life cycle cost analysis - info 1

Upload: shyamnair9667

Post on 01-Jun-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    1/80

     May 2007

    Final Methodology

    Life Cycle Costing(LCC) as acontribution tosustainable

    construction: acommonmethodology

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    2/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    Contents

    Tables and figures ............................................................................... i 0  Introduction ......................................................................................... 1 1  STEP 1: Identify the main purpose of the LCC analysis .................... 10 2  STEP 2: Identify the initial scope of the LCC analysis ....................... 13 3  STEP 3: Identify the extent to which sustainability – and specifically

    environmental – analysis relates to LCC ...........................................17 4  STEP 4: Identify the period of analysis and methods of economic

    evaluation.......................................................................................... 20 5  STEP 5: Identify the need for additional analyses (risk/uncertainty and

    sensitivity analyses) .......................................................................... 26 6  STEP 6: Identify project and/or asset requirements – confirm key

    parameters........................................................................................ 33 7  STEP 7: Identify options to be included in the LCC exercise ............ 38 8  STEP 8: Assemble cost and time data to be used in LCC analysis ... 40 9  STEP 9: Verify values of financial parameters and period of analysis46 10  STEP 10 (Optional): Review risk strategy and carry out preliminary

    uncertainty/risk assessment ..............................................................49 11  STEP 11: Perform required economic evaluation. ............................ 50 12  STEP 12: Carry out detailed risk/uncertainty analysis (if required) ... 55 13  STEP 13: Carry out sensitivity analysis (if required) ......................... 58 14  STEP 14: Interpret and present initial results in required format....... 61 15  STEP 15: Present final results in required format and prepare a final

    report. ...............................................................................................63 

    Annex A: Sample tabular and graphical outputs from typical LCC exercisesAnnex B: Bibliography and references

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    3/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    i

    Tables and figures

    Tables

    1  Summary and overview of steps2  Typical applications of LCC3  Impact of risk on decision-taking4  Generic cost classification and check list5  Factors affecting durability6  Examples of the application of LCC analysis

    Figures

    1  Core process of LCC2  Methodology flow diagram3  Risk management cycle4  Common tools and techniques in risk/uncertainty analysis

    5  Probability matrix6  Calculation of NPV7  Risk profile in histogram form8  Risk profile in cumulative form9  Spider diagram10  Spider diagram with contour lines11  Sample project data table12  Sample annual expenditure table13  Sample table of key parameters14  Sample tabulation of total cost profile15  Sample LCC model

    16  Sample component replacement cost build-up17  Sample cost profile chart18  Sample cost profile chart19  Sample cumulative cost chart20  Sample component option appraisal cost chart

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    4/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    1

    0  Introduction

    0.1 Background

    In 2006 the European Commission appointed Davis Langdon from the UK to undertake aproject

    (1) to develop a common European methodology for Life Cycle Costing (LCC) in

    construction.

    The origins of the project lay in the Commission’s Communication ‘The Competitiveness of

    the Construction Industry’ and, more specifically, in the recommendations of the

    Sustainable Construction Working Group established to help take forward key elements of

    the Competitiveness study. These recommendations proposed that a Task Group (TG4) be

    established to prepare a paper on how Life Cycle Costing could be integrated into European

    policy making. The Task Group’s paper(2)

     recommended the development of a common

    LCC methodology at European level, incorporating the overall sustainability performance

    of building and construction.

    The project was undertaken in recognition that a common methodology for LCC in

    construction is required across Europe in order to:

      Improve the competitiveness of the construction industry

      Improve the industry’s awareness of the influence of environmental goals on LCC

      Improve the performance of the supply chain, the value offered to clients, and clients’

    confidence to invest through a robust and appropriate LCC approach

      Improve long-term cost optimisation and forecast certainties

      Improve the reliability of project information, predictive methods, risk assessment and

    innovation in decision-making for procurement involving the whole supply chain

      Generate comparable information without creating national barriers and also considering

    the most applicable international developments.

    0.2 Purpose of this methodology

    It was recognised early on in the research process that LCC is applied in various ways and

    with differing parameters across the EU, and that a single prescriptive methodology would

    not be appropriate. Therefore this document provides a methodological framework for the

    common and consistent application of LCC across the EU without attempting to replace

    country-specific decision models and approaches. It identifies the key considerations to be

    taken into account at each stage in the LCC process and provides practical guidance on the

    application of LCC in a number of common scenarios. It is aimed primarily at public sector

    construction clients and their project advisors, but can also be used by private sector clients

    and their advisors, and by contractors.

    0.3 Using this methodology

    LCC may be applied in a wide range of circumstances in construction, for example in a

    project to invest in:

      A single complete constructed facility such as a building or civil engineering structure

      An individual component or assembly within a facility

      A portfolio comprising a number of facilities.

    LCC may also be applied in the context of existing constructed assets, for example as a

    means of assessing future operational budgets or for evaluating refurbishment and renewal

    options.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    5/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    2

    The period of analysis adopted for an LCC exercise may similarly vary. LCC may be

    employed to inform decisions throughout the complete life cycle of a constructed asset or

    for a selected limited period within it. However, irrespective of how or when LCC is

    applied, the core evaluation process as summarised in Figure 1 below remains the same.

    (1): Life cycle costing (LCC) as a contribution to sustainable construction: a common methodology’ No. 30-CE-0043513/00-47.(2): Task Group 4:  Life Cycle Costs in Construction; Version 29 October 2003, Enterprise Publications, European Commission.Endorsed during 3

    rd Tripartite Meeting Group (Member States/Industry/Commission) on the Competitiveness of the

    Construction Industry. 

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    6/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    3

    Figure 1: Core process of LCC

    Defining the objective of the proposed LCC analysis

     Preliminary identification of parameters and analysis

    requirements

     

    Confirmation of project and facility requirements

     

    Assembly of cost and performance data

     

    Carry out analysis, iterating as required

     

    Interpreting and reporting results

    The purpose of the LCC analysis as defined in the first step in Figure 1 will determine the

    scope and detail of subsequent steps. To be effective, the process should be undertaken

    collaboratively between all key stakeholders in the project.

    The LCC process is essentially iterative, both in the context of assessing options for a

    decision at a specific point and of repeating the analysis at future points in the life cycle of a

    project in the light of increasingly detailed information or changing client requirements.

    The methodology does not seek to represent these potential iterations, rather it takes the

    user through a series of numbered steps that follow a logical train of thought, as shown onthe flow diagram included as Figure 2 below.

    The steps in this methodology are not intended to reflect the actual chronology of a project

    to invest in a constructed asset. The accompanying guidance note contains a series of

    practical case studies that will assist the user in applying the methodology steps to the time

    line of an actual project.

    Figure 2 below summarises the methodology steps as a flow diagram. The following 15

    sections of this document relate to the individual steps in the methodology and are

    numbered accordingly.. Section 0.4 below provides an overview of the outcomes for the

    user as a result of taking each step.

    A number of steps relating to uncertainty and risk are optional and shown to be taken if

    required, because their application depends on early decisions at Step 5, concerning the

    extent to LCC analysis will be supported by risk/uncertainty analyses.

    The steps generally use a vocabulary appropriate to a project to construct a facility but the

    essential principles set out are entirely applicable to any constructed asset.

