link
TRANSCRIPT
What is a substation? What is a substation?
Location for automatic protective devicesInterconnects transmission linesPermits switching of system equipment. Directs flow of power Detects and isolates faulted system
components.
04/12/231
A properly planned and designed substation is essential for the reliable operation of the electric system.
Design ObjectivesDesign Objectives
04/12/23
2
•Achieve reliability and flexibility
•Satisfy electric system requirements
•Minimizing investment costs
Needs DeterminationNeeds Determination
04/12/233
The existing “Electric System” is analyzed to determine the need to build new or improve existing substation facilities.
Design Design ConsiderationsConsiderations
04/12/234
Analysis ParalysisAnalysis Paralysis
04/12/235
Through the planning process, system studies are conducted in order to properly design the substation.
CostsCosts
04/12/236
Substations are capital-intensive construction projects that require long term strategic planning.
BudgetingBudgeting
Preliminary equipment layouts ballpark the costs and establish the broad requirements.
Real-Estate Site, size, and location affect the bottom line.
Long lead Items - ordered ahead of time. Financing Bond issues
04/12/237
Basic single line designBasic single line design
Develop a single line of the station and bus configuration.
General concept of substationPhysical layout and location of major
equipment and steel structuresEquipment and materials specifications Electrical and safety clearances based on
IEEE standards
04/12/238
IEEE 1427 Guide for Recommended Electrical Clearances and Insulation Levels in Air Insulated Electrical Power Substations.
Bus Configurations Bus Configurations
04/12/239
Physical layoutPhysical layout
Indoors? Indoors the standard is Metal Clad Arc Flash IEEE
1584 guide to determine the arc flash hazard distance to which employees could be exposed during their work.
Gas insulated switchgear (GIS) Indoor Outdoor
Outdoors? Air insulated High profile Low profile
04/12/2310
Substation FootprintSubstation Footprint
Equipment foundations and plot plan. Locations of equipment and how they are connected to
each other. Physical orientation of the substation on site Incoming and outgoing power lines. Electrical clearances based on basic insulation level Spacing between equipment Equipment installation, maintenance and removal
access. Vehicle and personnel access
04/12/2311
IEEE 1427™, “Guide for Recommended Electrical Clearances and Insulation Levels in Air Insulated Electrical Power Substations.
Basic Impulse Level (BIL)Basic Impulse Level (BIL) Lightning, circuit breakers and high voltage switches can
create voltage surges that can be very damaging to electrical equipment.
The basic impulse level “BIL” of equipment measures its ability to withstand surges and indicates dielectric strength.
When power system components are designed with sufficient clearances and insulation to withstand these surges, the design is known as the Basic Impulse Level.
BIL dictates the phase to phase and phase to ground clearances and minimal spacing between components. 14.4kV = 110 BIL 69kV = 350 BIL 230kV = 900 BIL 04/12/23
12
Component SpacingComponent Spacing
04/12/2313
System kV BIL kV A B C D E F G H I J K L N P
230 1050 13 13 18 18 48 24 24 22 17 17 20 48 18 262
Structure LoadsStructure LoadsDesigned for mechanical and electrical forces.Seismic loadsDead loads
Line support, switches, insulators, phase wires, potential transformers
Wind loadsOperating loadsShort circuit forces
04/12/2314
FoundationsFoundations
Foundations transmit loads from structures and equipment to soils
Many soil types require different designs.Identify geotechnical information requiredSoil boring plan and specificationsLab testingGeotechnical reportConcrete design
04/12/2315
Essential Ground Design ElementsEssential Ground Design Elements
1. Data for soil resistivity, fault clearing times, and fault magnitude. 2. Conductor and ground rod layout, location of shield wires and
feeder neutrals.3. Know the material used and the depth of burial. 4. More ground rods and larger grids reduce the touch and step
potentials.5. Safe designs are required by IEEE 80, 81 and the NESC
04/12/2316
The metal to metal touch voltages between metallic objects or structures bonded to the ground grid is assumed to be negligible. However, the metal to metal touch voltages between metallic objects bonded to the grid and not bonded to the grid may be substantial.
IEEE 80-2000 Guide for Safety in AC Substation Grounding
Step and TouchStep and TouchPrimary purpose is to assure that “during fault
conditions” a person in the vicinity is not exposed to critical electric shock. The design must reduce the voltage individuals receive when they are in contact with equipment during fault conditions
04/12/2317
Protective RelayingProtective Relaying
Modern relays are Intelligent Electronic Device’s (IED) that replace older electro-mechanical relays
Detect abnormal or undesirable system operating conditions
Initiate operation of circuit-interrupting devices
Provide remote control and data monitoring
04/12/2318
Protection ZonesProtection Zones
Based on the single line there will be multiple zones of protection which protect the equipment inside the substation.
