London 2012 Learning Legacy Programme Monitoring and Control; Change and Baseline Management, Integrated Planning
David Birch Head of Programme Controls CLM
Programme Management Strategy
Integrated Approach to Manage commercial and Delivery Performance
Trusted information to the right people, at the right time which facilitated effective decision making
Active Risk Management to mitigate or control programme strategic or project specific risks
Image
Processes
Integrated Programme
Controls
The Plan & Physical Progress Design, Procurement
and Construction
Commercial Position
Budget, Commitments & Outturn Costs
Financial Position Invoiced and Accrued
Liabilities
Systems A single source of the truth for all programme information
Schedule – Oracle Primavera P6
Cost Management – Deltek Cobra
Actual Cost – Oracle Financials
Accruals – bespoke Programme Cost Management System (PCMS)
Reporting – Data warehouse and presentation/BI tools inc Crystal Reports
PCMS
Oracle Financials
Primavera P6
Data warehouse & presentation tools
Cobra
2012 Programme
Control
Strong Governance Rigorous change control • Approval of individual ‘business cases’ • Monthly Change Board - 6,100 changes
to date • Strict levels of delegated authority • Three lines of defence for contingency
management
Monthly Trend Reviews • Assess maturing risks / contingency burn • AFC glide path to achieve affordability targets
Monthly Performance Reviews • Status and progress (time, cost, quality, priority themes, risks and issues) • Independent assurance using robust, consistent performance information –
focused on the issues • Underpinned by back-to-back contractor reviews
Programme Baseline Established in June 2007, published in November 2007
Initially a ‘top down’ approach
Original Baseline Budget (OBB) agreed November 2007
OBB includes distributed project budget, contingency, and VAT
All projects within the baseline were defined by four elements:
Scope
Schedule
Cost/Budget
Risk
The Programme BASELINE was the basis for performance measurement during execution
The Programme Baseline was formally approved and published
Once approved, was the basis for CHANGE
Base Project Contingency
Programme Contingency (P80)
Funders Contingency (P95)
Total Big Build Completion
OBB £5.15bn £0.98bn £0.97bn £1.0bn £8.1bn 27 Jul 11
Work Breakdown Structure
London 2012 Work Breakdown Structure 69 Reporting Projects 1,000+ WBS Elements Common language across Programme
Programme Change Board - Monthly
Good governance structure that required authorisation for changes
Trends process to show potential changes looming, which gave sufficient time to stop
Control of Change and Contingency
Three contingency pots Project – held within project budgets
available with Change Board approval Programme held by the ODA
accessible with approval to Funders Funders – Held by the Funding bodies
only available by application to Funders
Level 1 Milestones
Programme Critical Paths
P6 Production
Database
Tier 1 Contractor Schedules
Contractor Critical Paths
Labour (hours and cost) Equipment Materials Contracted Services Other
P6 External
Database Resources & NEC Activity List
Schedule Performance & Cost Performance
Reports etc.
Detailed EV % complete
Reviewed by CLM - Summary
Submitted
Actual Cost (via CLM
Cert)
COBRA
Earned Value
Actual Cost
ODA Finance (Oracle)
Integrated Schedule & Performance Management
CLM Integrated Level 2 Schedule
Budget, Forecasting and AFC Risk, Trends & Contingency Management
Cost Planning Phase Delivery Phase (erosion of contingency)
Contingency
Risks
Design and
Construction Costs
ODA Costs CLM Fees
Contingency
Risks
Acknowledged Trends
Unsubstantiated Trends
Mitigated
PM’s Assessment of Unsubstantiated Trends
and Risks
Original Contract Values
Acknowledged Trends
Compensation Events
Potential AFC
QRA (P80) informs level of contingency
allowance
Savings Headroom
Dynamics of Cost and Schedule Data
Baseline • Fixed • Controlled through Change
Management • Reflected current delivery strategies • Aligned with contract s • High Level – Project Milestones and
summarised Cost Loaded activities
Forecast • Dynamic • Reflects contractor current status &
progress • Includes mitigation strategies and
trends • Takes account of integration impacts • Forecasts outturn
Change Control Fed from Trending process
Trending Process Fed from forecast data and enabler for Risk mitigation
Compare Inform
Change
Drive
Monthly Reporting Cycle
Gather data and upload to host systems
Assurance, analysis ,challenge and Project Reports
Executive Management Reviews & Programme Report
Executive Management Board and Change Board
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
F G I J K L M N O P Q R S T
P ID ACTIVITY ID ACTIVITY DESCRIPTION FORECAST MAY11
BASELINE MAY11
FORECAST JUN11
BASELINE JUN11
FORECAST JUL11
BASELINE JUL11
∆ FORECAST JUL11 - JUN11
∆ BASELINE
JUL11 - JUN11
∆ JUL11 FORECAS
T - BASELINE
REASON FOR VARIANCE (FC LAST MONTH - FC THIS MONTH)
EW EWSW7500 COMPLETION STOCKPILE MANAGEMENT OPERATION 04-Jul-11 04-Jul-11 27-Jun-11 04-Jul-11 27-Jun-11 04-Jul-11EW LKAV1050T HANDOVER TO AV - REMAINING MOL 6C AREA 25-Jul-11 25-Jul-11 25-Jul-11 25-Jul-11 25-Jul-11 25-Jul-11
EW LKEW2686T HANDOVER OF ATHLETE'S VILLAGE TRANSPORT MALL (ZONE 6A) FROM EW TO SBH (PROV. 2010) 04-Jul-11 28-Sep-10 04-Jul-11 28-Sep-10 01-Aug-11 28-Sep-10 -28 0 -307 Forecast for handover to SBH on
1st August.
