l&t summer training report
TRANSCRIPT
-
7/31/2019 L&T Summer Training Report
1/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 1
CHAPTER 1: INTRODUCTION
1.1About Larson and Toubro
1.1.1 Companys Vision:
-
7/31/2019 L&T Summer Training Report
2/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 2
1.1.2 Companys History:L&T was founded in Bombay (Mumbai) in 1938 by two Danish engineers, Henning
Holck-Larsen and Soren Kristian Toubro. Both of them were strongly committed
to developing India's engineering capabilities to meet the demands of industry.
Figure 1 Founders
Henning Holck-Larsen and Soren Kristian Toubro, school-mates in Denmark, would
not have dreamt, as they were learning about India in history classes that they would,
one day, create history in that land.
In 1938, the two friends decided to forgo the comforts of working in Europe, and
started their own operation in India. All they had was a dream. And the courage to
dare.
Their first office in Mumbai (Bombay) was so small that only one of the partners
could use the office at a time!
In the early years, they represented Danish manufacturers of dairy equipment for a
modest retainer. But with the start of the Second World War in 1939, imports were
restricted, compelling them to start a small work-shop to undertake jobs and provide
service facilities.
Germany's invasion of Denmark in 1940 stopped supplies of Danish products. Thiscrisis forced the partners to stand on their own feet and innovate. They started
manufacturing dairy equipment indigenously. These products proved to be a success,
and L&T came to be recognized as a reliable fabricator with high standards.
The war-time need to repair and refit ships offered L&T an opportunity, and led to
the formation of a new company, Hilda Ltd., to handle these operations. L&T alsostarted two repair and fabrication shops - the Company had begun to expand.
Henning Holck-Larsen
(4.7.190727.7.2003)
Soren Kristian Toubro
(27.2.19064.3.1982)
-
7/31/2019 L&T Summer Training Report
3/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 3
1.1.3 Companys Overview:Larsen & Toubro Limited (L&T) is a technology, engineering, construction and
manufacturing company. It is one of the largest and most respected companies in
India's private sector.More than seven decades of a strong, customer-focused approach and the continuous
quest for world-class quality have enabled it to attain and sustain leadership in all its
major lines of business.
L&T has an international presence, with a global spread of offices. A thrust on
international business has seen overseas earnings grow significantly. It continues to
grow its overseas manufacturing footprint, with facilities in China and the Gulf
region.
The company's businesses are supported by a wide marketing and distribution
network, and have established a reputation for strong customer support.
L&T believes that progress must be achieved in harmony with the environment. A
commitment to community welfare and environmental protection are an integral part
of the corporate vision.
In response to changing market dynamics, L&T has gone through a phased process of
redefining its organization model that facilitates growth through greater levels of
empowerment. The new structure is built around multiple businesses designated
Independent Companies or ICs.
1.
Hydrocarbon2. Heavy Engineering3. L&T Construction4. L&T Power5. Electrical & Automation6. Machinery & Industrial Products7. Information Technology8.
Financial Services
9. Shipbuilding10.Railway Projects
http://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_ENChttp://www.larsentoubro.com/lntcorporate/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_HEDhttp://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_ECChttp://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_PWRhttp://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_EBGhttp://www.larsentoubro.com/lntcorporate/lntcorporate/common/ui_templates/mipd_home.aspx?res=P_MIPDhttp://www.lntinfotech.com/http://www.larsentoubro.com/lntcorporate/LnT_Offerings/Offering.aspx?res=P_HED_COFF_SBU&sbu=72http://www.larsentoubro.com/lntcorporate/common/ui_templates/HtmlContainer.aspx?res=P_RAILWAY_AABL_AOV&sbu=133http://www.larsentoubro.com/lntcorporate/common/ui_templates/HtmlContainer.aspx?res=P_RAILWAY_AABL_AOV&sbu=133http://www.larsentoubro.com/lntcorporate/common/ui_templates/HtmlContainer.aspx?res=P_RAILWAY_AABL_AOV&sbu=133http://www.larsentoubro.com/lntcorporate/LnT_Offerings/Offering.aspx?res=P_HED_COFF_SBU&sbu=72http://www.lntinfotech.com/http://www.larsentoubro.com/lntcorporate/lntcorporate/common/ui_templates/mipd_home.aspx?res=P_MIPDhttp://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_EBGhttp://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_PWRhttp://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_ECChttp://www.larsentoubro.com/lntcorporate/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_HEDhttp://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news.aspx?res=P_ENC -
7/31/2019 L&T Summer Training Report
4/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 4
-
7/31/2019 L&T Summer Training Report
5/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 5
1.1.4 Faridabad Campus:At L&T Faridabad Campus, there are 8 Strategic Business Units (SBU), namely:
L&T Gulf L&T Railways Business Unit (RBU) L&T Valdel L&T Engineering L&T Mitsubishi Heavy Industries (MHI) L&T Howden L&T Power L&T Sargent & Linde (S&L)
1.1.5 L&T Engineering:L&T Engineering is the engineering part of L&T Engineering & Construction (E&C).
L&T E&C is an EPC firm i.e. Engineering, Procurement and Construction. LTEN
Faridabad does the engineering for Fertilizer and Oil & Gas plants. The current
ongoing projects are NFL Ammonia Feedstock Changeover and ONGC Additional
Gas Processing Facility Project. The total strength of engineers in LTEN is around250.
-
7/31/2019 L&T Summer Training Report
6/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 6
Departments:
1. MechanicalMechanical department is further divided into Rotary and Static Department. Thedepartments key role is to design rotary and static equipments as per the clients
requirement. The equipments are designed according to the international standards or
the standards set by the client or Project Management Consultant (PMC).
2. ProcessProcess department is the heart of engineering department. Process parameters
selection for various items/equipments (electrical, mechanical, instrumentation,
piping) is decided by process based on plant process requirements and licensors
technology.
3. PipingPiping department is responsible for preparing equipment layouts & isometrics. It is
also responsible for generating 3D model of the plant using PDS software, which
helps in avoiding clashes between the equipments and pipes. It also does the stress
analysis for pipe lines, using CAESAR software.
4. ElectricalIt deals with sizing of electrical equipments such as transformers, switchboards,
cables, motors etc. It also prepares layouts such as cable tray layouts, substation
equipment layouts, hazardous area layouts and lighting layouts etc. The codes
followed by the electrical department are IS (Indian Standards), IEC, ANSI or as per
the client requirement.
5. InstrumentationIt deals with the designing of DCS (Distributed Control System) from where plant is
controlled. Also, designing of valves, meters, control panels, gauges, etc.