    The methodology assumes that the user comes to it with a project in view for which the

    purpose, scale and initial capital cost have been broadly defined.

    The approach to the development of the LCC methodology was inspired by the Engineering

    Design Process (EDP). This is a structured decision-making process (often iterative), used

    in the development of engineering systems, components or processes to meet desired needs.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    7/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    4

    Among the fundamental elements of the design process are the establishment of objectives

    and criteria, synthesis, analysis, construction, testing, and evaluation. These broadly defined

    stages can be further subdivided into a more detailed process, which includes identifying a

    need, defining the problem, conducting research, narrowing the research, analysing set

    criteria, finding alternative solutions, analysing possible solutions, making a decision,presenting the product, and communicating and selling the product. EDP is a well known

    and established framework used world-wide, therefore applying it to the development of the

    methodology ensured that there were no omissions of any activities and that a logical

    sequence of steps was maintained.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    8/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting

    Figure 2: Methodology flow diagram

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    9/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    6

    0.4 Overview of outcomes

    Table 1 below summarises the outcomes that can be expected on completion of each of the

    steps in the methodology. Note that Steps 10, 12 and 13 are optional.

    Table 1: Summary and overview of Steps

    STEP OUTCOME / ACHIEVEMENT

    1 Identify the mainpurpose of the LCCanalysis

    Statement of purpose of analysisUnderstanding of appropriate application of LCC andrelated outcomes

    2 Identify the initial scopeof the analysis

    Understanding of:Scale of application of the LCC exerciseStages over which it will be applied

    Issues and information likely to be relevantSpecific client reporting requirements

    3 Identify the extent towhich sustainabilityanalysis relates to LCC

    Understanding of:Relationship between sustainability assessment and LCCExtent to which the outputs from a sustainabilityassessment will form inputs into the LCC processExtent to which the outputs of the LCC exercise will feedinto a sustainability assessment

    4 Identify the period ofanalysis and themethods of economicevaluation

    Identification of the period of analysis and what governs itschoiceIdentification of appropriate techniques for assessinginvestment options

    5 Identify the need foradditional analyses(risk/uncertainty andsensitivity analyses)

    Completion of preliminary assessment of risks/uncertaintiesAssessment of whether a formal risk management planand/or register is requiredDecision on which risk assessment procedures should beapplied

    6 Identify project andasset requirements -

    Definition of the scope of the project and the key featuresof the assetStatement of project constraintsDefinitions of relevant performance and qualityrequirements

    Confirmation of project budget and timescalesIncorporation of LCC timing into overall project plan

    7 Identify options to beincluded in the LCCexercise and cost itemsto be considered

    Identification of those elements of an asset that are to besubject to LCC analysisSelection of one or more options for each element to beanalysedIdentified which cost items are to be included

    8 Assemble cost and time(asset performance andother) data to be usedin the LCC analysis

    Identification of:All costs relevant to the LCC exerciseValues of each costAny on-costs to be appliedTime related data (e.g. service life/maintenance data)

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    10/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    7

    9 Verify values offinancial parametersand period of analysis 

    Period of analysis confirmedAppropriate values for the financial parameters confirmedTaxation issues consideredApplication of financial parameters within the costbreakdown structure decided

    10 Review risk strategyand carry outpreliminary uncertainty/risk analysis 

    Schedule of identified risks verifiedQualitative risk analysis undertaken – risk register updatedScope and extent of quantitative risk assessmentconfirmed

    11 Perform requiredeconomic evaluation 

    LCC analysis performedResults recorded for use at Step 14

    12 Carry out detailedrisk/uncertainty analysis(if required)

    Quantitative risk assessments undertakenResults interpreted

    13 Carry out sensitivityanalyses (if required)

    Sensitivity analyses undertakenResults interpreted

    14 Interpret and presentinitial results in requiredformat

    Initial results reviewed and interpretedResults presented using appropriate formatsNeed for further iterations of LCC exercise identified

    15 Present final results inrequired format andprepare a final report

    Final report issued, to agreed scope and formatComplete set of records prepared to ISO 15686 Part 3

    0.5 Tailoring the methodology to the specific project circumstances

    It is important to note that in practice it will often be possible for users to combine several

    of the above steps in order to tailor the methodology to the size of the project, the project

    stage and the level of detail required. For example, Steps 1 to 6 are concerned with

    defining the objectives and the analysis parameters. On smaller projects this definition

    exercise might typically take the form of a meeting or telephone discussion with the client

    and/or an exchange of correspondence. Similarly, the risk and sensitivity analyses might be

    incorporated into the economic evaluation exercise (Step 11) based on a small number of

    agreed parameters and/or the practitioner’s experience of common risk issues. Regardless

    of the scale or scope of the exercise, the guiding principle should always be that the key

    issues identified in this methodology are all considered, albeit at a level of detail

    appropriate to the particular exercise.

    0.6 Definitions

    This methodology is intended to be compatible with ISO 15686 Part 5 which is currently at

    the DIS ballot stage and is likely to be adopted shortly. Definitions used in this

    methodology are therefore as in ISO 15686 Part 5. For ease of use, key definitions are

    reproduced below.

     Life Cycle Costing

     A technique which enables the systematic appraisal of life cycle costs over a period of analysis, as

    defined in the agreed scope. 

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    11/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    8

     Life Cycle Cost

     Assessment expressed in monetary value taking into account all significant and relevant costs over

    the life cycle, as defined in the agreed scope. The projected costs are those needed to achieve definedlevels of performance, including reliability, safety and availability over the period of analysis.

     Life Cycle

    Consecutive and interlinked periods of time between a selected date and the disposal of the asset,

    over which the criteria (e.g., costs) are assessed. This period may be determined for the analysis

    (e.g., to match the period of tenancy or ownership) or cover the entire life cycle. The life cycle period

    shall be governed by defining the scope and the specific performance requirements for the particular

    asset.

     Nominal Cost

     Expected price which will be paid when a cost is due to be paid, including estimated changes in price due to, for example, forecast change in efficiency, inflation or deflation and technology

     Real Cost

    Cost expressed as a value as at the base date, including estimated changes in price due to forecast

    changes in efficiency and technology, but excluding general price inflation or deflation

     Discounted Cost

     Resulting cost when the real cost is discounted by the real discount rate or when the nominal cost is

    discounted by the nominal discount rate

     Discount Rate

    Factor reflecting the time value of money that is used to convert cash flows occurring at different

    times to a common time

     NOTE This may be used to convert future values to Present Day Values and vice versa. 

     Nominal Discount Rate

     Rate used to relate present and future money values in comparable terms taking into account the

    general inflation/ deflation rate

     Real Discount Rate

     Rate used to relate present and future money values in comparable terms, not taking into account the

    general or specific inflation in the cost of a particular asset under consideration

     Net Present Value

     Net Present Value is the sum of the discounted future cash flows. Where only costs are included this

    may be termed Net Present Cost (NPC)

     Present Day Value

     Monies accruing in the future that have been discounted to account for the fact that they are worth

    less at the time of calculation

    Sensitivity Analysis

    Test of the outcome of an analysis by altering one or more parameters from initial value(s)

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    12/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    9

     Residual Value

    Value assigned to an asset at the end of the period of analysis.

