life-cycle management cost analysis of transportation ... · economic value from the delayed cost...

26
Life-cycle management cost analysis of transportation bridges equipped with seismic structural health monitoring systems Michela Torti *1 , Ilaria Venanzi 1 , Simon Laflamme 2 , and Filippo Ubertini § 1 1 Department of Civil and Environmental Engineering, University of Perugia. Via G. Duranti, 93 - 06125 Perugia, Italy 2 Department of Civil, Construction, and Environmental Engineering, Iowa State University, Ames, IA, USA Abstract Life-Cycle Cost Analysis (LCCA) is an approach that has gained popularity for assisting the design of civil infrastructures. The LCCA approach can be leveraged for structures equipped with structural health monitoring (SHM) systems in order to quantify the benefits of the technology and de facto support its long-term implementation. However, for new structures, the long-term assessment of the expected value of the total investment cost, in terms of the current worth at the design time, is still the focus of ongoing research due to unknowns and uncertainties on the impact of the SHM system on long-term structural performance. This paper proposes a new combined model of life-cycle cost formulation and simulation methodology for the long-term financial assessment of transportation bridges equipped with seismic SHM systems, in order to evaluate the total costs and benefits offered by such monitoring systems for post-seismic assessments. The formulation characterizes the time evolution of bridge management cost terms, highlighting the most sensitive parameters. The simulation methodology allows to quantitatively weigh each maintenance action on the total cost based on when the action is performed. The model is used to compare structures managed by the traditional approach of post-earthquake inspection versus those managed by a condition-based approach enabled by SHM systems. The originality of the model empowers the comparison by payback time, defined as the break-even point between costs and benefits of an SHM system, as well as by economic gain, defined as the difference between the total costs of an unmonitored versus a monitored structure through the end of service life. The proposed model is demonstrated through parametric analyses on a case study consisting of a continuous steel-concrete composite bridge, where the SHM system is used to monitor the elastic limit state condition of bending forces in piers during the earthquake. Life-cycle cost analysis, Structural health monitoring, Earthquake-induced damage, Cost- benefit, Payback time 1 Introduction Civil infrastructures, such as transportation bridges, energy systems, and buildings, are prone to progressive deterioration and extraordinary events that may compromise their stability and lead to collapses that may cause large economic losses and fatalities [1, 2]. In order to prevent such consequences, these structures are subject to long-term management plans aimed at en- suring structural integrity, thereby reducing the expected value of the cost of failure. Typically, * [email protected] [email protected] lafl[email protected] § [email protected] 1

Upload: others

Post on 14-May-2021

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Life-cycle management cost analysis of transportation bridges

equipped with seismic structural health monitoring systems

Michela Torti∗1, Ilaria Venanzi†1, Simon Laflamme‡2, and Filippo Ubertini§1

1Department of Civil and Environmental Engineering, University of Perugia. Via G.Duranti, 93 - 06125 Perugia, Italy

2Department of Civil, Construction, and Environmental Engineering, Iowa StateUniversity, Ames, IA, USA

Abstract

Life-Cycle Cost Analysis (LCCA) is an approach that has gained popularity for assistingthe design of civil infrastructures. The LCCA approach can be leveraged for structuresequipped with structural health monitoring (SHM) systems in order to quantify the benefitsof the technology and de facto support its long-term implementation. However, for newstructures, the long-term assessment of the expected value of the total investment cost, interms of the current worth at the design time, is still the focus of ongoing research dueto unknowns and uncertainties on the impact of the SHM system on long-term structuralperformance. This paper proposes a new combined model of life-cycle cost formulationand simulation methodology for the long-term financial assessment of transportation bridgesequipped with seismic SHM systems, in order to evaluate the total costs and benefits offeredby such monitoring systems for post-seismic assessments. The formulation characterizes thetime evolution of bridge management cost terms, highlighting the most sensitive parameters.The simulation methodology allows to quantitatively weigh each maintenance action on thetotal cost based on when the action is performed. The model is used to compare structuresmanaged by the traditional approach of post-earthquake inspection versus those managed bya condition-based approach enabled by SHM systems. The originality of the model empowersthe comparison by payback time, defined as the break-even point between costs and benefitsof an SHM system, as well as by economic gain, defined as the difference between the totalcosts of an unmonitored versus a monitored structure through the end of service life. Theproposed model is demonstrated through parametric analyses on a case study consisting ofa continuous steel-concrete composite bridge, where the SHM system is used to monitor theelastic limit state condition of bending forces in piers during the earthquake.

Life-cycle cost analysis, Structural health monitoring, Earthquake-induced damage, Cost-benefit, Payback time

1 Introduction

Civil infrastructures, such as transportation bridges, energy systems, and buildings, are proneto progressive deterioration and extraordinary events that may compromise their stability andlead to collapses that may cause large economic losses and fatalities [1, 2]. In order to preventsuch consequences, these structures are subject to long-term management plans aimed at en-suring structural integrity, thereby reducing the expected value of the cost of failure. Typically,

[email protected][email protected][email protected]§[email protected]

1

Page 2: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

structural assessment is conducted through visual inspection conducted regularly as requiredby standards [3, 4]. It is also common to conduct post-event inspections to verify structuralintegrity [5]. It follows that such inspections result in time-based or maintenance-based actions.Nevertheless, it is known that condition-based maintenance actions could yield more optimalmaintenance operations, thereby reducing costs associated with operations [6, 7]. Such pro-cess would require immediate knowledge of structural conditions in order to plan managementcampaigns accordingly. The process of structural condition assessment can be automated bythe use of sensors and engineered signal processing algorithms, a process known as structuralhealth monitoring (SHM). Numerous research efforts have been devoted to the design and de-ployment of SHM strategies enabling condition-based maintenance, with a particular attentionto transportation bridges [8, 9, 10, 11]. However, the field deployment of these systems is stilluncommon, mainly attributable to the costs of the SHM systems and lack of clear financialbenefits.

A solution is to conduct life-cycle cost analysis (LCCA) to quantify the performance of SHMsystems over the structural lifetime. LCCA is often used to supplement the design process forcivil infrastructures deemed of great economic and societal importance. The methodology allowsto account for various costs, including those related to construction, inspection, maintenance,retrofits, and disposal [12, 13, 14, 15]. LCCA was extensively used to optimize bridge designs [16,17, 18, 19, 20, 21, 22], identify optimal retrofitting solutions [23, 24], evaluate the performanceof supplemental damping systems [25, 26], account for material degradation [27, 28, 29], andassess optimal bridge maintenance decisions [30, 31, 32]. LCCA was also proposed to quantifycosts and benefits of bridges equipped with SHM systems. Among those, Orcesi and Frangopol[33] included SHM data in a bridge life-cycle cost analysis framework in order to determineoptimal maintenance strategies based on monitoring information. Thomson [34] computed theeconomic value from the delayed cost of borrowing funds to replace or rehabilitate structuresresulting from SHM. Kim and Frangopol [35] proposed a computational platform to determinethe optimum number of monitorings, and the start and duration of the monitoring periods,based on multi-objective optimization. Cost analysis performs an active tool in the applicationof value of information theory of SHM [36], in order to tie SHM data to decision-making process:Long et al. [37] used economic benefit among the influencing parameters in the quantificationof the value of damage detection system (DDS), as part of SHM, and the Vega and Todd [38]in the quantification the value of implementing SHM using a Bayesian neural network (BNN)surrogate model.

Despite the existing efforts on cost-analysis for SHM systems, a complete tool that can bedirectly used by bridge managers during the decision process is still missing. In this paper, anovel combined model of life-cycle cost formulation and simulation methodology is proposed, inorder to evaluate the total costs and benefits offered by seismic SHM systems for post-earthquakeassessment of transportation bridges. The framework is termed LCCA-SHM. The cost modelcharacterizes the evolution of the different cost terms relative to the bridge management, suchas scheduled and post-event inspection and maintenance operations, over the lifetime of thestructure. The model accounts for the planned condition-based post-earthquake inspectionbased on seismic SHM data and maintenance strategy. In addition, the update on the probabilityof failure resulting from scheduled and post-event maintenance operations is performed, withconsequent improvement of the assessment of the expected value of maintenance costs. Thesimulation methodology consists of creating time distributions of seismic events along the lifetimeof a given bridge by sampling the site hazard curve, and numerically evaluating the structuralresponse by Finite Element (FE) modeling. Through an original combination of cost model andstochastic simulations, the main parameters influencing the financial gain for the specific typeof monitoring system are highlighted at first, and the expected gain quantified. The proposedmodel is demonstrated through the case study of a continuous steel-concrete composite bridgeequipped with a seismic SHM system in order to monitor the elastic limit state condition of

2

Page 3: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

the bending moment in piers during seismic events. The financial benefit of the seismic SHM-based inspection strategy is assessed and the performance is quantified in terms of paybacktime and economic gains. While the presented case study effectively illustrates how to applythe proposed LCCA framework in practice, reaching general conclusions on the superiority of aspecific monitoring strategy over a particular inspection plan is outside the scope of the presentpaper. The process is repeated a large number of times using the Monte Carlo method in orderto generate a probabilistic interpretation of the most sensitive parameters.

