lime and cement block 3

Upload: ea53

Post on 03-Jun-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Lime and Cement Block 3

    1/18

    &

    &

    Initial Set, Final Set & Hardening

    Initial set - provides an estimate of when (in hours &

    minutes) the concrete has reached the point where it

    has stiffened to such an extent that it can no longer

    be (vibrated) without damaging the concrete. This is

    roughly equivalent to a penetration resistance (using

    a weighted needle) of 3.4 MPa.

    Under hot weatherconditions, the time to initial

    set will be shorter than under

    normal temperatures, which

    will affect the construction

    crews ability to consolidate &

    finish the in-place concrete.

    Under cold weather

    conditions the time to initial

    set is extended.

    Concrete Penetrometer

    for determination of settingtime of the mortar fraction

    of fresh concrete. Spring

    loading device graduated

    from 2 to 150 lbs.

    Stainless steel needle

    points of 650, 325, 160,

    65, 32, and 16 mm area.

  • 8/12/2019 Lime and Cement Block 3

    2/18

    Final set - is roughly equivalent to a penetration resistance (weighted

    test needle) of 27.6 MPa at which point the concrete has reached acompressive strength of around 0.6 MPa and it could carry some

    measurable loads.

    Initial Set, Final Set & Hardening

    Soon after mixing, if insufficient sulfate is available (in solution in the

    pore fluid) from the added gypsum to slow the hydration of C3A, the

    resulting rapid hydration of the C3A produces AFm phase (e.g.

    monosulfate) in the form of hydroxy-AFm.

    These crystals link up the particles (cement, aggregate, hydrates) in the

    mix & quickly cause the mix to become unworkable. This is termed a flash set. The rapid hydration of the C3A results in

    the evolution of much heat. Concrete strengths where flash setting has

    occurred may be lower than normal.

    Flash set v.s. False set

  • 8/12/2019 Lime and Cement Block 3

    3/18

    Conversely, if an excess of sulfate is present in the form of hemihydrate

    (possibly caused by high mill temp.), the hemihydrate dissolves & then re-precipitates as gypsum.

    Again, the growth of gypsum crystals cause a rapid set due to the linking

    of the particles in the mix. This is referred to as false setting.

    However, unlike flash set, there is no rapid evolution of heat because

    C3A hydration is inhibited by the sulfate.

    Another difference between false set & flash set is that a false set may

    be reversed if continued mixing can break up the gypsum crystals

    bonding the solids. The resulting gypsum fragments then slowly dissolve &

    the concrete should set normally & show fairly normal strength growth.

    High mill temperatures can decompose the gypsum (CaSO4.2H2O) i.e. dihydrate

    form, to hemihydrate (CaSO4~0.5H2O), also known as plaster of Paris.

    Reminder, solubilities: hemihydrate > gypsum > natural anhydrite

    Flash set v.s. False set

    Particle size analysis laser diffraction

    Cement ground to a finer particle size will

    react more quickly with water than the same

    cement milled more coarsely.

    Fineness is measured as the specific

    surface area in (m2 kg-1).

    Typical range: (350-450 m2 kg-1)

    rapid-hardening (high early strength) cementswill be at the higher end of this range.

    Blaine fineness apparatus

    (air permeability)

    Clinker Grinding & Gypsum Addition

  • 8/12/2019 Lime and Cement Block 3

    4/18

    The control of fineness is critical to cement performance.

    Particles that are too fine (< 2m) lead to the cement curing

    exothermically, setting too fast & cracking.

    Large particles (> 32m) may not be fully hydrated, reducing

    the strength of the final product.

    &

    &

  • 8/12/2019 Lime and Cement Block 3

    5/18

    Hydration of cement and water/cement ratio

    The water/cement (w/c) ratio is a crucial parameter in cement hydration

    because it directly affects porosity & permeability. The w/c ratio influencesconcrete strength & resistance to water ingress, frost attack, leaching &

    other detrimental chemical & physical processes.

    w/c ratio is defined as: (mass of water)/(mass of cement)

    Most concrete has a w/c ratio between 0.3 and 0.7.

    Below a w/c ratio = 0.44 there will always be some residual un-hydrated

    cement if no water additional to the original mix water was available during

    curing.

    Above w/c = 0.44, there is sufficient water for complete hydration & also

    enough space in which the hydration products can form, so in principle, thecement can hydrate fully.

    Compaction is a process which

    expels entrapped air from freshly

    placed concrete & packs the

    aggregate particles together so as to

    increase the density of concrete.

    Compaction increases significantly

    the ultimate strength of concrete &

    enhances the bond with

    reinforcement. When first placed in the form,

    normal concretes, excluding those

    with very low or very high slumps, will

    contain between 5% & 20% by

    volume of entrapped air.

    Figure shows that the strength of

    concrete containing 10% entrapped

    air (air voids) may be as little as 50%

    of a fully compacted concrete.

