LPA Projects
2011 LPA projectsAlum Creek Bike Trail $3,200,000Parsons/Livingston $14,500,000
Riversouth Phase $9,900,000Lane Avenue $1,700,000Arcadia over Glen Echo $500,000Front St. $250,000
Preconstruction Conference
Monitoring ProgressStandard ODOT progress meeting agenda
ScheduleUse a CPM note nearly identical to ODOT’sRequire Primavera P6 on projects with a
CPM
Project DocumentationThe City of Columbus has adopted the ODOT filing system
Most inspection/testing forms have been adopted from ODOT
We utilize an Access Database to track payments and produce estimates
Prevailing Wage/ DBEPrevailing wage onsite interviews,
weekly payroll compliance, and prevailing wage affidavits are managed by a payroll coordinator within the construction section.
DBE goals and compliance are managed by the City of Columbus Equal Business Opportunity Commission Office.
Material Quality ControlThe City of Columbus requires submittals on
many items for approval prior to procurement.No integrated PBOM similar to ODOT’sCreate a PBOM in Excel and utilize that to ensure
material documentation is obtained for all itemsWe have an onsite testing lab but have limited
ability to inspect structural steel at the fabricator. Contractors that do not perform a lot of ODOT
work often do not request TE-24’s
Change OrdersUse a modified ODOT format for change
ordersDo not pay over plan quantity on any
reference without a prior approved change order
Copy of the approved change orders are sent to the ODOT CM for concurrence
Document time extensions on change orders
Example of CoC Change Order
InvoicingProcess pay estimates every 30 days via our
Access database, based on quantities tracked by inspection
The City of Columbus pays the contractor out of their funds and seeks reimbursement from ODOT
Submit a detailed request for reimbursement based on previously agreed funding splits
The request is reviewed at the ODOT District and the City of Columbus sends a signed invoice to ODOT CO
Project Closeout ProcessA final walkthrough is held with all
stakeholders including the ODOT CMThe PBOM is reviewed to ensure all
materials documentation is received Letter of acceptance is issued to the
contractor after all work is acceptedAudit performed on all project
documentation by CM
ConclusionAny questions?