The proposed approach yields an original quantitative measure of the financial gain of thesystem in a life cycle perspective, identifying when and to what extent a seismic SHM monitoringsystem is actually worth installing. A typical decision that an infrastructure operator or managermay take based on the proposed method would be that of installing an array of sensors over abridge if the seismic hazard exceeds a certain level or if the indirect costs associated to a possiblepost-earthquake closure of the bridge would be too high considering the transportation networkin which it is to be inserted. The proposed methodological approach, illustrated in detail forseismic threshold systems, aims at addressing an unexplored gap in literature by providing apractical tool for the design of infrastructure monitoring and decision systems.

2 Proposed LCCA-SHM Model

2.1 Cost analysis of bridges with SHM systems

The expected total life-cycle cost of a monitored bridge can be expressed by extending previouscost models [39, 22, 40] as follows:

E[C(tL)] = C0,b + C0,SHM +

tL∑t=1

E[CS(t)] + E[CI(t)] + E[CM(t)]

(1 + r)t+

CD(tL)

(1 + r)tL(1)

where tL is the lifetime of the bridge (in years); C0,b the initial cost of the bridge taken asthe sum of construction and material costs of the various elements (foundations, structure,pavement, piles and abutements, etc.) and costs associated with design and testing; C0,SHM theSHM system initial cost comprising sensors, data acquisition system, data transmission system,and installation costs; E[CS(t)] the expected SHM system management cost at time t; E[CI(t)]the expected inspection cost; E[CM(t)] the expected structural maintenance cost; CD(tL) thedisposal cost for the demolition of the structure that occurs at time tL at the end of service life,and r the discount rate.

If the structure is equipped with a permanent monitoring system, the expected monitoringsystem cost can be defined as an annual management cost:

E[CS(t)] = cSnS(t) (2)

where cS is the reference cost of the monitoring system per unit of time, and nS the number ofunits of time. This includes the cost of electricity for powering the sensors and data acquisitionsystem, and the data processing costs, which can be expressed as a percentage of the initialcost, C0,SHM, based on the known electricity consumption of various components. Also, thisterm may include an annual rate to account for the need to replace or repair some componentsof the SHM system over the structural lifetime.

The use of an SHM system has the potential to yield savings in inspection and maintenanceoperations. The inspection costs are associated with scheduled operations carried out at regularintervals [41, 42], while maintenance costs depend on the probability of damage detection [16].The expected inspection costs at time t can be computed as:

E[CI(t)] = cschdI (t) + E[cSHMI (t)

](3)

3

Page 4: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

where cschdI denotes costs associated with scheduled and periodic inspections, with:

cschdI (t) =

L(t)∑l=1

nI,l(t)(cschdI,l + cschdI,l,ind

)(4)

where L is the total number of scheduled inspection operation types at time t; nI,l the number ofl-type inspections planned at time t; cschdI,l the l-type scheduled inspection direct cost; cschdI,l,ind theindirect cost, here defined as the cost corresponding to the discomfort to users for interruptionsor deviations of traffic caused by inspection operations [21, 43, 44].

Term E[cSHMI (t)] in equation (3) represents the costs of additional inspections with respect

to scheduled operations, which are activated following alerts from the monitoring system. Itcan be generally defined as the product of the unit cost of inspection and the probability ofoccurrence:

E[cSHMI (t)

]=

N∑i=1

pSHMI,i (t)

(cSHMI,i + cSHM

I,i,ind

)(5)

where N is the total number of types of limit states, or damages, that the monitoring system iscapable of detecting; pSHM

I,i (t) the probability that the monitoring system detects the i-th type

of damage; cSHMI,i and cSHM

I,i,ind are the direct and indirect inspection cost associated to the i-thtype of damage.

The expected maintenance costs at time t can be taken as:

E[CM(t)] = E[cschdM (t)

]+ E

[cSHMM (t)

](6)

where E[cschdM (t)] is the expected value of cost related to maintenance that must be conductedafter a previous scheduled inspection has detected damage, and, for nomenclature consistency,this operation is defined as scheduled maintenance; and E[cSHM

M (t)] the cost of maintenanceoperations that follow the alerts from the SHM system.

Term E[cschdM (t)] can be computed as:

E[cschdM (t)

]=

L(t)∑l=1

nI,l(t)∑j=1

pj,l(t)(cschdM,l + cschdM,l,ind

)(7)

where pj,l(t) is the probability that the j-th l-type inspection at time t reveals a damage; cschdM,l

and cschdM,l,ind are the direct and indirect scheduled maintenance operations costs planned to fixthe damage identified by the l-type inspection.

Term E[cSHMM (t)

]can be taken as:

E[cSHMM (t)

]=

N∑i=1

pSHMM,i (t)

(cSHMM,i + cSHM

M,i,ind

)(8)

where pSHMM,i (t) is the probability that the inspection confirms the i-th detected damage; cSHM

M,i

and cSHMM,i,ind are the direct and indirect maintenance costs planned to fix the i-th type of damage.

Indirect costs can be of significant importance, especially for unscheduled operations. Amongthose surveyed by Lee et al. [16], the cost of fatalities and accidents (CH), associated with theconsequences caused by interruptions or deviations, and the cost of road users (CU), associatedwith the traffic delay caused by management operations, are selected and considered in thiswork. Therefore, the indirect costs in Eqs. (4), (5), (7) and (8) are written:

cind = CH + CU (9)

4

Page 5: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Cost CH is evaluated as [45]:

CH = CMfNf + CMdNd + CGNG (10)

where CMf is the mean cost per injured user; Nf the number of injured users; CMd the meancost per dead user; Nd the total number of deaths; CG the mean cost per accidents; and NG thenumber of accidents.

Cost CU can be taken as [46]:

CU =

(L

Vt− L

Vn,i

)N ·ADT

2∑i=1

DTCipi (11)

where L is the length of the considered section road; Vt the restricted speed in the work area;Vn,i the speed in normal condition for the i-th user type, either car or truck; N the number ofworking days; ADT the average daily traffic; DTCi the cost per hours for the i-th user typeand pi is the percentage of vehicles of i-th type.

2.2 Life-cycle management cost of bridges equipped with Seismic SHM sys-tem

In this section, the previous equations are further specialized for an SHM system used in thepost-seismic evaluation of the structure’s critical components [47]. The term failure mode isused to indicate the investigated damage mechanism, and the term damage state denotes theseverity of the failure mode. Monitoring data can be used to define a condition-based post-eventinspection strategy. The SHM system provides mutually exclusive information on the healthstate of components for specific failure mode, DSi. These assessments are made with referenceto a threshold value THs for each assumed damage state of an i-th failure mode. Thresholdsare expressed in terms of reference parameters detectable by the system and representative ofeach failure mode. If during a seismic event the response of some critical structural componentsexceeds a percentage, PT , of the reference threshold, the system reports an alert (e.g., Damagedor Undamaged, or Undamaged, Damage1, ..., DamageS, Failure) relative to a level of damage.The choice of the percentage values depends on the level of safety to be guaranteed. It is alsoused to englobe all major sources of uncertainty in the problem, such as the precision of thesensors, the errors due to signal processing, and the epistemic errors that influence the analyticalestimate of the thresholds. After an alert from the monitoring system, extraordinary inspectionoperations are performed. Eventually, extraordinary maintenance operations are executed if theprevious inspection operations verified that the damage state is actually reached.

