Republic of the Philippines . c:A\ (g. \1. Q,olODEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CENTRAL OFFICEManila
MAY 1 5 2020DEPARTMENT ORDER
No._5_0__Series of 2020 ~ ltlt1I~1P
))))
SUBJECT: Standard Project Logbook Format
In order to ensure the uniformity of format during Project Implementation for monitoring andupdating of day-to-day activities in the project site, this Standard Project (Construction& Materials) Logbook Format applicable for locally funded and foreign assisted projects ishereby issued to be utilized by all Implementing Offices of the Department.
The issuance of the standard project logbook aims to establish consistency in the format andimprove the Department's means of accomplishing the required project documents.
This standard template can be downloaded from the DPWH Intranet (http:dpwhnet) underConstruction Forms, and is advised to be printed in 50 or 100 pages, hardbound for eachproject.
This Order shall take effect immediately.
- ~--------:;7~MARK A. VILLARSecretary
6.1.3 RCNjECGjEAA
Departrrent of Public Works and HighwaysOffice of the Secretary
11111111111111111 "111111111111111111WINOW02153
COVER PAGE (HARDBOUND - royal blue)
Side View Front View
BACK PAGE (HARDBOUND - royal blue)
Rear View
Republic of the PhilippinesDEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
(IMPLEMENTING OFFICE)(Office Address)
PROJECT PROFILEImplementing Office DPWH -Contract 10 :Project Name & Address
A. PROJECT DESCRIPTION
Station Limits :Scope/Description of Works :
:::
:::::
B. CONTRACT DATA
Province :Region :Project Category :Source of Fund(Locally Funded/Foreign Assisted)
ContractorConsultant :Original Contract AmountRevised Contract Amount due to Approved
VO# :VO# :VOl :
Start DateOriginal Contract DurationRevised Contract Duration due to Approved
TE # __ /VO# __ :TE# __ /VO# __ :TE# __ /VO# __ :
:Original Completion DateRevised Completion Date due to Approved
TE# __ /VO# __ :TE# __ /VO# __TE# __ /VO# __ :
:
C. KEY PERSONNEL
C.l DPWH PERSONNEL:NAME ACCREDITATION NO./PRC NO.
Project Engineer -Materials Engineer -Project Inspectors -
---
C.2 CONSULTANTS PERSONNEL:NAME ACCREDITATION NO./PRC NO.
-----
C.3 CONTRACTOR'S PLEDGED KEY PERSONNEL:
NAME ACCREDITATION NO./PRC NO.
Project Engineer -Materials Engineer -Safety Engineer/Officer -Site Engineer/s -
------
D. UST OF CONTRACTOR'S PLEDGED EQUIPMENT
NO. OFEQUIPMENT DESCRIPTION NO. OF EQUIPMENT DESCRIPTIONUNITS UNITS
Republic of the PhilippinesDEPARTMENT OF PUBUC WORKS AND HIGHWAYS
(IMPLEMENTING OFFICE)(Office Address)
12
CONTRACT ID NO.PROJECT COMPONENT 10PROJECT NAMELOCATIONCONTRACTORCONSULTANTDATE
9 3
WEATHER
MANPOWER ON SITE:
A.M. (outer circle)P.M. (inner circle)
LEGEND:
FAIRCLOUDYRAIN SHOWERHEAVY RAIN
6
MANPOWER No.Project ManagerProject EngineerMaterials EngineerProject InspectorsSurvey EngineerMechanical EngineerElectrical EngineerPlumbing/Sanitary EngineerSafety Officer/Safety & Health PersonnelOthers (specify) :
EQUIPMENT ON SITE:
Status TYPE OF EQUIPMENTNo. ofUnits
BulldozerBackhoeBackhoe with BreakerPayloaderDump TruckWater TruckConcrete PaverVibratory RollerBatching Plant, Concrete/AsphaltConcrete VibratorScreederOne Bagger MixerPlate CompactorWelding Machine
CONSTRUCTION ACTIVITIES:
MANPOWER No.ForemanDriverHeavy Equipment OperatorsLaborersMechanicAuto ElectricianLaboratory TechnicianCarpentersMasonsOthers (specify) :
Status TYPE OF EQUIPMENTNo. ofUnits
Asphalt PaverAsphalt DistributorAir CompressorTandem RollerPneumatic RollerElectric GeneratorConcrete CutterCrawler CraneSubmerssible PumpMaterial Testing EquipmentOthers (specify) :
Continued at the back of this pdge.
STATUS OF EQUIPMENT :
;
OperationalIdle
" Breakdownn a Not Applicable
Page No..
REMARKS:
DPWH PERSONNEL ON-SITE:
NAME
CONSULTANTS PERSONNEL ON-SITE:
VISITORS ON-SITE:
Prepared by:
TIME-IN
Concurred by:
TIME-OUT SIGNATURE
Site Engineer /Site Inspector /Project Inspector (DPWH/Consultant)
Project Engineer (Contractor)
Noted by:
Project Engineer (DPWH)
Page No ..
COVER PAGE (HARDBOUND - royal blue)
Side View Front View
BACK PAGE (HARDBOUND - royal blue)
Rear View
•Republic of the Philippines
DEPARTMENT OF PUBUC WORKS AND HIGHWAYS(IMPLEMENTING OFFICE)
(Office Address)
PROJECT PROFILEImplementing Office : DPWH -Contract ID :Project Name & Address
A. PROJECT DESCRIPTION
Station Limits :Scope/Description of Works :
:
::::::
B. CONTRACT DATA
ProvinceRegion :Project Category :Source of Fund(Locally Funded/Foreign Assisted)
ContractorConsultantOriginal Contract AmountRevised Contract Amount due to Approved
VO# :VO#VO# :
:Start DateOriginal Contract DurationRevised Contract Duration due to Approved
TE # __ /VO# __
TE # __ /VO# __ :TE # __ /VO# __ :
Original Completion DateRevised Completion Date due to Approved
TE# __ /VO# __ :TE # __ /VO# __
TE # __ /VO# __
C. KEY PERSONNEL
C.l DPWH MATERIALS QUALITY ASSURANCE PERSONNEL:NAME ACCREDITATION NO./PRC NO.
Materials Engineer ------
C.2 CONSULTANTS QUALITY ASSURANCE PERSONNEL:
- NAME ACCREDITATION NO./PRC NO.
---
C.3 CONTRACTOR'S MATERIALS QUAUTY CONTROL PERSONNEL:NAME ACCREDITATION NO.{PRC NO.
Materials Engineer ----------
CONTRACT ID NO.PROJECT COMPONENT IDPROJECT NAMELOCATIONCONTRACTORCONSULTANTDATE
CONSTRUCTION ACTIVITIES:
Republic of the PhilippinesDEPARTMENT OF PUBUC WORKS AND HIGHWAYS
(IMPLEMENTING OFFICE)(Office Address)
QUALITY CONTROLI ASSURANCE ACTIVITIES:
Page No.
REMARKS:
Prepared by:
Materials Engineer (DPWH/Consultant)
ConcUlTed by:
Noted by:
Materials Engineer (Contractor)
Project Engineer (DPWH)
Page No.