 KV MAIHAR2. 220 KV S/S SATNA3. 220 KV S/S KOTAR
18-09-201919-09-201920-09-2019
220 KV TONS HPS220 KV S/S SIRMOUR220 KV S/S REWA
GROUP-II25-09-201926-09-201927-09-2019
GROUP-I
Minutes of 71st OCCM of MP 65
Frequent variation in Scheduling of MPPGCL Units.
Agenda pt. no. 6.8:-ED(O&M) generation, MPPGCL, Jabalpur has intimated vide letter no: 1500 dtd-26.08.2019 that it has been seen that there is frequent backing down/up of scheduling is being given to SSTPS Units without giving reasonable time to stabilize the unit on particular load. There is cases where after ramp down upto TMM in a particular block the unit again schedule for ramped up in next block and vice-versa. The MPPGCL has mentioned that thermal units are not designed to vary load such frequently as the thermal units take time to stabilize the machine and to maintain the desired differential expansion and overall expansion with other parameter of unit after ramp-up and ramp-down for safe operation. the MPPGCL has requested to give 4 time block to run the machine on the same load. Matter may be discussed for remedial action.
Minutes of 71st OCCM of MP 66
Frequent variation in Scheduling of MPPGCL Units.
Submission of MPPGCL:- There are incidences where frequent backing down and backing up scheduling
is being given by MPPMCL to MPPGCL units without giving reasonable time to stabilize the unit in particular load( No time block for constant loading).
There is cases where after ramp down the unit upto TMM in a particular block the unit again ramped up in next block and vice versa.
200
250
300
350
400
450
500
550
600
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Case-I:SG pattern given in some cases to MPPGCL
Case -I
Full SG
Full SG
TMM
TMM
Minutes of 71st OCCM of MP 67
Frequent variation in Scheduling of MPPGCL Units.
Submission of MPPGCL:- It is to mention here that the thermal units of MPPGCL are not designed for
cyclic loading as the thermal unit takes time to stabilize the machine and to maintain the desired parameter of unit after ramp-down and ramp-up for safe operation. The frequent variation in load in unit may leads to thermal stress in turbine & Boiler which may results serious damage to the machine.
Looking to the technical constraints of the thermal unit, it is requested to give minimum four blocks span to run the machine in same load after reaching to
TMM or Maximum load before ramp down/ramp up.
200
300
400
500
600
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Case-II: proposal of MPPGCL
Case-II(proposal of MPPGCL)
Full SG Full SG
TMM TMM
Minutes of 71st OCCM of MP 68
Frequent variation in Scheduling of MPPGCL Units.
To address the issues relating to Backing Down and Reserve Shutdown(RSD)
As directed vide letter GoMP no. 3619 dt. 30/05/15 a meeting was held on 10th june 2015 chaired by Hon’ble Principal Secretary(Energy) in the presence of MD MPPMCL, MD MPPGCL and CE(SLDC). During the meeting the matter was discussed in length and concluded that:
RSD as per MOD as is applicable for minimum period of 72hours.
Backing down in a unit shall be applicable for minimum 03 hours duration to avoid thermal stresses in the unit.
During backing down the rule of implementation from 4th time
block should be strictly followed. One clear time block shall be given preference of backing down.
The above is being followed since last 4 years. MPPGCL request to
continue the above.
Minutes of 71st OCCM of MP 69
As per BSC-2015 clause no. 5.11 (b): - “State Load Despatch Centre shall check that Schedules are operationally reasonable particularly in terms of ramping-up/ ramping-down rates and ratio between minimum and maximum generation levels. State Load Despatch Centre shall moderate the Schedule to the required extent by intimation to concerned Discoms. The ramping up/ ramping down rates in respect of different categories of Stations would be based on the technical data as substantiated by Electricity Generating Stations and as mutually agreed by Discoms or Madhya Pradesh Power Management Company Limited on behalf of Discoms with due consent of State Load Despatch Centre.”
Frequent variation in Scheduling of MPPGCL Units.