Due to the selected type of monitoring system, the costs associated with the alerts of themonitoring system are counted only when a seismic event occurs. For this purpose, the lifetimeof the instrumented bridge is subdivided into a set T of annual intervals ti (t1≤ti≤tL), fromwhich a subset T of earthquake arrival times ti is extracted. The management strategy for thebridge equipped with the SHM system is also specialized for post-seismic events. Two levels ofdamage, (Undamaged or Damaged), for each failure mode are considered in what follows. Sincefailure cost CF and disposal cost CD are not functions of monitoring, they are omitted in therest of the paper. For brevity, three possible conditions are considered:

a) ti 6∈ T;

b) ti ∈ T; for nDi (ti) critical bridge components, the monitoring system provides an alert forthe i-th failure mode so that they are classified as Damaged, but extraordinary inspectionsdo not confirm damage;

c) ti ∈ T; for nDi (ti) critical bridge components, the monitoring system provides an alert forthe i-th failure mode so that they are classified as Damaged, and extraordinary inspectionsconfirm damage.

5

Page 6: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

The possible presence of post-event damaged components not identified by the SHM systemis ignored in this paper.

For case a), the inspection and maintenance costs are obtained from Eqs.(3-5) and (6-8):

E[CI(ti)] =

L(ti)∑l=1

nI,l(ti)(cschdI,l + cschdI,l,ind

)(12)

E[CM(ti)] =

L(ti)∑l=1

nI,l(ti)∑j=1

pj,l(ti)(cschdM,l + cschdM,l,ind

)(13)

For case b), the inspection costs become:

E[CI(ti)] =

L(ti)∑l=1

nI,l(ti)(cschdI,l + cschdI,l,ind

)+

N∑i=i

nDi (ti)∑d=1

(cSHMI,i,d + cSHM

I,i,d,ind

)(14)

E[CM(ti)] =

L(ti)∑l=1

nI,l(ti)∑j=1

pj,l(ti)(cschdM,l + cschdM,l,ind

)(15)

where additional inspection operations are activated through the monitoring system’s alarmsfor the critical components of the bridge classified as ”Damaged” under a specific failure mode.

In case c), the inspection and maintenance costs become:

E[CI(ti)] =

L(ti)∑l=1

nI,l(ti)(cschdI,l + cschdI,l,ind

)+

N∑i=1

nDi (ti)∑d=1

(cSHMI,i,d + cSHM

I,i,d,ind

)(16)

E[CM(ti)] =

L(ti)∑l=1

nI,l(ti)∑j=1

pj,l(ti)(cschdM,l + cschdM,l,ind

)+

N∑i=1

nDi (ti)∑d=1

(cSHMM,i,d + cSHM

M,i,d,ind

)(17)

where, in addition to possible scheduled maintenance operations triggered at time ti, extraordi-nary inspections are also performed for the nDi (ti) critical components of the bridge.

3 Simulation methodology

3.1 Post-event operations

To simulate the probabilities associated with the SHM system, pSHMI,i (t) and pSHM

M,i (t), the set T(called hereafter earthquake realization) comprising the arrival times of seismic events, duringthe lifetime of the bridge and their intensities, and the structural responses are evaluated usingthe following methodology:

1) Outline condition-based post-earthquake inspection strategy, in accordance with the pre-vious section:

a) select the number, N , and the types of the failure modes, DSi, of the bridge tomonitor;

b) identify for each DSi the number and the types of the damage states;

c) choose the most representative damage parameter associated with the identified dam-age states, compute the corresponding threshold values, THs, and set the percentages;

d) set up the most suitable seismic SHM system able to monitor the selected damageparameter, in order to compute the monitoring costs; and

6

Page 7: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

e) organise the extraodinary inspections referred to the exceedace of each %THs, inorder to compute the costs related to each operations.

2) Generate earthquake realizations for the structure’s lifetime by Monte-Carlo method [12],as follows:

a) define the seismic hazard curve of the site (Peak Ground Acceleration, PGA, versusannual frequency of exceedance, λ);

b) sample the PGA values from the hazard curve of the bridge site;

c) generate for each pair PGA-λ a statistically significant size sample of the arrival times,ti, of the event of intensity PGA and mean λ according to the Poisson distribution:the events are considered as uncorrelated and the sample sizes are equal and chosenon the basis of the largest return period of the variables; and

d) extract randomly a lifetime size window for each PGA: the overlapping of the timewindows for the different PGAs provides the distribution of the seismic events ofinterest over bridge lifetime.

3) collect a database of acceleration time series sorted by seismic intensity corresponding tothe PGA values obtained by sampling of the hazard curve;

4) construct the FE model of the bridge and apply the acceleration time series in accordancewith the earthquake realizations; and

5) extract structural responses randomly from an acceleration time series among those avail-able within the intensity category corresponding to that of the earthquake.

Based on the presented methodology, the probabilities at time ti take binary values dependingon the simulation results: pSHM

I,i is equal to 1 when the percentage value PT of the reference

threshold THs is exceeded, while pSHMM,i is equal to 1 when the damage is confirmed by the

inspection, that here coincides with the case where the full threshold (100% value) is exceeded.

3.2 Scheduled operations

Scheduled inspections are meant to ensure structural integrity and are used to detect damagecaused by degradation, corrosion, etc. In this work, the effects of this process on the structuralperformance are represented by the probability pj,l(t), so defined in section ”Cost analysis ofbridges with SHM systems” and hereinafter defined as p(t). The assessment of the process’s timeevolution in the design phase allows to simulate the schedule management operations. This apriori evaluation can be conducted per failure mode.

To assess the damage probability, let EDP be a vector collecting the Engineering DemandParameter that have to be limited in order to avoid potential failure modes during an earthquake,the occurrence of a failure mode, DS, is described by a fragility function P (DS|EDP ) that isthe complementary cumulative distribution function of DS, conditional on the occurrence ofEDP . Without loss of generality, it is assumed that the fragility function varies discretely everyyear as a function of structural degradation. The mean value of the distribution represents thestructural capacity for the failure mode that decreases with ageing.

By exploiting the damage-dependent fragility function, the probability of failure is com-puted according to the following hypotheses: i) the uncertainty in the structural parametersis neglected; ii) the structural behaviour is linear; iii) the structure is restored to its originalcondition after each damage occurrence; and iv) damage is either caused by ageing or by theoccurrence of seismic events.

7

Page 8: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Under these assumptions, the generic annual probability of exceeding the examined failuremode, p(t), can be computed as [13, 14, 48, 49]:

p(t) =

∫ ∫P (DS|EDP )(t)f(EDP |IM)f(IM)d(EDP )d(IM) (18)

where IM the vector of the seismic intensity measures (e.g. the PGA at the site of the bridge);f(EDP |IM) the probability density function (PDF) of EDP conditional on IM and f(IM)the PDF of the seismic intensity measure.

4 Case Study

4.1 Bridge numerical model

The proposed LCCA methodology is numerically demonstrated on an example structure consist-ing of an existing curved plan configuration continuous steel-concrete composite highway bridgelocated in central Italy. The bridge includes 10 spans of lengths varying from 44 to 70 m, fora total length of 574 m. The deck is 12.55 m wide and the cross-section is constituted by twodouble-T steel girders spaced at 7 m and covered with 32 cm thick concrete slab (26 cm of castin-situ concrete and 6 cm of pre-cast slab). The steel girders are fabricated by welding togetherseveral segments, with lengths varying between 5 and 15 m. The cross-section of the steel beamsvaries along the length of the bridge, with a total of 20 different cross-sections. Both main girdersare transversely connected every 5 m. The concrete piers have a hollow rectangular cross-sectionthat remains constant along the height, while the caps have a variable cross-section. Bearingsare augmented with elastoplastics seismic isolators to improve seismic resistance. The strengthclass of concrete is C35/45 for slabs and C28/35 for piers. The characteristic yield strengthof reinforcement steel is 450 MPa, and S355 steel is used for steel elements. Figure 1 shows aplan view of the bridge (Figure 1(a)) and the cross-section of the deck (Figure 1(b)) and piers(Figure 1(c)).

A finite element (FE) model of the whole bridge is constructed in CSiBridge [50] usingshell elements for the concrete slabs, and beam elements for steel girders and transverse beams.The studs connecting the steel frame to concrete are modeled using linear link connections. Asingle nonprismatic frame is used to model each pier to take into account the variation in cross-section from the base of the column to the cap. The piers are considered fixed at the base, andsoil-structure interaction is neglected. The bearings are modeled by linear link elements withappropriate stiffness. Linear material properties are assumed for all structural elements in orderto limit computational effort and therefore facilitate large numbers of simulations. However,when cracking limit displacements are overcome, displacements obtained from linear analysesare manually amplified by the ratio of the bending stiffness equivalent to the elastic limit of thebase section to the bending stiffness of the uncracked section. Figure 2 summarizes the maindynamic properties of the structures.

