lime and cement block 3
TRANSCRIPT
-
8/12/2019 Lime and Cement Block 3
1/18
&
&
Initial Set, Final Set & Hardening
Initial set - provides an estimate of when (in hours &
minutes) the concrete has reached the point where it
has stiffened to such an extent that it can no longer
be (vibrated) without damaging the concrete. This is
roughly equivalent to a penetration resistance (using
a weighted needle) of 3.4 MPa.
Under hot weatherconditions, the time to initial
set will be shorter than under
normal temperatures, which
will affect the construction
crews ability to consolidate &
finish the in-place concrete.
Under cold weather
conditions the time to initial
set is extended.
Concrete Penetrometer
for determination of settingtime of the mortar fraction
of fresh concrete. Spring
loading device graduated
from 2 to 150 lbs.
Stainless steel needle
points of 650, 325, 160,
65, 32, and 16 mm area.
-
8/12/2019 Lime and Cement Block 3
2/18
Final set - is roughly equivalent to a penetration resistance (weighted
test needle) of 27.6 MPa at which point the concrete has reached acompressive strength of around 0.6 MPa and it could carry some
measurable loads.
Initial Set, Final Set & Hardening
Soon after mixing, if insufficient sulfate is available (in solution in the
pore fluid) from the added gypsum to slow the hydration of C3A, the
resulting rapid hydration of the C3A produces AFm phase (e.g.
monosulfate) in the form of hydroxy-AFm.
These crystals link up the particles (cement, aggregate, hydrates) in the
mix & quickly cause the mix to become unworkable. This is termed a flash set. The rapid hydration of the C3A results in
the evolution of much heat. Concrete strengths where flash setting has
occurred may be lower than normal.
Flash set v.s. False set
-
8/12/2019 Lime and Cement Block 3
3/18
Conversely, if an excess of sulfate is present in the form of hemihydrate
(possibly caused by high mill temp.), the hemihydrate dissolves & then re-precipitates as gypsum.
Again, the growth of gypsum crystals cause a rapid set due to the linking
of the particles in the mix. This is referred to as false setting.
However, unlike flash set, there is no rapid evolution of heat because
C3A hydration is inhibited by the sulfate.
Another difference between false set & flash set is that a false set may
be reversed if continued mixing can break up the gypsum crystals
bonding the solids. The resulting gypsum fragments then slowly dissolve &
the concrete should set normally & show fairly normal strength growth.
High mill temperatures can decompose the gypsum (CaSO4.2H2O) i.e. dihydrate
form, to hemihydrate (CaSO4~0.5H2O), also known as plaster of Paris.
Reminder, solubilities: hemihydrate > gypsum > natural anhydrite
Flash set v.s. False set
Particle size analysis laser diffraction
Cement ground to a finer particle size will
react more quickly with water than the same
cement milled more coarsely.
Fineness is measured as the specific
surface area in (m2 kg-1).
Typical range: (350-450 m2 kg-1)
rapid-hardening (high early strength) cementswill be at the higher end of this range.
Blaine fineness apparatus
(air permeability)
Clinker Grinding & Gypsum Addition
-
8/12/2019 Lime and Cement Block 3
4/18
The control of fineness is critical to cement performance.
Particles that are too fine (< 2m) lead to the cement curing
exothermically, setting too fast & cracking.
Large particles (> 32m) may not be fully hydrated, reducing
the strength of the final product.
&
&
-
8/12/2019 Lime and Cement Block 3
5/18
Hydration of cement and water/cement ratio
The water/cement (w/c) ratio is a crucial parameter in cement hydration
because it directly affects porosity & permeability. The w/c ratio influencesconcrete strength & resistance to water ingress, frost attack, leaching &
other detrimental chemical & physical processes.
w/c ratio is defined as: (mass of water)/(mass of cement)
Most concrete has a w/c ratio between 0.3 and 0.7.
Below a w/c ratio = 0.44 there will always be some residual un-hydrated
cement if no water additional to the original mix water was available during
curing.
Above w/c = 0.44, there is sufficient water for complete hydration & also
enough space in which the hydration products can form, so in principle, thecement can hydrate fully.
Compaction is a process which
expels entrapped air from freshly
placed concrete & packs the
aggregate particles together so as to
increase the density of concrete.
Compaction increases significantly
the ultimate strength of concrete &
enhances the bond with
reinforcement. When first placed in the form,
normal concretes, excluding those
with very low or very high slumps, will
contain between 5% & 20% by
volume of entrapped air.
Figure shows that the strength of
concrete containing 10% entrapped
air (air voids) may be as little as 50%
of a fully compacted concrete.
