Long-Term Surface Infiltration Monitoring of Permeable Interlocking Concrete Pavement Kevin Earley, Nicolock Paving Stones

Upload: others

Post on 08-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Long-Term Surface Infiltration Monitoring of

Permeable Interlocking Concrete Pavement

Kevin Earley, Nicolock Paving Stones

Page 2: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 3: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 4: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

PICP Case Study - Lindenhurst Library

Page 5: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Design

Page 6: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 7: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 8: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 9: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

3/31/10

Page 10: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

10% open area No. 8 Stone in Joints > 500 in/hr Surface Infiltration Rate

Let’s Look at another Project Example Before Discussing Surface Infiltration Rate Testing

Page 11: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

PICP Case Study Material Supply Yard in Long Island

Page 12: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Before

Page 13: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Starts with Engineering

Page 14: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Subgrade Soil Analysis

Light Brown Coarse to fine sand with few gravel (SP)

Page 15: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

•Appendix D NYS Stormwater Design Manual

•12” diameter pipe

• Pre-soak

• Falling head infiltration test

•Average infiltration rate > 100 in/hr.

Page 16: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Design

• Store 100,000 SF for 1.5” storm event=12,500 ft3 • Utilize existing drywells • Install 9,000 SF of PICP in lieu of more drywells • Allow for contributory run-on including roof

drains (~ 11 x’s permeable pavement area) • Installed in 2010

PICP avoided the installation of 22 12’ diam. drywells and provided a useful surface and recharge basin all in one

Page 17: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 18: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

NO. 9

Page 19: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 20: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 21: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 22: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

ASTM No. 9 Stone in Joints

Page 23: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 24: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 25: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Infiltration is Related to Joint Fill

Approx. Particle Size Permeability (k) in/hr

ASTM No. 8 (2-10 mm) 1,400 – 4,000

ASTM No. 9 (2-5 mm) 140 - 1,400

ASTM No. 10 (1-3 mm) 14 – 140

ASTM C 33 (sand) 1.4 to 14

Page 26: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Visual inspection during/after a rainstorm

Quantify using a test method

How Do We Measure Performance?

Page 27: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Visual Observation

Page 28: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Neoprene pad

300 mm dia. ring

Stone filled buckets

Research Devices

Showerhead

Page 29: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Surface Infiltration Testing

29

ASTM C 1781-13 Standard Test Method for Surface Infiltration Rate of Permeable Unit Pavement Systems

Page 30: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

ASTM C 1781 Origins

ASTM C 1701

Page 31: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

12” Diameter Ring Constant Head Test

Page 32: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 33: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 34: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 35: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

ASTM C1781 Procedures • 12” diameter ring with 0.4 and 0.6” marks • Plumbers Putty – Federal Spec A-A-3110 • 3 locations for up to 25,000 ft2 , one for each

additional 10,000 ft2 • Prewet with 8# of water – if < 30 sec use 40#,

otherwise use 8# • Test within 2 minutes, 2nd pour within 5

minutes of 1st

• Simple calculation: I = K*M/(D2*t)

Page 36: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

New Test Method Modifies C 1701 1. Broaden use to includes – clay pavers, concrete

pavers, and grid pavers 2. Recommends a maximum ring height of 6” to avoid

splash effect 3. Clarifies test location selection and adds more

documentation 4. Follows same procedures and calculations as

ASTM C 1701 5. Provides a non-mandatory appendix to normalize

ring drainage area to entire pavement area to improve accuracy

Page 37: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

How are we doing at the Library?

• No. 8 Stone in Joints • Little traffic or sediment, no maintenance • First test 20 months post-construction

Page 38: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Library Test Results and graph Location 1 Location 2 Location 3

(inches/hr) 20 months Post Construction 4/4/11 481 492 656

487 422 687 Location Average: 484 457 671

Site Average: 537 44 months Post Construction

4/18/2013 299 196 320 289 186 271

Location Average: 294 191 296 Site Average: 260

48 months Post Construction 8/29/2013 250 185 265

222 169 275 Location Average: 236 177 270

Site Average: 227

Page 39: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

80% reduction may be in ~ 6 yrs

60% reduction in 4.1 yrs

10 in/hr design rate

Page 40: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

How are we doing at the Supply Yard?

• No. 9 Stone in Joints • Lots of traffic and sediment, no maintenance • Detailed analysis underway

Page 41: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Location #1

Location #2

Location #3

Location of Measurements

Page 42: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Location 1 Location 2 Location 3

(inches/hr) Less than 1 week Post Construction 10/21/2010 206 302 358

183 350 313 Location Average: 195 326 336

Site Average: 285

6 months Post Construction 4/4/2011 321 341 336

340 327 353 Location Average: 331 334 345

Site Average: 336

13 months Post Construction 11/2/2011 250 229 242

244 232 238 Location Average: 247 231 240

Site Average: 239

Year 1 Results

Install Flush, Equilibrium???

Decreasing, But Consistent, No Patterns

Page 43: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Location 1 Location 2 Location 3

(inches/hr) 18 months Post Construction

4/11/2012 176 227 291

150 181 53

Location Avr. 163 204 172 Site Average: 180

30 months Post Construction

4/8/2013 78 98 153

83 94 147

Location Avr. 81 96 150 Site Average: 109

Year 2 Results

Decreasing, Location 3, Outlier

Decreasing, Pattern Develops

Page 44: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Location 1 Location 2 Location 3

35 months Post Construction

8/6/2013 36 113 207

74 110 140

Location Avr. 55 112 174

Site Average: 113

Year 3 Results

Stabilizing, Pattern Clear

(inches/hr)

Page 45: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

68% reduction in 3 yrs

Predict 80% reduction in ~ 4 yrs

10 in/hr design rate

Page 46: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

The Edge Effect

Page 47: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Results and picture of clogging test 5 in/hr (26 min.)

Page 48: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 49: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Gradation of clogged joint

Page 50: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Gradation of Joint Material

SIEVES collected collected

8/2/2010 8/29/2013 US sieve size Diameter, m % finer % finer 3/8" 9.5 100 100 No. 4 4.75 72.25 66.7 No. 8 2.36 15.36 24.7 No. 16 1.18 5.25 19.2 No. 30 0.6 2.67 14.6 No. 50 0.3 1.64 5.8 No. 100 0.15 1.03 2.2 No. 200 0.075 1.01 1.1

Page 51: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

Conclusions 1. Fine sediment in permeable pavements will reduce

long-term surface infiltration rates

2. Clogging is common and biased

3. Less clogging potential with # 8 stone vs. # 9 stone

4. ASTM C 1781 is an inexpensive and simple test to

measure surface infiltration on PICP and other forms of

permeable pavement

5. Use ASTM C 1781 for acceptance and corrective action

triggers

Joint Stone Reduction 80%

clogging

# 8 60% in 4 yrs > 6 yrs

# 9 68% in 3 yrs 4 yrs

Page 52: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

PICP Industry Recommendations 4th Edition PICP Manual

• Hydrologic design • Structural design • Construction guidelines C1701 acceptance testing Min. 100 in./hr (250 cm/hr) • Maintenance guidelines C1701 performance testing Min. 10 in./hr (25 cm/hr)

Page 53: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53
Page 54: Long-Term Surface Infiltration Monitoring of Permeable … · 2020. 6. 18. · Location 2 . Location 3 (inches/hr) 18 months Post Construction : 4/11/2012 . 176 227 291 150 181 53

For additional information about PICP contact: Kevin Earley 631-774-6431 [email protected]