4.2 SHM system and post-event operations strategy

In accordance with section ”Simulation methodology”, flexural failure at the base of the piersis the failure mode to monitor, considered as one of the most critical seismic-induced failuremode [51]. For that purpose, the SHM system consists of bidirectional accelerometers placed atthe top and bottom of each pier. During an earthquake, the accelerometers record the absoluteaccelerations in both principal directions. The column drift is estimated by double integratingthe recorded accelerations assuming zero initial displacements and velocities. Remark that suchmethodology is only applicable to short-length signals, such as those produced by a seismicevent, and yields the dynamics peak-to-peak displacement amplitude, but does not allow themeasurement of permanent displacements. The maximum dynamic amplitude displacements are

8

Page 9: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

15.5

55

5.6

9.6 10.1 9.115.5

55

10.6

506060 6040 70 70 50

11.110.6 11.6

Accelerometer

(b)

12.55

7.00

3.00

0.90

6.00

2.00

0.30

1.96

Φ16

Φ22

0.32

(a)

A

A

B B

Section A - A Section B - B

(c)

P1 P2 P3 P4 P5 P6 P7 P8 P9 P10

Figure 1: Plan and lateral views of the bridge, with annotated accelerometer positions at thebottom and the top of the piers and pier numbering (a), cross-sections of the deck (b) and piers(c) (dimensions in [m]).

leveraged to quantify possible flexural damage. The position of the accelerometers is annotatedin Figure 1(a).

The failure mode of interest is the elastic limit of steel reinforcement bars. Three damagestates are considered: Undamaged (UD), Damage-1 (D1) and Damage-2 (D2), and two thresh-olds are established: 1) the relative displacement between the top and bottom section of thepiers causing cracking, δcr,i, and 2) the relative displacement between the top and bottom sectioncausing yielding, δy,i. Given that scheduled maintenance activities are carried out during thebridge lifetime, the threshold values are assumed to be constant over time and are evaluatedbased on the characteristic values of fy and As at the time of construction. To take into accountthe error arising from the double integration of acceleration measurements to compute drift andsensors precision, the target threshold values are set to 80% of the analytically obtained values.From the estimation of the drift δi at pier i, following inspection strategies are adopted:

• for δi < 0.8δcr,i, the structure is undamaged (UD) and no extraordinary inspection isperformed;

• for δi ≥ 0.8δcr,i and δi < 0.8δy,i, damage state D1 is diagnosed and an extraordinaryinspection D1 is performed;

• for δi ≥ 0.8δy,i, damage state D2 is diagnosed and an extraordinary inspection D2 isperformed.

The selection of the PT value is commented in section ”Percentage value”. A maximumdegree of reliability has been associated to the post-event inspection outcomes as they do notusually limit to visual checks but also include in-situ instrumental testing. This assumption wasmade as a starting point for the proposed framework. While others have discussed the general

9

Page 10: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Figure 2: Main dynamic properties of the bridge: first longitidinal mode shape (a), first transver-sal mode shape (b), first vertical mode shape (c).

10

Page 11: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Figure 3: Seismic hazard curve.

high variability in inspections and thus lack of reliability[66], it can be estimated that morecareful inspections and extensive testing are conducted after strong earthquakes.

The two different extraordinary maintenance operations, D1 and D2, are performed followingpost-event inspections when the flexural, δcr,i, or the elastic limit, δy,i, are exceeded, respectively.

4.3 Scheduled inspection and maintenance operations strategy

The annual probability of reaching a failure mode, which increases with time due to degradation(i.e., corrosion in this case study), is assessed according to equation (18), with the followingassumptions:

• PGA is selected as the IM, because it was shown to be the best parameter to characterizethe seismic hazard for bridges [52]. The seismic hazard curve is taken from the ItalianNational Institute of Geophysics and Volcanology [53]. The hazard curve is plotted inFigure 3 and Table 1 lists its main parameters. Figure 3 also indicates the value of thePGA used in the original bridge design according to the Italian standards that governedwhen the bridge was constructed [54];

• The Interstory Drift Ratio (IDR) of each pier evaluated from the relative displacementbetween the top and bottom sections during a seismic event is taken as the EDP ;

• Only the bending in the weak direction of each pier is considered in order to derive thefragility curves;

The probability density function of the IDR is computed by structural analysis. The struc-tural response of the bridge is evaluated by linear time history analysis using 20 accelerationtime series taken from PEER-NISEE library [55] from the Los Angeles area, with a 10% prob-ability of exceedance in 50 years. From these analyses, the mean and standard deviation of thepeak response under earthquake (IDRm and IDRσ) are derived. Since the bridge response islinear, the peak values are computed in correspondence of each intensity level, PGAi, by scalingthe mean values, as follows:

IDRm|PGAi = IDRm|PGAref ·PGAiPGAref

(19)

IDRσ|PGAi = IDRσ|PGAref ·PGAiPGAref

(20)

11

Page 12: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Table 1: Parameters of the seismic hazard curve.

Mean annual rate PGA [g] Magnitude [M]-Distance [km]

0.0004 0.6247 6.600-6.0500.0010 0.4029 6.340-7.9100.0021 0.2780 6.140-9.6600.0050 0.1765 5.910-12.0000.0071 0.1416 5.800-13.2000.0099 0.1133 5.700-14.6000.0139 0.0887 5.590-16.3000.0200 0.0684 5.480-18.7000.0333 0.0498 5.340-23.400

where PGAref is the mean value of the peak ground acceleration computed with the 20 accel-eration time series [14]. The probability density function of IDR is evaluated from the mean-standard deviation pairs of the different hazard intensity values, adopting a lognormal fragilitydistribution [56, 57].

The time effect of corrosion is taken into account through a simple degradation model de-scribing the temporal variation of steel reinforcement bars’ yield strength (fy) and cross-sectionarea (As), as follows [22, 58]:

fy(t) = [1− δfy(t)]fy,0 (21)

As(t) = [1− δAs(t)]As,0 (22)

where δfy and δAs are damage states within the range [0,1], while fy,0 and As,0 are the initialvalues of the deteriorating quantities. The temporal trends of the δ-coefficients are representedby [22, 58]:

δfy = δAs =

ω(1−ρ)τρ τ ≤ ω1− (1− ω)(1−ρ)(1− τ)ρ ω < τ < 1

1 τ ≥ 1

where ω = 0.75, ρ = 1.5, τ = t/T1 and T1 is time when the failure threshold is reached; in thispaper, the value T1 = 75 years is taken.

Figure 4 plots the temporal evolution of the relative variation, ∆, of mechanical properties asa function of time t (in years) with respect to their initial values, showing the flexural strength atthe elastic limit at pier P8, ∆M; the ∆δ-coefficients; the steel reinforcement bars’ yield strength,∆fy, and the cross-section area, ∆As.

The time varying probability that the elastic limitfor bar yielding is reached at the bottomsection of the piers is computed by assuming a lognormal fragility function P (DS|EDP )(t) inequation (18), with EDP being the IDR. This lognormal fragility is specialized by consideringa mean value equal to ln(IDR(t)), IDR(t) being the capacity of the cross section in terms ofinterstory drift ratio computed considering mean material properties at time t, and a standarddeviation σln(IDR) equal to 0.5. Figure 5 plots the fragility curves of the considered limit stateover different years (Figure 5(a)) and the time evolution of the annual probability of exceedanceof the elastic limit at pier P8, obtained by applying equation (18) (Figure 5(b)).

Scheduled maintenance operations occur when scheduled inspections discover the presenceof a damage. Here, scheduled maintenance is assumed when the initial value of the annualprobability of failure, pi, of the i-th pier is exceeded by 50%.

Table 2 summarizes the adopted strategies for scheduled and post-event operations for abridge with a seismic SHM system.

12

Page 13: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Figure 4: Time evolution of relative changes in: flexural strength at pier P8 ∆M, δ-coefficients,bar yield strength ∆fy, and steel cross-section area ∆As.

Figure 5: Time-dependent fragility curves at t=1, t=25, t=50 and t=tL (a) and time evolutionof the annual probability of exceedance of the elastic limit at pier P8 (b).