6. CivilDepartment is responsible for designing of buildings (Sub Station and Control
Rooms), technical structures, pipe rack and also foundation for various equipments
such as pumps, columns, tanks etc.
-
7/31/2019 L&T Summer Training Report
7/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 7
1.2About Project1.2.1 Background
Crude oil, also called petroleum, is a complex mixture of carbon and hydrogen
(hydrocarbons), which exist as a liquid in the earth's crust.
Crude oil and associated gas produced from ONGCs Mumbai high and satellite fields
are transported to their Uran onshore facilities through sub-sea pipelines for further
processing.
Crude oil and gas are brought to Uran from Mumbai High and satellite fields of
western offshore through two sets of trunk lines MUT lines and through HUT lines.
The offshore gas from 28inch MUT line and 26 inch HUT line is received at slug
catchers where condensate, formed within the pipelines during transportation, gets
separated.The condensate free gas is routed to Gas Sweetening Unit (GSUs) which presently
consist of two trains for removal of CO2 and H2S gas as acid gas.
The remaining gas beyond the processing capacity of GSUs is directly sent to
consumers along the lean gas coming from the plant.
After removal of CO2 and H2S, the treated gas (sweet gas) is routed to LPG recovery
units for extraction of value added products like LPG, Naptha and Ethane-Propane.
The condensate received at slug catchers and that generated in the plant is routed to
existing Condensate Fractionating Units (CFUs) for removal of lighter hydrocarbon
and further extraction of LPG and Naptha.
Gas Sweetening Unit (GSUs)
1. It is designed to separate acid gas component such as CO2 and H2S from Sourgas. The separation achieved with the help of Amine solution in an Absorber
column.
2. The purpose of the Sulfinol solvent regenerator is to remove H2S, CO2, COSand RSH from the rich solvent and return solvent to the absorber system with
low enough residual CO2 and H2S to allow these system to meet their treating
requirements.
3. Acid Gas from the Regenerator is transferred to the Acid gas stack.
http://www.elmhurst.edu/~chm/vchembook/500hydrocarbons.htmlhttp://www.elmhurst.edu/~chm/vchembook/500hydrocarbons.html -
7/31/2019 L&T Summer Training Report
8/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 8
Condensate Handling Unit (CHUs)
1. It is designed to handle excess of water along with condensate during normaloperation and intermittent pigging operators of upstream BUT/MUT/HUT
trunk lines.
Condensate Fractionating Units (CFUs)
It is used to remove light ends and to recover LPG and Naptha from Pipeline
Condensates.
The new CFU will operate in parallel with existing CFU and it will consists of
Condensate Receiving System, Stripper, LPG Column & Off Gas
Compression Section.
The utility section of the unit comprises of cooling water, instrument air, Plantair, Nitrogen, Service water besides blow down system, flare system and
condensate recovery system.
LPG Recovery Unit (LPUs)
1. It is designed to recover maximum LPG from sweetened gas coming from gasSweetening units and produce value added products viz. LPG, NGL & Lean
gas.
2.
LPG recovery unit consists of feed gas compression and pre-cooling, Feed Gasdrying and regeneration, Chill down and expansion, Lean gas compression,
Propane refrigeration system and Fractionating system.
1.2.2 Objectives1. Our objective is to design a piping for columns in LPG Recovery Unit where LPG
and Naptha are produced from sweet gas.
2. In reference to the figure below, gases extracted from sea bed are sent to theCondensate Handling Unit (CHUs) condensate trapped in gas is further extracted andthe remaining gas is send to Gas Sweetening Unit (GSUs), from where it goes further
to LPG Recovery Unit to extract LPG and Naptha from it.
3. Whereas the condensate from CHUs after getting filtered moves to the CondensateFractionating Unit (CFUs), from where it again forms LPG and Naptha.
4. Finally LPG and Naptha are stored in their storage tanks respectively.
-
7/31/2019 L&T Summer Training Report
9/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 9
-
7/31/2019 L&T Summer Training Report
10/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 10
CHAPTER 2: LITERATURE OVERVIEW
2.1 Refinery Process
An oil refinery or petroleum refinery is an industrial process plant where crude oil is
processed and refined into more useful petroleum products, such as naphtha, gasoline,
diesel fuel, asphalt base, heating oil, kerosene, and liquefied petroleum gas.
Oil refineries are typically large, sprawling industrial complexes with extensive
piping running throughout, carrying streams of fluids between large chemical
processing units.
Common process units found in a refinery:
1. Desalter unit washes out salt from the crude oil before it enters theatmospheric distillation unit.
2. Atmospheric distillation unit distills crude oil into fractions.3. Vacuum distillation unit further distills residual bottoms after atmospheric
distillation.
4. Catalytic reformer unit is used to convert the naphtha-boiling rangemolecules into higher octane reformate (reformer product).
5. Fluid catalytic cracker (FCC) unit upgrades heavier fractions into lighter,more valuable products.
6. Hydrocracker unit uses hydrogen to upgrade heavier fractions into lighter,more valuable products.
7.
Alkylation unit produces high-octane component for gasoline blending.8. Isomerization unit converts linear molecules to higher-octane branchedmolecules for blending into gasoline or feed to alkylation units.
9. Steam reforming unit produces hydrogen for the hydro treaters orhydrocracker.
10.Slug catcher used when product (crude oil and gas) that comes from apipeline with two-phase flow, has to be buffered at the entry of the units.
11.Solvent dewaxing units remove the heavy waxy constituents petrolatum fromvacuum distillation products.
12.Solvent refining units use solvent such as cresol or furfural to removeunwanted, mainly aromatics from lubricating oil stock or diesel stock.
13.Utility units such as cooling towers circulate cooling water, boiler plantsgenerates steam, and instrument air systems include pneumatically operatedcontrol valves and an electrical substation.
14.Storage tanks store crude oil and finished products, usually cylindrical, withsome sort of vapor emission control and surrounded by an earthen berm to
contain spills.