EW EW1000 COMPLETION OF ALL ENABLING WORKS SCOPE 31-Aug-11 - 31-Aug-11 - 31-Aug-11 - 0 #VALUE!
NORTHPARK
LP LKLPR1000T HANDOVER OF HOCKEY PITCH 1 (EXC. EAST STAND) AND HOCKEY PITCH 2 FROM CLM TO LOCOG 15-Jun-11 01-Jul-11 01-Jul-11 01-Jul-11 15-Jun-11 01-Jul-11
LP LKLVZ6.6D1T Z6.6 HANDOVER DUCTS & ELEC EQPT + DT - F03 EAST - NLR (CH.400) - LPR TO UTILITIES 31-May-11 18-Mar-11 28-Jun-11 18-Mar-11 28-Jun-11 18-Mar-11
LP LKLPSEZ6.6T Z6.6 - HANDOVER BASES, DUCTS, PITS & POSTS FOR CCTV - - - - 28-Jun-11 05-Aug-11
LP CLMLPR28301 COMPLETION OF BACK OF HOUSE 4 - PHASE 1 HANDOVER to LOCOG for TEST EVENTS - - 01-Jul-11 - 04-Jul-11 -
LP CLMLPR28302 COMPLETION OF BACK OF HOUSE 4 - PHASE 2 HANDOVER TO LOCOG FOR TEST EVENTS - - 15-Jul-11 - 11-Jul-11 -
LP LKLVZ5.4D1T Z5.4 HANDOVER DUCTS & ELEC EQPT + DT - F02 WEST-L03A - LPR TO UTILITIES 06-Jun-11 31-Mar-11 07-Jul-11 31-Mar-11 13-Jul-11 31-Mar-11
LP LKLVZ6.4D1T Z6.4 HANDOVER DUCTS & ELEC EQPT + DT - F02-B/BALL WEST - LPR TO UTILITIES 31-May-11 14-Jun-11 04-Jul-11 14-Jun-11 13-Jul-11 14-Jun-11
LP LKLVZ6.3D1T Z6.3 HANDOVER DUCTS & ELEC EQPT + DT - VELO WEST & STH / BMX STH - LPR TO UTILITIES 07-Jul-11 21-Jul-11 14-Jul-11 21-Jul-11 29-Jul-11 21-Jul-11
LP CLMLPR2300 COMPLETION OF SOFT LANDSCAPING 7 21-Jul-11 21-Jan-11 27-Jun-11 21-Jan-11 01-Aug-11 21-Jan-11 -35 0 -192All works in SL7 are now complete. Works were previously in delay to revised phasing strategy.
LP CLMLPR2190 COMMENCE BACK OF HOUSE 1 (HOCKEY) 01-Jul-11 15-Jul-10 01-Jul-11 15-Jul-10 01-Aug-11 15-Jul-10 -31 0 -382
Works proceeding in line with accepted programme. Works commenced in all areas of BH1 where handovers have occurred. Due to revised handover strategy some areas of BH1 have not yet started.
LP CLMLPR2260 COMPLETION OF SOFT LANDSCAPING 3 01-Jul-11 01-Mar-11 01-Jul-11 01-Mar-11 05-Aug-11 01-Mar-11 -35 0 -157
All works in SL3 are complete. Only item of remaining works is the final connection of the irrigation booster station to permanent power. This will be completed in August.
LP CLMLPR24001 COMPLETION OF HL9 FOH BASKETBALL FOR TEST EVENT - - 05-Aug-11 - 05-Aug-11 - 0 #VALUE!
Works proceeding in line with accepted programme. Completion dates agreed in line with handover strategy to LOCOG.
LP CLMLPR2310 COMPLETION OF SOFT LANDSCAPING 10 27-Jul-11 14-Feb-11 08-Aug-11 14-Feb-11 05-Aug-11 14-Feb-11 3 0 -172Works progressing in line with accepted programme. Due for completion early August 2011.
