LINK 2000+ update Datalink Implementation EC Regulation 29/2009 ICAO WGM#20 Montreal, 23-25 January 2013 Liviu Popescu on behalf of Søren Dissing Link Central Reporting Office

Upload: jafari

Post on 19-Mar-2016

36 views

Category:

Documents


0 download

DESCRIPTION

LINK 2000+ update Datalink Implementation EC Regulation 29/2009. ICAO WGM#20 Montreal, 23-25 January 2013. Liviu Popescu on behalf of Søren Dissing Link Central Reporting Office. 29/2009 Key Dates. Aircraft Forward Fit. ANSPs LINK/Core Region. Aircraft Retrofit Fit. ANSPs All of EU. - PowerPoint PPT Presentation

TRANSCRIPT

LINK 2000+ updateDatalink ImplementationEC Regulation 29/2009

ICAO WGM#20 Montreal, 23-25 January 2013

Liviu Popescu on behalf of Søren DissingLink Central Reporting Office

2

29/2009 Key Dates

2009 2010 2011 2012 2013 20162015

1st Jan 2011 5th Feb 2015

Aircraft Forward Fit

2014

Aircraft Retrofit Fit

ANSPs All of EU

ANSPs LINK/Core Region

7th Feb 2013

3

Incentives Status

Some delays in Equipage, Cert (Re-Cert) Issues

Funded by TENT-EACirca 500 aircraft to be equipped

Scheme now closed

4

Total impact – 4.6 % of flights exemptedDoes not impact DLS-IR target 75% of flights

Final applicant submission End 2012 >> 3rd Report & Final Decision

DLS-IR Exemptions - Status

1st Report to European Commission Nov 2010 >> SSC Decision May 2011No Temporary Exemptions beyond Dec 2012

Max. 940 aircraft permanently exempted

2nd Report Sep 2011 >> SSC Decision Dec 2011Max. 2820 aircraft permanently exempted

No impact on Dates for Ground Implementation i.e. 2013 “core” Europe and 2015 rest of Europe

5

Ground Implementation Status...2013 States

Today: MUAC and DFS are operational

6

Ground Implementation Status...2013 States

Feb 2013: Skyguide and NAV Portugal

7

Ground Implementation Status...2013 States

Q2/2013: NATS

8

Ground Implementation Status...2013 States

Q4/2013: ENAV

9

Ground Implementation Status...2013 States

Q1/2014: IAA

10

Ground Implementation Status...2013 States

Q4/2014: Austrocontrol

11

Ground Implementation Status...2013 States

Q4/2015: AENA

12

Ground Implementation Status...2013 States

2016…2019: DSNA

13

• For the CRO

• Maintained by all CRO members

• Less formal, less control

• Forum for asking questions

Knowledge Management

• For the Programme

• Maintained by EUROCONTROL

• Official source for Programme documents

• FAQs for official answers

Wiki Website

www.eurocontrol.int/link2000www.eurocontrol.int/link2000/wiki

14

LINK 2000 Website Library

Official information

• Regulation• Community Specifications• Eurocontrol Documents

• Eurocontrol Specification• OPS guidance• TECH guidance

15

LINK 2000 Wiki

For the CRO community

• Deployment Status• Current Issues• Problem Reporting• CRO library• Forum

16