lmps_louie_strunz
TRANSCRIPT
-
8/8/2019 LMPs_Louie_Strunz
1/6
Locational Marginal Pricing in North American Power SystemsMr. Henry Louie, University of Washington, USA
Prof. Kai Strunz, Technische Universitt Berlin, Deutschland
Abstract
The methodology used in the pricing of electrical energy is a fundamental characteristic of electricity market design.
In deregulated North American power systems the utilization of locational marginal pricing is the dominant approach
to pricing electrical energy. Locational marginal prices (LMPs), which are spatially and temporally distinguished nodal
pricesbased uponshort-run marginal costs, reflect economicandphysical realities of thepower systemas well as operating
constraints. In addition, LMPs can be used to ascertain transmission congestion costs and are often included in ancillary
service market clearing or settlement calculations. It is therefore requisite to understand the fundamentals of LMPs to be
able to analyze deregulated North American power system economics. In this paper, the concept, calculation, utilization
and practical application of LMPs as well as a thorough educational illustration are provided.
1 IntroductionThe North American power system served approximately
4,926 TWh of electrical energy to customers in the U.S.,
Canada and Mexico in 2006 [1]. In the U.S. and Canada,
the majority of the load is procured through market trans-
actions in the geographic footprint of Regional Trans-
mission Organizations (RTOs), which are independent,
revenue-neutral entities charged with, among other respon-
sibilities, maintaining system reliability and market over-
sight [2]. Market designs differ amongst RTOs; however,
a characteristic common to many is the utilization of lo-
cational marginal prices (LMPs) for electrical energy pric-ing [3].
Locational marginal pricing, which is based on the short-
run marginal cost of supplying energy, was developed in
the 1980s [4, 5, 6] and has grown to be the dominant
method of pricing energy in electricity markets in North
America that operate under the auspices of an RTO [7, 3,
8, 9, 2]. The use of LMPs has grown because the phys-
ical constraints of the system and economic realities are
accurately represented. The resulting LMPs can be readily
utilized to price transmission and to determine congestion
costs. This paper formulates the concept of LMPs in an
educational manner and provides details on their practicalcalculation and utilization in North American power sys-
tems.
Currently, nodal LMPs are utilized in four North America
RTOs: Midwest Independent System Operator (MISO),
New England RTO, New York ISO (NYISO) and the
Pennsylvania-Jersey-Maryland Interconnection (PJM) [2].
In addition, LMPs are included in the new market designs
to be fully implemented in the California ISO (CAISO) in2008 and in the Electric Reliability Council of Texas (ER-
COT) in 2009 [8]. Other markets rely on bilateral transac-
tions, zonal pricing, or the last cleared generation offer to
set electricity prices. The impetuses for the adoption of the
LMP-basedpricing are to achieve greater marketefficiency
and to more accurately represent the price of transmission
and the cost of congestion [8, 9].
The LMPs are computed for each node and market period
in both the forward and balancing energy markets. The
forward energy market is typically for a period one day
ahead, commonly called a day-ahead market. The LMPs
are utilized in the market settlement processes to determinegenerator payments and load charges by multiplying the
amount of energy produced or consumed at a node by the
LMP at that node. In addition, LMPs are used in ancillary
service calculations and to price transmission and manage
congestion and therefore the understanding of their cal-
culation is crucial in North American power system eco-
nomic analyses.
The paper is arranged as follows. In Section 2, the concept
of locational marginal pricing is introduced. In Section 3,
the practical calculation of LMPs is formulated. In Sec-
tion 4, an educational illustration of LMP calculation is
demonstrated on a four-bus study system considering theeffects of congestion. Conclusions are drawn in Section 5.
2 Concept
The concept of locational marginal pricing is to assign the
price of energy based on the short-run marginal cost of
-
8/8/2019 LMPs_Louie_Strunz
2/6
supply. In so doing, economic signals for system opera-
tion are provided, including costs of congestion. An anal-
ogous formulation of LMP calculation for reactive power
is possible; however, real power is the focus of this paper
as reactive power and other component costs of supplying
energy are compensated in ancillary service markets and
market settlement procedures [3, 6].
