Listado de criticos Referencia: M2 Sector Estado Aprovechamiento (%) Esfuerzos Nx Ny Nxy Mx My Mxy Qx Qy Cimentación - Losa 1 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 113.52 95.03 120.17 90.21 69.42 17.94 412.80 -51.95 412.80 33.79 -1055.71 368.34 28.08 2.63 28.08 1.66 -68.90 24.53 -26.31 91.27 -26.31 86.73 77.87 5.36 0.00 1.82 -6.93 -0.02 -36.95 --- -0.88 0.31 -0.88 0.29 0.94 --- 0.06 0.11 0.06 0.09 0.46 --- --- --- --- --- --- 4.37 --- --- --- --- --- -2.92 Losa 1 - Losa 2 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 78.00 72.28 85.75 75.70 64.26 19.87 288.27 114.71 276.07 276.07 -836.38 176.03 14.12 -1.58 31.21 31.21 -100.39 18.94 -16.19 68.81 -24.53 -24.53 -1.24 -16.48 0.00 0.00 -7.54 -7.54 -29.27 --- -1.04 -0.56 -2.04 -2.04 2.56 --- 0.70 0.20 0.50 0.50 -0.95 --- --- --- --- --- --- 5.82 --- --- --- --- --- -0.01 Losa 2 - Losa 3 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 241.64 296.73 242.49 316.82 71.19 75.83 -809.66 -302.11 -809.66 -302.11 -868.01 172.03 85.32 190.12 85.32 190.12 0.32 -17.89 55.26 146.98 55.26 146.98 68.58 -55.35 -28.34 10.57 28.34 -14.70 -30.38 --- -4.76 -2.93 -4.76 -2.93 -7.26 --- 1.95 -0.13 1.95 -0.13 -2.33 --- --- --- --- --- --- 20.32 --- --- --- --- --- 19.22 Losa 3 - Losa 4 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 63.41 61.37 144.56 79.35 80.97 37.30 219.55 182.51 -479.97 206.93 -771.57 206.93 -5.45 25.15 9.56 31.27 -92.93 31.27 -28.86 -36.03 42.99 -28.97 -6.27 -28.97 0.00 0.00 12.00 -6.40 -19.29 --- 0.04 -1.07 -6.20 -1.97 3.69 --- 0.30 0.44 0.07 -0.16 -1.81 --- --- --- --- --- --- 7.49 --- --- --- --- --- 0.47 Losa 4 - Losa 5 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 106.60 120.32 105.61 72.52 75.18 37.57 -341.82 -261.99 -261.99 -261.99 -792.97 83.13 50.29 56.52 56.52 56.52 -32.79 11.45 24.26 27.41 27.41 27.41 34.38 -22.28 8.55 6.55 6.55 -6.55 -19.82 --- 0.24 0.08 0.08 0.08 0.38 --- -0.84 -0.71 -0.71 -0.71 -0.24 --- --- --- --- --- --- 6.38 --- --- --- --- --- 0.27 Losa 5 - Losa 6 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 256.75 507.56 258.85 560.83 98.39 359.34 -623.60 -175.60 -623.60 -175.60 -384.58 41.50 57.40 226.77 57.40 226.77 57.36 -42.88 49.24 143.36 49.24 143.36 1.52 -39.28 -15.59 4.39 15.59 -8.22 -9.61 --- -0.97 -1.29 -0.97 -1.29 -0.96 --- 1.72 -2.32 1.72 -2.32 -0.35 --- --- --- --- --- --- 48.59 --- --- --- --- --- 30.80 Losa 6 - Losa 7 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 96.46 161.58 173.80 77.70 91.18 60.23 -229.67 -144.49 -414.00 -185.16 -686.49 67.33 48.32 30.60 -4.07 30.12 -96.92 21.43 11.31 33.83 27.49 66.88 -9.37 40.16 -4.59 2.89 8.28 -3.70 -13.73 --- -0.14 6.00 -5.74 0.88 1.69 --- -0.58 0.05 0.16 -0.12 -1.49 --- --- --- --- --- --- 7.93 --- --- --- --- --- -0.48 Losa 7 - Losa 8 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 123.90 97.86 123.37 124.44 80.42 60.54 -294.09 -125.34 -294.19 49.94 -602.82 11.96 45.56 30.15 43.10 15.05 -76.44 -36.92 9.68 33.10 7.40 -52.86 -0.11 -28.21 -5.88 2.51 5.88 -3.21 -12.06 --- 0.07 6.63 0.11 -0.71 0.74 --- -0.85 0.23 -0.84 0.46 -0.27 --- --- --- --- --- --- 12.96 --- --- --- --- --- 7.94 Losa 8 - Losa 9 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 88.08 101.38 117.92 125.28 90.65 66.20 -244.77 -111.78 -281.21 -200.77 -281.21 -13.59 20.32 32.06 47.57 61.75 47.57 -39.89 62.98 32.27 5.61 9.23 5.61 -24.94 -4.90 2.24 5.62 -4.02 -5.62 --- 1.46 6.88 0.09 -0.30 0.09 --- 0.29 0.26 -0.91 -0.72 -0.91 --- --- --- --- --- --- 13.74 --- --- --- --- --- 8.26 Losa 9 - Losa 10 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 115.65 106.73 169.66 141.25 84.48 30.65 -274.58 -103.23 -274.53 -196.75 -262.08 -124.67 52.97 35.04 55.80 63.83 51.03 -60.65 2.52 30.73 1.60 5.37 3.93 -9.20 -5.49 2.06 5.49 -3.93 -5.24 --- 0.08 7.33 0.05 -0.31 -0.00 --- -1.06 0.29 -1.05 -0.85 -0.98 --- --- --- --- --- --- 18.11 --- --- --- --- --- 11.65 Losa 10 - Losa 11 Arm. vert. der. Arm. horz. der. Arm. vert. izq. Arm. horz. izq. Concreto Arm. transve. 174.99 125.35 209.56 125.09 82.38 35.66 -240.18 -61.51 -240.18 -19.06 -513.35 -160.65 55.05 44.34 55.05 9.02 -1.22 -59.05 -4.83 33.87 -4.83 -57.10 41.44 -22.13 -4.80 1.23 4.80 -2.93 -10.27 --- 0.08 6.45 0.08 -0.64 0.25 --- -1.38 -0.04 -1.38 1.16 -0.47 --- --- --- --- --- --- 17.55 --- --- --- --- --- 12.87