15.Alternative processes for removing mercaptans are known, e.g. doctorsweetening process and caustic washing.
http://en.wikipedia.org/wiki/Industrial_processhttp://en.wikipedia.org/wiki/Factoryhttp://en.wikipedia.org/wiki/Crude_oilhttp://en.wikipedia.org/wiki/Petroleum_productshttp://en.wikipedia.org/wiki/Petroleum_naphthahttp://en.wikipedia.org/wiki/Gasolinehttp://en.wikipedia.org/wiki/Diesel_fuelhttp://en.wikipedia.org/wiki/Asphalthttp://en.wikipedia.org/wiki/Heating_oilhttp://en.wikipedia.org/wiki/Kerosenehttp://en.wikipedia.org/wiki/Liquefied_petroleum_gashttp://en.wikipedia.org/wiki/Industryhttp://en.wikipedia.org/wiki/Pipinghttp://en.wikipedia.org/wiki/Fluidhttp://en.wikipedia.org/wiki/Chemical_processhttp://en.wikipedia.org/wiki/Chemical_processhttp://en.wikipedia.org/wiki/Desalterhttp://en.wikipedia.org/wiki/Vacuum_distillationhttp://en.wikipedia.org/wiki/Catalytic_reforminghttp://en.wikipedia.org/wiki/Reformatehttp://en.wikipedia.org/wiki/Fluid_catalytic_crackinghttp://en.wikipedia.org/wiki/Cracking_(chemistry)http://en.wikipedia.org/wiki/Alkylationhttp://en.wikipedia.org/wiki/Isomerizationhttp://en.wikipedia.org/wiki/Steam_reforminghttp://en.wikipedia.org/wiki/Slugcatcherhttp://en.wikipedia.org/wiki/Slugcatcherhttp://en.wikipedia.org/wiki/Petrolatumhttp://en.wikipedia.org/wiki/Cresolhttp://en.wikipedia.org/wiki/Furfuralhttp://en.wikipedia.org/wiki/Cooling_towershttp://en.wikipedia.org/wiki/Boilerhttp://en.wikipedia.org/wiki/Steamhttp://en.wikipedia.org/wiki/Control_valveshttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Bermhttp://en.wikipedia.org/wiki/Doctor_sweetening_processhttp://en.wikipedia.org/wiki/Doctor_sweetening_processhttp://en.wikipedia.org/wiki/Doctor_sweetening_processhttp://en.wikipedia.org/wiki/Doctor_sweetening_processhttp://en.wikipedia.org/wiki/Bermhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Control_valveshttp://en.wikipedia.org/wiki/Steamhttp://en.wikipedia.org/wiki/Boilerhttp://en.wikipedia.org/wiki/Cooling_towershttp://en.wikipedia.org/wiki/Furfuralhttp://en.wikipedia.org/wiki/Cresolhttp://en.wikipedia.org/wiki/Petrolatumhttp://en.wikipedia.org/wiki/Slugcatcherhttp://en.wikipedia.org/wiki/Steam_reforminghttp://en.wikipedia.org/wiki/Isomerizationhttp://en.wikipedia.org/wiki/Alkylationhttp://en.wikipedia.org/wiki/Cracking_(chemistry)http://en.wikipedia.org/wiki/Fluid_catalytic_crackinghttp://en.wikipedia.org/wiki/Reformatehttp://en.wikipedia.org/wiki/Catalytic_reforminghttp://en.wikipedia.org/wiki/Vacuum_distillationhttp://en.wikipedia.org/wiki/Desalterhttp://en.wikipedia.org/wiki/Chemical_processhttp://en.wikipedia.org/wiki/Chemical_processhttp://en.wikipedia.org/wiki/Fluidhttp://en.wikipedia.org/wiki/Pipinghttp://en.wikipedia.org/wiki/Industryhttp://en.wikipedia.org/wiki/Liquefied_petroleum_gashttp://en.wikipedia.org/wiki/Kerosenehttp://en.wikipedia.org/wiki/Heating_oilhttp://en.wikipedia.org/wiki/Asphalthttp://en.wikipedia.org/wiki/Diesel_fuelhttp://en.wikipedia.org/wiki/Gasolinehttp://en.wikipedia.org/wiki/Petroleum_naphthahttp://en.wikipedia.org/wiki/Petroleum_productshttp://en.wikipedia.org/wiki/Crude_oilhttp://en.wikipedia.org/wiki/Factoryhttp://en.wikipedia.org/wiki/Industrial_process -
7/31/2019 L&T Summer Training Report
11/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 11
Figure 4 Refinery Flow diagrams and Petroleum products
-
7/31/2019 L&T Summer Training Report
12/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 12
2.2 Process Flow Diagrams (PFDs)
A Process Flow Diagram - PFD - (or System Flow Diagram - SFD) shows therelationships between the major components in the system.
A PFD does not show minor components, piping systems, piping ratings and
designations.A PFD should include:
1. Process Piping2. Major equipment symbols, names and identification numbers3. Control, valves and valves that affect operation of the system4. Interconnection with other systems5. Major bypass and recirculation lines6. System ratings and operational values as minimum, normal and maximum
flow, temperature and pressure
7. Composition of fluidsFunction of the Flow Diagram:
1. Ideas and thoughts as to the physical system of an industrial process start outin somebodys head (typically an engineer or technician/designer)
2. These are transferred to paper, chalkboards or dry erase boards as sketchesand verbal descriptions
3. Once the initial bugs are worked out of the process sketch, then a drafterconverts the sketches into a flow diagram
4. This drawing can be altered and revised many times during the design processof the system
5. The main thing this drawing does is give a visual as to the intended systembeing designed sometimes it takes having this type of visual representation
to allow other considerations or views of the process to be realized,
redesigned, modified and re-engineered.
6. It is the basis for feedback, discussion and revisions by the project engineerand clients.
7. An Eg of PFD is given on next page:
-
7/31/2019 L&T Summer Training Report
13/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 13
Figure 5 Typical Example of PFD
-
7/31/2019 L&T Summer Training Report
14/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 14
2.3 Piping and Instrumentation Diagrams (P&IDs)
The piping and Instrument Diagram (P&ID) provides a schematic representation ofthe piping, process control, and instrumentation which shows the functional
relationships among the system components.The P&ID also provides important information needed by the constructor and
manufacturer to develop the other construction input documents (the isometric
drawings or orthographic physical layout drawings).
The P&ID provides direct input to the field for the physical design and installation of
field-run piping.
Typical P&ID characteristics:
1. shows all valves and instrumentation2. Piping is detailed and contains some fittings3. Tanks and vessels show all nozzles and flanges4. Values associated with pipe are show; such as flow rates, temperature,
pressureetc.
Figure 6 Typical P&ID
-
7/31/2019 L&T Summer Training Report
15/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 15
2.4Material Take off Sheets (MTOs)Definition used by the ISA (International Society of Automation) :
A Material Take Off (MTO) is the process of analyzing the drawings and determiningall the materials required to accomplish the design. We then use the material takeoff
to create a bill of materials (BOM). Inspection does not aid in creating a bill ofmaterials. Procurement and requisition are activities that occur after the bill of
materials is complete.
Material Take Off (MTO) is a term used in engineering and construction, and refers to
a list ofmaterials with quantities and types (such as specific grades ofsteel) that are
required to build a designed structure or item. This list is generated by analysis of a
blueprint or other design document. The list of required materials for construction is
sometimes referred to as the Material Take Off List (MTOL).
