life+ programme · 4 3. executive summary nordic alvar and precambrian calcareous flatrocks...
TRANSCRIPT
LIFE Project Number
LIFE13NAT/EE/000082
Progress Report II Covering the project activities from 31/01/2017 to 20/05/2018
Reporting Date
05/06/2018
Restoration of Estonian alvar grasslands, LIFE to alvars
Project Data
Project location ESTONIA
Project start date: 01/09/2014
Project end date: 01/09/2019
Total budget 3,725,865 €
EC contribution: 2,791,305 €
(%) of eligible costs 74.92 %
Beneficiary Data
Name Beneficiary Environmental Board
Contact person Ms Annely Esko
Postal address Narva mnt. 7a, 15172, Tallinn, Estonia
Telephone +372 511 6738
Fax: +372 680 7427
E-mail [email protected]
Project Website http://life.envir.ee/elualvaritel
1. List of Contents
1. List of Contents ................................................................................................................. 2 2. List of abbreviations ......................................................................................................... 3 3. Executive Summary ......................................................................................................... 4
3.1 General progress ........................................................................................................ 4 3.2 Assessment as to whether the project objectives and work plan are still viable . 6
3.3 Problems encountered ............................................................................................... 6 4. Administrative part .......................................................................................................... 6
4.1 Status of project management (distribution of tasks, changes) ........................................ 6 4.2 Reports delivered since the start of the project ............................................................ 8
5. Technical part ................................................................................................................... 8
5.1 Technical progress per task .............................................................................................. 8
5.1.1 Action A.1: Preparation of agreements with farmers ................................................ 8 5.1.2 Action C.1: Restoration of the habitat ....................................................................... 9
5.1.3 Action C.2. Re-introduction of grazing ................................................................... 10 5.1.4 Action C.3. Re-construction of access roads ........................................................... 11 5.1.5 Action C.4. Restoration of habitat through seed sowing ......................................... 11 5.1.6 Action D.1. Biodiversity monitoring....................................................................... 12
5.1.7 Action D.2. Restoration success monitoring ........................................................... 12 5.1.8 Action D.3. Socio-economic monitoring ................................................................ 13
5.1.9 Action E.1. Media work .......................................................................................... 13 5.1.10 Action E.2. Training for farmers ........................................................................... 15 5.1.11 Action E.3. Establishment of notice boards .......................................................... 16
5.1.12 Action E.4. Preparation of printed materials ......................................................... 16 5.1.13 Action E.5. Update of management guidelines ..................................................... 17
5.1.14 Action E.6. Work with landowners ....................................................................... 17 5.1.15 Action E.7. Web page ........................................................................................... 18
5.1.16 Action E.8. Working group for promotion of added-value products from alvar
grasslands ......................................................................................................................... 19
5.1.17 Action E.9. Layman´s report ................................................................................. 19 5.1.18 Action F.1. Project management ........................................................................... 20
5.1.19 Action F.2. Networking with other projects .......................................................... 20 5.1.20 Action F.3. After-Life conservation plan .............................................................. 20 5.2 Envisaged progress until the next report .................................................................... 21
5.3 Impact ............................................................................................................................ 23 5.4. Outside LIFE ............................................................................................................... 24
6. Financial part ...................................................................................................................... 25 6.1. Costs incurred ................................................................................................................ 25
7. Annexes ........................................................................................................................... 26
7.1 Due deliverables ........................................................................................................ 26 7.2 Financial annexes ...................................................................................................... 26 7.3 Other .......................................................................................................................... 26
3
2. List of abbreviations
AB – associated beneficiary;
ARIB (PRIA) – Estonian Agricultural Registers and Information Board;
CB – coordinating beneficiary;
EB – Environmental Board (coordinating beneficiary);
EIC (KIK) – The Foundation Environmental Investments Centre;
ESCCA – Estonian Seminatural Communities Conservation Association (associated
beneficiary);
EULS – Estonian University of Life Sciences (associated beneficiary);
PM – project manager;
PRIA (ARIB) – Põllumajanduse Registrite ja Informatsiooni Amet;
SFMC – State Forest Management Centre;
SC – Steering Committee;
UT – University of Tartu (associated beneficiary).
4
3. Executive Summary
Nordic alvar and precambrian calcareous flatrocks (habitat code 6280*) or alvar grassland is
the habitat type listed as priority habitat under Annex 1 of the Habitat Directive. Considering
the distribution of this habitat in EU, Estonia has high responsibility in securing the
conservation of it as one third of the total area of alvar grasslands in Europe is occurring in
Estonia. Moreover, the scientific studies have shown that Estonian alvars represent its own
characteristic subtype of habitat type, which slightly differs from those in Sweden. This
means, that for maintaining the habitat type, we cannot solely rely on Swedish alvars but also
ensure their persistence in Estonia. However, the situation of the habitat prior to the project
was near catastrophic. Most of the ~9800 hectares of alvar grasslands in Estonia were heavily
overgrown with shrubs (mostly juniper Juniperus communis) and trees (mostly pine Pinus
sylvestris), while only ~2000 hectares were managed and in more-or-less satisfactory
condition.
The necessity of large-scale restoration of alvar grasslands in Estonia is emphasized in
scientific literature already from 1990-s. During last decade Estonian scientists and nature
conservation associations have made several official complaints to respective Estonian
environmental officials, as well as written number of newspaper and popular science articles
for general public regarding the poor condition of alvar grasslands in Estonia and need for
rapid start of restoration activities. In order to maintain the ecological connectivity and
biodiversity of the alvar grassland habitat type in Estonia, a minimum of 7500 hectares of
habitat area needs to be under annual grazing, as also targeted in Estonian Nature
Conservation Development Plan until 2020.
The general aim of this project is to restore the most valuable, but overgrown alvar grassland
areas on 2500 hectares and to create possibilities for local farmers to manage these areas after
the restoration by grazing. The project has advanced positively since its’ start and during the
reporting period and following the project proposal. At this stage, we see no need for the
extension of the project duration.
3.1 General progress
The general progress of the project is illustrated below in the table of project’s milestones.
Name of the Milestone Action
code Deadline
Status 20/05/2018
Project coordinators are hired F 1 01/09/2014 Achieved in time
Participating on kick-off
meeting
F 1 01/12/2014 Achieved in Oct.