Loss of strength through
incomplete compaction
Fresh Concrete Workability
-
8/12/2019 Lime and Cement Block 3
6/18
Sufficient workability is necessary for virtually full compaction to be possible,
using a reasonable amount of work. Higher w/c ratio concrete mixes are more convenient when placing the
concrete, as it flows more easily. However, the consequences for the
hardened concrete are strongly negative.
Fresh Concrete Workability
Voids in hardened concrete are, in fact, either bubbles of entrapped air
or spaces left after excess water has been removed.
The volume of excess water depends solely on the w/c ratio of the mix.
Whereas the presence of air bubbles is governed by the grading of the
fine particles in the mix & by the fact that the bubbles are more easily
expelled from a wetter mix than a dry one.
Fresh Concrete Workability
-
8/12/2019 Lime and Cement Block 3
7/18
Water content of the mix adding more water increases inter-particle lubrication.
Finer particles require more water to wet their larger specific surface. Irregular shape & rougher texture of an angular aggregate demands more
water than a rounded aggregate.
Porosity or absorption of the aggregate mixing water will be removed from that
required for lubrication of the particles.
For a constant w/c ratio, workability increases as the aggregate/cement ratio is
reduced because the amount of water relative to the total surface of solids is
increased.
A high ratio of volumes of coarse to fine aggregate can result in segregation & in
a lower workability, so that the mix is harsh and not easily finished.
Too much fine aggregate leads to a higher workability, but such an over-sanded
mix makes less durable concrete. Air entrainment (admixture) - reduces the water requirement for a given
workability.
Factors affecting workability:
&
&
-
8/12/2019 Lime and Cement Block 3
8/18
Slump: true, shear & collapseWorkability tests
Cone height = 305mm, base dia. 203mm
placed on a smooth surface with smaller opening
(102mm dia.) at the top. Inside of container ismoistened & is filled with concrete in 3 layers.
Each layer is tamped 25 times with a standard
16mm dia. steel rod. Top surface is struck off by
means of screeding & rolling motion of the
tamping rod.
Cone is slowly lifted & unsupported concrete
will slump. The decrease in height of the centre
of the slumped concrete is called the slump
(measured to 5mm).
Shear slump indicates harsher mixes (harsh = high
vol. coarse to fine agg.) caused by lack of cohesion inthe mix.
In lean mixes (i.e. high aggregate/cement ratio) with
tendency to harshness, a true slump can easily
change to the shear type or even to collapse.
Slump test is unreliable for lean mixes.
Compacting factor apparatusWorkability tests
Compacting factor test:
Test consists of 2 hoppers (with hinged doors at the bottom) &
1 cylinder. Total height = 1.2m.
Upper hopper is gently filled with concrete. Door is released &
concrete falls into lower hopper. This hopper is smaller than the
upper one & is therefore filled to overflowing (this reduces the
influence of the personal factor in filling the top hopper).
Door of lower hopper is released & concrete falls into cylinder,
top surface is struck off. Net mass of concrete in the known volume of the cylinder is
determined.
Compacting factor = ratio of density actually achieved in the
test to the density of the same concrete fully compacted (i.e. 4
layers each tamped or vibrated).
Unlike the slump test, the variations in the workability of dry
concrete are reflected in a large change in the compacting
factor, i.e. The test is more sensitive at the low workability
end of the scale than at high workability .
-
8/12/2019 Lime and Cement Block 3
9/18
Workability tests
Degree ofworkability
Slump(mm)
CompactingFactor
Applications
Very Low 0-25 0.8 Vibrated concrete in roads or other
large sections
Low 25-50 0.87 Mass concrete foundations without
vibration. Simple reinforced sections
with vibration.
Medium 50-100 0.935 Normal reinforced work without
vibration & heavily reinforced sections
with vibration.
High 100-180 0.96 Sections with congested reinforcement.Not normally suitable for vibration.
Vebe apparatusWorkability tests
Vebe test
A standard slump cone is placed in a cylinder
240mm in dia. & 200mm high.
The slump cone is filled in the standard manner,
removed, & a disc-shaped rider (weighing 2.75kg) is
placed on top of the concrete.
Compaction is achieved using a vibrating table
(50Hz) & is assumed to be complete when the
transparent rider is totally covered with concrete & allcavities in the surface of the concrete have
disappeared. This is judged visually.
It is assumed that the input of energy required for
full compaction is a measure of workability of the mix,
& this is expressed in Vebe seconds.
This is a good test for very dry mixes. This is in contrast to the compacting factor test
where error may be introduced by the tendency of some dry mixes to stick in the hoppers.
Vebe test also has the advantage that the treatment of concrete during the test is
comparatively closely related to the method of placing in practice.