Table 1 Typical MTO
http://en.wikipedia.org/wiki/Bill_of_materialshttp://en.wikipedia.org/wiki/Engineeringhttp://en.wikipedia.org/wiki/Constructionhttp://en.wikipedia.org/wiki/Materialshttp://en.wikipedia.org/wiki/Steelhttp://en.wikipedia.org/wiki/Blueprinthttp://en.wikipedia.org/wiki/Blueprinthttp://en.wikipedia.org/wiki/Steelhttp://en.wikipedia.org/wiki/Materialshttp://en.wikipedia.org/wiki/Constructionhttp://en.wikipedia.org/wiki/Engineeringhttp://en.wikipedia.org/wiki/Bill_of_materials -
7/31/2019 L&T Summer Training Report
16/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 16
2.5General Arrangement Drawings (GADs)These drawings indicate the locations of main equipments in the plant. The mainpiping items, valves, and fittings are also indicated in the General Arrangement or GA
drawings. Most often the piping is indicated using a top-view. Sometimes a side viewof the pipe rack is also presented on the GA drawing.
General arrangement drawings are also developed for individual equipments. These
drawings present the main dimensions of that equipment using 2D views, top-view,side-view and sometimes front-view. All the nozzles for concerned equipment are
indicated on the equipment General Arrangement or GA drawing.
Figure 7 Typical GAD
-
7/31/2019 L&T Summer Training Report
17/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 17
2.6IsometricsThe Iso, as isometric are commonly referred, is oriented on the grid relative to thenorth arrow found on plan drawings. Because iso's are not drawn to scale, dimensions
are required to specify exact lengths of piping runs.
PIPING isometrics are generally produced from orthographic drawings and are
important pieces of information to engineers. In very complex or large piping
systems, piping isometrics are essential to the design and manufacturing phases of a
project.
PIPING isometrics allow the pipe to be drawn in a manner by which the length, width
and depth are shown in a single view. Isometrics are usually drawn from information
found on a plan and elevation views. The symbols that represent fittings, Valves and
flanges are modified to adapt to the isometric grid. Usually, piping isometrics are
drawn on preprinted paper, with lines of equilateral triangles form of 60.
Pipe lengths are determined through calculations using coordinates and elevations.Vertical lengths of pipe are calculated using elevations, while horizontal lengths are
calculated using north-south and east-west coordinates.
Figure 8 Different views in Piping
-
7/31/2019 L&T Summer Training Report
18/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 18
Orthographic view Isometric view
The image on the right shows a isometric view of the same pipe as here on the
left. The red lines show the pipe, the black dots are the butt welds and A, B & Care the dimensions of front to center line and center line to center line
Figure 9 Typical Isometric Drawing
-
7/31/2019 L&T Summer Training Report
19/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 19
CHAPTER 3: BASICS OF PIPING
3.1 Categories of Piping
Piping is divided into three categories:
1. Large bore pipe: Generally includes piping greater than two inches in diameter.2. Small bore pipe: Generally includes piping which is two inches and smaller in
diameter.3. Tubing: Tubing is supplied in sizes up to four inches in diameter but has a wall
thickness less than that of either large bore or small piping.
3.2 Pipe Terminologies and Definitions
3.2.1 Nominal Pipe Size:The term diameter for piping sizes is identified by nominal size.The manufacture of nominal sizes of 1/8 inches through 12 inches inclusive is
based on a standardized outside diameter (OD).The 14 inch and larger sizes have the OD equal to the nominal pipe size.
Tubing however is sized to the outside diameter for all applications.
Pipe Sizes 3/8'', 1 1/4'', 3 1/2'', 4 1/2' and 5 inches are considered as non-standardand should not be used except to connect to equipment having these sizes. In this
case the line is increased to a standard size as soon as it leaves the equipment.
3.2.2 Schedule NumberPipes are manufactured in a multitude of wall thickness. These wall thicknesshave been standardized so that a series of specific thickness applies to each size of
piping. Each thickness is designated by a schedule number rather than the actualwall thickness.
The original thickness was referred to as standard (STD), extra strong (XS) anddouble extra strong (XXS). These designation or weight classes have now either
been replaced or supplemented by SCHEDULE NUMBERS in most cases.
Schedules begin with 5 and 5s followed by 10 and 10S, then progress in
increments of ten through Schedule 40 and then finally by increments of twenty to
Schedule 160.
Wall thickness for Schedule 40 and STD are the same for sizes 1/8'' to 10''.
Schedule 80 and XS also have the same wall thickness for 1/8'' through 8'' dia
pipe.
Schedules 5 and 10 are generally used for stainless steel piping.
-
7/31/2019 L&T Summer Training Report
20/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 20
3.2.3 Pipe LengthPipe is usually supplied in random lengths. The shortest, longest and average
length may vary for piping of different materials, sizes and wall thickness
schedules.
Typically an average length of 20 feet is used for carbon steel pipe, but doublerandom lengths are available from most suppliers and are generally preferred
especially for rack installations.
3.2.4 Pipe Ends1. Plain ends (PE) are cut square and reamed to remove burrs. This type of end is used
for mechanical couplings, socket weld fittings or slip on flanges.
2. Beveled ends (BE) are required for most butt-weld applications.3. Threaded ends (TE) are used for screwedjoints. Pipe order is placed as threaded
both ends (TBE) or threaded one end (TOE).
3.3 Standard Piping Materials
3.3.1 Carbon Steel
Itis one of the most commonly used pipe materials.The specifications that cover most of the pipe used are published by the ASTM
(American Society for Testing of Materials) and ASME ( American Society Of
Mechanical Engineers )
e.g. A106 is a Carbon Steel material specification and is available in grades A,B
and C.The grades refer the tensile strength.3.3.2 Stainless Steel Pipe
Itis virtually non-magnetic. There are eighteen different grades and type 304 L isthe most widely used.L denotes low carbon content and is best suited for welding.
3.3.3 Chromium-Molybedenum Alloy
Thispipe is commonly referred to as ''chrome-moly''. There are ten grades ofthis type of pipe material and are covered by ASTM 335. Chrome - moly pipe is
used extensively in heat exchangers.
-
7/31/2019 L&T Summer Training Report
21/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 21
3.3.4 PlasticThermoplastic pipe available in compositions
eg polyvinyl chloride (PVC), Polyethylene (PE),
Polypropylene (PP)
Thermosetting (Fiberglass) pipe.
3.4 Piping Components
3.4.1 Flanges
Flanges are divided by class which is normally rated by working pressure in
pounds per square inch. They are available in a variety of primary pressureratings from 25psi to 2500 psi.