    0.7 Relationship with ISO 14040

    It is important to note that the ISO 15686 definition of the term ‘life cycle’ differs from that

    used in the environmental standard, ISO 14040. The latter adopts a broad ‘cradle to grave’

    definition of life cycle, whereas the ISO 15686 definition can represent either ‘cradle to

    grave’ or a shorter economic analysis timeframe driven by the specific client or project

    needs.

    The ISO 14040 definition of life cycle feeds into that of life cycle assessment (LCA) as

    follows:

     Life cycle

    Consecutive and interlinked stages of a product system, from raw material acquisition or generation

    of natural resources to the final disposal.

     Life cycle assessment

    Compilation and evaluation of the inputs, outputs and the potential environmental impacts of a

     product system throughout its life cycle.

    This methodology aligns with the ISO 15686 definition of life cycle. However, for the

    purposes of consistency, users applying LCC to evaluate the outcomes of an LCA analysis

    may wish to align with the broader ISO 14040 definition of life cycle. Further specific

    public sector guidance on the appropriate parameters for carrying out an LCC analysis is

    provided in the guidance note that accompanies this methodology.

    0.8 Companion documents

    This methodology is accompanied by a guidance note and a set of case studies of the

    common use of LCC in Europe. The guidance note is aimed at public sector clients and

    provides an introduction to LCC along with guidance on why it should be used, its benefits,

    the information to be gained from it, and its relationship with the EU procurement

    framework. The case studies are included as an appendix to the guidance note.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    13/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    10

    1  STEP 1: Identify the main purpose of the LCC analysis

    1.1 Purpose of this step

    LCC is a versatile technique capable of being applied for a range of purposes and atdifferent stages in the project or asset life cycle. The purpose of this step is to clearly

    identify the purpose of the proposed LCC analysis and to gain an understanding of how it

    can be appropriately and successfully applied and of the outcomes that can be expected.

    1.2 Purposes for which LCC may be employed

    The purposes for which LCC may be employed can be divided into, in two broad

    categories:

      As an absolute analysis, when used to support the processes of planning, budgeting and

    contracting for investment in constructed assets

      As a relative analysis, when used to undertake robust financial option appraisals, for

    example in relation to potential acquisition of assets, design approaches or alternative

    technologies.

    More specifically, LCC can be used to support decision-making in a number of ways:

      In assessing the total cost commitment of investing in and owning an asset, either over

    its complete life cycle (“cradle to grave”) or over a selected intermediate period

      By improving understanding of the total cost of an asset, particularly by construction

    clients, and improving the transparency of the composition of these costs

      By facilitating effective choices between different means of achieving desired

    objectives, for example reducing energy use or lengthening a maintenance cycle

      By helping to achieve an appropriate balance between initial capital costs and future

    revenue costs

      In helping to identify opportunities for greater cost-effectiveness, for example selection

    of components with a longer service life or reduced maintenance requirements

      As a tool for the financial assessment of alternative options identified during a

    sustainability analysis, for example components with less environmental impact or

    HVAC systems with greater energy efficiency

      Overall, by instilling greater confidence in decision-making in a project.

    LCC can be employed throughout or at different stages of the life cycle of an asset or a

    project to invest in construction; this is considered in detail at step 2.

    Some examples of common applications of LCC follow below in this section to furtherillustrate these points.

    1.3 Typical applications of LCC

    Table 2 below illustrates how LCC can be applied in a variety of circumstances, with

    examples drawn from a building development. The same principles apply in an

    infrastructure or engineering context. The successive stages in the whole life cycle of a

    scheme and the related need for decisions are considered in more detail in section 2

    following. More detailed examples are provided in the Guide that accompanies this

    methodology.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    14/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    11

    Table 2: Typical applications of LCC

    Context and need Typical application of LCCDuring investment planning, clientswill need to understand the full costimplications of operating as well asbuilding the scheme, to establish itsessential viability.

    The analysis will be based on approximatedata, typically historical information fromsimilar projects, but sufficient for budgetingand option ranking to allow a decision onwhether to go ahead, to reduce the schemeor stop.

    During the early stages of schemedesign, decisions will be required onthe fundamental elements –structure, envelope, services,finishes

    The analysis can draw on feasibility studiesand pre-project professional advice, as wellhistorical information, to support decisions onthe key features of the scheme – its size,scope, method of construction and operation.

    By detail design stage, the essential

    cost parameters of the scheme willbe determined but decisions will stillbe required on details and whether,finally, to commit to construction.

    Information can now be fed into the analysis

    based on a clear view of all primary elementsof the scheme and access to related cost,service life and maintenance data frommanufacturers’ specifications, as well assimilar projects and national price books.This allows a detailed LCC breakdownconfirming the viability of the scheme andappraisal of detailed design options.Sensitivity and risk analyses may also becarried out.

    Detailed design also requires finalselection of materials, componentsand systems. Potentially, similar

    decisions will subsequently berequired in the event of theirreplacement during operation andmaintenance

    LCC analysis can be focused on the specificcomponent or system with the benefit ofrelated cost, service life and maintenance

    data from manufacturers’ specifications, aswell as from similar projects and nationalprice books. The main focus will be onoption evaluation, ranking and selection.

    During the operation of thecompleted asset refurbishment andrenewal of some elements might berequired, driven by (for example):High operational costsHigh energy consumptionObsolescence (for example:physical, technical, economic,social)

    Change in use of the assetComponents or systems reachingthe end of their service life

    LCC can be applied in supporting selection ofthe most appropriate refurbishment orrenewal option, at either an asset orcomponent level. The analysis can be basedon historic or benchmark data, or on detaileddata derived from manufacturers’specifications and comparable cost-in-usedata. It is essential that the analysis takesinto account the impact on interdependent

    systems and the overall asset.

    1.4 The need for clarity of objectives

    The different purposes for which LCC may be employed, and the different stages of the

    asset life cycle at which it is used, imply the need for different levels of detail and accuracy

    in the process, and in the inputs and outputs. For example, if LCC is employed to support

    an early budgeting process, all relevant costs must be considered and the analysis may be

    based on approximate data such as historic benchmark information. As the LCC analysis is

    subsequently refined during the detailed design stages, further detail will be required on all

    cost items, along with robust service life and maintenance data. The process may also need

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    15/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    12

    to support auxiliary outputs such as an estimate of resources or a reporting schedule to

    provide all necessary support for decision-making.

    If the primary purpose is to appraise options, the process of iteration will involve refining or

    eliminating the available alternatives as they are measured against project objectives and

    budget constraints. This process will include identification of those cost elements that do

    not have a significant impact on the overall LCC or which do not vary between the

    alternatives. These elements can be then be eliminated from further consideration.

    Accordingly, clearly defining the objectives of a proposed LCC analysis must be seen as an

    essential first step in ensuring that it will be fit for the user’s purpose.

    1.5 The ingredients for success

    Successful application of an LCC approach requires:

      A team approach incorporating all key players in a project

      Integration of the LCC exercise into the whole investment decision-making process

    through the conception, design, construction and operation of a facility

      Recognition that the robustness of the outputs of the LCC exercise is highly dependent

    on the level of detail and certainty in the cost and time inputs used

      Clear definition of scope and consideration of all relevant parameters (note that scoping

    issues are covered in Step 2)

      Recognition of the limitations of the techniques employed, leading to the proper exercise

    of professional judgement.