2014
Public meeting I is organized E 1 31/12/2014 Completed in Dec.
2014
2 articles are written to the
local newspapers
E 1 31/12/2014 Achieved in Oct.
2014
Visual materials for the
exhibition/learning centre are
E 1 02/02/2015 Completed in Jan.
2016
5
designed
Visual materials for training
are printed and
exhibition/learning centre
established on reference areas
E 1 01/05/2015 Indoor portable
information boards
established in Jan.
2016; interactive
study tools in
February 2017
Public meeting II is organized E 1 31/12/2015 Completed in Apr.
2016
4 articles are written to the
local newspapers
E 1 31/12/2015 Achieved in May
2015
Networking with other
projects I visit completed
F 2 31/07/2016 Completed in Apr.
2016
All the participants are trained
to carry out
restoration work
E 2 31/08/2016 Achieved in Apr.
2016
Educational trip for land-
owners
E 6 31/08/2016 Completed on time
All restoration contacts are
signed
A 1 01/12/2016 Completed
Contracts are signed with
farmers to carry out grazing in
restored sites
C 2 01/12/2016 Achieved on time
The booklets are printed and
delivered to the local
businesses
E 4 01/12/2016 Achieved on time
Information boards are placed
on each project area
E 3 31/12/2016 49 out of 51
established
4 articles are written to the
local newspapers
E 1 31/12/2016 Achieved in May
2016
Public meeting III is
organized
E 1 31/12/2016 Completed in Jan.
2017
Networking with other
projects visit II completed
F 2 31/07/2017 Completed in May
2017
Public meeting IV is
organized
E 1 31/12/2017 Completed in Jan.
2018
4 articles are written to the
local newspapers
E 1 31/12/2017 Achieved in March
2017
Seed sowing is carried out C 4 01/12/2018 In progress
Public meeting V is organized E 1 31/12/2018 In progress
Restoration work is finished C 1 31/12/2018 Not relevant yet
4 articles are written to the
local newspapers
E 1 31/12/2018 Achieved in April
2018
2 articles are written to the
local newspapers
E 1 30/06/2019 Not relevant yet
Participating on end of the
project meeting
F 1 30/09/2019 Not relevant yet
6
3.2 Assessment as to whether the project objectives and work plan are still
viable
The project has advanced positively during the reporting period and follows the project
proposal. The completion of some actions has been slightly delayed but there have not been
significant delays. Thus we have all reasons to believe that achieving the objectives of the
project in the manner and on the conditions declared in the proposal is realistic and feasible.
At this stage we see no need for the extension of the project duration.
3.3 Problems encountered
We are glad to report that we have overcome the problems described in the Mid-term report:
1. the delay related to Action (C.3) (Re-construction of access roads) have been caught
up
2. all information boards (Action E.3) have been erected and complemented with
mention of EU support in addition to existing logos
During this reporting period we have found out that
3. reaching quantitative goal of action C.1. (2500 ha) might be problematic but we are
working hard to increase the percentage (currently 91,5%). For measures taken please
see section 5 (Actions A.1. and C.1.).
Other small problems are common in everyday project management but those are handled as
soon as they turn up (e.g. there have been some vandalism and cattle fence had to be
repaired).
4. Administrative part
4.1 Status of project management (distribution of tasks, changes)
No changes have appeared at the associated beneficiaries since the beginning of the project.
At the coordinating beneficiary there has been a change of project coordinators II. Mr Bert
Holm left the position in December 2017 and Ms Kaia Treier started in February 2018. The
distribution of tasks between PM I and PM II remained the same after the changes of persons.
The roles of full time PM (PM I) and part time project manager (PM II) are defined in their
personal job descriptions. The field of project activities of PM I is broader, the daily
communication with landowners, farmers restoring the project areas, preparation of the
respective contracts, controlling the restoration quality and media communication are her
main responsibilities. The job of the PM II is more technical involving double checking of the
project documentation, preparation and verification of different documentation (reporting
guidelines, public procurement documents, contracts with farmers etc.), preparing the reports
to financiers, fieldwork, verification of cost documents, budget control etc.
Bookkeeping has been provided by the bookkeepers of each organisation.
Project management structure and the team are illustrated below. Project management
structure has not changed since the beginning of the project.
7
Each associated partner implements its activities according to the description of the project
verified by the PMs of coordinating beneficiary. The main method to update the state and the
developments of the project and to concretize the plans and personal roles is to organise a
special kick-off meeting held at the beginning of each year to revise the progress and to clear
all the goals by project partners that have to be achieved during current year together with
giving an overview to the rest of the team on the most recent project activities of each partner.
Year Seq. no. Time and place Type of meeting
2014 1 11.11.2014, Tartu Project kick-off
meeting
2015 2 11.05.2015, Vätta Steering committee
2016 3 11.02.2016, Pärnu Partners’ meeting
4 20.09.2016, Hiiumaa (Aruküla) Steering committee
2017 5 09.10.2017, Saaremaa (Nässuma) Steering committee
2018 6 30.01.2018, Tartu Partners’ meeting
7 Next Steering Committee meeting is planned for the September-
October in Hiiumaa
2019
Table 1. List of project management meetings since the start of the project
8
4.2 Reports delivered since the start of the project
Name of the report Progress until Reporting date
Inception report 10/05/2015 18/05/2015
Progress report I 30/04/2016 30/04/2016
Mid-term report 31/01/2017 31/01/2017
Progress report II (current) 20/05/2018 05/06/2018
Table 2. Reports delivered since the start of the project
Extension of the project duration is not envisioned at this stage. Thus, at this stage we see no
need to postpone the deadline of Final report.
5. Technical part
5.1 Technical progress per task
5.1.1 Action A.1: Preparation of agreements with farmers
Milestone Deadline in Proposal Status 20/05/2018
All restoration contracts
signed
01/12/2016 74+41, ca 2287 ha (962
private land, 295+1030 state
owned land)
Preparation of agreements with farmers started right after the first training for farmers was
organised by ESCCA in November 2014. As the interest towards starting with the restoration
activities as soon as possible was great from the side of farmers we started with restoration
contracts sooner than initially proposed. Since the last report we have signed 17 contracts. 74
contracts are signed by EB. Some of the state owned land (295 hectares) is also covered by
the restoration contracts signed by EB which means that the total area that will be covered
with the contracts signed by EB is around 1257 hectares. Much of that work was done by the
PM I of EB. However, since the beginning of the project the livestock owners interested in
restoration and re-introduction of grazing in some particular areas also took the initiative in
getting the landowners’ clearances and gained several by themselves.