Upload: jordan2588

Post on 26-Sep-2015

214 views

Category:

Documents


1 download

DESCRIPTION

Listado de Criticos

TRANSCRIPT

  • Listado de criticos

    Referencia: M2Sector Estado Aprovechamiento (%) Esfuerzos

    Nx Ny Nxy Mx My Mxy Qx Qy Cimentacin - Losa 1 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    113.5295.03120.1790.2169.4217.94

    412.80-51.95412.8033.79-1055.71368.34

    28.082.6328.081.66-68.9024.53

    -26.3191.27-26.3186.7377.875.36

    0.001.82-6.93-0.02-36.95

    ---

    -0.880.31-0.880.290.94

    ---

    0.060.110.060.090.46

    ---

    ---------------

    4.37

    ---------------

    -2.92Losa 1 - Losa 2 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    78.0072.2885.7575.7064.2619.87

    288.27114.71276.07276.07-836.38176.03

    14.12-1.5831.2131.21-100.3918.94

    -16.1968.81-24.53-24.53-1.24-16.48

    0.000.00-7.54-7.54-29.27

    ---

    -1.04-0.56-2.04-2.042.56

    ---

    0.700.200.500.50-0.95

    ---

    ---------------

    5.82

    ---------------

    -0.01Losa 2 - Losa 3 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    241.64296.73242.49316.8271.1975.83