    1.6 At the end of Step 1

    At the end of Step 1 the user will have developed:

      A clear and comprehensive statement of the purpose of the proposed LCC analysis  An understanding of how LCC analysis can be appropriately and successfully applied

    and the outcomes that can be expected.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    16/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    13

    2  STEP 2: Identify the initial scope of the LCC analysis

    2.1 Purpose of this step

    In step 1 the broad purpose and outcomes of the LCC exercise were identified. For theoutcomes to be achieved it is also important to identify the scope of the exercise, including

    the stage(s) in the asset life cycle at which it is undertaken, the boundaries of the analysis

    and whether there are any specific inclusions or exclusions.

    2.2 The scale of application of LCC

    LCC analysis may be undertaken to support a project to invest in:

      A single complete constructed asset that comprises a usable facility such as a building or

    civil engineering structure

      An individual component , material or system within such an asset

      A portfolio comprising a number of assets

    For clarity, this methodology assumes the scenario of a project to construct and use a single

    asset, but the same principles and basic processes apply whatever the scale of application of

    LCC.

    The scale of application for a proposed LCC analysis will be defined by the client, in the

    light of the objectives defined as discussed in section 1 above.

    2.3 Stages in the life cycle of an asset

    For the purposes of this methodology the life-cycle of an asset is divided into the following

    stages:

      Investment planning, pre-construction

      Design, construction

      Operation, maintenance

      End of life / disposal

    Activities in the investment planning / pre-construction phase might typically include:

      Business case preparation

      Acquisition of site(s) or of existing asset(s)

      Professional consultancy

      Inspections and surveys

      Arranging finance

      Assembling the project team / consortium  Procurement planning

    Activities in the design and construction phase might include:

      Scheme design

      Detailed design

      Site clearance

      Placing contracts for construction

      Construction of the fabric

      Fitting out

      Commissioning and handover

      Landscaping

    Activities in the operation and maintenance phase might include:

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    17/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    14

      Employing an FM team or placing an appropriate contract

      Placing contracts for energy supply and other utilities

      Arranging insurances and compliance with regulatory requirements, eg inspections

      Planning and carrying out pre-planned (cyclical) maintenance and replacements

      Carrying out unplanned (responsive) maintenance and replacements  Planning and carrying out pre-planned refurbishment and/or adaptation (such works may

    be better considered as separate projects subject to their own LCC considerations)

      Cleaning

      Redecoration

      Grounds maintenance.

    Activities in the end of life/disposal phase might include:

      Sale of asset

      Change of use of asset

      Demolition

      Site and land clearance and clean up  Recycling of materials

    A proposed LCC analysis might take place over one or more or all of these stages, as

    discussed below. Its purpose must be defined by the client, in the light of the objectives

    defined at step 1.

    2.4 Use of LCC through successive stages.

    LCC analysis can be used either as a one-off intervention to a project or, in a broader

    context, to inform different decisions at different stages of the project or asset life cycle. In

    the latter case, input data is progressively refined as the project moves through successive

    stages. Accordingly, as calculations are based on increasingly detailed and reliable data andinitial assumptions are tested and validated, early strategic decisions are confirmed and

    subsequent decisions taken at increasing levels of detail.

    2.4.1 Investment planning / pre-construction

    Decisions at planning / pre-construction stage are of a strategic nature relating to the

    essential features of the proposed project, with data typically input at a low level of detail.

    They typically cover the following considerations:

      The essential features of the proposed scheme

      Methods of investment appraisal

      Finance – costs, budgets, cash flow, funding sources

      Procurement policy and methods

      Balance between economic, technical and sustainability considerations

      Risk management strategies and techniques

      Key project drivers and overall priorities.

    The application of LCC at this stage in the in the project might include:

      Identification of the purpose(s) of using LCC, both at this stage and in subsequent stages

      Incorporating LCC requirements into business case, project documentation and supply

    chain terms of reference

      Identification of methods of analysis, required outcomes and reporting formats

      Identification of required analysis period and/or design life for the proposed facility

      Consideration of cost drivers, including capital v operating cost priorities

      Use of LCC as an assessment criterion in project approval/gateway processes

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    18/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    15

      Use of LCC in assessing initial strategic project options such as whether to refurbish or

    build new.

    2.4.2 Design and construction

    Design and construction is a broad stage with design decisions taken successively throughthree levels:

      Scheme level, fixing the basic physical characteristics of the facility

      System level, deciding the major installations and assemblies

      Detail design.

    The level of detail in the LCC analysis typically increases progressively though these levels

    and its purpose and implementation should be kept under review as it is reiterated. LCC

    considerations through this stage typically include:

      LCC impact of high level design decisions such as format, composition, orientation and

    layout of the proposed asset

      Selection of components, materials and systems and assessment of their costs over thelife cycle (or part thereof)

      Life cycle costing of sustainability options identified as part of a sustainability

    assessment process

      Assessment of future operating costs of the facility and its constituent parts

      Contractual framework, both for construction and future operation and maintenance

      Resource implications during the operational stages

      Need for and ease of functional reconfiguration / adaptation during operation

      Any planned replacement / refurbishment during operation

      Ease of carrying out future maintenance, replacement and refurbishment, including

    health and safety implications

      Impact of future LCC works on the use and users of the asset

    2.4.3 Operation and maintenance

    The opportunities and need for LCC analysis continue into the operation and maintenance

    stage and might typically relate to:

      Cost and performance drivers during operation and maintenance

      Assessment of options in relation to component replacements, refurbishment, adaptation

      Financial framework and funding of LCC works, including use of sinking funds

      Denial-of-use costs, whether loss of amenity or contractual penalties (such as in PPP or

    other FM contractual payment mechanisms)

      Strategies and planning for operation and related cost models:o  FM

    o  Energy

    o  Other utilities

    o  Cleaning

    o  Waste disposal and recycling

      Strategy and planning for maintenance, repair and replacement works:

    o  Contractual framework and responsibilities (for example in-house delivery or

    outsourcing of some/all activities)

    o  Maintenance planning and management systems (including use of condition-based

    monitoring)

      Collection and use of feedback data

      Risk allocation for operation, maintenance and finance costs

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    19/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    16

    2.4.4 End-of-life / disposal

    LCC considerations at the end-of-life stage might include:

      Strategy for disposal, including methods, costs, residual values

      Evaluation of alternative uses of the facility

      Evaluation of options for demolition and site / land clean up, including methods, costs

      Strategy for salvage and recycling – opportunities, costs, potential value

      Collection and use of feedback data

    2.5 Identification of analysis boundaries

    It is important during the early scoping exercise to identify the broad boundaries of the LCC

    analysis, including:

      Whether the analysis period is to include the entire asset life cycle or a defined part

    thereof (see Step 3 below)

      What costs (and revenues) are to be included or excluded from the analysis (for example

    the client’s contractual or financial interest in the asset may require certain costs to beexcluded)

      Whether there are particular project, contractual, regulatory or economic issues that will

    influence key criteria (such as analysis period, method of economic evaluation) that are

    to be defined in future steps.