In state owned land the respective contracts (41) are prepared by the SFMC who is
responsible for alvar grassland restoration in this land. The SFMC signs the land lease
contract with livestock keeper to ensure the management of the area and after that usually
organises the public procurement to find the subcontractor to carry out the habitat restoration.
The goal for SFMC to cover with restoration contracts is ca 1150 hectares of which ca 1030
hectares have the restoration contract by now. In the preparation of contracts, it has become
evident, that some of the alvar areas are too small and scattered or with too poor soil to attract
the interest of the farmers. See example of situation in Neeme project site (map in Annex 4)
where rented areas are indicated with red and unrented small/scattered alvar areas are
indicated with green. Suitable size areas are all rented out and under restoration. So far 2287
9
hectares (91,5 % of the goal) of alvars are covered with contracts but we are looking into
possibility to find more areas more attractive for the farmers, outside the project areas.
It should be also noted that we have used most of the funds of C1. The average cost per ha is
1700 EUR but as the cost of the fuel has increased significantly over the past few years it has
become more and more difficult to find sub-contractors with this cost. Thus, if we get offer
with significantly higher than 1700 EUR7ha, we have to waive. Thus, we see that the only
way to reach is 2500 ha is by increasing the total area of state land managed by SFMC. We
will consult the Commission after the analysis is carried out, by the time of next monitoring
visit in July 2018.
5.1.2 Action C.1: Restoration of the habitat
Milestone Deadline in
Proposal
Status 20/05/2018
Restoration work finished 31/12/2018 - 2287 ha under restoration
(covered by contracts)
- 1697 ha accepted and
joined/joining PRIA scheme
Deliverable Deadline in
Proposal
Status 20/05/2018
Report: Assessment of project
development by external experts I
01/09/2016 Completed on time, report
submitted with Mid-term report
(Annex 4)
Report: Assessment of project
development by external experts
II
03/09/2018 Visit in July 2017, report in
progress and completed as
foreseen
Report: Description of restoration
works carried out on project areas
31/12/2018 Not relevant yet
The restoration is carried out in two phases: the first phase involves cutting down and
removing the woody biomass from the areas. We have managed to carry out this phase on ca
2085 hectares by now (1274 ha state owned land; 811 private land). The second phase will
usually be carried out after one year has passed since the end of the first phase when the
stumps height of bushes and trees is corrected after the first grazing season. This has been
carried out on ca 1697 hectares which means the area where the restoration has already
finished and joined the continuous management scheme. By the reporting date restoration
work was initiated at all 25 areas.
The physical works in Hanila have not started but the contract covering 11,5 ha has been
signed by the time of this report and works will start also in Hanila as soon as bird nesting
period will end (15 July 2018)). The reasons for delay in Hanila and measures taken by the
project team were described in the Mid-term report and acknowledged in the Commission
letter of 22/03/2017.
For the assessment of the action the project was visited by the external experts in year 2015
(for details please see the Mid-term Report). The reports from the experts are available on
project’s web site.
10
5.1.3 Action C.2. Re-introduction of grazing
Milestone Deadline in Proposal Status 20/05/2018
Contracts signed with farmers to
carry out grazing in restored sites
01/12/2016 Achieved on time
By now we have covered the need of livestock breeders for the supplies for grazing
reintroduction in approximately 1700 hectares of the project area. In around 200 hectares the
livestock breeders have had no need for the additional support from the project. The overview
of grazing infrastructure has been given in the table below.
Type of grazing facility Foreseen Actual Comment
Generators (together with a
battery and some equipped also
with a solar panel for the
electrical fences)
67 69
Shelters 47 21 Turned out to be more expensive
than estimated but the practical
need for those has been smaller
Freshwater accesses or facilities 50 65 Larger number as bigger need by
farmers occurred. Sets of livestock collection pens 25 34
Cattle grid 10 30 Larger number because have proved
to be effective in terms of both
keeping the livestock in pasture plots
and comfortability of the visitors of
the areas.
Electrical fences 376 km 200 Finally we will probably establish
less kilometres but the fences
established are in general in better
quality (incl. wolf proof with 5
lines instead of 2) and pasture plots
are bigger than estimated.
Access gates 543 208 Bigger pasture plots need less
access gates as less fences. Table 3. Overview of grazing infrastructure as of 20/05/2018
In despite of the changes in the numerical targets of the supplies for re-introduction of grazing
we can assure that the respective budget of consumables and infrastructure is sufficient to
assure the sustainability of the grazing of the areas restored during the project. The actual
numbers will increase after the fourth procurement (currently in progress, deadline for
biddings is 11 June 2018). In case the current procurement is successful we have covered all
the actual needs of our partner farmers and will not need to organise the procurement in year
2019. The final numbers per facility will be reported with the Final report.
11
5.1.4 Action C.3. Re-construction of access roads
Deliverable Deadline in Proposal Status 20/05/2018
Report: Map and
description of work of re-
constructed access roads
01/12/2018 In progress
The action is progressing as foreseen. The overview of two procurements needed to carry out
the works is given in the table below.
Name of the public
procurement
Sub-contractors (best
offers)
Comment
1. Technical
documentation
specifying the
methods and
materials to be used
ViaVelo Inseneribüroo
OÜ
The work is completed and
technical documentation available
on project’s web site at:
https://life.envir.ee/sites/default/fil
es/pictures/Tehniline_kirjeldus_te
ede%20rekonstrueerimine.pdf
2. Reconstruction of
roads
AS Tariston (Hiiumaa)
Muhu Varahalduse OÜ
(Muhu)
AS Level (Saaremaa)
The deadline of the contract is
September 2018.
Table 4. Overview of public procurements for the implementation of action C.3.