    -809.66-302.11-809.66-302.11-868.01172.03

    85.32190.1285.32190.120.32-17.89

    55.26146.9855.26146.9868.58-55.35

    -28.3410.5728.34-14.70-30.38

    ---

    -4.76-2.93-4.76-2.93-7.26

    ---

    1.95-0.131.95-0.13-2.33

    ---

    ---------------

    20.32

    ---------------

    19.22Losa 3 - Losa 4 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    63.4161.37144.5679.3580.9737.30

    219.55182.51-479.97206.93-771.57206.93

    -5.4525.159.5631.27-92.9331.27

    -28.86-36.0342.99-28.97-6.27-28.97

    0.000.0012.00-6.40-19.29

    ---

    0.04-1.07-6.20-1.973.69

    ---

    0.300.440.07-0.16-1.81

    ---

    ---------------

    7.49

    ---------------

    0.47Losa 4 - Losa 5 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    106.60120.32105.6172.5275.1837.57

    -341.82-261.99-261.99-261.99-792.9783.13

    50.2956.5256.5256.52-32.7911.45

    24.2627.4127.4127.4134.38-22.28

    8.556.556.55-6.55-19.82

    ---

    0.240.080.080.080.38

    ---

    -0.84-0.71-0.71-0.71-0.24

    ---

    ---------------

    6.38

    ---------------

    0.27Losa 5 - Losa 6 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    256.75507.56258.85560.8398.39359.34

    -623.60-175.60-623.60-175.60-384.5841.50

    57.40226.7757.40226.7757.36-42.88

    49.24143.3649.24143.361.52-39.28

    -15.594.3915.59-8.22-9.61

    ---

    -0.97-1.29-0.97-1.29-0.96

    ---

    1.72-2.321.72-2.32-0.35

    ---

    ---------------

    48.59

    ---------------

    30.80Losa 6 - Losa 7 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    96.46161.58173.8077.7091.1860.23

    -229.67-144.49-414.00-185.16-686.4967.33

    48.3230.60-4.0730.12-96.9221.43

    11.3133.8327.4966.88-9.3740.16

    -4.592.898.28-3.70-13.73

    ---

    -0.146.00-5.740.881.69

    ---

    -0.580.050.16-0.12-1.49

    ---

    ---------------

    7.93

    ---------------

    -0.48Losa 7 - Losa 8 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    123.9097.86123.37124.4480.4260.54

    -294.09-125.34-294.1949.94-602.8211.96

    45.5630.1543.1015.05-76.44-36.92

    9.6833.107.40-52.86-0.11-28.21

    -5.882.515.88-3.21-12.06

    ---

    0.076.630.11-0.710.74

    ---

    -0.850.23-0.840.46-0.27

    ---

    ---------------

    12.96

    ---------------

    7.94Losa 8 - Losa 9 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    88.08101.38117.92125.2890.6566.20

    -244.77-111.78-281.21-200.77-281.21-13.59

    20.3232.0647.5761.7547.57-39.89

    62.9832.275.619.235.61-24.94

    -4.902.245.62-4.02-5.62

    ---

    1.466.880.09-0.300.09

    ---

    0.290.26-0.91-0.72-0.91

    ---

    ---------------

    13.74

    ---------------

    8.26Losa 9 - Losa 10 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    115.65106.73169.66141.2584.4830.65

    -274.58-103.23-274.53-196.75-262.08-124.67

    52.9735.0455.8063.8351.03-60.65

    2.5230.731.605.373.93-9.20

    -5.492.065.49-3.93-5.24

    ---

    0.087.330.05-0.31-0.00

    ---

    -1.060.29-1.05-0.85-0.98

    ---

    ---------------

    18.11

    ---------------

    11.65Losa 10 - Losa 11 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    174.99125.35209.56125.0982.3835.66

    -240.18-61.51-240.18-19.06-513.35-160.65

    55.0544.3455.059.02-1.22-59.05

    -4.8333.87-4.83-57.1041.44-22.13

    -4.801.234.80-2.93-10.27

    ---

    0.086.450.08-0.640.25

    ---

    -1.38-0.04-1.381.16-0.47

    ---

    ---------------

    17.55

    ---------------

    12.87

  • Sector Estado Aprovechamiento (%) Esfuerzos Nx Ny Nxy Mx My Mxy Qx Qy

    Losa 11 - Losa 12 Arm. vert. der.Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    161.79111.62217.14113.5872.54

