London Bridge Station RedevelopmentProject Team Brief November 2017
![Page 2: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/2.jpg)
Let’s start with some success ….
![Page 3: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/3.jpg)
![Page 4: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/4.jpg)
![Page 5: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/5.jpg)
Reserve P06/17 £19.2M
• Period Movement £4.4M – reflects completion of TCF45
Forecast Reserve £29.9M
![Page 6: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/6.jpg)
Relies upon….
![Page 7: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/7.jpg)
![Page 8: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/8.jpg)
GRCCopersWater IngressGranite2A DOWL
StaffSecurityAttendant Labour
![Page 9: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/9.jpg)
![Page 10: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/10.jpg)
![Page 11: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/11.jpg)
![Page 12: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/12.jpg)
Safety
Success?
![Page 13: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/13.jpg)
![Page 14: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/14.jpg)
![Page 15: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/15.jpg)
![Page 16: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/16.jpg)
A Good Time to Investigate
Accident Investigation
Significant Event (Investigation after a potentially harmful event)
Time to Talk – investigate something that’s not gone wrong yet….
“Hazardous Event”
![Page 17: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/17.jpg)
• The last 2 months
– September; 2 minor accidents
– October; 1 minor accident, 2no lost time
– November; 1 minor accident
![Page 18: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/18.jpg)
![Page 19: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/19.jpg)
![Page 20: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/20.jpg)
Mission and Values
![Page 21: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/21.jpg)
Our mission …
To collaboratively and safely deliver a new London Bridge Station for the future of
London rail travel – on time, defect free, fully assured
![Page 22: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/22.jpg)
Our medium term goals to successful project completion
Mission
![Page 23: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/23.jpg)
What does success on 2nd January 2018 look like?
• Project Milestones to date achieved
• The station fully operational in all areas defined by Day 1 stage 4
drawings
• HL17 achieved, p1-15 in use
• Northern concourse and Tooley St entrances open
• Western Arcade fully open
• Stage 2A DOWL complete
• Stage 3 DOWL at less than 500
Our medium term goals to successful project completion
Mission
![Page 24: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/24.jpg)
By behaving in the following ways;
• Alignment on one goal incorporating the safety, quality, programme, budget and gain share.
• Openness – both formal and informal, using one set of information supported by cabinet responsibility for the
decisions reached.
• Positivity – To see good and poor performance as opportunities for improvement not to blame.
• Trust – to believe people are aligned and will act in the best interests of the project both when in public and in
private.
• Accountability – linked with conscientiousness, by delivering on your promises.
We know we will have been successful when
• We and our stakeholders are proud to be both associated with and use the beautiful and iconic new station
Values that support the Mission
![Page 25: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/25.jpg)
To collaboratively and safely deliver a new London Bridge Station for the future of London rail travel – on time, defect free, fully assured
We know we will have been successful when : We and our stakeholders are proud to be both associated with and use the beautiful and iconic new station
Alignment
Openness
Positivity
Trust
Accountability
Our Behaviours: What does success on 2nd January 2018 look like?
• Project Milestones to date achieved• The station fully operational in all areas defined by Day 1 stage 4 drawings:
• HL17 achieved, p1-15 in use• Northern concourse and Tooley St entrances open• Western Arcade fully open
• Stage 2A DOWL complete• Stage 3 DOWL at less than 500
Complete First TimeRight First Time
![Page 26: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/26.jpg)
9. Progress Update
![Page 27: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/27.jpg)
27
Progress – Tooley St Facade
![Page 28: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/28.jpg)
28
Progress – Area A Granite / Soffits
![Page 29: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/29.jpg)
29
Progress – Area A Granite / Soffits
![Page 30: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/30.jpg)
30
Progress – Area B / C Granite / Soffits
![Page 31: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/31.jpg)
31
Progress – Area B / C Granite / Soffits
![Page 32: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/32.jpg)
32
Progress – Block C East – 18th Nov
![Page 33: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/33.jpg)
33
Progress – Customer Information Point – 2nd Dec
![Page 34: London Bridge Station Redevelopment Project Team Brief](https://reader035.vdocuments.site/reader035/viewer/2022081612/6157da7fce5a9d02d46fd80e/html5/thumbnails/34.jpg)
How can you influence ….
34
Complete First TimeRight First Time