PROJECT BUILDING HOI AN CITY
AS ECOCITY
THE PEOPLE’S COMMITTEE OF HOI AN CITYOF HOI AN CITY
THE MAJOR PREMISE FOR ESTABLISING THE PROJECT BUILDING HOI AN CITYAS ECOCITY
THE MAJOR PREMISE FOR ESTABLISING THE PROJECT BUILDING HOI AN CITYAS ECOCITY
THE REGIONAL RELATION
Internal region Hoi An city belongs to Quang
Nam province, located on the central coast of Viet Nam
Has the Cultural heritage site and Biosphere Reserve in national and international levels.
The Economic structure: Tourism – Services – Commerce,Industry, small scale industry, agriculture.
External region Hoi An City is about 30km
south of Da Nang city and about 50km north of Tam Ky city and in the major economic region of Central Viet Nam
Be contiguous with East – West Economic Corridor and has the very advantageous position for connecting to many economic regions in the North, South, High-land, Vietnam – Laos border gates, etc.
POTENTIALITY AND ORGANIC BIOLOGICAL DIVERSITY
1. Has a biological diversity system
2. Cham Island Marine Protected Area.
3. Coconut –palm tree ecosystem in Cam Thanh village
4. The diversified sand dune system
5. Awarded 02 honourable names for best conservation in international level.
6. Supported by many national and international governmental and non-governmental organizations
Some requirements for sustainable development in Hoi An
Ensuring the balance between economic development and conservation.
Building the circulative, safe and friendly society.
MODELMODEL
ECO-CITYECO-CITY(The appropriate model for Hoi An City (The appropriate model for Hoi An City
at present and in the future)at present and in the future)
CH
OS
ING
TH
E A
PP
RO
PR
IAT
E D
EV
EL
OP
ME
NT
AL
MO
DE
L
LONG-TERM PLAN
ORIENTATION
INTERNATIONAL INTEGRATION INTERNATIONAL INTEGRATION AND INTERNAL FORCE PROMOTIONAND INTERNAL FORCE PROMOTION
INTERNATIONINTERNATION
JICA, UNIDOJICA, UNIDO,,
UNESCO (Heritage, UNESCO (Heritage, Biosphere Reserve, Biosphere Reserve,
Geological Park, Geological Park, Memory, Material,... Memory, Material,...
…) UNHABITAT, …) UNHABITAT, IUCN, Asean…IUCN, Asean…
NATIONNATION
QN Provincial QN Provincial People’s CommitteePeople’s Committee
Hoi An City People’s Hoi An City People’s CommitteeCommittee
Danh hiệu / CertificateDanh hiệu / Certificate
TECHNICAL ADVISE AND ASSISTANCETECHNICAL ADVISE AND ASSISTANCE
PARTNER AND NETWORK DEVELOPMENTPARTNER AND NETWORK DEVELOPMENT
PERIODIC AND YEARLY REPORTSPERIODIC AND YEARLY REPORTS
NATIONAL RESPONSIBILITY (INTERNATIONAL CONVENTIONS)NATIONAL RESPONSIBILITY (INTERNATIONAL CONVENTIONS)
04/19/23 [email protected] 9
3R services and management to wastewater, solid waste, etc. such as MRF, Sewerage system
Utilities: clean water, clean energy, etc.