    117647.06

    -185.75-26.72-249.17-62.74-224.68-340.41

    51.1224.94-8.137.99-8.17-80.13

    3.8228.84-2.83-55.623.9245.39

    -3.721.024.98-2.674.49

    ---

    0.267.47-6.76-0.65-6.48

    ---

    -1.700.150.971.380.96

    ---

    ---------------

    16.22

    ---------------

    9.96Losa 12 - Losa 13 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    148.87140.78246.35166.1087.60

    117647.06

    -171.45-22.76-283.41-106.27-272.16-312.42

    52.2127.40-1.6460.42-2.23-81.16

    3.8223.40-2.233.894.8152.00

    -3.431.005.67-2.135.44

    ---

    0.376.41-5.64-0.10-5.80

    ---

    -1.45-0.040.52-1.160.54

    ---

    ---------------

    16.42

    ---------------

    10.23Losa 13 - Losa 14 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    133.74136.40180.77160.3787.38

    117647.06

    -154.18-13.11-210.75-90.28-271.48-294.33

    50.0126.37-4.0358.30-1.50-80.23

    2.7722.00-18.473.541.4549.22

    -3.080.974.22-1.815.43

    ---

    0.406.20-5.98-0.06-5.55

    ---

    -1.42-0.030.86-1.140.53

    ---

    ---------------

    16.41

    ---------------

    10.02Losa 14 - Losa 15 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    117.57129.45225.38150.8281.89

    117647.06

    -135.77-4.60-259.28-78.80-254.41-274.68

    47.0825.01-2.2354.25-1.81-79.56

    1.8620.38-0.814.582.5247.96

    -2.720.915.19-1.585.09

    ---

    0.455.85-5.78-0.00-5.85

    ---

    -1.39-0.020.64-1.120.67

    ---

    ---------------

    16.37

    ---------------

    9.86Losa 15 - Losa 16 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    102.58124.53215.06142.7761.19

    117647.06

    -118.71-41.60-247.52-66.97-190.10-254.48

    44.1721.73-2.2051.34-1.96-78.78

    1.4848.45-3.724.275.0447.05

    -2.371.474.95-1.343.80

    ---

    0.511.77-5.450.05-5.90

    ---

    -1.370.370.61-1.100.80

    ---

    ---------------

    16.30

    ---------------

    9.67Losa 16 - Losa 17 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    98.73119.36207.31144.4257.39

    117647.06

    -114.90-32.83-238.56-1.66-178.30-234.37

    41.1619.88-1.2518.17-2.09-78.61

    -1.4846.13-0.2338.255.2346.52

    -2.301.484.77-3.013.57

    ---

    0.561.71-6.05-0.69-5.85

    ---

    -1.340.370.850.050.81

    ---

    ---------------

    16.31

    ---------------

    9.50Losa 17 - Losa 18 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    87.36117.25139.09120.2643.636.89

    -100.83-22.85-161.47-2.89-264.77-102.63

    28.8324.322.0518.22-0.1715.46

    1.5424.87-12.9038.92-33.70-18.93

    -2.020.463.23-3.025.30

    ---

    0.831.75-5.74-0.69-0.85

    ---

    -0.790.560.120.030.43

    ---

    ---------------

    11.66

    ---------------

    -6.33Losa 18 - Losa 19 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    76.16103.51120.14113.7339.704.74

    20.68-38.63-139.89-33.36-241.98-195.49

    -26.933.740.586.334.63-36.36

    6.5445.92-12.3747.43-27.23-24.52

    4.421.982.80-2.134.84

    ---

    1.050.99-5.40-0.91-0.97

    ---

    0.430.160.18-0.310.23

    ---

    ---------------

    9.08

    ---------------

    -1.02Losa 19 - Losa 20 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    79.41118.76111.5189.3036.224.72