    2.6 Identification of analysis outputs

    The required outputs and reporting format of the LCC analysis should be agreed in broad

    terms at this stage. Clients may require the detailed analysis and/or the summary findings

    to be presented in a particular format to suit their internal reporting processes or those of an

    external regulatory or funding body. Early identification enables the user to address theseissues before the analysis has been undertaken, thereby eliminating unnecessary reworking

    of reports at a later stage. LCC consultants often use in-house software with standard report

    formats that might require amendment. Note that detailed reporting issues are considered in

    Steps 14 and 15 of this methodology.

    2.7 At the end of Step 2

    At the end of step 2, the user will have developed a clear understanding of:

      The scale of application of the LCC exercise

      The stage(s) of the project or asset life cycle over which it is likely to be undertaken

      The scope and nature of the issues and information likely to be relevant.

      Any specific client reporting requirements that require early consideration.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    20/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    17

    3  STEP 3: Identify the extent to which sustainability – and

    specifically environmental – analysis relates to LCC

    3.1 Purpose of this stepEnvironmental sustainability is becoming a key consideration in any long term assessment

    of constructed assets. The relationship between LCC and sustainability assessment and the

    extent to which the latter forms an input to the LCC analysis is defined at this step.

    3.2 Assessing sustainability

    Practitioners recognise three fundamental and interlinked sets of issues within the

    ‘sustainability’ agenda:

      Environmental – relating typically to air quality, land use, use of natural resources (raw

    materials, energy, water, waste etc), transportation, biodiversity, cultural heritage, etc.

      Social – relating typically to access, amenity, user comfort and satisfaction, community

    health and welfare

      Economic – relating typically to opportunities for employment, skills development,

    local businesses including SMEs,

    Some sustainability issues are difficult to measure and to incorporate into a LCC analysis.

    However, LCC practitioners widely accept that the environmental impact associated with

    constructed assets can be significant and should always be considered. A range of

    approaches to assessing environmental impact are available to suit the type of asset, the

    aspects of the environment that are of concern and the particular parameters that are of

    interest. The following are the most frequently used:

      Life Cycle Assessment (LCA) – LCA addresses the environmental aspects and potential

    environmental impacts (e.g. use of resources and the environmental consequences of

    releases) throughout a product's life cycle from raw material acquisition through

    production, use, end-of-life treatment, recycling and final disposal

      Environmental Impact Assessment (EIA) – a process for informing decision-makers

    of the local environmental consequences/effects potentially caused by different project

    options

      Multi-Criteria Analysis (MCA) – a process that initially identifies a set of goals or

    objectives and then seeks to identify the trade-offs between those objectives for different

    options. The 'best' environmental solution is identified by attaching weights (scores) to

    the objectives.

    While a number of approaches to assessing environmental impact are available to suit

    individual requirements, LCA is one of the most versatile and widely recognised in

    construction and is referred to in this methodology. It is also the only approach that is the

    subject of International Standards (ISO 14040 and ISO 14044).

    To be properly comprehensive, an environmental impact assessment of a constructed asset

    must extend to the manufacturing process and transport of materials and components.

    3.3 Measures employed in LCA

    Environmental impact is caused primarily by the consumption and/or transformation of

    materials and energy. Accordingly LCA measures the consumed and emitted flows (that is,

    raw material and energy consumption, and emissions to air, water, soil) over the whole life

    cycle of the asset from raw material acquisition through production, use, end-of-life

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    21/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    18

    treatment, recycling and final disposal of the asset. This compilation of inputs and outputs

    is called Life Cycle Inventory (LCI).

    The LCI is the basis for a later analysis and potential assessment of the environmental

    effects related to the product or process. This aggregation of the many single resources and

    emissions is then translated into indicators about the potential impacts on the environment,

    health, and use of natural resources. This step is called Life Cycle Impact Assessment

    (LCIA). In general, this process involves associating inventory data with specific

    environmental impact categories and category indicators. The collection of indicator results

    (LCIA results) or the LCIA profile provides information on the environmental issues

    associated with the inputs and outputs of the system assessed.

    Life Cycle Impact Assessment (LCIA) methods can be grouped into two families: classical

    methods determining impact category indicators at an intermediate position of the impact

    pathways (e.g. ozone depletion potentials) and damage-oriented methods aiming at more

    easily interpretable results in the form of damage indicators at the level of the ultimate

    societal concern (e.g. human health damage). Although users may choose to work at eitherthe midpoint or damage levels, a current tendency in LCIA method development aims at

    reconciling these two approaches. Both of them have their merits, and optimal solutions can

    be expected if the 'midpoint-oriented methods' and the 'damage-oriented methods' are fitted

    into a consistent framework.

    Because there is no single accepted method carrying out LCA, the European Commission

    has provided a standardisation mandate M/350 to CEN in order to establish a set of specific

    LCA rules for assessment of environmental performance of buildings and construction

    products. The rules are to be based on the generic ISO standards 14040, 14044 and 14025

    for Environmental Product Declarations and they are also in line with the building

    construction sector specific standards under development in ISO. As a consequence CENhas established a technical committee CEN/TC350 “Sustainability of Construction Works”

    to fulfil the work specified in the mandate M/350.

    Note: Where the term LCA is used in the following sections it should be taken to

    encompass all environmental sustainability assessment methods.

    3.4 Interrelationship between LCC and sustainability analysis

    Whilst LCC and LCA are two distinct and different processes that have developed and are

    practised as separate disciplines in the construction industry, there are many parallels and

    interrelationships between the two. For example, both:

      Are concerned with assessing the long term impacts of decisions  Require analysis of an often diverse range of inputs

      Use similar data on inputs of materials and energy

      Take into account operation and maintenance

      Consider opportunities for recycling vs. disposal

      Provide a basis for rational decision making, particularly in appraising options.

    However, the two disciplines differ in the basis of the resulting decisions:

      LCC combines all relevant costs associated with an asset into outputs expressed in

    financial terms as a basis for making investment decisions

      LCA enables decisions to be made on the basis of potential environmental impacts by

    scoring and rating on environmental criteria. Whilst costs can be firmly attributed to

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    22/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    19

    some environmental factors there is currently no widely agreed methodology for others

    and some cannot be quantified at all in cost terms.

    As a result LCC and LCA do not necessarily produce a common output. Nevertheless

    environmental impact assessment has a key place in overall long term decision-making and

    consideration should be given to how to integrate it with the LCC process at the earliest

    stages.

    3.5 The use of LCA with LCC

    As discussed above, in LCC the primary driver in decision-making is cost and LCA informs

    decisions on the basis of potential environmental impacts. The use and sequence of LCC

    and LCA will depend on the priorities of the decision-maker. The range of approaches

    might cover, for example:

      Use of LCC and LCA as two of the criteria in the evaluation of a single investment

    option (such as the decision to construct an asset), where other evaluation criteria might

    include functionality, aesthetics, speed of construction, future investment returns etc.  Use of LCC and LCA as two of the criteria in the evaluation of a number of alternative

    investment options (either entire constructed assets or specific components, materials

    or assemblies within them)

      Use of LCC to provide a financial/economic evaluation of those sustainability impacts

    that have a widely agreed and readily calculated monetary value

      Use of LCC to provide a financial/economic evaluation of alternative options identified

    in a LCA assessment

      Use of LCA as a means of identifying alternative options with a good environmental

    performance and then carrying out a LCC analysis on those options only

      Use of LCC to select cost effective options, then making a final decision in the light of a

    process of LCA carried out on those options only.