5.1.5 Action C.4. Restoration of habitat through seed sowing
Milestone Deadline in Proposal Status 20/05/2018
Seed sowing carried out on
4,5 ha
01/12/2018 In progress, seed sowing
carried out on 3,5 hectares
During the summer of 2015, the survey of seed donor sites was carried out on alvar grassland
habitats in the vicinity of project sites Kurese (project area no 3) and Neeme (area no 23). UT
identified suitable sites in 3 ha which were further surveyed for suitability during the summer
of 2016 and tested for seed collection via brush harvester and for green hay collection. Final
selection was made on 2017, and selected site for Neeme area was Kõruse/Tammese-Kehila
alvar grassland and for Kurese restoration area a nearby grassland site outside of project site.
Progress of works on Neeme site: by using brush harvester, seeds were collected from
Kõruse/Tammese-Kehila donor site over 2 periods in 2017 (in the beginning of August and in
the beginning of September). Following collection, seeds were instantly sown to restored
Neeme site (in August and in September 2017), covering 1.25 ha. Green hay was mown in the
beginning of August from 2 hectares. Hay was instantly moved to recipient site in Neeme and
spread over 1-hectare area. All seed sowing activities in Neeme site have been completed.
Progress of works on Kurese site: seeds were collected with brush harvester over 2 periods in
2017 (August and September) from a good-quality grassland in the vicinity of Kurese
restoration area. Seeds were stored over winter and then sown to Kurese site in April 2018,
following the clearing of young forest and shrubs. Sowing area covered 1.25 ha. Hay transfer
12
in Kurese will occur in end of July 2018 – hay will be collected from 2 hectares of donor site
near restoration area and will be instantly spread to recipient site. All activities related to seed
sowing will be completed by August 2018. The overview table is attached to the report
(Annex 5).
For both sites, collected seeds were also analyzed for species composition and amount of
viable seeds. Seed samples were germinated in the laboratory of University of Tartu, all
emerging seedlings were identified. Obtained information will be used to assess seed sowing
efficiency during biodiversity monitoring in action D.1. Photos of germination test are
attached to the report (Annex 5).
5.1.6 Action D.1. Biodiversity monitoring
Deliverable Deadline in Proposal Status 20/05/2018
Report: Results of
monitoring of biodiversity
on restored sites
01/03/2019 In progress
The data collection for the respective report was replicated in the unrestored and also carried
out in restored sites in summer 2016. Biodiversity survey was carried out on all project areas,
altogether on 25 sites. On each site, permanent plots have been established, where vascular
plant diversity, butterfly diversity, management, disturbance regime and environmental
indicators were quantified and soil samples for soil chemistry analysis were collected. The
fieldwork also engage checking the markings of the permanent plots and estimating the visual
changes in the management and disturbance indicators following the restoration activities. On
seed sowing sites (Kurese, Neeme), permanent observation plots (additional to those already
present) were established in summer 2016 and 2017 to monitor the changes after the seed
sowing. In year 2018 we will collect field work data on vascular plants, in year 2019 in
addition to vascular plants we also collect data about invertebrates (butterflies). There are
some areas that are ready for post-restoration monitoring only in the beginning of year 2019
(e.g. Hanila, Käina-lahe Kassari). Consequently, we see a need to postpone the deadline of
deliverable Report: Results of monitoring of biodiversity on restored. We propose 01/09/2019
as a new deadline by which the report will be upload on project’s web site. The paper copy
will be submitted with the Final report due on 01/12/2019.
5.1.7 Action D.2. Restoration success monitoring
Deliverable Deadline in Proposal Status 20/05/2018
Report: Results of the
monitoring of restoration
success
01/03/2019 In progress
The restoration success is monitored constantly by the PM I and PM II of the coordinating
beneficiary. There has been continuous fieldwork to assess the restoration quality in each
month. The terms of the habitat restoration contracts demand that the contractor shall inform
EB when the first hectare of the alvar grassland is restored. Then PM I or PM II visit the area
13
and check the quality (stump height, coverage of bushes and trees etc.). Based on this
fieldwork inspection protocol is compiled and the direct feedback to the contractor given at
the site. Only after that the contractor is allowed to proceed with the restoration. So far this
constant verification has assured high quality of the habitat restoration. Similar process of
onsite verification is repeated when the contractor/farmer declares that some stage of the
restoration is finished and wishes to be paid. Then the PM I or/and PM II (depending on sum
of the deed less than 5000 EUR 1 person, 5000 – 40000 EUR two persons, more than 40000
EUR three persons) of EB visit the area once again and check the quality of work after what
the documentation of acceptance are signed and the work done rewarded.
After the restoration work is completed the quality is checked also by the scientist of the
EULS. Scientist will evaluate the restoration success of the area by checking different aspects
of the restoration work and filling the respective data form for later analysis. Report of the
results is written by the EULS after the restoration work is finished on all the project areas.
There are some areas that are ready for post-restoration monitoring only in the beginning of
year 2019 (e.g. Hanila, Käina-lahe Kassari). The action’s timetable is attached to the report
(Annex 6). Consequently, we see a need to postpone the deadline of deliverable Report:
Results of the monitoring of restoration success to ensure that the results and analysis from all
project areas are included in the report. We propose 01/09/2019 as a new deadline by which
the report will be upload on project’s web site. The paper copy will be submitted with the
Final report due on 01/12/2019.
5.1.8 Action D.3. Socio-economic monitoring
Deliverable Deadline in Proposal Status 20/05/2018
Report: Results of the
socio-economic impact
monitoring
01/03/2019 In progress
The action is progressing as foreseen. The progress per indicator is given in the overview
table attached to this report (Annex 7). The summarising results of the whole study will be
included in the Final Report.
As a very big honour to our project- LIFE to alvars was presented with a Natura 2000 award
in the socio-economic benefit category this year. Information was received by the organizers
of the ceremony event in Brussels that Commission members also wish to visit our project
this year.