    27.81-30.30-129.24-32.36-221.06-186.86

    -25.423.990.166.434.17-35.45

    5.1640.68-10.4644.17-21.02-22.91

    3.892.002.58-2.174.42

    ---

    0.931.07-5.06-0.93-0.90

    ---

    0.380.240.19-0.320.28

    ---

    ---------------

    9.01

    ---------------

    -0.98Losa 20 - Losa 21 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    68.04112.2682.60128.3134.224.69

    -9.58-25.38-99.43-64.50-193.55-173.21

    -37.471.432.586.66-62.56-34.66

    18.2340.21-13.6644.714.84-21.09

    6.382.021.99-2.8313.39

    ---

    1.461.05-4.53-1.152.96

    ---

    0.450.190.23-0.331.67

    ---

    ---------------

    8.99

    ---------------

    -0.94Losa 21 - Losa 22 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    72.70102.7774.05115.0630.624.66

    -6.11-16.2633.55-62.69-163.12-154.91

    -35.841.323.177.13-60.78-33.54

    20.0334.6116.6739.043.60-18.56

    6.172.03-0.54-2.8013.38

    ---

    1.421.09-0.11-1.132.95

    ---

    0.380.23-0.34-0.251.68

    ---

    ---------------

    8.93

    ---------------

    -0.88Losa 22 - Losa 23 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    77.12155.9971.67121.9226.815.06

    5.2423.9833.8623.98-162.34-141.02

    11.8551.6943.3451.69-19.32-29.17

    35.2318.8812.8118.880.35-24.56

    1.600.340.000.00-6.95

    ---

    1.821.991.701.99-1.30

    ---

    0.19-0.69-0.70-0.69-0.15

    ---

    ---------------

    5.71

    ---------------

    -7.90

  • Sector Estado Aprovechamiento (%) Esfuerzos Nx Ny Nxy Mx My Mxy Qx Qy

    Losa 23 - Losa 24 Arm. vert. der.Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    122.70171.2074.7788.4024.084.70

    1.4726.0838.4126.08-148.39-83.46

    -45.3545.596.4645.59-5.30-19.81

    15.8615.9212.2815.923.44-13.87

    6.770.36-0.800.002.97

    ---

    1.681.74-0.251.74-1.15

    ---

    0.15-0.68-0.28-0.680.26

    ---

    ---------------

    6.17

    ---------------

    -6.60Losa 24 - Losa 25 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    129.74152.07115.9182.7020.814.36

    5.7429.371.7329.37-19.75-60.35

    -43.8141.29-0.1741.292.61-18.41

    13.6112.9914.1412.9933.61-10.62

    6.850.37-5.540.00-2.04

    ---

    1.701.56-1.061.56-0.85

    ---

    0.22-0.65-0.61-0.65-0.50

    ---

    ---------------

    5.68

    ---------------

    -6.18Losa 25 - Losa 26 Arm. vert. der.

    Arm. horz. der.Arm. vert. izq.Arm. horz. izq.ConcretoArm. transve.

    160.09158.49109.50205.7730.71

    117647.06

    36.6430.7330.7330.73-41.35-14.90

    -81.5660.2160.2160.21-73.51-20.89

    -2.1813.0413.0413.0455.88-11.04

    15.500.00-0.43-0.436.19

    ---

    3.80-0.49-0.49-0.493.35

    ---

    3.08-0.99-0.99-0.99-0.23

    ---

    ---------------

    10.20

    ---------------

    -12.53

    Aprovechamiento: Nivel de esfuerzos (relacin entre el esfuerzo mximo y el admisible). Equivale al inversodel coeficiente de seguridad.Nx : Axial vertical (t/m).Ny : Axial horizontal (t/m).Nxy: Axial tangencial (t/m).Mx : Momento vertical (alrededor del eje horizontal) (tm/m).My : Momento horizontal (alrededor del eje vertical) (tm/m).Mxy: Momento torsor (tm/m).Qx : Cortante transversal vertical (t/m).Qy : Cortante transversal horizontal (t/m).