    Loss of strength through

    incomplete compaction

    Fresh Concrete Workability

  • 8/12/2019 Lime and Cement Block 3

    6/18

    Sufficient workability is necessary for virtually full compaction to be possible,

    using a reasonable amount of work. Higher w/c ratio concrete mixes are more convenient when placing the

    concrete, as it flows more easily. However, the consequences for the

    hardened concrete are strongly negative.

    Fresh Concrete Workability

    Voids in hardened concrete are, in fact, either bubbles of entrapped air

    or spaces left after excess water has been removed.

    The volume of excess water depends solely on the w/c ratio of the mix.

    Whereas the presence of air bubbles is governed by the grading of the

    fine particles in the mix & by the fact that the bubbles are more easily

    expelled from a wetter mix than a dry one.

    Fresh Concrete Workability

  • 8/12/2019 Lime and Cement Block 3

    7/18

    Water content of the mix adding more water increases inter-particle lubrication.

    Finer particles require more water to wet their larger specific surface. Irregular shape & rougher texture of an angular aggregate demands more

    water than a rounded aggregate.

    Porosity or absorption of the aggregate mixing water will be removed from that

    required for lubrication of the particles.

    For a constant w/c ratio, workability increases as the aggregate/cement ratio is

    reduced because the amount of water relative to the total surface of solids is

    increased.

    A high ratio of volumes of coarse to fine aggregate can result in segregation & in

    a lower workability, so that the mix is harsh and not easily finished.

    Too much fine aggregate leads to a higher workability, but such an over-sanded

    mix makes less durable concrete. Air entrainment (admixture) - reduces the water requirement for a given

    workability.

    Factors affecting workability:

    &

    &

  • 8/12/2019 Lime and Cement Block 3

    8/18

    Slump: true, shear & collapseWorkability tests

    Cone height = 305mm, base dia. 203mm

    placed on a smooth surface with smaller opening

    (102mm dia.) at the top. Inside of container ismoistened & is filled with concrete in 3 layers.

    Each layer is tamped 25 times with a standard

    16mm dia. steel rod. Top surface is struck off by

    means of screeding & rolling motion of the

    tamping rod.

    Cone is slowly lifted & unsupported concrete

    will slump. The decrease in height of the centre

    of the slumped concrete is called the slump

    (measured to 5mm).

    Shear slump indicates harsher mixes (harsh = high

    vol. coarse to fine agg.) caused by lack of cohesion inthe mix.

    In lean mixes (i.e. high aggregate/cement ratio) with

    tendency to harshness, a true slump can easily

    change to the shear type or even to collapse.

    Slump test is unreliable for lean mixes.

    Compacting factor apparatusWorkability tests

    Compacting factor test:

    Test consists of 2 hoppers (with hinged doors at the bottom) &

    1 cylinder. Total height = 1.2m.

    Upper hopper is gently filled with concrete. Door is released &

    concrete falls into lower hopper. This hopper is smaller than the

    upper one & is therefore filled to overflowing (this reduces the

    influence of the personal factor in filling the top hopper).

    Door of lower hopper is released & concrete falls into cylinder,

    top surface is struck off. Net mass of concrete in the known volume of the cylinder is

    determined.

    Compacting factor = ratio of density actually achieved in the

    test to the density of the same concrete fully compacted (i.e. 4

    layers each tamped or vibrated).

    Unlike the slump test, the variations in the workability of dry

    concrete are reflected in a large change in the compacting

    factor, i.e. The test is more sensitive at the low workability

    end of the scale than at high workability .

  • 8/12/2019 Lime and Cement Block 3

    9/18

    Workability tests

    Degree ofworkability

    Slump(mm)

    CompactingFactor

    Applications

    Very Low 0-25 0.8 Vibrated concrete in roads or other

    large sections

    Low 25-50 0.87 Mass concrete foundations without

    vibration. Simple reinforced sections

    with vibration.

    Medium 50-100 0.935 Normal reinforced work without

    vibration & heavily reinforced sections

    with vibration.

    High 100-180 0.96 Sections with congested reinforcement.Not normally suitable for vibration.

    Vebe apparatusWorkability tests

    Vebe test

    A standard slump cone is placed in a cylinder

    240mm in dia. & 200mm high.

    The slump cone is filled in the standard manner,

    removed, & a disc-shaped rider (weighing 2.75kg) is

    placed on top of the concrete.

    Compaction is achieved using a vibrating table

    (50Hz) & is assumed to be complete when the

    transparent rider is totally covered with concrete & allcavities in the surface of the concrete have

    disappeared. This is judged visually.

    It is assumed that the input of energy required for

    full compaction is a measure of workability of the mix,

    & this is expressed in Vebe seconds.

    This is a good test for very dry mixes. This is in contrast to the compacting factor test

    where error may be introduced by the tendency of some dry mixes to stick in the hoppers.

    Vebe test also has the advantage that the treatment of concrete during the test is

    comparatively closely related to the method of placing in practice.