In the event of a fault being detected. The protective relays determine the fault location and open the circuit breakers clearing the fault.
Initiate back-up protection operations when necessary.
04/12/2319
Surge protectionSurge protection
Substation design involves more than installing circuit breakers, transformers, and relays. Significant capital investment and reliability standards require attention to prevent surges (transient voltages) from entering the facility. These surges can be direct lightning strokes on the substation or on connected transmission lines.
1. Evaluate significance of facility being protected.2. Evaluate geographical thunderstorm exposure.3. Design suitable system of protection. 4. Evaluate the cost and effectiveness of the design.
04/12/2320
IEEE Std. 998-1996, Guide for Direct Stroke Shielding
Seismic ThoughtsSeismic Thoughts
Prior to 1970 seismic requirements were minimal.Equipment commonly includes brittle materials such as porcelain. When two or more structures are mechanically linked by electrical
conductors, they will interact with each other.Equipment may be installed with little or no slack for a “clean”
look. Ideally, link the equipment so the two components can move
independently.
04/12/2321
IEEE Std 693 - 2005 IEEE Recommended Practice for Seismic Design for Substations
Material & Equipment Material & Equipment SpecificationsSpecifications
IEEEA document that specifies, in a complete, precise, and
verifiable manner, the requirements, design , behavior, or other characteristics of a system component.
04/12/2322
TransformersTransformers
Oil cooling230-69kV Wye-Delta Connection +/- 30 degrees69-12kV Delta-Wye Connection +/- 30 degrees
04/12/2323
IEEE C57.12.36, Standard Requirements for Liquid-Immersed Distribution Substation Transformers
Air insulated Circuit breakersAir insulated Circuit breakers Make, break and carry normal load currents. Make and break abnormal currents (short circuit).
http://animatedmanuals.com/S2%20anim.html Dissipates the energy in the arc by lengthening and cooling
the arc before interrupting at current zero Live or dead tank design
04/12/2324
Gas insulated Switchgear “GIS”Gas insulated Switchgear “GIS”
Conductors are enclosed in a metallic housing in which a compressed gas sulfa hexafluoride (SF-6) is the primary insulating system
Compact, multi-component assembly of breakers and buses.
No live parts meets arc flash requirements.
04/12/2325
C37.123-1991 IEEE guide to specifications for GIS
Disconnect SwitchesDisconnect Switches
04/12/2326
Non-load breaking device designed to open and close an electric circuit.
Isolate major equipment from the electric system and provide a visible open.
Capacitor BanksCapacitor Banks
04/12/2327
Primary purpose is power factor correction.
Back-to-back switching can produce high peak transient in-rush current values.
These currents can exceed the available fault current levels at the bus.
These currents can damage substation equipment
Appropriate precautions taken during the design process.
Capacitor bank transient currents, based on ANSI/IEEE C37.012-1979
Control houseControl houseLocated to minimize cable lengthsCable entry method basement or cable
trench. Grade higher so that water runs away. Provides weather proof and temperature
control for equipment. Control panels grouped by voltage level and
sized for future expansion.Block wall offers best design and cost.Location of Station Batteries
04/12/2328
Station BatteriesStation BatteriesBatteries provide control power to switching andsubstation components in times of an Ac power loss.
04/12/2329
All critical control power comes from the DC System.
Instruments and MetersInstruments and Meters
04/12/2330
Current Transformer…An instrument transformer intended to have its primary winding connected in series with the conductor carrying the current to be measured or controlled
Environmental ConcernsEnvironmental Concerns
Storm water runoff occurs when precipitation from rain flows over the ground.
Hard surfaces like driveways, sidewalks, and streets prevent storm water runoff from naturally soaking into the ground.
All new construction shall have storm water provisions so rain water settles into the ground and does not flow out to the street.
04/12/2331
Substation CommunicationsSubstation Communications
04/12/2332
Fiber optics is the communication backbone that interconnects the substations for line relaying.
Substation AutomationSubstation Automation
04/12/2333
Substation SecuritySubstation SecurityNERC requires utilities to implement physical
security measures at their critical substations to safeguard personnel and prevent unauthorized access to critical assets and control systems.
Physical security typically comprises five distinct systems:
1. Delay/Deterrence 2. Detection3. Assessment4. Communication5. Response
04/12/2334
Testing hits the mark
The End Thank YouCommissioning TestsCommissioning Tests04/12/23
35