The short-run marginal cost at a node is equal to the change
in optimal economic cost associated with supplying an
additional increment of load at that node. This value is
readily available from the Lagrangianmultiplier associated
with the nodal real power balance equation at the solution
to the N-node Optimal Power Flow (OPF) problem:
min {f(PG,PD)} (1)
where
f(PG,PD) =Ni=1
CG,i(PG,i) Ni=1
CD,i(PD,i) (2)
and CG,i(PG,i) is the generator cost as a function of the
real power output of a generator at node i, PG,i, and
CD,i(PG,i) is the dispatchable load cost as a function of
the real load at node i, PD,i. Nodes without generation or
without load have the respective PG,i or PD,i values set
equal to zero. This optimization is subject to:
g(x) = 0 (3)
h(x) 0 (4)
where x is a vector of the optimization variables, which
include generator power output and dispatchable load; and
g(x) and h(x) are equality and inequality constraints,
respectively. The equality constraints are composed of
the nodal power balance equations, whereas the inequality
constraints are the voltage, branch power flow and genera-
tor maximum and minimum output limitations.
The definition of the LMPthe cost of serving an ad-
ditional increment of load at a nodeis equivalent in
meaning to that of the Lagrangian multiplier of the real
power balance equationat the node at the optimal solution.
Therefore, the LMP for node j is:
LMPj =
p,j (5)
wherep,j is the Lagrangianmultiplier at the optimal solu-
tion to (1) associated with the real power balance equation
at node j. Obtaining the LMP from the OPF implicitly
includes voltage, transmission and generation constraints
that affect the economics of the delivery of energy in a
transparent fashion.
3 Practical Calculation
Solving (1) for each market period is not practical in most
market applications due to computational and implemen-
tation requirements. Therefore, in practical application
the simplified dc system model is used in LMP calcula-
tions [7]. Differences in specific LMP calculation method-
ologies between the RTOs dictate that a specific method
be delineated hereafter, though it is noted that similar ap-
proaches are used in other markets.
In the following formulation, theLMPcalculation is reflec-
tive of the method utilized in the PJM market, which is se-
lected due to its prominence as the worlds largest electric-
ity market and its lengthy experience with LMPs [7]. The
most notable influenceof this method is the omission of the
lossesand theutilizationof a dc systemmodel [10]. Losses
can be ignored without significant inaccuracy if they are
small in value, as in the case of tightly meshed systems in-
dicative of certain regions of North America. In addition,
generation offers and load bids and not costs are utilized in
the calculation.
The LMP at a given node can be decomposed into the
marginal cost of generation based upon generator offers,
congestion costs and marginal loss costs [6]. Consistent
with the dc model, marginal loss costs are ignored and the
LMP for node j can then be expressed as:
LMPj = s Kk=1
kk,j (6)
where s is the marginal price of generation at the refer-
ence node, K is the number of branches, and k is the
shadow price of the congestion of branch k. Conceptually,
the shadow price, k, is the change in cost due to an in-
cremental relaxation of the constraint on branch k. The In-
jection Shift Factor (ISF) [11], k,j , is the fraction of real
power that flows on branch k due to a unit production of
powerat nodej and consumptionof power at the reference
node under dc assumptions. A derivation of ISF calcula-tion is reserved in the Appendix. The sum of products of
k and k,j is the congestion cost.
The variables s and k are Lagrangian multipliers whose
values are determined from solving an incremental linear
optimization around a given operating point. The oper-
ating point in terms of real power produced, PG,j , and
consumed, PD,j , at each node j is based upon the sched-
uled dispatch and load in the day-ahead market and is in-
put from a state-estimator in balancing markets. Nodes
without generation or without load have the corresponding
PG,j and PD,j values set equal to zero.
The objective of the incremental optimization in the prac-tical LMP calculation of an N-node system is:
min
Ni=1
OG,i(PG,i) Ni=1
OD,i(PD,i)
(7)
where PG,i and PD,i are the changes in real power
production and consumption from the operating point, and
-
8/8/2019 LMPs_Louie_Strunz
3/6
OG,i(PG,i) and OD,i(PD,i) are the offers and bids as-
sociated with the changes, respectively. The hypothetical
changes to power production and consumption must re-
spect the power balance equation, generator and dispatch-
able load limits:
Ni=1
PG,i Ni=1
PD,i = 0 (8)
PminG,j PG,j PmaxG,j j (1, . . . ,N ) (9)
PminD,j PD,j P
maxD,j j (1, . . . ,N ) (10)
where the superscript max and min refer to the maximum
and minimum changes to real power production and con-
sumption at each node, respectively. In addition to the con-
straints in (8)(10), the limitations on branch flow must be
obeyed:
Fmaxk Ni=1
{(PG,i + PG,i)k,i}
N
i=1
{(PD,i + PD,i)k,i} Fmaxk k (1, . . . , K )
(11)
where Fmaxk is the magnitude of the maximum power flow
limit on branch k. In certain markets, only branches at or
approaching their limits are included in (11).