  • 8/12/2019 Lime and Cement Block 3

    10/18

    Vebe apparatusCompacting factor

    apparatus

    Reminder:

    Slump is insensitive at the low workability end (i.e. unreliable for lean mixes).

    Vebe is less sensitive at the high workability end (good test for very dry mixes).

    Compacting Factor test is more sensitive at the low workability end of the scale

    than at high workability.

    Flow table testWorkability tests

    Test is more widespread for

    flowing concrete made with

    superplasticizing admixtures.

    Concrete is compacted by light

    tamping in a cone: 200mm high,

    bottom dia. 200mm, top dia.

    130mm.

    Board is hinged along one side

    & can be lifted up to a stop sothat the free edge rises 40mm.

    After mould is removed, table

    top is lifted & allowed to drop 15

    times, each cycle taking approx.

    4 sec.

    The concrete spreads & the

    max. spread in mm parallel to the

    2 edges of the table is measured.

    A value of 400 indicates a

    medium workability, 500 = high

    workability.

  • 8/12/2019 Lime and Cement Block 3

    11/18

    Density of compacted

    fresh concrete

    Obtained by weighing thecompacted fresh concrete

    in a standard container of

    known volume & mass.

    From the known density

    (), the volume of the

    concrete can be found from

    mass of the ingredients.

    When these are

    expressed as quantities in

    1 batch put into the mixer,we can calculate the yield

    of concrete per batch.

    V = volume of compacted concrete obtained

    from one batch (yield).

    Masses per batch of: W = water, C = cement,Af= fine aggregate, Ac= coarse aggregate,

    &

    &

  • 8/12/2019 Lime and Cement Block 3

    12/18

    The correct quantities of cement,

    aggregate, & water, possibly also of

    admixture, are batched & mixed in a

    concrete mixer.

    This produces fresh concrete, which is

    transported from the mixer to its final

    location.

    The fresh concrete is then placed in

    the forms, & compacted so as to

    achieve a dense mass which is allowed,

    & helped to harden.

    Note: the size of a mixer should be described by the volume of concrete

    aftercompaction, as distinct from the volume of the unmixed ingredients in

    a loose state, which is up to 50% greater than the compacted volume.

    Ready-mixed concrete

    If instead of being batched & mixed on site, concrete is delivered for

    placing from a central plant, it is referred to as ready-mixed or pre-mixed

    concrete. This type of concrete is used extensively as it offers numerous

    advantages, including:

    Close quality control of batching which reduces the variability of the

    desired properties of hardened concrete. Use on congested sites or in highway construction where there is little

    space for a mixing plant & aggregate stockpiles.

    Use of agitator trucks to ensure care in transportation, thus preventing

    segregation & maintaining workability.

    Convenience when small quantities of concrete or intermittent placing is

    required.

  • 8/12/2019 Lime and Cement Block 3

    13/18

    350 m3/ h output Capacity

    200 tons x 4 cement silo

    30 m3 x 10 aggregates hopper

    Central-mixed concrete

    Concrete Batching Plant

    Transit-mixed concrete:

    materials batched at a central

    plant but are mixed in the truck

    either in transit or immediately

    prior to discharging the

    concrete on site.

  • 8/12/2019 Lime and Cement Block 3

    14/18

    Agitating differs from mixing

    solely by the speed of rotation

    of the mixer;

    agitating speed = 2 to 6 rpm

    mixing speed = 4 to 14 rpm.

    The time during which

    cement & moist aggregate

    are allowed to remain in

    contact should be limited to 2

    hours (BS 5328:1991).

    Ready-mixed concrete

    Placing & Compacting

    The main objective is to deposit the concrete as close as possible to its final

    position so that segregation is avoided & the concrete can be fully compacted.

    Collision between concrete & formwork or reinforcement should be avoided.

  • 8/12/2019 Lime and Cement Block 3

    15/18

    Placing & Compacting

    The concrete should be placed in uniform layers, not in large heaps orsloping layers.

    The rates of placing & of compaction should be equal.

    Each layer should be fully compacted before placing the next one, &

    each subsequent layer should be placed whilst the underlying layer is still

    plastic so that monolithic construction is achieved (long delays can result

    in the formation of cold joints)

  • 8/12/2019 Lime and Cement Block 3

    16/18

    For deep sections, a long

    down pipe ensures accuracy

    of location of the concrete &minimum segregation.

    Placing & Compacting

    The purpose of compaction is to remove as much of the entrapped air as possible

    so that the hardened concrete has a min. of voids & consequently is strong, durable

    & of low permeabil ity.

    This effort is mainly provided by the use of internal vibrators. Poker is moved

    from place to place so concrete is vibrated every 0.5-1m. Other methods: External

    vibrators (clamped to formwork which rests on an elastic support) & Vibrating tables.

    Placing of poker (or immersion) vibrators

  • 8/12/2019 Lime and Cement Block 3

    17/18

    Concrete Vibrator Poker

    (70-200Hz).

    High frequency external vibrators

  • 8/12/2019 Lime and Cement Block 3

    18/18