    Thus it can be seen that LCC and LCA can either be used alongside each other in a broader

    evaluation process, or either process can form an input into the other.

    3.6 At the end of Step 3

    At the end of step 3 the user will have developed a clear understanding of:

      The relationship between sustainability assessment and LCC

      The extent to which the outputs of a sustainability assessment will form inputs into the

    LCC analysis

      The extent to which the outputs of the LCC analysis will feed into a sustainability

    assessment

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    23/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    20

    4  STEP 4: Identify the period of analysis and methods of economic

    evaluation.

    4.1 Purpose of this stepThe selection of the appropriate period of analysis is fundamental to the outcome of a LCC

    exercise. In step 2 the User identified the likely broad timescale of the LCC exercise. In

    this step, the timescale over which the analysis takes place is confirmed as the ‘period of

    analysis’.

    4.2 Period of analysis

    The period of analysis is formally defined in ISO15686 Part 5 as follows:

      “The length of time over which an LCC assessment is analysed. This period of analysis

    shall be determined by the client at the outset (e.g. to match the period of ownership) or

    on the basis of the entire life cycle of the asset itself.”ISO 15686 Part 5 provides further definitions as follows:

      Life Cycle as “Consecutive and interlinked periods of time between a selected date and

    the disposal of the asset, over which the criteria (e.g., costs) are assessed. This period

    may be determined for the analysis (e.g., to match the period of tenancy or ownership)

    or cover the entire life cycle. The life cycle period shall be governed by defining the

    scope and the specific performance requirements for the particular asset.”

      Entire Life Cycle as “Consecutive and interlinked periods of time between a selected

    date and the end of service life of the asset, including the end of life period.”

    It should be noted that the ISO 15686 definition of life cycle differs from that in the

    environmental standard, ISO 14040. The latter adopts a broad ‘cradle to grave’ definitionof life cycle, whereas the ISO 15686 definition can represent either ‘cradle to grave’ or a

    shorter economic analysis timeframe driven by the specific client or project needs. Users

    should confirm with the client which definition is to be adopted for their LCC analysis.

    The decision on the appropriate analysis period for a LCC exercise may be driven by a

    number of factors relating to the client, the project and/or asset, and the financial, legal and

    regulatory framework in which they operate. Key drivers might include:

      Design life of the asset

      Project duration (for example PPP projects typically last for 20-30 years)

      Period of economic interest in the asset (for example lease period)

      Financial drivers (for example investment requirements, loan periods)  Projected refurbishment/remodelling periods

      Regulatory requirements (for example treasury guidance may stipulate analysis period)

      Business planning cycle

      Client requirement to adopt the ISO 14040 environmental definition of ‘life cycle’

    The selected analysis period can have a fundamental impact on the outcome of a LCC

    exercise and it is essential that the appropriate consideration is given to it. In particular, the

    potential effects of selecting a particularly long or short analysis period should be

    understood. Selection of a longer analysis period introduces higher levels of risk into the

    analysis, as the long term impacts of issues such as inflation, future need for and use of the

    asset, component maintenance and replacement requirements (i.e. service life) and system

    obsolescence become more difficult to predict over time. This is not to suggest that users

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    24/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    21

    should not carry out LCC exercises over longer time periods, rather that the increased risks

    need to be adequately understood and accounted for.

    Users should also be aware of the impact of the chosen discount rate (see below) when

    applied over different analysis periods. The longer the analysis period, the greater the

    impact that the chosen discount rate will have on future costs. Conversely, the shorter the

    analysis period, the less effect discount rates will have on the analysis outcome.

    4.3 Asset and component life

    In order to identify the appropriate analysis period users may need to make an assessment

    of the expected life of the asset or its constituent parts. The first distinction that users

    should understand is that of ‘design life’ and ‘service life’. ISO 15686 Part 1 defines the

    terms as follows:

    Service life: period of time after installation during which a building or its parts meets or

    exceeds the performance requirements.

     Design life: intended service life, or expected service life, or service life intended by the

    designer.

    In practice, the term “life” when applied to a constructed asset can be defined in a number

    of ways depending on the interests and objectives of the user, as follows:

      Physical life (from construction to demolition or replacement). Every asset has a

    predicted length of life at the end of which a physical collapse is possible. However

    most assets never reach that point and are demolished or replaced beforehand, generally

    due to economic obsolescence. Note that physical life corresponds to the ISO 15686

    definition of ‘service life’.

      Economic life (from construction to economic obsolescence). Economic obsolescencehappens when the further use of an asset is no longer the most economic solution among

    alternatives.

      Functional life (from construction to the point when the asset ceases to function for its

    intended purpose). An asset reaches the end of functional life when it can no longer

    function for the purpose for which it was intended.

      Technological life (from construction to the point when the asset is technologically

    obsolete). End of technological life occurs when an asset, typically a system or

    component, is no longer technologically equal to or better than available alternatives.

      Social / legal life (from construction to the point when replacement is required for social

    or regulatory reasons). An asset reaches the end of its social or legal life when

    requirements other than economic dictate replacement or change, e.g. health and safetyor legislative issues.

      Contractual / ‘duration of interest’ life (for any period of time during the duration of

    the physical life of an asset). This period of analysis covers the length of a contract for a

    particular service, e.g. construction, operation, etc.

      Arbitrary life (length of time e.g. 25, 30, 50 years), assumed due to national practice,

    local best practice, client’s stipulation, etc.

    It can be seen from the above range of potential definitions of life that the period of analysis

    for a LCC exercise can often be shorter than the physical life of an asset, that is, from

    “cradle to the grave”. The ‘period of analysis’ must therefore be specifically defined for

    each LCC exercise.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    25/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    22

    4.4 Discounting

    4.4.1 The purpose of discounting

    Discounting is a widely used technique for comparing costs and revenues occurring at

    different points in time on a common basis, normally the present time. It is based on theprinciple that a sum of money to hand at the present time has a higher value than the same

    sum to hand at a future date, because of the earning power of that sum in the interim.

    Discounting to present value makes an adjustment to the future costs of an asset that takes

    account of inflation and the real earning power of money, allowing them to be compared

    and evaluated on the same basis as costs incurred at the present.

    The need to discount depends on the use to which the LCC analysis will be put. It is

    necessary only where a series of costs over time has to be put onto a common basis for the

    purpose of a decision, not where the objective is simply to project annual costs on a year by

    year basis. Therefore when carrying out a LCC evaluation of two or more options with

    different cost profiles over time it is likely that discounting will need to be applied, whereas

    it may not be necessary if the aim is simply to prepare a cost profile for one option alone.

    4.4.2 The effect of discount rates

    A decision not to discount, that is, to apply a zero rate, implies that the timing of a cost (eg

    for repair or renewal) is immaterial and disregards the earning power of money. However,

    use of a zero rate presents the best case for spending a greater sum up front (i.e. capital

    costs) in order to generate greater savings through the analysis period (e.g. operating,

    maintenance, energy costs). It can therefore be argued that a zero discount rate should be

    applied to all public sector investments intended to leave a lasting legacy for future

    generations.