Table 2: Inspection and maintenance strategies with SHM system.

Operation Type Cost Frequency

Scheduled inspection

Visual inspectionlevel-1

e 3 months [3]

Visual inspectionlevel-2

ee Annual [3]

Post-event inspectionExtra I. D1 e Post-seismic when

0.8δy,i≤δi¡0.8δy,iExtra I. D2 eee Post-seismic when δi≥0.8δy,i

Scheduled maintenance Schduled e when pi(t)≥1.5pi(t = 1)

Post-event maintenanceExtra M. D1 e Post-seismic when

δcr,i≤δi<δy,iExtra M. D2 ee Post-eart. when δi≥δy,i

13

Page 14: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Table 3: Direct operation costs.[59, 60]

Type Cost item Cost

cschdI,lVisual inspection level-1 297 [e/pier]Visual inspection level-2 553 [e/pier]

cSHMI,i

Extra I. D1 297 [e/pier]Extra I. D1 975 [e/pier]

cschdM,l Scheduled 875 · h [e/m]

cSHMM,i

Extra M. D1 875 · h [e/m]Extra M. D1 3100 · h [e/m]

4.4 Cost quantities

The cost quantities for this case study are taken as follows. The initial cost of the bridge,C0 = 2.10 Me, is taken from design documents and corresponds to the cost of the substructure.

A low-cost SHM system, characterized by low acquisition and maintenance costs, is consid-ered in the analysis. Twenty biaxial sensors are considered with a purchase cost of 100 eeach.An additional cost for installation, and data acquisition and transmission electronics, equal to50% of the sensors purchase cost, is assumed, bringing the total initial cost of the monitoringsystem to 3000 e. The yearly cost of the SHM system management, CS, is taken as 10% ofC0,SHM.

The direct costs of the inspection and maintenance operations (cschdI,l , cSHMI,i , cschdM,l , cSHM

M,i inEqs.(4), (5), (7) and (8)) are quantified using costs reported in proper cost lists [59, 60]. InTable 3, the direct costs for each operation referred to the analyzed failure mode are reported,where h indicates the height of a given pier.

Two indirect cost cases are considered: low indirect costs and high indirect costs. Lowindirect costs scenario corresponds to a small deviation length of traffic, equal to the lengthof the bridge plus 350 m on both sides. High indirect costs scenario corresponds to a longerdeviation, here taken as the actual required deviation for the considered bridge, equal to 6.8km. The units cost in equation (10) are derived from standards [45]. Up-to-date statistics onthe number of accidents, injuries and deaths on Italian roads used in the case study are takenas the averaged values for the Umbria and Marche Italian regions to be consistent with thebridge’s location [61]. These values refer to normal circulation conditions. In order to evaluatethe impact produced by a road deviation, the percentages of increases in accidents equal to 31%for Nd and 41% for Nf and NG are applied [62]. Also, since the available values are annual valuesand refer to the unit of road length [61], they are multiplied by the length of the consideredroad section and for the duration of the work. A time equal to 1 day is required to carryout the extraordinary inspections D2 of all 10 piers and a time equal to 3 days is required forextraordinary maintenance D2 of all 10 piers. Therefore, in the case of extraordinary inspectionsD2 or extraordinary maintenance D2 on a single pier, the unit cost is estimated as 1/10 of thatrelating to all the piers. No traffic disruption is required for other operations, hence no indirectcosts are associated with them. The values of Vn,i and DTCi in equation (11) can be found inOrcesi et al. [46], while the ADT and pi values are obtained from traffic data collecting processes[63]. Table 4 lists the values associated with indirect costs.

4.5 Example LCCA-SHM result

Figure 6 shows a typical LCCA-SHM result. It plots the time evolution of the key cumulative costitems at the top, and the trend of the probabilities of failure of the ten piers at the bottom. These

14

Page 15: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Table 4: Indirect costs associated with fatalities and accidents, CH and indirect costs associatedto road users, CU.[45, 61, 62, 63, 46]

Cost item Low indirect costs High indirect costs

CH-Extra I. D2 11 [e/pier] 63 [e/pier]CU-Extra I. D2 332 [e/pier] 1773 [e/pier]CH-Extra M. D2 33 [e/pier] 179 [e/pier]CU-Extra M. D2 997 [e/pier] 5320 [e/pier]

results are obtained from a realization, where the occurrence of seismic events are representedby dashed vertical lines. The analysis was conducted for the low indirect costs scenario, overthe assumed 100 years structural lifetime. A discount rate, r = 0.00 is assumed in order toprovide a conservative estimate of the cost increases of the operations and so to maximize thecorresponding leaps on the graph.

Examining the effect of scheduled operations, the figure reports i) the progressive increasingof cschdI due to the regular scheduling of operations over the bridge’s lifetime as prescribedby the standards; and ii) the evolution of cschdM . cschdM following the growing trends of theprobability of failure of the piers due to corrosion, and takes into account the costs of scheduledmaintenances at the years where the probabilities exceed the limit value (section ”Scheduledinspection and maintenance operations strategy”), as shown by the leaps in cost followed by thedrop in probabilities.

For the extraordinary operations, the figure shows the adopted condition-based maintenancestrategies. For example, at the years 39, 73 and 88, no piers exceed the thresholds, thereforethe SHM system does not provide alerts and neither inspection nor maintenance are performed(cSHM

I and cSHMM remain flat). In the year 31, a false alert is generated by the monitoring system

(leap on cSHMI ), but these alarms are not confirmed by the extraordinary inspection (cSHM

M

remains flat). For the remaining events, the post-event inspections (rise on cSHMI ) confirm the

results of the SHM systems, therefore, extraordinary maintenance are performed (leap on cSHMM

and probabilities are updated). The bold lines at the bottom of the figure indicate the piersthat have reached or exceeded the yielding in the bottom section during an earthquake. Theseare piers P5, P8 and P9 at years 25 abd 43 and pier P10 at year 27.

Finally, the total cost C includes all the previous items, the initial purchase costs, C0 andC0,SHM, and the cost of the SHM system management, CS, that gradually increases over thelifetime.

The cumulative cost of post-earthquake inspections remains affordable thanks to the monitor-ing system data, limiting the number of controls to be carried out based on structural response:for only four out of seven seismic events, and for a reduced number of elements, the post-eventinspections are triggered.

5 Comparison of traditional versus SHM-based inspection strate-gies

The LCCA-SHM model is used to compare cost evolutions of the bridge managed by a tradi-tional approach versus an SHM-based approach. Traditional post-event inspection managementstrategies require detailed inspections to be carried out on the whole structure, leading to highdirect and indirect costs. The SHM data allows to reduce these operations only to piers thatexceed the thresholds during the earthquake. Two parameters are identified among the morerelevant ones for highlighting the benefit of the monitoring system: indirect costs, which signif-icantly affect the total cost of extraordinary operations, and the discount rate, which reduces

15

Page 16: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Figure 6: Time evolution of cumulative cost items, at the top, and of probabilities of failure ofthe piers, at the bottom, for a generic earthquake realization.

over time the accumulated gain with the seismic events. Site seismic hazard and the duration ofthe monitoring period are two other important aspects that may significantly influence the costanalyses for the selected monitoring system, that is for a seismic SHM system. These parametershave been addressed in [64].

The evaluation parameters are the economic gain, G, and the payback time tPB. The eco-nomic gain, G, of the monitoring system is defined as the difference between the final totalcost of the monitored bridge and that without the SHM system [65]. The generation of theearthquake realizations through the simulation methodology allows to compare, annually, thecost terms. This comparison on the time distribution of seismic events leads to the paybacktime tPB of the monitoring system, which is used as another metric. Here, the economic gain Gis taken as:

G = E[C(100)]− E[C(100)]|SHM (23)

The payback time tPB is taken at the time when the cumulative costs are equal, assessed for thecases in which a positive value of G is obtained:

tPB : E[C(tPB)]|SHM = E[C(tPB)] (24)

The comparison is made for the two indirect costs scenarios, low and high, and for discountrates r = 0.00, 0.01, 0.02, 0.03, 0.04, and 0.05. In order to provide accurate estimates of theevaluation parameters with the respective probability values, comparisons have been performedfor a high number of earthquake realizations, equal to 2000 in the following analyses, that is theminimum number of simulations required to make the sample statistically significant.