5.1.9 Action E.1. Media work
Milestone Deadline in
proposal
Status 20/05/2018
Public meeting I organised 31/12/2014 Completed in Dec. 2014
2 articles published in local
newspapers
31/12/2014 Achieved in Oct. 2014
Visual materials for the
exhibition/learning centre designed
02/02/2015 Completed in Jan. 2016, proof of
photos submitted with MtR (Annex
14
6)
Visual materials for training are
printed and exhibition/learning
centre established on reference areas
01/05/2015 Indoor portable information boards
established in Jan. 2016;
Interactive study tool in on site
installation stage.
proof of photos submitted with MtR
(Annex 6)
Public meeting II organised 31/12/2015 Completed in Apr. 2016
4 articles published in local
newspapers
31/12/2015 Achieved in May 2015
Public meeting III organised 31/12/2016 Completed
4 articles published in local
newspapers
31/12/2016 Accomplished by May 2016
Public meeting IV organised 31/12/2017 Completed
4 articles published in local
newspapers
31/12/2017 Accomplished by February 2017
Public meeting V organised 31/12/2018 Planning started
4 articles published in local
newspapers
31/12/2018 In progress
2 articles published in local
newspapers
30/06/2019 Not relevant yet
Deliverable Deadline Status 20/05/2018
Report: Summary of dissemination
work carried out during the project
01/03/2019 Preparations started
The indoor portable information boards and the interactive study tools are available in the
nature centres of Sõrve and Orjaku since February 2017. The photos have been attached to the
report (Annex 10). The study tool is also available on project’s web site at
http://life.envir.ee/elu-alvaritel-m%C3%A4ng-life-alvars-game which is an additional benefit
created in the frames of the project if compared with the project proposal.
The media coverage of the project activities has been fruitful and the initial numerical goal (4
articles in local newspapers, 20 in total) has been significantly exceeded. Yet, we will still
continue with that task to reach larger audience until the end of the project. All the media
reflections of the project are listed at http://life.envir.ee/meist-meedias-project-media
The updated list of published newspaper articles is also attached to this report (Annex 8).
We are very happy of the article published in the biggest (print-run 124 000 and FB followers
2,3 millions) popular-science magazine New Scientist:
https://www.newscientist.com/article/2141576-restoring-estonian-alvar-grasslands-to-save-
unique-species/
In addition to New Scientist there has been even more international media coverage since the
last reporting period:
- https://www.rapport.fi/journalistit/marjatta-sihvonen/neuvostomannikosta-
kammekkaniityille-ja-sammakkolammille-viro-ennallistaa-luontoaan-eu-
rahalla?rs=art_355019&rsd=13397
15
- an interview to German radio (Deutchlandradio). LIFE to Alvars - neue
graslandschaften sorgen fuer alte. Deutchlandradio, 30.06.2017
http://ondemandmp3.dradio.de/file/dradio/2017/06/30/life_to_alvars_neue_graslandschaften_
sorgen_fuer_alte_dlf_20170630_1650_9c99f885.mp3
The public meetings have been regularly organised as the project progresses. The list of
public meetings and participant’s lists of the events held during this reporting period have
been attached to the report (Annex 9). The agenda’s as well as some presentations are
available on project’s web site in section News and Events. In addition there have been
several other meetings which we have organised upon need. (The costs of other meetings
have been insignificant and mostly reported in the cost category Overheads.) The list of
participants of the seminar Wake Up Boreal grasslands is also attached to the report (Annex
12).
We would like to organise a project’s final conference in the 3Q of year 2019 targeted to
different stakeholders: alvar managers, interested landowners, conservation specialists and
officials, scientists. The conference would be a full one day event (presentations, field trip,
joint dinner) for approximately 50 participants. The venue is to be clarified but most likely it
will take place either in island Muhu or Saaremaa. The estimated cost is 2500 EUR (room
rent, lunch, coffee break, bus rental to project areas, joint dinner). We would like to use the
savings we have from other dissemination actions in cost categories External assistance and
Consumables. There will be high level scientists among invited speakers (M.Pärtel. M. Zobel,
T.Kukk) and some costs might also appear if they wish to arrive the day before and need
accommodation.
5.1.10 Action E.2. Training for farmers
Milestone Deadline in Proposal Status 20/05/2018
All participant trained to carry
out the restoration works
31/08/2016 Completed
ESCCA organised the first training for farmers in November 2014 in Saaremaa so we could
start with the habitat restoration one season earlier. Sooner start of the activity was initiated
by the farmers and entrepreneurs who were interested to start the restoration work already
during 2014…2015 winter season. At the first training 70 farmers, landowners and
entrepreneurs were trained (we expected to train only 50 people in total initially). The second
training for farmers was organised by ESCCA in September 2015. PM I and PM II of EB
helped to organise the event in Muhu island. The number of participants of that training was
50. In February 2016 the third farmers training was carried out in Muhu Island. This was
specifically targeted to the contractors of SFMC restoring the project areas at state owned
land. The number of participants was 22. Another training focussing on to the same target
group was organised in of April 2017 in Muhu Island. This time the number of participants
was 16. After each training the respective certificate has been issued to each of the participant.
During last three trainings the Koguva-Igaküla project area (area no 7) was visited for the
practical demonstration.
By now we have trained more than 180 farmers, landowners and entrepreneurs. This is due to
substantially greater interest towards the project than initially predicted. As we changed the
16
reference areas we managed to save the budget and were able to train substantially more
participants with the same amount of funds. Therefore we have been within the planned
budget carrying out this action with much larger impact than initially planned. On demand we
will organise one additional training event also in 2018. Otherwise we can conclude this
action successfully finished.
5.1.11 Action E.3. Establishment of notice boards
Milestone Deadline in Proposal Status 20/05/2018
59 information boards
(1x1,5 m) are placed on
each project area
31/12/2016 All produced
49 erected, 2 more (Hanila,
Paadla) to erect
The preparations of the action started as planned but the implementation of the action was
delayed due to the unsuccessful public procurement (details provided in the Mid-term report).
In the beginning of 2017 EB initiated a new procurement process to order all the necessary
information boards all together and to erect the stands by the start of the tourism season in
early summer 2017. The final number of the information boards that will be established is 51.
The location maps as well as overview table with photos have been attached to the report
(Annexes 11-12).
In addition we have ordered smaller information boards for the purpose of practical
management of grazing in the restored areas which inform the visitors how to behave in the
vicinity of livestock and electric fences. All the livestock shelters and portable watering
facilities were also marked with the notice boards or stickers bearing the NATURA 2000 and
LIFE logos. This kind of marking will also continue this year.