Selection of the proper flange facing depends on the combination of manyfactors:
1. Flange material2. Gasket Material3. Bolt Strength4. Operating Pressure and Temperature5. Fluid Properties Contained
Types of Flanges:
1. Weld Neck Flanges are the most common type of flanges used andpreferred for the majority of service conditions. The strength of the fitting
increases and stress is distributed so that this style can withstand extreme
temperature. Shear, impact, bending and vibratory loading.
Figure 10 Weld Neck Flange
-
7/31/2019 L&T Summer Training Report
22/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 22
2. Socket Weld flanges are most commonly used on two inch and smallerp
i
p
i
n
g
.
3. Slip-on Flangesare sometimes preferred because of its lower installationcost and because it can accommodate slight misalignment. The calculated
strength of the slip-on flange under internal pressure is approximately two
thirds that of the weld neck style flanges and its life under fatigue is about
one-third that of the weld-neck.
Figure 11 Socket Weld Flange
Figure 12 Slip-On Flange
-
7/31/2019 L&T Summer Training Report
23/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 23
4. Threaded Flanges are attached by screwing the flange onto the threadedend of the pipe. As with other threaded fittings its use is restricted to
systems having relatively low operating temperatures and pressures.
5. Lap Joint Flangesare used in piping that will be frequently dismantled.The flange is free to revolve on the pipe thus avoiding the problem of
accurate alignments.
Figure 13 Threaded Flange
Figure 14 Lap Joint Flange
-
7/31/2019 L&T Summer Training Report
24/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 24
3.4.2 Elbows
They make an angle between adjacent pipes. There are standard elbows of 90
degrees and 45 degrees.
Long radius 90 deg elbow:
Radius of bend = 1.5 times the nominal pipe diameter.
Short radius 90 deg elbow: Radius of bend = nominal diameter. Reducing elbowsare 90 deg elbows with two different size ends
3.4.3 Tees
Straight Tee has three openings. Two have the same axis while the third is
perpendicular to this axis for connecting a branch line.
Reducing Teeis similar to a straight tee except that the branch line connection issmaller in size.
3.4.4 Lateral pipe fittings
They are of two types:
Straight Lateral pipe fittingshave three outlets two of which have the same axisand a third on the side joined at 45 deg angle from the main axis.
Reducing Lateral fittings are similar to straight laterals except that the branchconnection is smaller in size.
Figure 15 Elbow Figure 16 Tees
-
7/31/2019 L&T Summer Training Report
25/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 25
3.4.5 Reducers
Concentric Reducers are pipefitting with different nominal diameters on each
end while maintaining the same centerline.
Eccentric Reducersare pipefitting with different nominal diameters on each endand the fitting is flat on one side with an eccentric centerline. Eccentric reducers
are used for connecting different size pipes especially at centrifugal pump inlet
connections for preventing air pockets which may cause the pump to CAVIATE.
3.4.6 Swage nipples
A Swage Nipple is a reducing fitting used to join piping of different sizes. Caremust be taken in matching the correct pipe schedules and end styles when
ordering. Swages are available in both concentric and eccentric types.
3.4.7 Pipe caps
Pipe Capsis specialized fittings that are used to close an open end.
3.4.8 Strainers
Strainersare used to remove solid particles from liquids. They generally have apermanent screen that can be cleaned by emptying, washing or blowdown.
Strainers are generally placed in the main line so that all of the process fluid
passes through them.
Figure 17 Reducers Figure 18 Swage nipples
-
7/31/2019 L&T Summer Training Report
26/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 26
Strainers are either permanent plant components designed for the life of the plant
or temporary components for the removal of construction residue during initial
start up.
3.4.9 Weldolets
They are integral reinforcement fittings used for branch connection strength.
They are designed to minimize stress concentrations and provide integral
reinforcement.
(a)
(b)
(c)
Figure 19 Different Weldolets
(a) Weldolet
(b) Tapered Weldolet
(c) Straight Weldolet
-
7/31/2019 L&T Summer Training Report
27/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 27
3.4.10 Full Couplings and Threaded Unions
Full couplingsare used to join a pipe segment to another pipe or pipefitting.
Screwed Unionsare basically screwed joint that can be disassembledwithin a completed system for subsequent maintenance.
3.5 Valves
3.5.1 Definition and Function
A Valve may be defined as a mechanical device by which the flow of liquid or gas
may be started, stopped or regulated by a movable part that opens, shuts or
partially obstructs one or more ports or passageways.
A Valve may be designed to direct, start, stop, mix or regulate the flow, pressure,
or temperature of a process fluid.
A Valve by nature of their design and materials can :
Open and Close Turn on and off Regulate Isolate extremely large array of liquids and gases.
3.5.2 Valve Materials
Carbon Steel is the ideal material for non-corrosive fluids. It is also used for
steam and condensate services. Carbon Steel is readily available in most common
general service valves and generally inexpensive. It is recommended in
temperatures up to 425 Deg Celsius in continuous service or up to 535 Deg
Celsius in non-continuous service.
Figure 20 Full Couplings
-
7/31/2019 L&T Summer Training Report
28/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 28
Stainless Steel is very corrosion resistant, extremely strong and is commonly
specified for high- temperature application temperatures at 535 Deg Celsius and
higher. The cost of Stainless Steel is higher than carbon steel but less than other
alloy steels.
Chrome-Molybdenum steel is a good material that falls between the
characteristics of carbon steel and stainless steel. It can handle higher pressure and
temperatures than carbon steel making it ideal for high pressure steam or flashing
condensate applications. Special alloys are specified for special service or severe
service valves e.g. Hastealloy B & C may be selected for a highly acidic fluid
service or Monel or bronze body may be selected for a pure Oxygen Service.
3.5.3 Types of valves
Figure 21 Types of Valves
-
7/31/2019 L&T Summer Training Report
29/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 29
1. Gate valves:A Gate valve is a multi turn valve in which the port is closed by a flat-
faced vertical disk that slides at right angles over the seat. It is primarily
designed for on-off service, where it is operated infrequently.
It can be applied to general service, oil, gas, air slurries, heavy liquids,
steam, non-condensing gases and liquids, corrosive liquids
2.
Globe valves:A Globe valve is a linear motion valve and is generally used for both on-
off throttling applications.
Although the globe design can handle high-pressure classes, due to the
thrust limitations of the hand operator globe valves are usually applied to
lower pressure applications.
3. Ball valvesThe valves, which are best, used for on-off service, as well as moderate
throttling situations that require minimal accuracy.
They are made in three general patterns: Venturi port, Full port and
Reduced port
4. Butterfly valvesIn a Butterfly valve the fluid moves from the inlet to the outlet, with the
disk being the only obstruction to the flow.
