Page 1: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

LNF activities on WPC

• Panels • Construction of prototypes and layout

• Status of tooling

• Proto 0, open items, plan, ...

Page 2: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

First long panel (M3R3) produced on last Thursday, measured on Friday.

Quite satisfactory (within specs). No border effects, except in one point, where O-ring to avoid foam leakage was uncorrectly mounted.

Some small improvements under way (better foam mixing). More panels under construction to test reliability of production.

Meanwhile we proceed for construction of mould for stations M4, M5 (drawings ready)

Mechanical characterization nearly completed in Potenza

Page 3: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,
Page 4: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,
Page 5: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

Some more mechanics is needed to move easily the top cover of the mould and speed up operations, together with cooling system

To study and to setup :• production and quality controls procedures (at the

company and at home)• production time plan• optimization of no. of moulds vs cost and production time:

• M3R3 (done), M5R2 (all R1 & R2 panels), all smaller panels obtained by cut ? Build also M2R3 ? • About 5000 panels to be produced : @ 2/hour =

70 weeks (to be verified)

Page 6: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

Status of 3 protos

• All closed with glue, under HV training. In air up to 3.2 kV, 0 nA. Up to now, no problems.

• Soon after HV training, gain scan with source and equip with ASDQ. Bring to test beam in May.

• We are satisfied with geometry and construction procedures:

HV bars at 2.5 mm level, 5 mm spacers, closing bars with protection for HV traces, cathode ground planes with no traces, gas bars with economic nipples for plastic pipes with

independent I/O per each gap, no screws, only reference holes at the 4 corners

Page 7: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

New type of glue (3M DP460) for chamber closing

Araldite not good for structural gluing (does not attach on copper Fr4 plates). DP460 is tixthropic and can be handled for a while (few hours curing) : very strong attachement

Two methods

1. “or-ing” of glue: a calibrated amount all around the frame

2. “peripheral”: glue on the outside part of the chamber, to seal against gas leaks

Both methods fast and easy, although (2) seems better, but...

Page 8: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

In a chamber glued on the periphery, we observed dark current (few nA) with wet atmospheric conditions, due toglue between outer traces and ground plane

panel

panel Wire bar

glue

May be this is due only to bad surface cleaning, but we want to investigate better this effect.

No problems (no current) with the other gluing.Not yet fully tested the real gas leakage (not measurable with present setup: much less than 1 bubble/min)

HV traces

ground

Page 9: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

Wire Tension Measurement

Test done with 1 channel (KLOE /Atlas method) and “hand movement ”- 16 channels unit with serial interface under production

Probe (100 m Al wire)

WPC wires to ground

Mechanical frame and automated movement needed

Page 10: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

Status of other tooling / other activities (LNF)

• Tools for chamber assembly and gluing under definition:reference bars with ventouses, chariots, working tables, shelfs, etc...

• Wiring machine: we started to copy Fe & CERN ones

• Assembly clean area (delayed): civil works will start in May, ready in summer

Page 11: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

• Soldering machine : final cabling, ctrls and second head (to be used for proto 0)

• Drawings for all PNPI-INFN chambers (10 types)

• HV cards: 3 cards to fit all regions (prototypes ready to be tested)

• Mechanics of muon system: ready to mount the wall (half of M2)

Page 12: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

Steps to INFN proto 0

M3R3 Pads, HV bars, closing bars, gas bars ordered (pads and HV bars in 3 pieces to be joined)Material for panels available

ASDQ and SPB ordered and under arrivalHV cards to be prepared

Ferrara wiring machine adapted to M3R3Plan to wire in Ferrara, bring to LNF, solder and closeWork to be done in May-June, test in August

Meanwhile, as M4M5 mould is ready, prepare above steps for proto M5R2

Page 13: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

Open items :

• Wire choice (Toshiba vs Luma; Kloe had positive experience with Luma, 70 km, inspection tests)• Gas flow and connections (as simple as possible!, plastics)

• Quality tests after closing : gas leakage, source test, CR (see Rome 1 contribution)

• 2002 and beyond production plan and material procurement

Page 14: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

Cost update

• quotation on pads (in 3 pieces, one side, R3) around 100 FS/pad

• quotation on HV bars : 40 FS/m

These prices can be lower for large production, and the company could produce long elements if needed

• gas bars (large #, Fr4, machined) : 6 FS/unit

• closing bars (large #, Fr4, machined) : 10 FS/m

Prices in agreement with previous table costs

Page 15: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,
Page 16: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

Jan02 apr jul oct Jan03

Definition of constr. Elements XConstr. Of proto 0 (1) X X X XConstr. Of proto 0 (2) X X X X XPreseries Production X X X XPRR XX

Preparation of Prod. Centers X X X X X Xclean areas

wiring machinesoldering machine

quality controlsCR test stand

Setup of Prod. Centers X X X XTests of Proto 0 X X X X X

Tooling for panels (1) XTooling for panels (2) X X XPreproduction of panels XEnd of panel qualification X X XXPanel production X X X X X X X XEDR XX

Material Procurements X X X X X X

Page 17: LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,

0.05 l/h

50cc/60min

1cc/min in 75 litri