5.1.12 Action E.4. Preparation of printed materials
Milestone Deadline in Proposal Status 20/05/2018
The booklets are printed and
delivered to the local businesses
01/12/2016 Completed
Deliverables Deadline in Proposal Status 20/05/2018
Three (Saaremaa, Hiiumaa,
Muhu) booklets (in total 10 000
copies) in Estonian
01/06/2016 Completed in Nov. 2015
(14000 copies printed)
Booklet on project translated into
English, Russian and Finnish
Completed in Nov. 2015
(4000 copies printed)
Delivering booklets to the local businesses of all the islands involved in the project started in
November 2015 and it continued more actively in summer 2016 as this period is the main
tourism season. By now most of the booklets are distributed. The English versions are
finished; one box (150 – 200 each) of Estonian, Finnish and Russian language is left for the
remaining project duration. At the time of the last monitoring visit (September 2017) we were
considering reprinting the folders but after discussions with project’s partners we decided to
focus on publishing high quality Layman’s Report. For final project stage and after-LIFE
17
period we have Layman’s report available for all interested stakeholders including wider
public and tourists.
5.1.13 Action E.5. Update of management guidelines
Deliverable Deadline in Proposal Status 20/05/2018
Best practice guidelines are
updated
31/12/2018 In progress
The information for updating the best practice guidelines is gathered constantly during the
project. As the conception of the methodology of alvar grassland restoration has changed
during the project and reached beyond the frames of the project also, the first step would be to
update the legislative act according to which the restoration is usually carried out and also
subsidised in Estonia. In the current act the methodology described is not appropriate any
more as the restoration can be much more effective than the manual restoration used so far.
The project team was involved in giving input to update these legislative acts (regulations
Poolloodusliku koosluse hooldamise toetus and Loodushoiutoetuse taotlemise, taotluse
läbivaatamise ja toetuse maksmise kord, nõuded toetuse maksmiseks, toetuse määrad ning
toetuse tagasinõudmise kord).
The guidelines were also discussed at the partner’s meeting on 30 January 2018 in Tartu
where it was agreed to produce the updated guidelines in a more thorough and designed
format than initially planned. The associated beneficiary EULS volunteered to coordinate this
action. Consequently, we would like to shift the funds for updating, illustrating and printing
the deliverable (in total 6500 EUR) from the budget of EB to the budget of EULS. The
foreseen budget for this action is 3850 EUR (cost category Personnel) but we would like to
illustrate and print the updated guidelines, and therefore estimate the total costs approximately
6500 EUR. We plan to balance the difference with cost category Other costs as we have
managed to save funds planned for author fees.
5.1.14 Action E.6. Work with landowners
Milestone Deadline in Proposal Status 20/05/2018
Educational trip for land-
owners
31/08/2016 Completed in May 2015
There have been few personal meetings and e-mail communications with foreign landowners
on demand to introduce the project activities and plans and to get the landowner to
communicate with the farmer interested in the restoration and re-introduction of grazing.
Foreign land owners are also contacted personally to give the overview of the restoration
work carried out in their land. This involves both written overviews and site visits. In January
2017 first letters and photos about the restoration work carried out were sent out to 11 foreign
landowners participating in the project. The next round of letters will be send in the beginning
of 2019. The study trips to introduce the idea, methods and the results of the project are
progressing as foreseen. The overview of the trips is shown in the table below.
18
Date and place Project areas visited Number of
participants
23 May 2015, Muhu 7 – Koguva-Igaküla
9 – Nõmmküla-Üügu
10 – Lõetsa
45
18 June 2015, Hiiumaa 18 – Käina lahe - Kassari 13
19 Sept. 2016, Hiiumaa 18 – Käina lahe – Kassari
1 – Sarve
14
24 Sept. 2016, Muhu 9 – Nõmmküla-Üügu 13 of which 2 foreign
landowners
25 April 2017, Muhu 7 – Koguva-Igaküla
9 – Nõmmküla-Üügu
13 of which 1 foreign
landowner
25 June 2018, Saaremaa Vätta
Table 5. Overview of the study trips to landowners
The target, to reach 80 participants, was reached already by the time of Mid-term report but
we will carry out six study trips as foreseen in the proposal. At the next meeting we plan to
discuss with landowners how they can contribute to reach the quantitative goals of the project,
2500 ha of restored grassland.
5.1.15 Action E.7. Web page
Deliverable Deadline in Proposal Status 20/05/2018
Project home page
published
01/06/2016 Estonian version available since Sept.
2014
English version since March 2015
Approximately 35 000 people have visited the web page since the beginning of the project.
The majority of visitors seems to be from abroad and approximately 1/3 from Estonia. As the
average duration of each visit is more than 2 minutes we can conclude that those visits are
targeted and not random.
In year 2017 the location of the web page changed due to the centralisation of the web design
and structure of all governmental institutions. The new environment for LIFE projects is
provided by the Ministry of Environment and created for all the LIFE projects in Estonia. By
2Q 2018 we managed to restore all sections and the new web site at
http://life.envir.ee/elualvaritel is fully functional.
The Facebook page of the project (https://www.facebook.com/lifetoalvars) is modified and
renewed continuously by adding relevant information, announcements of the project events
and photos of the conservation activities. By now we have gained 363 “likes” which is the
number of direct followers reaching each inscription as soon as they log in their FB account.
However, the number of people reached by a single inscription could be up to several hundred
depending on the amount of people sharing the news in this social media network. Interesting
posts get engagement numbers up to 2000 people. For example in 2018 already 32 postings
are made on the LIFE to alvars FB page.
19
5.1.16 Action E.8. Working group for promotion of added-value products
from alvar grasslands
Deliverable Deadline in Proposal Status 20/05/2018
Report: added-value
products working group
work results
01/06/2017 Completed; available since
October 2017
To promote the sustainable use of the wooden material produced during the restoration and
also the side products like meat and wool from the livestock grazing the areas afterwards, the
working group of added-value products from alvar grasslands was formed. The purpose of the
group was to identify the obstacles and to come up with the ideas for the added-value
products from the alvar grassland that could give additional income for the farmer managing
the area in long term. The action was started in 2015 with gathering the information on the
interest groups possible involved in any kind of products originating from alvar grasslands.