Figure 7 shows two realizations of seismic events corresponding to opposite cases: in Fig-ure 7(a), the SHM system is economically viable, and in Figure 7(b), the SHM is not. Thecomparison refers to the low indirect costs scenario and r equal to 0.02. Seismic events aredepicted by vertical lines. A large number of seismic events occurs during realization n◦ 500,

16

Page 17: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Table 5: Mean and COV of the G sample for Low and High indirect costs scenarios and thedifferent value of r.∗ average percentage value of the relative variations counted for each increase in r.

Low indirect costs High indirect costsr mean [e] COV mean [e] COV

0.00 43520 0.72 131030 0.510.01 26200 0.78 81210 0.540.02 16780 0.94 54170 0.620.03 12638 1.02 41360 0.670.04 8670 1.24 30410 0.760.05 6380 1.55 23901 0.88

δm ∗ 32% 17% 28% 11%

most of them in the first half of the lifetime when the discount rate has a low effect on thecost. For simulation case n◦ 500, Figure 7(a) shows the cumulative annual total costs with andwithout the SHM system. The payback time tPBcan be identified between t = 4 and t = 5.Conversely, for simulation case n◦ 712, Figure 7(b) shows that the cumulative annual total costswith and without SHM are similar. Simulation case n◦ 712 is characterized by a single seismicevent, which occurs in the final part of the realization, where costs are reduced as a result ofthe discount rate. For simulation case n◦ 712, no payback time can be identified, whereas theSHM system fails at being economically viable.

5.1 Results - Economic gain

The G values obtained for the 2000 earthquake realizations are shown in Figure 8 by theirrelative frequency distributions, for the two analyzed scenarios (low indirect costs in black andhigh indirect costs in red) and for the different r values. For clarity, the frequency distributionis only graphed for r = 0.00 and low indirect costs along with its fitting curve; for the othercases, only the distribution fitting curves are graphed. Results show that, for the selectedmonitoring system, G may sometimes take a negative value. However, the distribution is stronglyskewed towards positive values. The sample mean of the distributions are always positive forboth indirect costs scenarios, as reported in Table 5. When r = 0.00, the relative frequencydistribution is quite symmetric around the mean value. When the r effect is excluded, the gainis mainly influenced by the number of seismic events, as well as by the system’s response to thewaveform, hence the shape of the distribution is directly related to the distribution of the numberof events occurring in the simulated realizations. The increase in the discount rate has the dualeffect of reducing the expected value of G and making the frequency distribution increasinglyasymmetric. Since seismic events that occur in later years cause a progressively smaller expectedgain, G is mainly determined by the seismic events that occur in the early years of the lifetimeand, therefore, the distribution is unbalanced towards lower values. Positive distribution tailsrepresent cases with a high number of events balancing the effect of r. In the scenario of highindirect costs, the G histogram shifts to higher positive values. The same effect of r is found onthe mean and the coefficient of variation, but to a minor extent due to the higher gain offeredfor each seismic event.

5.2 Results - Payback time

The results of the analyses by payback time, tPB, are reported in Table 6 and in Figure 9.The figure shows the overlapping of relative frequency distributions of the payback periods for

17

Page 18: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Figure 7: Comparison of cumulative annual total costs in simulation case n◦ 500 (a) and n◦ 712(b), for low indirect costs and r=0.02.

18

Page 19: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Figure 8: Fitting curves of relative frequency distributions of G for Low (black) and High (red)indirect costs and the different value of r.

Table 6: Mean of payback period and percentage of economically viable cases.

Low indirect costs High indirect costsr mean [years] NC% mean [years] NC%

0.00 18.3 93.8 17.4 98.50.01 18.1 91.4 17.5 98.50.02 17.6 86.7 17.6 97.10.03 15.5 83.1 16.4 96.10.04 14.1 77.6 15.8 92.60.05 13.3 70.8 14.7 88.1

low and high indirect costs, for r = 0.00 (a), r = 0.02 (b), and r = 0.05 (c). These resultsshow that, when economically viable, the payback period of the SHM system tends to be inthe early 10-20 years after the implementation in any condition, as reported by the averagevalues in Table 6. Denoting with NC the relative frequency of the total number of realizationsin which G is positive, namely when the SHM system is economically viable, one can note thatNC increases from 70% for low indirect costs and r = 0.05 to more then 98% for high indirectcosts and r = 0.00.

5.3 Percentage value

For completeness, the sensitivity analysis of the financial gain G with respect to the PT valuesis reported, by studying a variation of PT in the range [0, 100] % with 0.01% step increments.Figure 10 shows the mean value of G for the 2000 simulations conducted at every analyzedpercentage value, under r = 0.00, r = 0.02 and r = 0.05. The sensitivity of the gain G to thedamage detection performance of monitoring system is insignificant starting from 60% for all r-values. In light of these results, a value of PT = 80% is selected, arguing that it is small enoughfor considering all major sources of uncertainty affecting the problem, but also large enough tohave limited influence on G. In this regard, it should be also noted that structural capacity

19

Page 20: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Figure 9: Relative frequency distribution of payback period for Low (black) and High (red)indirect costs, overlapping distributions, for r = 0.00 (a), r = 0.02 (b) and r = 0.05 (c).

values are here computed considering characteristic material properties and are, therefore, likelysignificantly underestimated. This aspect contributes to making PT = 80% a reasonable numberfor constituting the alarm thresholds.

6 Conclusions

This paper proposed a novel combined life-cycle cost analysis (LCCA) formulation and simula-tion methodology for transportation bridges equipped with seismic structural health monitoring(SHM) systems. The model, termed LCCA-SHM, is capable of taking into account the extracosts arising from the SHM system, namely the initial and SHM management/maintenancecosts, as well as the economic benefits resulting from the use of SHM data for optimal inspec-tion strategies. The model can be used both as a tool for optimal design of the monitoringsystem targeting specific limit states, and as a mean to compare between different managementstrategies by defining cost benefit indicators. The payback time, defined as the break-even pointbetween costs and benefits of an SHM system, has been evaluated by annual comparison ofthe responses to earthquake realizations generated by the simulation methodology, as well asthe economic gain. The analyses were performed for different values of discount rate and indi-rect costs, which parameters were identified as the most sensitive with respect to post-seismicinspection strategies.

The proposed methodology has been numerically demonstrated on an example steel-concretecomposite bridge equipped with a seismic SHM system, where the SHM system was used toanalyze if critical components were reaching a given limit state. Results showed that the SHMsystem designed to monitor seismic performance was capable of yielding economic gains in termsof post-event inspection costs, but that the gain on total cost was strongly dependent on theassumed value of the discount rate and the level of indirect costs. It is noted, however, thatthe results obtained for the case study are aimed at demonstrating how to apply the proposedLCCA framework in practice and at showing what type of financial performance metrics couldbe obtained considering realistic cases; the objective is not to reach general conclusions aboutthe superiority of a specific monitoring strategy over a particular inspection plan. Applying theproposed method to the specific case study, it was shown for instance that, under low indirectcosts where traffic deviation only occurred over a limited length of road, the SHM system yieldedan increase in costs of approximately the 30% under a r=0.05, and below the 7% for r=0.00. Theeconomic benefits of the SHM system were more substantial in the case of high indirect costs,where traffic was deviated over a long transition length, in which approximately only 1/10 of the

20

Page 21: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

Figure 10: Comparison of the expected value of G (mean value among 2000 simulation cases)as a function of percentage value PT for r = 0.00, r = 0.02 and r = 0.05.

realizations resulted in an increase in costs for high discount rates. Nevertheless, when the effectof the discount rate is neglected, SHM system was viable in nearly all cases. It is worth notingthat the reduction in indirect costs depends on the availability of accurate information regardingthe conditions of the bridge. In this specific example, such information was provided by the SHMsystem; in other situations, the information may be provided by successful inspection. Finally,it was found that, when economically viable, the SHM system provided a payback period under50 years, with an average between 13 and 18 years. Although the mean value of the economicgain was severely influenced by both the discount rate and the indirect costs, the distribution ofthe payback time for positive cases did not show the same sensitivity. The higher the discountrate, the less the distribution was scattered, but the variation on the mean value was practicallynegligible.

Overall, the presented results showed that the proposed combined model could be used toquantify the economic benefits of an SHM system installed on a multi-span bridge. Whileequipping a bridge with a monitoring system comes at extra costs, enabling condition-basedpost-event inspections can yield important gains. The objective of the proposed LCCA-SHMmodel is to quantify such gains with respect to overall costs. The adopted probabilistic approachof the analyses allows to obtain weighted measures of the financial gain of the system in a lifecycle perspective, supporting bridge operators and managers by indicating whether a seismicSHM monitoring system is actually worth installing.