Minutes of 71st OCCM of MP 70
Frequent variation in Scheduling of MPPGCL Units. Due to variation in load, the problem being faced by thermal units:- Critical components are subjected to thermal stresses which are
cyclic in nature. Higher fatigue rates leading to shorter life of components. Frequent start and stop of auxiliaries, which may lead to equipment
damage and failure. Increased in forced outage rates as a function of startup type Heat rate is affected as a result of cycling. Boiler Economizer Header Damage Boiler Drum to Boiler Bank Tubes Expansion Joint Failure due to
Cyclic Loading. Failure of Attachment Welding – Due to constant cyclic loading the
failure of attachment welding due to Thermo Cyclic Stress will increase
Minutes of 71st OCCM of MP 71
Frequent variation in Scheduling of MPPGCL Units. Contd…
Turbine Blade Material Loss – Turbine Internal Corrossion. Turbine Blade Root Erosion due to Wet Steam. Advanced aging of Generator insulation system due to increased
thermal stresses life-limiting deterioration from fatigue through cycling are the boiler
pressure parts and the turbine and its associated equipment. Turbine Blade Root Corrosion – Result of High Moisture Steam As per OEM BCW pumps are designed for base load for a sustained
period of time. Boiler water circulating pump in that is that there are minimal thermal cycles and hence minimal cyclic thermal stresses. Due to outage of BCW pump in SSTPP # 2 unit was run on half load for around two to three months.
Minutes of 71st OCCM of MP 72
ANNESURE – 6.17 DETAILED OPERATING PROCEDURE
FOR
BACKING DOWN OF COAL BASED THERMAL UNITS OF THE STATE SECTOR
GENERATING STATIONS
AND
MECHANISM FOR COMPENSATION FOR DEGRADATION OF HEAT RATE, AUX
CONSUMPTION AND SECONDARY FUEL OIL CONSUMPTION, DUE TO PART LOAD OPERATION
AND MULTIPLE START/STOP OF UNITS Minutes of 71st OCCM of MP 73
REGULATORY REQUIREMENT
• As per clause no 8.8(6) of the MP Grid Code, State Load Despatch Centre (SLDC) shall prepare a Detailed Operating Procedure in consultation with the generators and MPPMCL/Discoms at OCC forum.
• The DOP shall come into force with effect from the date of approval by the MP Electricity Regulatory Commission.
Minutes of 71st OCCM of MP 74
RESERVE SHUT DOWN • SLDC shall suo-moto revise the schedule of any generating station as per
clauses 8.6 and 8.7 of the MP Grid Code to operate at or above technical minimum in the ratio of under-requisitioned quantum (with respect to technical minimum) in the interest of smooth system operation under the following conditions:
• Extreme variation in Weather Conditions • High Load Forecast • To maintain reserves on State level basis • Network Congestion • Any other event which in the opinion of SLDC/RLDC shall affect the grid security.
• If the grid conditions do not demand for providing technical minimum to a generating station, under such situation, the SSGS shall have the option to go for RSD with intimation to SLDC.
• No maintenance activities on unit under RSD shall be undertaken by the generating station so that the RSD unit is always readily available for revival/synchronization. Minutes of 71st OCCM of MP 75
METHODOLOGY FOR REVIVAL OF GENERATING STATION OR UNIT(S) FROM RSD • Once a unit is taken out under RSD, the generating station shall notify the period for
which the unit will remain under RSD and the unit can be recalled any time after 8 hours. In case of system requirements, the generating unit can be revived before 8 hrs as well. The time to start a machine under different conditions such as HOT, WARM and COLD shall be as per the declaration given by the generating station in the Format AS-1 annexed herewith this procedure.
• MPPMCL as well as the generating station may decide for revival of unit(s) under RSD with commitment for technical minimum schedule with minimum run time of 8 hrs for Coal based generating stations post revival.
• SLDC may also advise the generating stations to revive unit(s) under RSD for better system operation (MPEGC 8.8.(2)). In such cases, SLDC shall ensure technical minimum schedule by increasing schedule of MPPMCL.
• In case the machine is not revived as per the revival time declared by the generating station under different types of start, the machine shall be treated under outage for the duration starting from the likely revival time and the actual revival time. SLDC shall ensure that intimation is sent to the generating station sufficiently in advance keeping in view its start-up time.