LP LKLPSEZ6.4T Z6.4 - HANDOVER BASES, DUCTS, PITS & POSTS FOR CCTV - - - - 12-Aug-11 05-Aug-11 #VALUE! -7
Works being mitigated to achieve handover, but completion of amp base likely to be 19 Aug partially due to late instruction.
LP LKLPSEZ6.3T Z6.3 - HANDOVER BASES, DUCTS, PITS & POSTS FOR CCTV & PA - - - - 12-Aug-11 12-Aug-11 #VALUE! 0
Works proceeding in line with accepted programme. Completion dates agreed in line with handover strategy to ODA/BT.
LP LKLVZ5.2D1T Z5.2 HANDOVER DUCTS & ELEC EQPT + DT - H01 WEST-F02 WEST - LPR TO UTILITIES 29-Jul-11 14-Aug-11 02-Aug-11 14-Aug-11 15-Aug-11 14-Aug-11 -13 0 -1
Works proceeding in line with accepted programme. Completion dates agreed in line with handover strategy to UKPN.
ENABLING WORKS
LANDSCAPE & PUBLIC REALM
Schedule Reporting All Milestone Report ≈700 key milestones in change-controlled Baseline, AMR includes commentary and RAG status
Project Status Report Simple view of project Baseline
Critical Items Report Status/action on issues escalated in schedule integration process
Critical Paths The path or paths that drive project completion
Strategic Plan High-level view of key interfaces and handovers for LOCOG Test Events and security lockdown of Olympic Park
Project Cost Performance Reports At EVM Control Account level
Project Status Report Adds Project Manager’s narrative and variance analysis to raw data
Programme Cost Performance Report Summarises performance data in funding slices
Project and Programme Cost Reports Risk, Trends and Contingency / AFC modelling
Monthly Progress Report Short, simple distillation of status and key issues. Dashboards to communicate key performance trends to Executive
Progress, Performance & Cost Reporting
Key Components of the Project Status Report
Health and Safety
Project Summary and critical issues
Quality Assurance
Design issues and decisions
Performance data (EVM) and cost / EV forecasts
...supported by quantities
Priority themes
Key risks and issues
Baseline milestones and forecasts
Project Cost Report – AFC model
Governance Framework
Mature Programme Controls Schematic
Tailored reports to support
Governance decision points
Key Meeting
Key Meeting
Functions (Design, Town Planning, SHQE, etc) and Stakeholder defined
priority themes
Contract Admin
(inc Procurement)
Change Control
Risks, Issues and Trends
Schedule & Integration
Cost Engineering
Enterprise Accounting Co
ntro
lled
Perf
orm
ance
M
anag
emen
t Bas
elin
e WBS
WBS
Approved Changes
Contractor Project Team
Contractor Project Team
Contractor Project Team
Com
mon
pro
cess
es &
tool
s de
fined
in
Cont
ract
Wor
ks In
form
atio
n
Perf
orm
ance
D
ata
Contractor Project Team
Performance
Data
Reporting hub for analysis
Data with
Narrative
Data
with
Nar
rativ
e
2006 2007 2008 2009 2010 2011 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Controls Building Blocks in Place
Baseline developed & Yellow Book Published
Culture & Trust Established
Systems Maturing
Change Control implemented
Monthly & Quarterly Reviews
Trending Process
AFC process
Monthly Trend Reviews
Monthly Trend & AFC Reviews
Simplify Baseline
Schedule Integration maturing
Support & Training
Assurance, Support & Intervention (where necessary)
Align Reporting
Maturity Timeline
Big Build; Completion Big Build; Structures Big Build; Foundations Design, Dig, Demolish
Controls mature and
fully functional
Lessons Learned Agree on a ‘single source of the truth’ to fuel the Governance process
Align the reporting / governance calendar across the Programme team
Agree the detailed content of reports early and evolve to suit phase
Keep it short and simple – avoid jargon, concise and graphic exception reporting, invest time in analysis
Use data analytics but discuss only the issues and what to do about them
Keep Baseline high-level and ensure Forecast is dynamic and integrated
When fully functional an ‘Earned Value System’ is the key to success
If Projects fail to Perform, the Plan needed to change
Executive Management must accept the need to keep the plan current and approve any major plan ‘corrections’ before bringing Changes forward
Differentiators
Flexibility
Systems adjusted to suit the phase
and nature of construction
Simplicity Clear, concise and graphic reporting
Data analytics but report on the issues
‘No Surprises’ Culture Comprehensive Baseline
Spot and mitigate risks and issues early Leading to effective management of scope,
cost & schedule
Controlling Delivery
£800m returned to Funders:
• £50m efficiency savings early site works
• £120m of value engineering savings
• £150m of procurement gains
...and the balance in risks successfully mitigated and contingencies released