-
7/31/2019 L&T Summer Training Report
30/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 30
Unlike gate or globe valve designs, where the closure element moves out
of the flow stream, the butterfly disk is located in the middle of the flow
stream.
It creates some turbulence to the flow, even in the open position.
5. Check valvesCheck valves (also known as non-return valves) are automatic valves that
prevent a return or reverse flow of the process.
The check valve operation is dependent upon the flow direction of the
process, which may be created by a pump or pressure drop.
6. Plug valvesIt is a quarter-turn manual valve that uses a cylindrical or tapered plug topermit or prevent straight-through flow through the body.
Plug valves are either lubricated or non-lubricated.
For non-lubricated valves, the plug may be inserted from the top or bottom
of the valve body.
7. Diaphragm valvesDiaphragm Valves consist of a rigid body formed with a weir placed in theflow path, a flexible diaphragm which forms the upper pressure boundary
of the valve, a compressor which is used to force diaphragm against the
weir, and the bonnet and hand wheel which secure the diaphragm to the
body and actuate the compressor.
They are manufactured in Variety of end connections:
Welding end socket or butt welding, flanged, screwed or threaded, clamp
ends, solvent cement joint ends for thermoplastic valves and male sanitary
threaded ends.
8. Safety valvesThey are also known as pop safety valves.
They are spring loaded, quick opening, full flow valves for systems
containing pressurized, compressible fluids such as steam, air, or other
vapors or gases.
The set pressure is adjusted by increasing or decreasing the spring
compression.
The difference between the opening pressure and the closing pressure is
called blowdown.
-
7/31/2019 L&T Summer Training Report
31/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 31
9. Relief valvesThey are similar to safety valve but open only slightly at set pressure.
Instead of full opening, they open wider if the pressure increase above the
set pressure.
Relief valves are normally used for liquids, such as water or oil, whererelease of a small volume will rapidly lower the pressure.
3.6 Gaskets
A gasket is a malleable material, which can be either soft or hard, that is inserted
between two parts to prevent leakage between that joint.
Pressure is applied by bolting or using a clamp to compress the gasket firmly in
place.
Gaskets are made from all different types of materials, depending on the
temperature, pressure or fluid characteristics of the process.
Gaskets are used in valves for three major purposes:
To prevent leakage around the closure mechanism To prevent leakage of fluid to atmosphere To allow the function of internal mechanisms that depend on separate fluid
chambers, such as pressure balance trim
Figure 22 Gaskets
-
7/31/2019 L&T Summer Training Report
32/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 32
3.7 Piping nomenclature
3.7.1 Need for nomenclature
Several documents are required as a part of design of process plants. Out of these
the documents related to piping are:1. Piping & Instrumentation Diagram (P&ID),2. Piping Layout3. Piping Elevation etc.Each of these documents contains several lines of different sizes, MOC and
service.
Thus it becomes necessary to identify each line and assign a unique identity to
each of them.A line can be identified by its number, fluid to be handled, location in plant, line
size, MOC etc.These parameters are the basic elements of line identity and when put in a proper
order forms what is called as Elements/Parameters of Piping Nomenclature .
Figure 23 PIPING NOMENCLATURE
-
7/31/2019 L&T Summer Training Report
33/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 33
3.7.2 Detailed description
Parameter 1: Line Number
1. Line Number is a unique number assigned to every line. Every line musthave a different line number i.e. the number should not be repeated for
various lines.2. The simplest way of line numbering can be assigning numbers 1, 2, 3
and so on to lines.
3. Depending on the type of fluid the lines can be further numbered. Forexample lines for process fluids can have numbering in one range, say, 1 to
100, utility lines can have numbering falling in another range, say, 101 to
200 and so on.4. Yet another way of line numbering can be assigning letters/alphabets to
various fluid services and accordingly numberings the lines. For examplethe process lines can be assigned letter 'P', utility lines can be assigned
letter U and then depending on various lines the number follows the
corresponding letter e.g. P123 indicates process line with no.123.
Parameter 2: Fluid to be handled
1. Process lines are meant for handling various fluids. The fluids handled canbe classified as Process fluids (which further includes the raw materials,
the intermediate streams and the final product).
2. Utilities (which includes cooling water, chilled water, steam, thermicfluids, soft water, DM water etc.).
3. For nomenclature, each of these lines are given specific codes dependingon the fluid handled e.g. CHS may indicate chilled water supply, CHR
may indicate chilled water return DMS may indicate DM water supply and
so on.
Parameter 3: Location in plant
1. This parameter is included in the nomenclature so as to indicate the originof any stream in various locations of the plant.
2. The various sections of plants are Raw material storage, processing,Intermediate Product Storage, Final product storage, Water treatment
section, utility section, waste treatment section etc.
3. These sections can be indicated as RMS-SEC for Raw Material Storagesection, PRO-SEC for processing section, WTP-SEC for Water treatment
section-WSTSEC for waste treatment section, UTI-SEC for Utilitysection and so on.4. Each of these sections can be numbered depending on the process flow and
this number appears in the nomenclature. For example Raw MaterialStorage section can be designated as I, Processing Section by II and so on.
Parameter 4: Line size
1. Although the selection of line is a job of piping engineer, the line sizingcan be done by Process or Piping engineer. Commercial pipes are available
either as NB (Nominal Bore ) based or OD (Outside Diameter) based
depending on the material of construction.
-
7/31/2019 L&T Summer Training Report
34/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 34
2. The standard sizes on NB basis are 25, 50, 80,100,150,200 etc. Thecorresponding sizes on OD basis are 33.4, 60.3, 88.9, 114.3, 168.3, 219.1etc. The same are mentioned in the nomenclature.
Parameter 5: Material of Construction
1. Commercial pipes are available with various materials of constructions.Most commonly used materials are CS, AISI 304, AISI 316, Copper, PVC
etc.
2. In the nomenclature MOC can be written as it is like CS for Carbon steel,AISI 304, AISI 316 etc. for various grades of Stainless Steel. Type 2
second way can be giving code for various MOC. For example Code 1 can
denote CS, Code 2 can denote AISI 304 and so on.
Parameter 6: Insulation1. Heat transfer is the common operation used in Process industries. Process
equipments and pipes are insulated either to prevent heat loss to the
surroundings or to prevent heat gain from the surroundings.2. Accordingly there are two types of insulations hot and cold. Depending
on the temperature inside the pipe and that of the surroundings, the nature
of insulation differs. The terms H and C can thus be used to indicate
the type of insulation.
3. The inclusion of this parameter in the nomenclature is essential because itindicates the nature of fluid in the pipe which is mainly required for
personnel safety in the plant.