Minutes of 71st OCCM of MP 76
MECHANISM FOR COMPENSATION FOR DEGRADATION OF HEAT RATE, AUX CONSUMPTION AND SECONDARY FUEL OIL CONSUMPTION, DUE TO PART LOAD OPERATION AND MULTIPLE START/STOP OF UNITS
Minutes of 71st OCCM of MP 77
Average Unit Loading (AUL) in % = Effective Generation of station (in MWhr) x 100 Effective Capacity (in MWhr) X (1- Normative Auxiliary Consumption)
Three different values are to be calculated of Average Unit Loading (AUL) depending upon three sets of Effective Generation of Station, Effective Capacity and Normative Auxiliary Consumption based on Actual Generation, Declared Capacity and Scheduled Generation.
"Average Unit Loading (AUL) of the station" (in %) means loading of the station during the Calculation Period determined as follows:
Minutes of 71st OCCM of MP 78
COMPENSATION FOR DEGRADATION OF HEAT RATE(SHR) AND AUXILIARY ENERGY CONSUMPTION (AUX)
• The Compensation shall be worked out for a month on cumulative basis considering degradation in SHR and AUX based on Average Unit Loading, subject to reconciliation at the end of the year.
• Average Unit loading shall be used for getting increase in SHR and AUX in accordance with the Regulations Provided that no compensation for SHR degradation or increase in AUX shall be payable if the Average Unit Loading for the generating station for the computation period works out more than or equal to 85% i.e. Normative Annual Plant Availability Factor defined in Generation tariff regulation of MPERC.
• Based on the values of increased SHR and AUX arrived at step(iii), Energy Charge Rate (ECR) for Average Unit Loading i.e. ECR(SE) for the station shall be calculated using the formula specified in Tariff Regulations of the Commission. The same is reproduced below:
Minutes of 71st OCCM of MP 79
• For Coal based Units, Energy Charge Rate (ECR) in Rupees per kWh on ex-power plant basis shall be determined to three decimal places in accordance with the following formulae:
ECR = {(GHR – SFC x CVSF) x LPPF / CVPF+SFC x LPSFi } x 100 / (100 – AUX)
Where, • AUX =Normative auxiliary energy consumption in percentage. • CVPF=(a) Weighted Average Gross calorific value of coal as received, in kCal per kg for coal based stations (b) In case of blending of fuel from different sources, the weighted average Gross calorific value of primary fuel shall be arrived in proportion to blending ratio. • CVSF =Calorific value of secondary fuel, in kCal per ml. • ECR = Energy charge rate, in Rupees per kWh sent out. • GHR = Gross station heat rate, in kCal per kWh. • LPPF= Weighted average landed price of primary fuel, in Rupees per kg, during the month. (In case of blending of fuel from different sources, the weighted average landed price of primary fuel shall be arrived in proportion to blending ratio) • SFC = Normative Specific fuel oil consumption, in ml per kWh. • LPSFi=Weighted Average Landed Price of Secondary Fuel in Rs./ml during the month
Minutes of 71st OCCM of MP 80
>. ECR corresponding to average Declared Capacity (DC) i.e. ECR(DC) for the calculation period shall also be calculated using the formula specified in Tariff Regulations of the Commission and used as reference for calculating compensation. This is because, the effect of less declaration (with respect to normative ex-bus installed capacity), if any, on the SHR and AUX should be to the account of SSGS: • The compensation to be paid to SSGS for the calculation period ending nth month
shall be difference in the ECR(SE) and ECR(DC) for that period. ECR (Comp) for the calculation period ending nth month shall be calculated as:
ECRn(Comp) = ECR(SE) – ECRn(DC) • The compensation Compn(P) payable to SSGS for the calculation period ending nth
month shall be calculated as below:
Compn(P) = (Total Generation Schedule (Energy) to MPPMCL)* ECRn(Comp) • ECRn(A) for the calculation period shall be calculated using actual values of SHR and
AUX Consumption furnished by SSGS at the end of the calculation period and normative secondary fuel oil consumption as per MPERC Tariff Regulation for which the requisite information shall be submitted by the generating station to the SLDC.
Similarly, ECRn(N) shall be calculated using normative values of SHR and Aux Consumption and normative secondary fuel oil consumption as per MPERC Tariff Regulation furnished by SSGS.