RESIDENT & COM’L
CERAMICVILLAGE
HOTELS
RESTAURANTS
CRAFTTOUR OPERATOR
BUSES
BOATS VEGEVILLAGE
THE LAW OF VALUE EXPLOITATIONTHE LAW OF VALUE EXPLOITATION
Giai đoạn chưa được công nhận Giai đoạn tăng trưởng nhanh Giai đoạn khai thác tối đa Giai đoạn đi xuống
Tổng giá trị kinh tế
Thời gian
IMPORTANCE OF IMPORTANCE OF MANAGEMENTMANAGEMENT
Not recognized period Speedy growth periodMaximum exploitation periodMaximum exploitation period Down-grade period
Economic overral worth
Time
11
HOI AN RESIDENTS AND
COMMERCIAL ESTABLISHMENTS
1MTOURISTS
RESOURCES INPUT
PRODUCT SERVICES
= GDP+ENVI+ HAPPINES
HOI AN CITY PEOPLE’S COMMITTEESTRATEGIC VISION OF ECO CITY
Minimum non-product
LANDSCAPE MANAGEMENTLANDSCAPE MANAGEMENT
Landscape Ecology (Spatial arrangement basing on the connections)
Interdisciplinary and Multi-field Management
Knowledge Economy: Modelization Tool and Scenario Development
ECO-ECONOMYECO-ECONOMY
Harmonious Integration between Using and Conservation of Ecological Services (provide, advise, culture)
Knowledge content in every product: less material, minimum pollution
Quality Economy (Eco-label, eco-quality,…)
ECO-RESIDENCEECO-RESIDENCE
Harmonizing between residence and nature (internal and external)
Ecological Group and Creative Ecology
Awareness and Eco-resident behaviour
ECO-CULTUREECO-CULTURE
System of values between people together and between people with nature
Indigenous culture and cultural exchange (focus and diffuse)
Cultural and Ecological diversity
HARMONIOUS COMMUNITYHARMONIOUS COMMUNITY
Properietary and collective awareness
Social and ecological durability
Blood-relationships, village regulations and laws
SCIENTIFIC MANAGEMENTSCIENTIFIC MANAGEMENT
Applying Systematic Thought in Management
Analyzing underlying reasons and measures (theory of drift-ice)
Developing scenario basing on reality.
Problem:Surface, float
Operation processes for raising problem
Underlying reasonsof problem
PROCESS OF PROJECT ESTABLSHMENT
Hoi An City Committee of the Party has issued the Article 275-CV/TV dated May 16, 2008 on assigning tasks for building criteria of Ecology – Culture and Tourism Hoi An city.
Some relevant authorities cooperated together for compiling the plan of “the project on building Hoi An as a eco town” (renamed as “the project on building Hoi An city as Ecocity”
PROCESS OF PROJECT ESTABLSHMENT
On Sept 24th, 2008, as proposed by Department of Resource and Environment, Hoi An People’s Committee has issued the Decision No 3266/QD-UBND on establishing the compiling group of the project for building Hoi An city as Ecocity.
On Nov 8th, 2008, the seminar on Hoi An Ecocity is organized by Hoi An People’s Committee. Its purposes aim to get the opinions for the project on building Hoi An city as Ecocity
The draft project has been implemented one year later. The Scientific Symposium on Building Hoi An city as Ecocity ( supported by Akzonobel Paint Company)
PROCESS OF PROJECT ESTABLSHMENT
On Dec 12th, 2009, The People Council of Hoi An City has issued the specialized resolution No11/2009/NQ-HĐND on building Hoi An City as Ecocity
IMPLEMENTATION SCHEDULE
2021-2030
2016-2020
2009-2015
Sustainable development ecocity
TOTAL OF INVESTMENT BUDGET
BUDGET FOR ESTABLSHING PROJECT
BUDGET FOR IMPLEMENTING PROJECT
TOTAL BUDGET
21,450 20,790,700 20,812,150
UNIT: MILLION VND
IMPLEMENTATION RESULTS OF 37 COMPONENT PROJECTS
Obtained results:
- 18 projects (including 11 approved projects, among of them 10 projects have been carried out)
- Preparing 05 projects.
- Drafting 04 projects.
IMPLEMENTATION PROGRESS PROJECTS ON IMPROVING THE NATURAL
ENVIRONMENT
N0 Name of project/planningImplemented
agencyNotes
1Infrastructure and underground system planning, modernization and multi-function
Dept. of City Management
Not yet planed
2 City green trees planningDept. of City Management
Be planning
3 City traffic network planning Dept. City Management
Be planning
4 Project on environmental information systemDept. of Resource and Environment
Be planning
5 Project on sewage gathered treatment Public Work Company
Be implementing
6 Project on garbage gathered treatmentPublic Work Company
Be implementing
7 Project on hospital garbage treatment Public Work Company
Be implementing
8Planning on dyke and embankment system and digging canals.