    Conversely, a high discount rate will present options with low up-front costs as appearing

    more desirable and it can be argued that this has the effect of sacrificing the interests of

    future generations to those of the present decision-makers. However, future uncertainties

    and external influences unrelated to the asset (eg budgetary constraints or changed political

    priorities) may have an impact on the timing or extent of future costs. It can therefore be

    argued that this represents an argument for affording future costs less weight in decision-

    making and hence for discounting.

    Further guidance on the selection of the appropriate discount rate is provided below.

    4.4.3 The treatment of inflation

    The discount rate is the investment premium over and above inflation and as such is a

    separate concept and distinct from it. There are two possible approaches to dealing with

    inflation:

      Using a ‘nominal’ discount rate, that is a rate that is not adjusted to remove the effects of

    actual or expected inflation. This means that inflation predictions are built into forecast

    costs and prices

      Using a ‘real’ discount rate, that is a rate that has been adjusted to remove the effect of

    actual or expected inflation. This means that future costs and prices are estimated at

    present day (‘real’) prices and inflation can be dealt with separately.

    If inflation rates for all costs in the analysis are approximately equal, it is common practice

    to exclude inflation from the LCC analysis (i.e. to adopt a ‘real’ discount rate). However, if

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    26/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    23

    the analysis includes commodities subject to widely differing rates of inflation, for example

    energy prices and labour rates, inflation would have to be included (i.e. using a ‘nominal’

    discount rate).

    Because constructed assets typically have long service lives and it is difficult to predict

    inflation in the long term, it is generally recommended to carry out LCC analyses on using

    real costs and discount rates. It is further often recommended that results should be tested

    by applying at least two real discount rates, including one relatively lower rate, and

    appraising the difference in outcomes (see Step 13 guidance on sensitivity analysis).

    4.4.4 Selecting the discount rate

    Selecting the most appropriate discount rate is critical to the success of an LCC exercise. In

    the private sector, selecting the rate can be a highly judgemental process with reference to

    the financial status of the client and the circumstances of the particular project, and in

    practice rates can vary widely. Key considerations will be the cost of capital, the perceived

    level of project risk and the opportunity cost of capital (i.e. the level of return that could begenerated by investing the capital elsewhere).

    In the public sector, national ministries of finance generally specify the discount rates to be

    used in the economic analysis of publicly funded projects. These typically fall into the

    range of 3 to 5%. The rate may also be assessed on a case by case basis by reference to:

      The opportunity cost of capital

      The societal rate of time preference

      The cost of borrowing funds.

    The ‘opportunity cost of capital’ is the cost of foregoing an alternative investment. This

    approach assumes that finance for public sector projects is withdrawn from private savings

    and which would otherwise have gone into private investment. Hence the discount rate is

    equated to the pre-tax rate of return available to private capital.

    The ‘societal rate of time preference’ is the interest rate that reflects a government’s

     judgment about the relative value which society as a whole assigns (or which the

    government feels it ought to assign) to present versus future consumption. The societal

    time preference rate is not observed in the market and bears no relation to the rates of return

    in the private sector, interest rates, or any other measurable market phenomena.

    The rationale of the ‘Cost of Borrowing Funds’ approach is that the interest rate should

    match the rate paid by government for borrowed money. This approach is favoured by

    many agencies and is supported by the argument that government bonds are in direct

    competition with other investment opportunities available in the private sector.

    Some advocate use of a zero interest rate in the public sector, arguing that when tax monies

    (eg road tax) are used, such funds are “free money” because no principal or interest

    payments are required. A counter-argument is that zero or very low interest rates can

    produce positive cost/benefit ratios for even very marginal projects and thereby take money

    away from more worthwhile projects. A zero interest rate also fails to discount future

    expenditure, making tomorrow’s relatively uncertain predicted costs as significant in the

    decision as today’s known costs.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    27/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    24

    4.5 Methods of economic evaluation

    A number of widely used financial analysis techniques are available for the assessment of

    alternative investment options. Using two or more techniques together provides a broader

    picture of value implications.

    4.5.1 Net Present Value (NPV), Net Present Cost (NPC)

    The NPV is the sum of the discounted future cash flows, both costs and benefits/revenues.

    Where only costs are included this may be termed Net Present Cost (NPC).

    NPV is a standard measure in LCC analyses, used to determine and compare the cost

    effectiveness of proposed options. It can be applied across the full range of construction

    investments, covering whole investment programmes, assets, systems, components and

    operating and maintenance models. The costs and revenues/benefits to be included in each

    analysis are defined according to its objectives. For example, revenues from recycling of

    materials or from surplus energy generation are typically included in a LCC analysis of

    alternative sustainability options.

    4.5.2 Payback (PB)

    The PB period is the measure of how long it takes to recover initial investment costs and is

    a useful basis for evaluating alternative investment options. It may be calculated using

    either real (non-discounted) values for future costs, that is ‘Simple PB’, or present

    (discounted) values, that is ‘Discounted PB’. PB in general ignores all costs and savings

    after the payback point has been reached and it is possible that an investment with a short

    PB is a poorer option than one with a longer payback over the entire period of analysis.

    PB is a useful technique for assessing whether additional investment in, for example, lower

    energy plant, is worthwhile. It enables users to weigh the additional capital costs against

    the time it takes for these costs to be recouped through savings or income during the

    operational period. This may be a useful means of judging whether an investment

    represents good value for money, although the subjective nature of the value for money

    assessment may make it inappropriate for some public sector investment decisions.

    4.5.3 Net Savings (NS), Net Benefit (NB)

    NS/NB is the present value of savings/benefits in the operation phase less the present value

    of the additional investment costs to achieve them. It provides a measure of cost-

    effectiveness and of the benefits to be achieved from investment options. NS/NB greater

    than 0 indicates positive cost-effectiveness.

    4.5.4 Savings to Investment Ratio (SIR)

    The SIR is a measure of the cost-effectiveness of a proposed investment (an SIR greater

    than 1 is positive) and can be used to prioritise and select investment options.

    4.5.5 Adjusted Internal Rate of Return (AIRR)

    The AIRR is a measure of the annual yield from a project over the period of analysis taking

    into account reinvestments of interim receipts, indicating projects with greater net savings.

    An AIRR greater than the minimum acceptable rate of return (ie the discount rate) is

    positive.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    28/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    25

    4.5.6 Annual Cost and Annual Equivalent Value (AC or AEV)

    The AC or AEV is a uniform annual amount that, when totalled over the period of analysis,

    equals the total net cost of the project taking into account the time value of money over the

    period. It is used to compare investment options where the natural replacement cycle

    cannot easily be directly related to the period of analysis. The lowest AEV indicates the

    lowest cost option.

    4.6 Guidance on which evaluation technique(s) to use

    Further guidance on which evaluation techniques are most appropriate in a public sector

    context is provided in the Guidance Note that accompanies this methodology.