The model can be easily extended to other limit states of interest, therefore applying toother types of SHM systems and structures, as well as for evaluating the influence of othermeaningful parameters. Future developments of the work are to extend the proposed model todifferent types of monitoring strategies, for instance fatigue monitoring in steel bridges usingweigh in motion sensors and continuous vibration-based monitoring through statistical patternrecognition approaches. A more in-depth evaluation of costs associated with signal processingerrors and, in particular, missing alarms also needs to be carried out. Likewise, the considerationof the other SHM strategies and other failure mechanisms may elevate the LCCA-SHM algorithmfrom the component level (e.g. assessment at each pier) to the global level.

The support of the Italian Ministry of University and Research (MIUR) and of the Universityof Perugia are acknowledged, within the program ”Dipartimenti di Eccellenza 2018-2022”. The

21

Page 22: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

authors gratefully acknowledge the support of the “Fondazione Cassa di Risparmio di Perugia”that funded this study through the project “Sviluppo di un modello originale di costo di ciclo divita per la gestione ottimale di ponti e viadotti con sistema di monitoraggio integrato” (ProjectCode 2019.0338.029).

References

[1] Bazzucchi F, Restuccia L and Ferro G. Considerations over the italian road bridge infras-tructure safety after the polcevera viaduct collapse: Past errors and future perspectives.Frattura ed Integrita Strutturale 2018; 12: 400–421. DOI:10.3221/IGF-ESIS.46.37.

[2] Ragni L, Scozzese F, Gara F et al. Dynamic identification and collapse assessment ofRubbianello Bridge. In IABSE Symposium, Guimaraes 2019: Towards a Resilient BuiltEnvironment Risk and Asset Management - Report. pp. 619–626.

[3] Ministero dei Lavori Pubblici. Circolare n° 6736/61/AI del 19.07.1967, ”Controllo dellecondizioni di stabilita delle opere d’arte stradali”, 1967.

[4] Nielsen D, Raman D and Chattopadhyay G. Life cycle management for railway bridgeassets. Proceedings of the Institution of Mechanical Engineers, Part F: Journal of Rail andRapid Transit 2013; 227(5): 570–581. DOI:10.1177/0954409713501297.

[5] Limongelli MP, Miraglia S and Fathi A. The value of visual inspections for emergencymanagement of bridges under seismic hazard, 2018.

[6] Downey A, Laflamme S and Ubertini F. Experimental wind tunnel study of a smart sensingskin for condition evaluation of a wind turbine blade. Smart Materials and Structures 2017;26(12): 125005.

[7] Vagnoli M, Remenyte-Prescott R and Andrews J. Railway bridge structural health monitor-ing and fault detection: State-of-the-art methods and future challenges. Structural HealthMonitoring 2018; 17(4): 971–1007. DOI:10.1177/1475921717721137.

[8] Kong X, Li J, Collins W et al. Sensing distortion-induced fatigue cracks in steel bridgeswith capacitive skin sensor arrays. Smart Materials and Structures 2018; 27(11): 115008.DOI:10.1088/1361-665x/aadbfb.

[9] An Y, Chatzi E, Sim SH et al. Recent progress and future trends on damage identificationmethods for bridge structures. Structural Control and Health Monitoring 2019; 26(10):e2416. DOI:10.1002/stc.2416.

[10] Abdulkarem M, Samsudin K, Rokhani FZ et al. Wireless sensor network for structuralhealth monitoring: A contemporary review of technologies, challenges, and future direction.Structural Health Monitoring 2019; DOI:10.1177/1475921719854528.

[11] Wu RT and Jahanshahi MR. Data fusion approaches for structural health monitoring andsystem identification: Past, present, and future. Structural Health Monitoring 2020; 19(2):552–586. DOI:10.1177/1475921718798769.

[12] Ierimonti L, Caracoglia L, Venanzi I et al. Investigation on life-cycle damage cost of wind-excited tall buildings considering directionality effects. Journal of Wind Engineering andIndustrial Aerodynamics 2017; 171: 207–218. DOI:10.1016/j.jweia.2017.09.020.

[13] Ierimonti L, Venanzi I and Caracoglia L. Life-cycle damage-based cost analysis of tallbuildings equipped with tuned mass dampers. Journal of Wind Engineering and IndustrialAerodynamics 2018; 176: 54–64. DOI:10.1016/j.jweia.2018.03.009.

22

Page 23: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

[14] Venanzi I, Lavan O, Ierimonti L et al. Multi-hazard loss analysis of tall buildings underwind and seismic loads. Structure and Infrastructure Engineering 2018; 14(10): 1295–1311.DOI:10.1080/15732479.2018.1442482.

[15] Venanzi L I Ierimonti and Caracoglia tLjWvnpy L ; .

[16] Lee K, Cho H and Choi Y. Life-cycle cost-effective optimum design of steel bridges. Journalof constructional steel research 2004; 60(11): 1585–1613. DOI:https://doi.org/10.1016/j.jcsr.2003.10.009.

[17] Shin Y, Park J and Ha DH. Optimal design of a steel box girder bridge consideringlife cycle cost. KSCE Journal of Civil Engineering 2009; 13: 433–440. DOI:10.1007/s12205-009-0433-9.

[18] Han SH, Lee WS and Bang MS. Probabilistic optimal safety with minimum life-cyclecost based on stochastic finite element analysis of steel cable-stayed bridges. InternationalJournal of Steel Structures 2011; 11: 335–349. DOI:10.1007/s13296-011-3008-9.

[19] Bang M. Optimal design of suspension bridge based on minimization of life cycle cost.Advanced Materials Research 2014; 919-921: 577–582. DOI:10.4028/www.scientific.net/amr.

[20] Veganzones JJ, Pettersson L, Sundquist H et al. Life-cycle cost analysis as a tool in thedeveloping process for new bridge edge beam solutions. Structure and Infrastructure Engi-neering 2016; 12: 1–17. DOI:10.1080/15732479.2015.1095770.

[21] Saad L, Aissani A, Chateauneuf A et al. Reliability-based optimization of direct andindirect lcc of rc bridge elements under coupled fatigue-corrosion deterioration processes.Engineering Failure Analysis 2015; 59: 570–587. DOI:10.1016/j.engfailanal.2015.11.006.

[22] Venanzi I, Castellani R, Ierimonti L et al. An automated procedure for assessing localreliability index and life-cycle cost of alternative girder bridge design solutions. Advancesin Civil Engineering 2019; 2019: 1–17. DOI:10.1155/2019/5152031.

[23] Padgett J, Dennemann K and Ghosh J. Risk-based seismic life-cycle cost–benefit (lcc-b) analysis for bridge retrofit assessment. Structural Safety 2010; 32: 165–173. DOI:10.1016/j.strusafe.2009.10.003.

[24] Ebrahimian H, Jalayer F and Manfredi G. Seismic retrofit decision-making of bridges basedon life-cycle cost criteria. In COMPDYN 2015 - 5th ECCOMAS Thematic Conference onComputational Methods in Structural Dynamics and Earthquake Engineering. pp. 1591–1627.

[25] Hahm D, Ok SY, Park W et al. Cost-effectiveness evaluation of an mr damper system basedon a life-cycle cost concept. KSCE Journal of Civil Engineering 2013; 17(1): 145–154.

[26] Micheli L, Hong J, Laflamme S et al. Surrogate models for high performance control systemsin wind-excited tall buildings. Applied Soft Computing 2020; 90: 106133.

[27] Frangopol D, Lin KY and Estes A. Life-cycle cost design of deteriorating structure. Journalof Structural Engineering 1997; 123: 1390–1401. DOI:10.1061/(ASCE)0733-9445(1997)123:10(1390).

[28] Hatami A and Morcous G. Deterioration models for life-cycle cost analysis of bridge decksin nebraska. Transportation Research Record Journal of the Transportation Research Board2012; 2313: 3–11. DOI:10.3141/2313-01.

23

Page 24: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

[29] Barone G, Frangopol D and Soliman M. Optimal design of suspension bridge based onminimization of life cycle cost. Journal of Structural Engineering 2013; 140: 04013043.DOI:10.1061/(ASCE)ST.1943-541X.0000812.