Dept. of Economy Be drafting
9 Project on minimizing traffic dustDept. of Resource and Environment
Not yet planed
10 Project on minimizing noise in ancient town Dept. of Resource and Environment
Not yet planed
IMPLEMENTATION PROGRESS PROJECTS ON IMPROVING THE NATURAL
ENVIRONMENT
N0 Name of project/planningImplemented
agencyNotes
11 3R projectDept. of Resource and Environment
Be planning
12Project on moving environmental polluted production enterprises out residential area.
Dept. of Resource and Environment
Not yet planed
13Project on capacity building for protecting environment in enterprises
Dept. of Resource and Environment
Be implementing
14 Project on minimizing household garbage Dept. of Resource and Environment
Be implementing
15 Project on minimizing nylon bag usingDept. of Resource and Environment
Be implementing
16Project on teaching environmental education programme in school.
Dept. of Resource and Environment
Be implementing
17Environmental hygienic garbage dump Construction Project.
Dept. of Resource and Environment
Not yet planed
18City WC system and public garbage bin Construction Project
Public Work Company
Not yet planed
19Project on capacity building for protecting environment in community.
Youth Union Carried out
IMPLEMENTATION PROGRESS PROJECTS ON SOCIAL ENVIRONMENT
N0 Name of project/planningImplemented
agencyNotes
1Project on continue for building Hoi An as cultural city.
Dept. of Culture and Information
Be implementing
2Master plan on Hoi An Ancient town’s values preservation, reconstruction and promotion
Hoi An CCHMP
Not yet planned
3Project on teaching history and culture of Hoi An in school.
Hoi An CCHMP
Be implementing
4Project on capacity building in intangible heritage activities.
Hoi An Center for Culture and Sports
Be implementing
IMPLEMENTATION PROGRESS SUSTAINABLE DEVELOPMENT PROJECTS
N0 Name of project/planningImplemented
agencyNotes
1 City space planning Dept. of City Management
Not yet planned
2 City land using planning Dept. of Resource and Environment
Not yet planned
3 The sustainable development tourism planningDept. of Tourism and Commerce
Be planning
4 Biosphere Reserve ProjectDept. of Resource and Environment
Be implementing
5 City population planning Dept. of Heath Not yet planned
6Running Water Supply Network and Reserves Planning of City
Dept. of City Management
Be implementing
7Mineral Management and Exploitation Planning
Dept. of Resource and Environment
Be implementing
IMPLEMENTATION PROGRESS SUSTAINABLE DEVELOPMENT PROJECTS
N0 Name of project/planningImplemented
agencyNotes
8Water Resource Management and Exploitation Planning
Dept. of Resource and Environment
Be planning
9 Architectural Construction Planning of City Hoi An CCHMP Be planning
10Industrial and agricultural economy planning
Dept. of EconomyBe drafting
11Project for using clean energy source in Cham Island
Cham Island Marine Protected Area Management Board
Not yet planned
12Project on Cham Island Marine Protected Area
Cham Island Marine Protected Area Management Board
Finished and operated
13 Project on ecology preservation of CityDept. of Resource and Environment
Be planning
14Project on Risk Preparedness caused by natural disaster
Dept. of Economy Be drafting
OBSTACLES, DIFFICULTIES AND CHALLENGES IN IMPLEMENTING PROJECT ONBUILDING HOI AN CITY AS ECOCITY
OBSTACLES, DIFFICULTIES AND CHALLENGES IN IMPLEMENTING PROJECT ONBUILDING HOI AN CITY AS ECOCITY
OBSTACLES
- The approved component projects are few in number (only 11/37 projects, 29%);
- The relative professional agencies and local authorities have not yet coordinated closely to implement synchronously, systematic some major works of project.
- Issuing the implementation guideline and supervising, assessment of the implementation are not carried out frequency…
DIFFICULTIES AND CHALLENGES
OBJECTIVE Worldwide Climate
change Not learnt on some past
successful models
POSITIVE Poor Human Capacity/
Finance Not have synchronous
policy from national to local level.
Not connected projects together.
Inertia in Management Thought