Parameter 7: Phase
1. Materials that are handled in Process plants exist in different phases. Ingeneral the flow can classified as single phase flow, two phase flow and
three phase flow.
2. Single phase flow indicates flow of solid, liquid, gases or vapors. Twophase flow indicates combination of any two of these e.g. solid + liquid,
solid + gases, liquid + vapors etc
3. Three phase flow indicated combination of any three of these. Theinclusion of this parameter in the nomenclature may be optional, but the
inclusion proves to be very helpful especially when the process involves
several phase flows through various lines in the plant. Type 1)4. The details of phase can be given by complete name of the phase like
solid, liquid etc. Type 2) Letters such as S, L, G and V can be used todenote respectively solids, liquids, gas and vapors.
Parameter 8: Other Details
1. At times it becomes necessary to provide additional details in thenomenclature.
2. These include jacketing of pipe, pipe tracing, special lines like IBR etc.The additional detail can be indicated as it is in the nomenclature.
-
7/31/2019 L&T Summer Training Report
35/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 35
CHAPTER 4: PROJECT WORK
4.1 Analysis
Though the LPG recovery unit consists of many components but our main focus
is on two columns: 40-C-401 & 40-C-402. So throughout the entire project work all the
DESCRIPTION, WORKING PROPORTION AND DESIGN CALCULATIONS will be
in context of two COLUMNS.
4.1.1 Process description
The Fractionation section consists of two columns:
1. Light end fractionation column (LEF)Liquid from HP & LP separator under level control LIC-1301 & LIC 1501
(cascaded with flow) after exchange of cold in feed gas chiller and then fed
to LEF column(40-C-401) on 9th
tray.
The column has a total of 40 valves trays. The column operates at a
pressure of 28.2kg/cm2g at the top.
Reflux is generated by condensing part of overhead vapors in LEF
Condenser (40-E-406) by using LP separator overhead vapors and fed to
the column top by reflux pump (40-P-401A/B) under flow control.
Reflux drum level is controlled by LIC/FIC-2001 cascade acting on thereflux flow to the column.
Temperature at the inlet of the LEF reflux drum is controlled by bypassing
LEF condenser and hence controlling condensation of LEF column
overhead vapor.
In case of lower condensing temperatures, a split range control bypasses
cold lean gas from LP separator passing through LEF column condenser.
Lean gas is generated at the LEF column overhead vapor with main
constituents of methane, ethane.
Cold from uncondensed LEF column overhead vapors is recovered in Feedgas chiller and the gas is then used for regeneration of feed gas dryers.
Thermosiphon type LEF column Reboiler (40-E-407) is provided at LEF
column bottom using LP steam.
Steam flow to reboiler is controlled by 39 th tray temperature. Liquid from
LEF column bottoms is withdrawn under LIC-1904/FIC-1901 cascade at
approximately 97 degree Celsius and fed to LPG column (40-C-402).
Steam Condensate from LEF column bottom reboiler is routed to steam
condensate recovery system within ISBL under level control of reboiler
condensate pot (40-V-404).
-
7/31/2019 L&T Summer Training Report
36/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 36
2. LPG columnBottom liquid from LEF column is taken to LPG column (40-C-402) on
the 22nd tray.
This column has 52 valve trays and is designed to separate LPG (propane
and butane) from heavier components.The column is operated at a pressure of 15kg/cm2g at the top.
The pressure is maintained by varying surface area of LPG column
condenser.
LPG product is withdrawn as overhead liquid product from Reflux Drum
(40-V-408) under level control (LIC-2201) and sent to existing LPG
storage. Reflux is sent back to column through LPG column Reflux Pumps
(40-P-402A/B), under flow control (FIC-2201).
The column bottom has a thermosiphon type Reboiler (40-E-409) using
MP steam.Steam flow to reboiler is controlled by a 51st tray temperature.
NGL from column bottom is cooled to 40 degree Celsius by water cooler
(40-E-410) and then sent to storage under level control (LIC-2102) of LPG
column bottoms.
Provision for diverting off-sped NGL to the crude stabilization unit has
also been kept, in case NGL rundown temperature goes higher than 50
degree Celsius due to fouling of rundown cooler or LPG column
temperature going down due to any operational failure.
Steam condensate from LPG column bottom reboiler is routed to steam
condensate recover system with ISBL under level control of reboiler
condensate pot (40-V-409).
4.1.2 Process flow diagram (PFDs)
It is designed to recover maximum LPG from sweetened gas coming from gas
Sweetening units and produce value added products viz. LPG, NGL & Lean gas.
LPG recovery unit consists of feed gas compression and pre-cooling, Feed Gas
drying and regeneration, Chill down and expansion, Lean gas compression,
Propane refrigeration system and Fractionating system.
PFD of the process is shown on the next page:
-
7/31/2019 L&T Summer Training Report
37/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 37
Figure 24 PFD of LPG recovery Unit.
-
7/31/2019 L&T Summer Training Report
38/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 38
4.1.3 PIPING AND INSTRUMENTATION DIAGRAM (P&IDs)
Here are P&IDs of two Fractionating Columns:
3. 40-C-401
Figure 25 P&ID of 40-C-401 fractionating column
-
7/31/2019 L&T Summer Training Report
39/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 39
4. 40-C-402
Figure 26 P&ID of 40-C-402 fractionating column
-
7/31/2019 L&T Summer Training Report
40/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 40
4.2 Working proportions
4.2.1 Capacity
The unit is designed to process a total of 5.65 MMSCMD of sweet gas.
4.2.2 On stream factor
No of operating days per year: 330
4.2.3 Turndown capacity
It is 50% of designed capacity.
4.2.4 Feed specifications
It has been designed for the following composition of sweet gas from GSU:
Table 2 Feed specification of LPG unit
-
7/31/2019 L&T Summer Training Report
41/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 41
4.2.5 Product specification
The specifications of LPG, NGL & Lean gas from the unit have been considered
as:
Table 3 Specification of LPG, NGL & Lean gas
4.2.6 Battery limit conditions
The battery limit temperature and pressure conditions for the incoming and
outgoing process streams are indicated below:
Table 4 Battery limit conditions
-
7/31/2019 L&T Summer Training Report
42/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 42
4.3 Designing and its calculations
4.3.1 PFDs
As done in section 4.1.2
4.3.2 P&IDs
Main P&ID of any column or reboiler consist of all the piping and instrument
related information so as to be circulated within both departments- Piping and
Instrumentation.
Since I am allotted PIPING task, I deduced that official P&ID of column 40-C-
401 and 40-C-402 to the extent such that it is of use for piping only.