Minutes of 71st OCCM of MP 81
Now, following values shall be calculated:
• Total Energy Charges payable to SSGS based on actual parameters
• ECn(A) = ECRn(A) x (Total Generation Schedule (Energy) to MPPMCL during the calculation period ending nth month)
• Total Energy Charges payable to SSGS based on Normative parameters
• ECn(N) = ECRn(N) x (Total Generation Schedule (Energy) to MPPMCL during the calculation period ending nth month)
• Compensation payable for the calculation period ending nth month to SSGS would be decided based on following criteria:
• If ECn(A) is less than or equal to ECn(N):
No compensation shall be payable to SSGS • If ECn(A) is more than ECn(N):
• (b1) If Compn(P) is less than or equal to ECn(A) minus ECn(N) then final compensation amount payable to SSGS for the calculation period ending nth month:
Compn(F) = Compn(P)
Minutes of 71st OCCM of MP 82
• (b2) If Compn(P) is more than ECn(A) minus ECn(N), then final compensation amount payable to SSGS for the calculation period ending nth month
Compn(F) = ECRn(A) - ECRn(N)
• Final Compensation payable by MPPMCL for the calculation period ending nth month
• No compensation shall be payable by MPPMCL if it has requisitioned at least 85% of its entitlement during the calculation period. However, adjustments shall be carried out for compensation already paid for calculation period ending (n-1)th month.
• Net compensation payable/receivable by MPPMCL for the nth month
NCBn=FCBn – FCB(n-1)
• If NCBn is negative, this is amount payable by SSGS to the MPPMCL and vice versa. This way reconciliation would automatically take place at the end of the Financial Year.
Minutes of 71st OCCM of MP 83
Calculation for Secondary Fuel Oil consumption:
• No compensation for degradation of Secondary Fuel oil consumption is payable for the year if total number of start-ups(against RSD) is equal to or less than 7 x no. of units in the generating station (FOR RSD only) or the Actual Secondary Fuel Oil consumption is less than Normative Fuel Oil Consumption.
• Compensation (in terms of KL of Secondary Oil) shall be payable to SSGS for the year due to degradation of Secondary Fuel Oil Consumption shall be calculated by multiplying no. of start-ups exceeding 7 per unit and solely attributable to reserve shut-downs with the appropriate value of additional secondary oil consumption specified in Regulation.
• Compensation payable to SSGS shall be restricted such that Oil Consumption based on Norms plus Compensation calculated in step (ii) above does not exceed actual Secondary Fuel oil consumption for the year.
• Compensation in terms of Rupees shall be calculated by multiplying compensation in terms of KL as calculated in step (ii) and average landed price of Secondary fuel oil for the year.
• Each start-up due to reserve shutdown shall be attributed to the MPPMCL, who had requisitioned below 55% of their entitlement.
• The SSGS is to take all due care to keep a check on secondary oil use during part operations and during start-ups to the extent possible. The SLDC shall review the secondary oil consumptions of plants on quarterly basis along with SSGS to find out high consuming plants and reasons for high consumption and for suggesting measures to mitigate excess use of secondary oil to the extent possible. Minutes of 71st OCCM of MP 84
CALCULATION OF COMPENSATION, BILLING AND SUBMISSION OF DATA BY THE GENERATOR
• Generating station shall calculate the compensation as specified in these procedures and bill the same to MPPMCL along with its monthly bill which shall be subject to adjustment based on compensation statement issued by SLDC subsequently.
• Generating station shall submit the requisite data along with compensation calculation to SLDC as prescribed in Annexure-I for a month by 15th day of the following month. The data to be submitted is for the month and reconciled up to the month.
Minutes of 71st OCCM of MP 85
ISSUANCE OF COMPENSATION STATEMENT
• SLDC will issue the compensation statement for the month on 21st of next month.
• In case any anomaly or discrepancy is noticed by any Utility, the same may be brought to the notice of SLDC within 15 days of issuance of Compensation Statement.
Minutes of 71st OCCM of MP 86
REVIEW OF THE PROCEDURE(DOP):
• The Procedure shall be reviewed after one year of its approval and implementation based on feedback received from MP Genco, Discoms, SLDC and MPPMCL.