Solving (7) produces the Lagrangianmultiplierss and k.
The Lagrangianmultiplier,s, is associated with the power
balance equality constraint (8), whereas k is associated
with branch power flow constraint. There is a k for each
constraint in (11).
A consequence of utilizing the dc system model is that
voltage, stability and reactive power constraints cannot beexplicitly modeled. In practical application, these con-
straints are approximately represented and enforced in
LMP calculation as real power branch flow constraints.
4 Educational Illustration
A four-bus study system is used to demonstrate the prac-
tical calculation of LMP under two scenarios: Uncon-
strained Case and Constrained Case. It is shown that in the
Unconstrained Case, the only non-zero component com-
prising the LMP is the marginal generationpriceand hencethe LMPs are uniform. In the Constrained Case, conges-
tion in the network results in non-zero and non-uniform
congestions costs and there is differentiation in LMP. The
illustration also shows that the definitionof the LMP as the
cost to serve an additional increment of demand at each
node is equivalent to (6) if linear generator energy offer
functions are utilized.
4.1 Study System Parameters
The study system is comprised of four buses and four
branches with equal reactances of 0.10 p.u. The corre-
sponding ISFs for a unit of power produced at each bus
with Bus 1 arbitrarily selected as the reference is shown in
Table 1.
Table 1: Injection Shift Factors
Injection Branch Terminus Buses
Bus 12 23 24 43
1 0 0 0 0
2 1 0 0 0
3 1 0.667 0.333 0.333
4 1 0.333 0.667 0.333
Table 1 is interpreted as follows. Concerning the second
row, if1 MW of power is injected in Bus 2 and withdrawn
from the reference bus, Bus 1, then 1 MW would flow from
Bus 2 to Bus 1. No power would flow on any other branchdue to this injection. Therefore, since the ISF are direc-
tional, there is a 1 in the second column and zeros in the
third through fifth columns. For the third row, the power
flow resulting from an injection of 1 MW of power into
Bus 3 divides between the branches in accordancewith the
branch impedances enroute to the reference bus. Account-
ing for the direction of the ISFs defined in Table 1 and due
to the equal branch impedances, one third the power flows
from Bus 3 to Bus 4 and then to Bus 2; two thirds of the
power flows from Bus 3 to Bus 2. The entire unit of power
flows from Bus 2 to Bus 1. The elements in Table 1 for the
other bus injections are calculated in a similar fashion.
The system has three generators, whose technical and eco-
nomic data are shown in Table 2. In this educational il-
lustration, it is assumed that generator offers are linear,
as described by the coefficient c1 and that the load is not
dispatchable. Differentiation of the generator offer with
respect to power for each generator gives the offer-based
marginal generation cost which is used in LMP calcula-
tion. It is also assumed that the market period is one hour.
For the purposes of clarity in illustration, voltage limits and
losses are ignored.
Table 2: Generator Data
Gen. c1 Pmax Pmin
Bus ($/MW) (MW) (MW)
1 20 500 0
3 25 200 0
4 30 200 0
-
8/8/2019 LMPs_Louie_Strunz
4/6
4.2 Unconstrained Network
The calculation of the LMP is intuitively demonstrated by
determining the change in total cost of supplying energy
when the demand is independently increased at each bus
by 1 MW for one hour. The dispatch, load and resulting
branch flows are shown in Fig. 1 with a resulting total pro-
duction cost of $8, 000, which is found by evaluating the
generator offer functions at the given dispatch.
1
4
32
100 MW 300 MW
0 MW
200 MW
100 MW100 MW
0 MW
0 MW400 MW
Figure 1: Illustrative 4-bus system for the unconstrained
case.
The LMP at Bus 1 is calculated by assuming a hypotheti-
cal load of1 MW is present at Bus 1. The least cost hy-
pothetical dispatch that serves the load is to increase the
power output of Generator 1 by 1 MW to 401 MW, thus
increasing the operating costs to $8,020an increase of
$20. Therefore the LMP at Bus 1 is $20/MWh. A visual-
ization of this LMP calculation is provided in Fig. 2.
1
4
32
100 MW 300 MW
0 MW
200 MW
100 MW100 MW
0 MW
0 MW401 MW
1 MW
Figure 2: Conceptualization of LMP calculation for Bus 1.
For Bus 2, an increase of load to 101 MW can be economi-
cally met by increasing the power output of Generator 1 to
401 MW, resulting in an increase in operatingcosts by $20.Therefore the resulting LMP of Bus 2 is also $20/MWh. In
fact, since there are no constraints and marginal losses are
ignored, the LMP at each node is equal to $20/MWh. This
result is applicable to any system with like conditions.