Several meetings focussing on different product groups (wood, meadow meat, wool) took
place in the following years. We think that the action has been successful. The proof is the
establishment of the slaughtering house is beyond the scope of Life to alvars project but
definitely a spin-off of this project. Coop initiated by the farmers opened up their own
grassland meat selling counter on Muhu Island in May 2018. More information is provided in
the report of the action attached to this report (Annex 1) and available at project’s web page at
http://life.envir.ee/sites/default/files/pictures/Lisandv%C3%A4%C3%A4rtusega_toodete_t%
C3%B6%C3%B6grupi_t%C3%B6%C3%B6_aruanne_0.pdf
5.1.17 Action E.9. Layman´s report
Deliverable Deadline in Proposal Status 20/05/2018
Layman`s report completed 03/06/2019 Planning started
The concept of Layman’s report was discussed at the partner’s meeting on 30 January 2018 in
Tartu. It was decided that as the associated beneficiary ESCCA has great experience in
compiling and publishing publications the action implementation of the will be coordinated
by the ESCCA and not EB. Consequently, we would like to shift the funds for compiling,
translating and printing the Layman’s report from the budget of EB to the budget of ESCCA.
We also see a need to increase the budget of this action (foreseen 5400 EUR) up to 9000
EUR. It seems that the foreseen cost (5400 EUR) has been slightly underestimated (e.g. the
cost of Layman’s report of Urbancows in year 2016 was 6359,24 EUR). We plan to balance
this modification with funds planned for project’s audit (cost category External assistance)
which we managed to organise for less funds.
20
5.1.18 Action F.1. Project management
According to the project description the Milestones and Deliverable characterising the general
management of the project correspond to Action F.1 Project management:
Milestone Deadline in Proposal Status 20/05/2018
Project coordinators are
hired
01/09/2014 Completed in time
Participation on kick-off
meeting
01/12/2014 Achieved in Oct. 2014
Participating in end of the
project meeting
30/09/2019 Not relevant yet
Deliverable Deadline in Proposal Status 20/05/2018
Report: Financial audit 01/08/2019 Not relevant yet
During the reporting period we also gathered the SC members. The minutes of the meeting
held on 09.10.2017 in Nässuma, Saaremaa are attached to the report (Annex 14).
5.1.19 Action F.2. Networking with other projects
Milestone Deadline in Proposal Status 20/05/2018
Networking with other
projects visit I completed
31/07/2016 Accomplished in April 2016
Networking with other
projects visit II completed
31/07/2017 Accomplished in May 2017
Deliverable Deadline in Proposal Status 20/05/2018
Report: Results of networking
with other projects
04/09/2017 Completed, available since
November 2017 on project’s web
site, submitted with PRII (Annex
2)
The progress and our assessment of this action were described in the Mid-term report. With
this report we are submitting the deliverable, a report on the results of networking with other
projects (Annex 2). In addition to visiting other LIFE projects and hosting several
conservation projects we have participated at several networking events. The list of events
attended during the reporting period has been attached to this report (Annex 15). Even though
the action is completed we continue networking and when possible and justified attend to
different networking events in Estonia as well as outside Estonia.
5.1.20 Action F.3. After-Life conservation plan
Deliverable Deadline in Proposal Status 20/05/2018
After-Life conservation
plan
01/12/2019 Not relevant yet
5.2 Envisaged progress until the next report
Action 2014 2015 2016 2017 2018 2019 Envisaged progress until
the next report II III I II III IV I II III IV I II III IV I II III IV I II III IV
Overall project
schedule:
Proposed
O -
Start date
IncR PRI MtR PR
II FR
Final report submitted on 01/12/2019.
Actual X
A.1. Preparation of agreements with
farmers
Proposed X X X X X
Action finished by MTR.
Actual
C.1. Restoration of
the habitat
Proposed X X X X X X X X X X X X X X
Habitat restoration completed.
Actual
C.2. Re-introduction
of grazing
Proposed X X X X X X X X X
Grazing reintroduced in all project areas.
Actual
C.3. Re-construction of access roads
Proposed X X X X X X X X X X X X X X The deadline for sub-contractor is 1 Sept 2018. Re-construction of roads completed.
Actual
C.4. Restoration of
habitat through seed
sowing
Proposed X X X X X X X X
Seed sowing carried out on 4,5 ha.
Actual
D.1. Biodiversity
monitoring
Proposed X X X X X X X X X Post-restoration monitoring completed;
monitoring reports produced and published. Actual
D.2 :Restoration
success monitoring
Proposed X X X X X X X X X X X X The second phase of restoration success
monitoring carried out and report published. Actual
D.3. Socio-economic monitoring
Proposed X X X X X X X X X X X The socio-economic monitoring completed; monitoring reports produced and published. Actual
E.1. Media work Proposed X X X X X X X X X X X X X X X X X X X Regular media work proceeded.
22
Actual
E.2. Training for farmers
Proposed X X X X Action completed; additional farmers´ training organised on a demand.
Actual
E.3. Establishment of
notice boards
Proposed X X X X X X X X
51 information boards established in all the
areas; grazing-related appliances marked with logos. Actual
Han
ila, Paa
dla
E.4. Preparation of printed materials
Proposed X X X X X X X X X X X X X X X X Action completed; the English versions are
finished; one box (150 – 200 each) of Estonian, Finnish and Russian language is left for the remaining project
duration. Actual
E.5. Update of
management guidelines
Proposed X X Production and publishing updated
management guidelines. Actual
E.6. Work with
landowners
Proposed X X X X X X X X X X X X X X X X X X X X X Completed; next landowners study trip
scheduled on 25 June 2018. Actual
E.7. Web page Proposed X X X X X X X X
Web page operational and updated.
Actual
E.8. Working group
for promotion of
added-value products from alvar grasslands
Proposed X X X X X X X X X X Action finalised, respective deliverable
completed. Actual
E.9. Layman´s report Proposed X X X X X X
Report produced and published.
Actual
F.1. Project
management
Proposed X X X X X X X X X X X X X X X X X X X X X X Carried out according to the proposal,
PRII prepared and submitted. Actual
F.2. Networking with
other projects
Proposed X X X X Even though the action is completed we
continue networking and when possible and
justified attend to different networking events in Estonia as well as outside Estonia.