All these changes were done in AUTOCAD 2012 version and PDF files of them
are shown below:
1. 40-C-402
Figure 27 P&ID of LPG column 40-C-402 after Alterations
-
7/31/2019 L&T Summer Training Report
43/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 43
2. 40-C-401
Figure 28 P&ID of LEF Column 40-C-401 after Alterations
-
7/31/2019 L&T Summer Training Report
44/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 44
4.3.3 Elevations of LPG & LEF column
1. 40-C-402 LPG column
Figure 29 ELEVATION of LPG COLUMN 40-C-402
-
7/31/2019 L&T Summer Training Report
45/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 45
2. 40-C-401 LEF COLUMN
Figure 30 ELEVATION OF LEF COLUMN 40-C-401
-
7/31/2019 L&T Summer Training Report
46/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 46
4.3.4 MTO of 40-C-402
-
7/31/2019 L&T Summer Training Report
47/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 47
Table 5MTO of 40-C-402 COLUMN
-
7/31/2019 L&T Summer Training Report
48/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 48
4.3.5 Pipe thickness calculation for Spec B1APipe wall thickness calculation in accordance with ASME B 31.3 paragraph 304.1
(A)Nomenclaturetm = Minimum required thickness, including mechanical, corrosion and erosionallowance,(mm)
t = Pressure design thickness, (mm)
c = the sum of mechanical allowance (thread or groove depth) plus corrosion and
erosion allowance, (mm)
P = Internal design gauge pressure, (N/mm2)
D = outside diameter of pipe, (mm)
E = Quality factor from table A-1A or A-1B
S = Stress value for material from table A-1, (Ksi)
Y = Coefficient from table 304.1.1, valid for t
-
7/31/2019 L&T Summer Training Report
49/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 49
Table 6 PIPE THICKNESS CALCULATION FOR SPEC B1A (D
-
7/31/2019 L&T Summer Training Report
50/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 50
Table 7 PIPE THICKNESS CALCULATION FOR SPEC B1A (D>14)
-
7/31/2019 L&T Summer Training Report
51/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 51
4.3.6GAD of LPG & LEF column
Figure 31 GAD of LPG & LEF COLUMN
-
7/31/2019 L&T Summer Training Report
52/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 52
4.3.7 Isometric of line no 1.5-SL-40-1904-D1A-IH
Figure 32 ISOMETRIC OF LINE NO 1.5-SL-40-1904-D1A-IH
-
7/31/2019 L&T Summer Training Report
53/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 53
CHAPTER 5: SUMMARY AND CONCLUSIONIn Oil and Gas industry, in order to setup a plant PIPING plays a critical role. Fluid is
transferred through pipes between different and within processing units. Our project is based
on piping of a sub unit of LPG Recovery plant in ONGC, URAN.
For piping, in this project as well as other units; elementary steps are almost same and are
mentioned below:
1. PFDs and Descriptions of each unit.2. Multiple P&IDs of single PFD showing detailed description of each Equipment.3. Mechanical Data Sheets (MDS) for every equipment.4. MTOs for each processing unit.5. GADs for whole unit.6. Modeling of plant through software like PDS/PDMS.7. Extraction of isometrics.
After this designing section, these isometrics are issued for construction sites. And the
modeling is done in accordance with following standards:
1. OISD 118.2. ASME B16.5, B31.3 & B36.10.
Before Modeling, calculations are done for the elevations of equipments, pipe diameter, pipe
thickness and nozzle orientation.
-
7/31/2019 L&T Summer Training Report
54/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 54
BIBLIOGRAPHY
1. http://en.wikipedia.org/wiki/Oil_refinery2. http://pipingdesigners.com/Training%20-%20section%202b.htm3. http://www.epcpj.com/check-list-for-piping-material-take-off/4. http://wiki.answers.com/Q/What_is_the_difference_between_Material_take_off_and_
Bill_of_materials_in_piping
5. http://www.wermac.org/documents/isometric.html6. http://www.wermac.org/documents/pid.html7. http://www.enggcyclopedia.com/2011/08/general-arrangement-ga-drawings-piping/8. http://www.engineeringtoolbox.com/pfd-process-flow-diagram-d_465.html9. OISD Guidelines Table 1 & Table 2.10.Product Material Specification (PMS) by ONGC.11.Piping Design Basis 6812-00-16-43-DB-01 by EIL.12.ASME standards B16.5, B31.3, and B36.10.
http://en.wikipedia.org/wiki/Oil_refineryhttp://pipingdesigners.com/Training%20-%20section%202b.htmhttp://www.epcpj.com/check-list-for-piping-material-take-off/http://wiki.answers.com/Q/What_is_the_difference_between_Material_take_off_and_Bill_of_materials_in_pipinghttp://wiki.answers.com/Q/What_is_the_difference_between_Material_take_off_and_Bill_of_materials_in_pipinghttp://www.wermac.org/documents/isometric.htmlhttp://www.wermac.org/documents/pid.htmlhttp://www.enggcyclopedia.com/2011/08/general-arrangement-ga-drawings-piping/http://www.engineeringtoolbox.com/pfd-process-flow-diagram-d_465.htmlhttp://www.engineeringtoolbox.com/pfd-process-flow-diagram-d_465.htmlhttp://www.enggcyclopedia.com/2011/08/general-arrangement-ga-drawings-piping/http://www.wermac.org/documents/pid.htmlhttp://www.wermac.org/documents/isometric.htmlhttp://wiki.answers.com/Q/What_is_the_difference_between_Material_take_off_and_Bill_of_materials_in_pipinghttp://wiki.answers.com/Q/What_is_the_difference_between_Material_take_off_and_Bill_of_materials_in_pipinghttp://www.epcpj.com/check-list-for-piping-material-take-off/http://pipingdesigners.com/Training%20-%20section%202b.htmhttp://en.wikipedia.org/wiki/Oil_refinery -
7/31/2019 L&T Summer Training Report
55/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 55
Appendices
Appendix i: Legend Sheet
-
7/31/2019 L&T Summer Training Report
56/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 56
-
7/31/2019 L&T Summer Training Report
57/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 57
Appendix ii: Product Material Specification (PMS)
B1A
-
7/31/2019 L&T Summer Training Report
58/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 58
-
7/31/2019 L&T Summer Training Report
59/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 59
B2A
-
7/31/2019 L&T Summer Training Report
60/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 60
-
7/31/2019 L&T Summer Training Report
61/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 61
Appendix iii:
ASME B16.5
-
7/31/2019 L&T Summer Training Report
62/63
LPG-LEF DISTILLATION UNIT DESIGN 2012
Page | 62
ASME B31.3
-
7/31/2019 L&T Summer Training Report
63/63
LPG-LEF DISTILLATION UNIT DESIGN 2012 ASME B36.10M