[30] Liu M and Frangopol DM. Optimizing bridge network maintenance management underuncertainty with conflicting criteria: Life-cycle maintenance, failure, and user costs. Journalof Structural Engineering 2006; 132(11): 1835–1845. DOI:10.1061/(ASCE)0733-9445(2006)132:11(1835).

[31] Sabatino S, Frangopol D and Dong Y. Sustainability-informed maintenance optimization ofhighway bridges considering multi-attribute utility and risk attitude. Engineering Structures2015; 102: 310–321. DOI:10.1016/j.engstruct.2015.07.030.

[32] Almeida J, Teixeira P and Delgado R. Life cycle cost optimisation in highway concretebridges management. Structure and Infrastructure Engineering 2015; 11: 1–14. DOI:10.1080/15732479.2013.845578.

[33] Orcesi A and Frangopol D. Optimization of bridge maintenance strategies based onstructural health monitoring information. Structural Safety 2011; 33: 26–41. DOI:10.1016/j.strusafe.2010.05.002.

[34] Thomson D. The economic case for service life extension of structures using structuralhealth monitoring based on the delayed cost of borrowing. J Civil Struct Health Monit2013; 3: 335–340. DOI:https://doi.org/10.1007/s13349-013-0057-0.

[35] Kim S and Frangopol D. Computational platform for probabilistic optimum monitoringplanning for effective and efficient service life management. J Civil Struct Health Monit2020; 10: 1–15. DOI:https://doi.org/10.1007/s13349-019-00365-4.

[36] Bolognani D, Verzobio A, Tonelli D et al. Iwshm 2017: Quantifying the benefit of structuralhealth monitoring: what if the manager is not the owner? Structural Health Monitoring2018; 17(6): 1393–1409. DOI:10.1177/1475921718794506.

[37] Long L, Dohler M and Thons S. Determination of structural and damage detection systeminfluencing parameters on the value of information. Structural Health Monitoring 2020; :1475921719900918DOI:10.1177/1475921719900918.

[38] Vega MA and Todd MD. A variational bayesian neural network for structural healthmonitoring and cost-informed decision-making in miter gates. Structural Health Monitoring2020; : 1475921720904543DOI:10.1177/1475921720904543.

[39] Micheli L, Cao L, Laflamme S et al. Life cycle cost evaluation strategy for high performancecontrol systems under uncertainties. Civil, Construction and Environmental EngineeringPublications 2019; : 241.

[40] Neves A, Leander J, Gonzalez I et al. An approach to decision-making analysis for imple-mentation of shm in bridges. Structural Control and Health Monitoring 2019; 26: e2352.DOI:10.1002/stc.2352.

[41] Okasha N and Frangopol D. Computational platform for the integrated life-cycle man-agement of highway bridges. Engineering Structures 2011; 33: 2145–2153. DOI:10.1016/j.engstruct.2011.03.005.

[42] Shim H and Lee S. Developing a probable cost analysis model for comparing bridge deckrehabilitation methods. KSCE Journal of Civil Engineering 2015; 20: 68–76. DOI:10.1007/s12205-015-1634-z.

24

Page 25: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

[43] Kilanitis I and Sextos A. Integrated seismic risk and resilience assessment of roadwaynetworks in earthquake prone areas. Bulletin of Earthquake Engineering 2019; 17(1): 181–210. DOI:10.1007/s10518-018-0457-y.

[44] Kilanitis I and Sextos A. Impact of earthquake-induced bridge damage and time evolv-ing traffic demand on the road network resilience. Journal of Traffic and TransportationEngineering (English Edition) 2019; 6(1): 35 – 48. DOI:10.1016/j.jtte.2018.07.002.

[45] Ministero delle Infrastrutture e dei Trasporti. Studio di valutazione dei Costi Socialidell’incidentalita stradale, 2012.

[46] D Orcesi A, Feraille A and Chataigner S. Fatigue strengthening of steel structures usinghigh modulus cfrp plates: Development of a life-cycle analysis approach. Construction andBuilding Materials 2019; 227: 116628. DOI:10.1016/j.conbuildmat.2019.08.009.

[47] Ettouney MM and Alampalli S. Infrastructure Health in Civil Engineering: Applicationsand Management. CRC Press, 2011.

[48] Ciampoli M, Petrini F and Augusti G. Performance-based wind engineering: Towards ageneral procedure. Structural Safety 2011; 33(6): 367 – 378. DOI:10.1016/j.strusafe.2011.07.001.

[49] Gunay S and Mosalam KM. Peer performance-based earthquake engineering methodology,revisited. Journal of Earthquake Engineering 2013; 17(6): 829–858. DOI:10.1080/13632469.2013.787377.

[50] Computers and Structures Inc. CSIbridge, Version 20, Structural software. http://fs.

fish.govt.nz/Page.aspx?pk=7\&sc=SUR, 2018. Berkley.

[51] Cassese P, Ricci P and Verderame G. Experimental study on the seismic performanceof existing reinforced concrete bridge piers with hollow rectangular section. EngineeringStructures 2017; 144: 88–106. DOI:https://doi.org/10.1016/j.engstruct.2017.04.047.

[52] Padgett JE, Nielson BG and DesRoches R. Selection of optimal intensity measures inprobabilistic seismic demand models of highway bridge portfolios. Earthquake Engineering& Structural Dynamics 2008; 37(5): 711–725. DOI:10.1002/eqe.782.

[53] INGV. Mappe interattive di pericolosita sismica. URL http://esse1-gis.mi.ingv.it/.

[54] Ministero delle Infrastrutture e dei Trasporti. D.M. 14 settembre 2005, Norme tecniche perle costruzioni, 2005.

[55] PEER-NISEE. On line library, 2017. URL https://nisee.berkeley.edu/elibrary/.

[56] Porter K, Kennedy R and Bachman R. Creating fragility functions for performance-basedearthquake engineering. Earthquake Spectra 2007; 23: 471–489. DOI:10.1193/1.2720892.

[57] Ramanathan K, Padgett J and DesRoches R. Temporal evolution of seismic fragility curvesfor concrete box-girder bridges in california. Engineering Structures 2015; 97: 29–46. DOI:https://doi.org/10.1016/j.engstruct.2015.03.069.

[58] Biondini F and Frangopol D. Life-cycle multi-objective optimization of deteriorating struc-tures. Taylor, F. Group (Eds.), Life Cycle Civil Engineering, London, 2008.

[59] Regione Umbria. DELIBERAZIONE DELLA GIUNTA REGIONALE 19 settembre 2018,n. 1027, Elenco regionale dei prezzi e dei costi minimi della manodopera per lavori edili,impianti tecnologici, infrastrutture a rete, lavori stradali e impianti sportivi per l’esecuzionedi opere pubbliche - edizione 2018. Elenco regionale dei costi per la sicurezza dei lavoratori- edizione 2018. Approvazione., 2018.

25

Page 26: Life-cycle management cost analysis of transportation ... · economic value from the delayed cost of borrowing funds to replace or rehabilitate structures resulting from SHM. Kim

[60] Anas SpA. Listino prezzi 2019; Prove, Indagini e Monitoraggio, 2019.

[61] Automobile Club Italia. Localizzazione incidenti stradali, 2017. URL http://www.lis.

aci.it/dati/#/localizzati/2017.

[62] Ministero dei Lavori Pubblici. Ispettorato generale per la circolazione e la sicurezza stradale,”Definizione dei principali temi di ricerca per il miglioramento della sicurezza delle infras-trutture nel breve, medio e lungo periodo - scheda 8: misure per il miglioramento dellasicurezza della circolazione in presenza di cantieri ”, 2000.

[63] Anas SpA. Dati di traffico medio giornaliero annuale, 2017. URL https://www.

stradeanas.it/sites/default/files/Anas\%20Dati\%20TGMA\%202017.pdf. Online.

[64] Torti M, Venanzi I and Ubertini F. Seismic structural health monitoring for reducing lifecycle cost of road bridges. In EURODYN 2020 - XI International Conference on StructuralDynamics. pp. 1063–1074.

[65] Frangopol D and Kim S. Prognosis and life-cycle assessment based on shm information.Sensor Technologies for Civil Infrastructures 2014; 56: 145 – 171. DOI:https://doi.org/10.1533/9781782422433.1.145.

[66] G. Washer. Reliability of visual inspection for highway bridges, USDOT, FHWA, 1(FHWA-RD-01-020), 2001.

26