Actual
F.3. After-Life conservation plan
Proposed X All exsisting management plans will be overlooked. Actual
5.3 Impact
Nature & Biodiversity:
The project is benefiting a priority habitat - Nordic alvar and precambrian calcareous flatrocks
with the European Union’s Habitats Directive code 6280* (alvar grasslands). Until the project
start, only a small area of alvar grasslands were restored in Estonia. During the project the
conditions of this priority habitat are directly improved by more than doubling the habitat area
of alvar grasslands in favourable condition in Estonia. Only 2000 hectares (25% of the 2020
year goal) of alvars grasslands was under management prior to the project in Estonia. By 2019
this area is expected to be at least 4500 hectares (60% of the 2020 year goal). As 1/3 of all the
alvar grasslands situate in Estonia, this is a European scale Natura 2000 habitat improvement.
Figure 1. The dynamics of the area of managed alvar grassland habitat type in Estonia since
2007. The red dotted line is the 2020 goal of this habitat type under management.
The species targeted concern a number of protected species at the national level and several
species listed in the Annex II of the Habitat Directive (Directive 92/43/EEC): Sisymbrium
supinum, Cypripedium calceoulus, Liparis loeselii, Thesium ebracteatum, Pulsatilla patens,
Tortella rigens, Encalypta mutica, Maculinea arion; and three bird species listed in Annex I
of the Birds Directive (Directive 2009/147/EC): Crex crex, Lanius collurio and Sylvia nisoria.
Already now there is clear evidence from the biodiversity monitoring carried out during the
project that the restoration activities are beneficial to many protected plant species as the
vegetation recovery including protected species is much faster than predicted.
24
Indirect impacts:
The main indirect impact is that several livestock keepers and landowners outside the project
areas or even outside the NATURA 2000 sites have been interested in the alvar restoration
after we initiated the restoration activities. The direct change of the landscape appearance
(open area instead of bushland) and media coverage of the restoration activities have probably
been the main motivators.
5.4. Outside LIFE
1. Participation in WOODMEADOWLIFE
As described in the Progress report I the PMI and former PMII Mr Bert Holm took part in
consulting of another LIFE+ project proposal concerning the restoration of Fennoscandian
wooded meadows (habitat type 6530* in the Directive 92/43/EEC) called
WOODMEADOWLIFE which is currently under preparation.
2. Participation in the MDI case study
Estonian Ministry of Environment proposed LIFE to alvars as being a genuine measure-based
improvement in conservation status, and selected as one of the case studies which will be
published by the Commission. This mainly reflects the habitat’s status improvement since
2012. The aim of this study is to create a database of species and habitats in the Birds and
Habitats Directives that have shown Genuine Measure Driven Improvements in their
conservation status and secondly to identify the main drivers of these improvements.
3. Training applicants of the Cohesion Fund
The project team was invited to participate with presentation to the training of applicants of
Cohesion Fund organised by the EIC. The EIC is using technical drawings of grazing
infrastructure for the applicants of Cohesion Funds. Restoration methodology designed, tested
and implemented by the project is now a common standard in Estonia for the semi-natural
community restoration and widely used.
4. MSc thesis, E.Prangel, Tartu University
The provisioning of ecosystem services on open and successional alvar grasslands
https://botany.ut.ee/sites/default/files/www_ut/magistritoo_elisabeth_prangel.pdf
25
6. Financial part
The detailed description of the accounting system can be found in the Mid-term Report. The
VAT declarations have been attached to this report (Annex 3).
6.1. Costs incurred
Budget breakdown
categories
Total
costs (€)
Costs incurred
01.09.14-30.04.2018 (€)
% of total
costs
1. Personnel 213022,00 181962,42 85,42
2. Travel and
subsistence 39900,00 41385,52 103,72
3. External assistance 2354900,00 2073887,00 88,07
4. Durable goods
Infrastructure 341000,00 149580,00 43,87
Equipment 0,00 0,00 0,00
Prototype 0,00 0,00 0,00
5. Land purchase / long-
term lease 0,00 0,00 0,00
6. Consumables 704575,00 548583,40 77,86
7. Other Costs 12100,00 1747,20 14,44
8. Overheads 60368,00 56647,89 93,84
TOTAL 3725865,00 3053793,43 81,96
The slight overspending in cost category Personnel compared to the duration of the project’s
lifetime is related to the higher workload of PM II at the CB. This was highlighted already in
the Mid-term report stage. The overspending will not exceed the limits of €30 000/10% and
we plan to balance the overspending with funds from cost category Infrastructure.
The slight overspending in cost category Travel and subsistence is related to active
networking. We plan not to report more costs in this cost category and use Overheads for
travel purposes (e.g. for participation of PM I at the Nordic Platform Meeting we use cost
category Overheads).
The underspending compared to the duration of the project’s lifetime in cost category
Infrastructure is related to the re-construction of access roads (C.3). The works are expected
to be completed by September 2018 after which the balance will change significantly.
Some changes have appeared also in cost category Other costs. There we would to shift the
funds (€ 4000) planned for author fees of printed materials (E.4) from CB to associated
beneficiary EULS for updating the management guidelines (E.5.).
26
We will have a detailed overview of the foreseen changes per cost category and action by the
time of the next monitoring, in July 2018. The overview of costs by action was submitted with
the Mid-term Report and we will include the overview also in the Final report.
7. Annexes
7.1 Due deliverables
Annex 1 – Report on Action E.8.
Annex 2 – Report on Action F.2.
7.2 Financial annexes
Annex 3 – VAT declarations
7.3 Other
Annex 4 – Map illustrating the alvar grasslands rented by SFMC
Annex 5 – Overview of seed sowing and photos of germination test (Action C.4.)
Annex 6 – Overview of monitoring (Action D.2.)
Annex 7 – Overview of socio-economic monitoring (Action D.3.)
Annex 8 – List of media coverage during the reporting period (Action E.1.)
Annex 9 – Overview of information days (Action E.1.)
Annex 10 – Photos of interactive study tools (Action E.1.)
Annex 11 – Location maps of notice boards (Action E.3.)
Annex 12 – Participant’s list of the seminar Wake Up Boreal grasslands
Annex 13 – Overview table of information boards and photos (Action E.3.)
Annex 14 – Minutes of SC meeting (Action F.1.)
Annex 15 – List of networking events (Action F.2.)