lugo marine - barge presentation 2011
TRANSCRIPT
![Page 1: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/1.jpg)
Presentation ofLugo Marine International
Barge Projects
![Page 2: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/2.jpg)
Project 1:Marathon Refinery Expansion – Garyville, Louisiana
Total Number of Heavy Lifts: 30Ranging from 18 mt to 110 mt
Total Revenue Tons of Cargo: 16,897
Project Time Frame: First Quarter 2009
Total Barge Moves: 4
Load Port: Port of Altamira, Mexico
![Page 3: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/3.jpg)
Pre-planning meetings with fabrication yards in Mexico to ensure that the cargo wasbeing fabricated to the specifications needed to make an ocean voyage via barge.
![Page 4: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/4.jpg)
Survey of the Port of Altamira and the roads entering the facility to specify routes tobe taken as the cargo is shipped from fabrication yards to port for loading onto barges.
![Page 5: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/5.jpg)
Preparing of the barges in Louisiana including the barge layouts, loading and pre-welding of elevated stow components and materials used for final tiedown of cargo in
Mexico.
![Page 6: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/6.jpg)
Transporting of cargo from fabrication yards to the laydown yard at the Port ofAltamira in proximity to the wharf identified for loading the barges.
![Page 7: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/7.jpg)
Lugo Marine managed the Ro-Ro operations with the Port of Altamira, the stevedores,heavy hauling companies, marine surveyors and the tug/barge crew.
![Page 8: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/8.jpg)
Cargo being loaded on barges as outlined in the ballast and stow plans engineered byLugo Marine.
![Page 9: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/9.jpg)
Heavy lifts loaded , securing inspected and approved by underwriting surveyor, sailaway certificate issued and barge cleared for transport to Garyville, Louisiana for off
loading.
![Page 10: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/10.jpg)
Project 2:Power Plant Expansion Project
Total Number of Heavy Lifts: 6
Total Revenue Tons of Cargo: 1,263
Project Time Frame: First Quarter 2009
Total Barge Moves: 1
Load Port: Port of Houston
![Page 11: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/11.jpg)
Performing barge layout, loading dunnage with the assistance of the stevedoringcompany and shifting the barge along side the vessel for loading of heavy lifts with the
ship’s gear.
![Page 12: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/12.jpg)
Heavy lifts discharged from the number three starboard hatch, were loaded on bargeas outlined in the stow plan designed by Lugo Marine.
![Page 13: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/13.jpg)
Vessel discharging to barge continued the next day for heavy lifts stowed in thenumber three portside lower hold.
![Page 14: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/14.jpg)
Final welding and securing of all heavy lifts and departure of the tug/barge fromthe Port of Houston.
![Page 15: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/15.jpg)
Project 3:
Reactor Vessel Barge Tiedown
Total Number of Heavy Lifts: 1 @ 1,000 mt
Project Time Frame: Third Quarter 2009
Total Barge Moves: 1
Load Port: Port of New Orleans, Louisiana
![Page 16: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/16.jpg)
Reactor arrived via heavy lift steamship vessel and discharged directly tobarge using ship’s gear.
![Page 17: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/17.jpg)
Reactor vessel was positioned on the elevated stow equipment as per Lugo Marineengineering and stow plan calculations .
![Page 18: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/18.jpg)
Final welding of steel tiedown devices and wirerope lashing of the reactor vessel to thebarge for transport up the Mississippi River to Chicago.
![Page 19: Lugo Marine - Barge Presentation 2011](https://reader033.vdocuments.site/reader033/viewer/2022051314/55906f9b1a28ab642f8b45ed/html5/thumbnails/19.jpg)
For additional information, please contact:
- Robert Lugo, Jr.Managing DirectorEmail: [email protected]
- Norbert LugoManaging Director – Operations & EngineeringEmail: [email protected]
-Stacy BrowningDirector of International TransportationEmail: [email protected]