This intuitive result is now compared with (6). Solving (7)
yields a s value equal to $20 and k equal to zero for
all branches k. Therefore, from (6) the LMP is equal to
$20/MWh at all buses.
The results for the Unconstrained Case are summarized in
Table 3. The absence of congestion or other constraints
has lead to uniform LMPs equal to the marginal generation
cost of $20/MWh. From the last two columns of Table 3, it
is seen that money charged to the loads equals the money
credited to the generators. Therefore, the RTO remains
revenue neutral and there are no congestion costs.
Table 3: Unconstrained Case Results
LMP Generation Load Credit Charge
Bus ($/MWh) (MW) (MW) ($) ($)
1 20 400 8,000 0
2 20 100 0 2,000
3 20 0 300 0 6,000
4 20 0 0 0 0
Total 8,000 8,000
4.3 Constrained NetworkThe next scenario examined includes a branch power flow
constraint. Assume that the real power flow on branch 43
is limited to 50 MW and that the dispatch, load and result-
ing branch flows of the system are shown in Fig. 3. The
production cost for this dispatch is $8,750.
1
4
32
100 MW 300 MW
0 MW
100 MW
50 MW50 MW
0 MW
150 MW250 MW
Figure 3: Illustrative 4-bus system for the constrainedcase.
The LMP for Bus 1 and 2 are the same as in the uncon-
strained case as Generator1 cansupplyoneadditional MW
of power without violating the branch limit. However, if
the load at Bus 3 is increased to 301 MW, Generator 1 can-
not supply additional power since it would cause the powerflow on branch 43 to increase past its limit to 50.333
MW. Instead, power must come from the next cheapest
power sourceGenerator 3whose increased power out-
putto 151 MW does not affect the power flow on branch 4
3 if the load is concomitantly increased to 301 MW. There-
fore, the production cost increases to $8,775an increase
of $25, and hence the LMP at Bus 3 becomes $25. The vi-
-
8/8/2019 LMPs_Louie_Strunz
5/6
sualization for this LMP calculation is provided in Fig. 4.
1
4
32
100 MW 301 MW
0 MW
100 MW
50 MW50 MW
0 MW
151 MW250 MW
Figure 4: Conceptualization of LMP calculation for Bus 3.
Finally, in order to serve an additional MW of load at Bus
4 at the lowest production cost, Generator 1 increases its
power output by 2 MW to 252 MW and Generator 3 de-
creases its power output by 1 MW to 149 MW, as shown in
Fig. 5. The resulting power flow on branch 43 in this case
is 50 MW and the net result is an increase in production
cost by $15. Therefore the LMP at Bus 4 is $15/MWh.
Note that this value is less than the offer of any generator.
1
4
32
100 MW 300 MW
1 MW
101 MW
50 MW51 MW
0 MW
149 MW252 MW
Figure 5: Conceptualization of LMP calculation for Bus 4.
Solution of (7) yields s equal to $20 and a non-zero kfor branch 43 of $15. Since the ISFs for Bus 1 and 2 onto
branch 43 are zero, the LMP is equal to $20/MWh. For
Bus 3, the ISF is equal to 0.333 so that the LMP becomes
$25/MWh in accordance with (6). In similar fashion, the
LMP for Bus 4 is computed to be $15/MWh. Therefore,
the results are identical to the approach of increasing the
demand by 1 MW at each bus.
The results for the Constrained Case are summarized in
Table 4. The presence of congestion has caused differen-tiated LMPs equal to the marginal generation cost as de-
termined from generation offers plus the congestion costs.
From the last two columns of Table 4, it is seen that money
charged to the loads is greater than the money credited
to the generators. The congestion costs are equal to the
difference between the money charged and credited and
is equal to $750. Quantifying the congestion cost in this
manner is a significant advantage of LMPs and allows
for loads to hedge against high energy prices through fi-
nancial instruments such as Financial Transmission Rights
(FTRs) [12, 7].
Table 4: Constrained Case Results
LMP Generation Load Credit Charge
Bus ($/MWh) (MW) (MW) ($) ($)
1 20 250 5,000 0
2 20 100 0 2,000
3 25 150 300 3,750 7,500
4 15 0 0 0 0
Total 8,750 9,500
5 Conclusions
Locational marginal pricing is a powerful and elegant tool
that is commonly used in electricity markets in the U. S.
and Canada. The method of assigning nodal prices based
upon short-run marginal costs, which is interpreted as the
cost of serving the next increment of demand at each nodein the system, is intuitive and adequately reflects system
constraints and economics. Based upon this definition, the
LMP at a node is equal to the Lagrangian multiplier asso-
ciated with the real power balance equation at that node.