Minutes of 71st OCCM of MP 87
Sr. No
(a)
(b)
Unit No 1
(c)
Unit No 2
(d)
Unit No 3
(e)
Unit No 4
(f)
Total
(g)
1 Installed capacity/MCR
2 Planned outage/Tripped (Hrs)
3 On bar hrs
4 Normative SHR or Net SHR as
the case may be
5 Normative SFC
6 CVSF
7 LPPF
8 LPSFi
9 LPL
10 Normative Aux. Cons
11 Actual GHR/SHR
12 Actual SFC
13 Actual Aux. Cons
14 RSD start /stop in the month
15 RSD start/stop cumulative
16 Total no. of Start /stop during year 17 CVPF
Information to be submitted by SSGS to the SLDC by 15th of each month (say in May) for the previous month (say of April)
Minutes of 71st OCCM of MP 88
S.No. Title/Parameters Values/Data
a) Number of Generating Units (e.g. 1 x 210 MW + 2 x 500 MW) b) Total Installed Capacity (MW) c) Maximum possible Ex-bus injection (MW) (including overload if any) d) Technical Minimum (MW) e) Type of Fuel f) Fixed Cost (paise / kWh upto one decimal place) g) Variable Cost (paise / kWh upto one decimal place) h) Ramp-Up Rate (MW/Min) for each unit i) Ramp-Down Rate (MW/Min) for each unit j) Start-up Time from Cold Start (in Min) & Warm Start of each unit k) Any other information
Format AS1: Generator Details From: (Name of Generating Station) / (Name of Owner Organization) To: SLDC, MPPTCL, Jabalpur Validity of the Information From: 16/mm/yyyy To:15/mm/yyyy Date: dd/mm/yyyy
Copy to: Signature of Authorized Signatory (with Stamp) Name: Designation: Minutes of 71st OCCM of MP 89
Minutes of 71st OCCM of MP 90
Annexure-8.1
132KV33KV132KV33KV132KV33KV132KV33KV132KV33KV
NOTE:-
3
5
M.P. POWER TRANSMISSION COMPANY LTDNAME OF T & C CIRCLE :-
CONSU- MPTION (MWH)
MFSl. No.
132KV/33KV INPUT/OUTPUT AT TRANSFORMERS - (ACTIVE ENERGY IN MWH) MONTH:-
NAME OF SUBSTATION
ASSESEMENT
IMPORT
MF
1
2
PREVIOUS READING WITH TIME & DATE
4 2
1
3
1
PRESENT READING WITH TIME & DATE
PRESENT READING WITH TIME & DATE
132/33 KV SIDE
EXPORT
ASSESEMENTMETER SERIAL NO.
New Transformer add in substation please marke Below
REMARKS
2
PREVIOUS READING
WITH TIME & DATE
CONSUMPTION (MWH)
DETAILS OF TRANSFORMERS
Minutes of 71st OCCM of MP 91
1 220 KV SATNA PGCIL CB FAULTY CLOSE
1 132KV KYMORE CB FAULTY CLOSE
1 132KV RAMPUR NIKEN CB FAULTY CLOSE
1 132/33 KV XMER (PRI) CB FAULTY CLOSE
1
1 125 MVAR BUS REACTOR CB N/A Process connection required2 400 KV DAMOH CB OPEN CLOSE
1 220 KV SUKHA 1 CB FAULTY CLOSE
LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETER
Sr.no. DESCRIPTION Status Telemetry value at SLDC Actual value at site1 132 KV BUS BALAGHAT 1 & 2 MW/MVAR 26/16 ;-40/20
LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETERKATNI 400 KV S/S
PANAGAR 220 KV S/S
KIRNAPUR 132 KV S/S
UMARIYA 132ALL ANALOG SHOWING 0 PROBLEM IN PT SUPPLY
BEOHARI 132
LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETER
SATNA CIRCLEKOTAR 220 KV S/S
SATNA 220
KOTMA 132
Minutes of 71st OCCM of MP 92
sr.no. Name of Element sldc side Field
2 220 Kv TBC Bus Coupler Open Faulty
1 220kv dewas CB close faulty
1 400kv Singhaji malwa Ckt -4 CB close Faulty