-
8/12/2019 Lime and Cement Block 3
10/18
Vebe apparatusCompacting factor
apparatus
Reminder:
Slump is insensitive at the low workability end (i.e. unreliable for lean mixes).
Vebe is less sensitive at the high workability end (good test for very dry mixes).
Compacting Factor test is more sensitive at the low workability end of the scale
than at high workability.
Flow table testWorkability tests
Test is more widespread for
flowing concrete made with
superplasticizing admixtures.
Concrete is compacted by light
tamping in a cone: 200mm high,
bottom dia. 200mm, top dia.
130mm.
Board is hinged along one side
& can be lifted up to a stop sothat the free edge rises 40mm.
After mould is removed, table
top is lifted & allowed to drop 15
times, each cycle taking approx.
4 sec.
The concrete spreads & the
max. spread in mm parallel to the
2 edges of the table is measured.
A value of 400 indicates a
medium workability, 500 = high
workability.
-
8/12/2019 Lime and Cement Block 3
11/18
Density of compacted
fresh concrete
Obtained by weighing thecompacted fresh concrete
in a standard container of
known volume & mass.
From the known density
(), the volume of the
concrete can be found from
mass of the ingredients.
When these are
expressed as quantities in
1 batch put into the mixer,we can calculate the yield
of concrete per batch.
V = volume of compacted concrete obtained
from one batch (yield).
Masses per batch of: W = water, C = cement,Af= fine aggregate, Ac= coarse aggregate,
&
&
-
8/12/2019 Lime and Cement Block 3
12/18
The correct quantities of cement,
aggregate, & water, possibly also of
admixture, are batched & mixed in a
concrete mixer.
This produces fresh concrete, which is
transported from the mixer to its final
location.
The fresh concrete is then placed in
the forms, & compacted so as to
achieve a dense mass which is allowed,
& helped to harden.
Note: the size of a mixer should be described by the volume of concrete
aftercompaction, as distinct from the volume of the unmixed ingredients in
a loose state, which is up to 50% greater than the compacted volume.
Ready-mixed concrete
If instead of being batched & mixed on site, concrete is delivered for
placing from a central plant, it is referred to as ready-mixed or pre-mixed
concrete. This type of concrete is used extensively as it offers numerous
advantages, including:
Close quality control of batching which reduces the variability of the
desired properties of hardened concrete. Use on congested sites or in highway construction where there is little
space for a mixing plant & aggregate stockpiles.
Use of agitator trucks to ensure care in transportation, thus preventing
segregation & maintaining workability.
Convenience when small quantities of concrete or intermittent placing is
required.
-
8/12/2019 Lime and Cement Block 3
13/18
350 m3/ h output Capacity
200 tons x 4 cement silo
30 m3 x 10 aggregates hopper
Central-mixed concrete
Concrete Batching Plant
Transit-mixed concrete:
materials batched at a central
plant but are mixed in the truck
either in transit or immediately
prior to discharging the
concrete on site.
-
8/12/2019 Lime and Cement Block 3
14/18
Agitating differs from mixing
solely by the speed of rotation
of the mixer;
agitating speed = 2 to 6 rpm
mixing speed = 4 to 14 rpm.
The time during which
cement & moist aggregate
are allowed to remain in
contact should be limited to 2
hours (BS 5328:1991).
Ready-mixed concrete
Placing & Compacting
The main objective is to deposit the concrete as close as possible to its final
position so that segregation is avoided & the concrete can be fully compacted.
Collision between concrete & formwork or reinforcement should be avoided.
-
8/12/2019 Lime and Cement Block 3
15/18
Placing & Compacting
The concrete should be placed in uniform layers, not in large heaps orsloping layers.
The rates of placing & of compaction should be equal.
Each layer should be fully compacted before placing the next one, &
each subsequent layer should be placed whilst the underlying layer is still
plastic so that monolithic construction is achieved (long delays can result
in the formation of cold joints)
-
8/12/2019 Lime and Cement Block 3
16/18
For deep sections, a long
down pipe ensures accuracy
of location of the concrete &minimum segregation.
Placing & Compacting
The purpose of compaction is to remove as much of the entrapped air as possible
so that the hardened concrete has a min. of voids & consequently is strong, durable
& of low permeabil ity.
This effort is mainly provided by the use of internal vibrators. Poker is moved
from place to place so concrete is vibrated every 0.5-1m. Other methods: External
vibrators (clamped to formwork which rests on an elastic support) & Vibrating tables.
Placing of poker (or immersion) vibrators
-
8/12/2019 Lime and Cement Block 3
17/18
Concrete Vibrator Poker
(70-200Hz).
High frequency external vibrators
-
8/12/2019 Lime and Cement Block 3
18/18