In practice however, a simplified dc model is employed
and the LMP can be determined from an incremental lin-
ear program by adding the offer-based marginal generation
cost at the reference node with congestion costs, as shown
in this paper.
The calculation of LMPs for a four-bus study system for
constrained and unconstrained operation illustrated an in-
tuitive method for calculating LMPs and demonstrated theutility in LMPs to determine congestion costs. The con-
gestion costs are determined from the differences in LMPs
between two nodes and are used to economically manage
congestion through the use of financial instruments such as
financial transmission rights.
The use of Injection Shift Factors (ISFs) is a computation-
ally efficient method of determining the impact of changes
in generation or load on branch power flow under dc as-
sumptions.
In accordance with the linear problem formulation, the to-
tal real power flowing on any branch under dc assumptions
is found by:
F = H (12)
where F is a vector of branch power flow, H is a matrix
of coefficients that relate the node voltage angles,, across
a branch to the power flowing on that branch. The ele-
ments ofH are determined from the bus impedance ma-
trix. Since there is a linear relationship between the bus
-
8/8/2019 LMPs_Louie_Strunz
6/6
voltage angles and the net power injection at a node, it is
possible to calculate the amount that a particular nodes
net power injection contributes to the flow on any branch.
Therefore (12) can be expressed as:
F = Pnet (13)
wherePnet is a vectorof net power injections at each node.
The net power injected is equal to PG minus PD at each
node. For an N-node system with Kbranches the matrix,
, is a concatenation of ISFs arranged as:F1...
FK
=
1,1 1,N
......
1,N K,N
Pnet,1
...
Pnet,N
(14)
wherek,j is the injection shift factor from a nodej onto a
branch k and Fk is the real power flow on branch k whose
terminal nodes are p and q. The ISF is computed as:
k,j =zpj zqj
xk(15)
where xk is the simple reactance of branch k and zpj and
zqj are the elements of the node impedance matrix under
dc assumptions [11].
References
[1] Monthly energy statistics, International Energy
Agency, Paris, France, Sept. 2007.
[2] Federal Energy Regulatory Commis-
sion. (2007, Dec.) Regional Transmis-
sion Organizations (RTO)/Independent Sys-
tem Operators (ISO). [Online]. Avail-
able: http://www.ferc.gov/industries/electric/indus-
act/rto.asp
[3] R. Baldick, U. Helman, B. Hobbs, and R. ONeill,
Design of efficient generation markets, Proceed-
ings of the IEEE, vol. 93, no. 11, pp. 19982012,
Nov. 2005.
[4] F. C. Schweppe, M. C. Caramanis, R. D. Tabors, and
R. E. Bohn, Spot Pricing of Electricity. Norwell,
MA, USA: Kluwer Academic Publishers, 1988.
[5] M. C. Caramanis, R. E. Bohn, and F. C. Schweppe,
Optimal spot pricing: Practice and theory, IEEE
Transactions on Power Apparatus and Systems, vol.
101, no. 9, pp. 32343245, Sept. 1982.
[6] Y. Song and X. Wang, Eds., Operation of Market-
Oriented Power Systems. London, UK: Springer,
2003.
[7] A. Ott, Experience with PJM market operation, sys-
tem design and implementation, IEEE Transactions
on Power Systems, vol. 18, no. 2, pp. 528534, May
2003.
[8] J. Yu, Locational marginal pricing in ERCOT mar-
ket, in IEEE PES General Meeting, Montral, QC,
Canada, June 1822, 2006, pp. 13.
[9] J. E. Price, Market-based price differentials in zonal
and LMP market designs, IEEE Transactions on
Power Systems, vol. 22, no. 4, pp. 14861494, Nov.
2007.
[10] J. Grainger and W. Stevenson, Power System Analy-
sis. New York, NY, USA: McGraw-Hill, Inc., 1994.
[11] P. W. Sauer, K. E. Reinhard, and T. J. Overbye, Ex-
tended factors for linear contingency analysis, in
Proceedings of the 34th Hawaii International Con-
ference on System Science, Maui, HI, USA, 2001, pp.
697703.
[12] W. Hogan, Financial transmission rights formula-
tions, Kennedy School of Government, Harvard
University, Mar. 2002.