1 132 Kv PRASRAM PURIYA CB open close
1 220 kv all breakers suspected2 220kv bus voltag-1 wrong3 132kv all brekers suspected
1 22/132Xmer HV and LV Side MW 17 27NOTE:-
NOTE:-
1
2 220 Kv TBC CBNot
Coming open
1 220 KV SENDHWA 1 CBNot
Coming Close
2 221 KV SENDHWA 12 CB/MW/MVARNot
Coming Close3 220 KV BUSCOUPLER CB FAULTY CLOSED
1 132 KV BUS-COUPLER CB FAULTY
2 132/33KV 40MVA-XMER-2 MW/MVARNON-
CURRENT
1 132KV BUS COUPLER CB FOULTY OPEN
1 132kV Buscoupler CB Faulty Close
LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETER 03-09-2019
KHATEGAON 132 KV S/S
Kannod 132 KV S/S All 132 Kv side BC and 33 kv side BC not coming
UJJAIN 220 KV S/S
132 KV S/S AGAR
400 KV S/s JULWANIA
132 KV S/S PolykalanNIL
220 KV S/S RATLAM
132 kV S/s KhachrodAll 132 Kv Side brekaer is open Actually closed
132 KV S/S MALHARGARALL 132 KV SIDE BREAKER NOT COMING
RAJGRAH (DHAR) 220 KV S/S
220KV S/s JULWANIA
All 132 Kv Side brekaer is open Actually closed
INDORE 400 KV S/S
INDORE EAST 220 KV S/S
INDORE 400 KV S/S
PITAMPUR 220 KV S/S Sector-III
Minutes of 71st OCCM of MP 93
LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETER
1 400 KV BUS-COUPLER CB FAULTY2 132 KV BUS-COUPLER CB FAULTY
1 220 KV MAIN BUS FREQUENCYNON
CURRENT
1 160 MVA XMER(LV SIDE) CB FAULTY CLOSE
1 132 KV KHIRKIYA CBNON
CURRENT CLOSE2 KV CHANNERA(TAP KHIRKIYA RLY TRC CB FAULTY CLOSE3 132 KV KHIRKIYA RLY TRCN-1 CB FAULTY
1 132 KV BUS AGE/FREQUNON
CURRENT
2 132 KV BUS-COUPLER MW/MVARNON
CURRENT
1 400 KV DAMOH-1 PG CB OPEN CLOSE2 400 KV BINA-1 TIE-CB OPEN CLOSE3 220 KV BUS TIE CB OPEN CLOSE
LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETER
1 132 KV SABALGARH-2 CB FAULTY CLOSE
2 132 KV SABALGARH-1 & 2MW,MVA
R
3 132 KV BARODAMW,MVA
R
4 132/33KV 63MVAX-MER-2(HV)MW,MVA
R
WRONG DIRECTION
WRONG DIRECTION
WRONG VALUES
03-09-2019
BHOPAL 400 KV S/s
LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETER
03-09-2019
SHOEPURKALAN 132 KV S/S
03-09-2019
ASTHA 400 KV S/S
RAJGARH 220 KV S/S
SARNI 220 KV S/S
HARDA 132 KV S/S
ZEERAPUR 132 KV S/S
Minutes of 71st OCCM of MP 94
Name at SLDC end at site end
1 400 KV AASTHA 1 & 2 LINE REACTOR N/A2 400 KV SEONI MW 99 85
1 GEN NO 3 & 4 RGMO N/A
1 220 /33 KV TR MW/MVAR NA2 400 KV BUS 1 FREQ 49.79 49.983 220 KV BUS 2 VOLTAGE 264 2304 GEN NO.1,2,3,4 RGMO N/A
1 GEN 1 CB FAULTY OPEN
1 GEN NO 1 ,2 RGMO N/A
1 132 KV BUS 1 KV 127 1312 33 KV Rajisthan feeder MW/MVAR N/A3 132 KV BUS 2 KV 122 132
1 220 KV SIDHI CB TRANSMIT CLOSE
Sr.No Parameter Field value Scada value /status1 ISP –INDORE 400 KV Feeder 1 ( 91 9082 ISP –NAGDA 400 KV Feeder (MV 94 9383 GENERATOR 5 & 6 MAVR 5 N /A4 GENERATOR (OFF CONDITION) N/C
ISP
ATPS
GANDHI SAGAR H P S
BARGI
SATPURA T P S
SINGHA JI phase 2 S T P S
S G T P S
RAJGHAT H P S
ALL CB SUSPECTED
Minutes of 71st OCCM of MP 95
ANNEXURE-9.8
220 KV Mugaliyachhap400 KV Astha132 KV Astha132 KV Icchwar132 KV Sheopur Kalan132 KV Harda132 KV Picchore132 KV Sehore132 KV Ayodhya Nagar132 KV Kurawar
SOE VERIFICATION PENDING
Minutes of 71st OCCM of MP 96