    4.7 Taxation issues

    Fiscal considerations can be highly significant in LCC analyses, particularly in the private

    sector, with tax efficiency a major objective in designing investment portfolios, finance

    arrangements and individual projects. Taxation is a complex area, varying between

    member states. Accordingly it is important at this step to develop a strategy for managing

    fiscal issues, seeking at the earliest stage the specialist professional advice which is

    available in this area. Such a strategy should be designed to minimise the tax burden on the

    project by identifying appropriate innovative and practical tax and business solutions.

    Key considerations in the strategy include:

      The tax relief or offsets which may be available against certain costs in the overall CBS,

    e.g. typically for repairs and maintenance, which would tend to favour options with

    lower initial costs

      Similarly the tax penalties which might apply to the use of certain materials or have an

    indirect impact, e.g. through higher energy costs.

    Tax can also represent an area of risk, for example in:

      The probability of environmentally inefficient structures attracting current or future

    environmental taxes

      The possibility of tax rates changing.

    Value added tax (VAT is subject to similar considerations. Both the rate and accounting

    methods vary between member states and specialist advice is again likely to be essential.

    4.8 At the end of Step 4

    At the end of Step 4 the user will have:  Identified and confirmed with the client the period of analysis and the considerations

    governing its choice

      Identified and confirmed with the client the appropriate technique(s) for assessing

    investment options, including the discount rate(s) to be used and the implications

    therein.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    29/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    26

    5  STEP 5: Identify the need for additional analyses (risk/uncertainty

    and sensitivity analyses)

    5.1 The purpose of this stepRisk and uncertainty analysis is a body of theory and practice which has been developed to

    help decision-makers assess their risk exposure and attitudes in a systematic manner. At

    this step the user considers how and why it can be applied in conjunction with LCC

    analyses to support decision-making and in particular, which risk assessment methodologies

    will be most appropriate.

    5.2 Risk and uncertainty in LCC

    Ownership, investment and occupation of constructed assets are by nature long-term

    activities and as such are characterised by a range of uncertainties, principally in the value

    and timing of future costs and revenues. Within this context, LCC is a forward lookingprocess that requires predictions of these variables to be made in order that robust decisions

    can be taken. Consequently, certain risks are inherent in the LCC assessment process,

    namely:

      That the total life cycle costs in a given period exceed those calculated, and;

      That the life cycle cost profile over a given period differs from that predicted (e.g. the

    total costs may be the same, but the distribution of those costs over time differs from

    that predicted).

    These key risks can arise as a result of variability in one or more of the predicted values or

    assumptions in the LCC model (see Sec.5.4 below).

    While robust assessment of the key cost and time variables can help reduce the risksinherent in the LCC process, the fact that LCC is concerned with predicting future costs and

    activities means that an element of risk will almost always be built into the calculations. It

    is therefore important that clients are made aware of this issue and of the steps that can be

    taken to quantify and in some cases mitigate the risks.

    Often, the identification and assessment of LCC related risks can have a significant

    influence on decision-making process, with a resulting impact on the LCC of a project –

    examples are given in table 3 below.

    Table 3: Potential impact of risk on decision-making

    Examples of risks identified Possible decisions taken in response

    Risk of more demandingenvironmental legislation

    Selection of higher capital cost HVACsystem with improved environmentalperformanceSelection of lower capital cost HVACsystem with shorter life and due forreplacement in short period of time

    Risk of LCC increases and/ordisruption due to high cost/quantitycomponents requiring earlyreplacement

    Selection of alternative components withlonger service life or improved warrantiesImprove planned maintenance regime toprevent early failures

    Risk that labour costs will rise in

    excess of inflation allowances inmodel

    Selection of less labour intensive

    materials and systems (e.g. requiring lesscleaning and maintenance)

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    30/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    27

    Increase inflation allowances in model.Risk of increased land-fill/waste taxes Selection of longer-life components in

    order to minimise wasteSpecify greater proportion of recyclablematerials

    5.3 Managing risk/uncertainty

    The management of risk is fundamentally a three stage process:

      Identifying the risk

      Assessing the risk in terms of its likelihood and impact

      Taking appropriate action in response, which might variously be to accept, mitigate,

    transfer or avoid the risk.

    The extent to which the above process is applied and whether it is undertaken for LCC in

    isolation or as part of a wider, formalised risk management process is a matter of judgement

    for the client in the light of the scope and complexity of the project. This decision should

    be taken at this step in the LCC methodology. For a major investment a risk management

    plan should be formally established with clear objectives and success criteria, proper

    planning and resourcing, and effective management and control.

    The risk management plan should be progressively updated as a project moves through its

    stages. The overall process is illustrated in figure 3 below.

    Figure 3: Risk management cycle.

    PeriodicUpdate

     

    5.4 Identifying causes of variability in the LCC analysis

    A number of common risk identification methods can be used for identifying potential

    causes of variability in the LCC analysis including:

      Accessing relevant databases, where available

      Obtaining feedback from past projects

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    31/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    28

      Drawing out the knowledge and experience of individuals within the team, eg by

    ‘brainstorming’ techniques

      Conducting interviews

      The ‘Delphi’ method, gathering information from project participants by email or post

      Checklists of variability factors commonly associated with particular tasks.

    Common causes of variability in LCC include:

      Capital costs (actual v predicted)

      Operational costs, including maintenance, FM, energy, component replacements

      Costs of refurbishment/upgrading

      Disposal costs

      Future levels of inflation (labour and materials) underpinning the above costs

      Interest rates (in relation to loan payments)

      The service lives of the components, systems and materials that make up the asset

      The extent and timings of planned (cyclical) maintenance and refurbishment works

    required  The extent and timings of unplanned (responsive) maintenance required

      Energy consumption levels

      Changes in the use of the asset

      Obsolescence / technological development

      Change in the fiscal regime

      New legislation, for example on sustainability issues

    Only risks that are strictly relevant to the LCC exercise in hand should be considered.

    Some risks such as future obsolescence and legislative changes are almost impossible to

    assess and the decision may be taken to discount them.

    Further guidance on the prediction of service lives of constructed assets and theircomponents, and the factors affecting service lives is provided in ISO 15686 Part 1.

    During this risk identification process initial views may be formed on the probability of

    occurrence, impact, ownership and possible actions to address or mitigate the risks.

    A preliminary LCC risk/variability identification process should be carried out on every

    project at this step, unless the scope of the project is such that risk is manifestly very low.

    The depth and rigour of the process should be appropriate for the scope and nature of the

    project. The results should be recorded on the first draft of a risk register (see section 5.6.1

    following).

    5.5 Assessing variability

    Having identified potential causes of variability in the LCC assessment it is then necessary

    to assess their potential likelihood and extent, for which a variety of risk assessment tools

    and techniques is available. These fall into two broad categories:

      Qualitative, employing subjective scoring techniques

      Quantitative, using mathematical approaches.

    Quantitative techniques fall into two further categories:

      Statistical and probabilistic (stochastic) approaches

      Deterministic, with numerical computation of risk.

    The range of approaches is illustrated in figure 4 below, with those most widely applied toLCC highlighted.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    32/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    29

    The choice of an appropriate methodology depends not only on the scope and rigour of the

    analysis required but also on the quality and extent of data available. Relevant historical

    data might be available in databases, or from organisations involved in the project.

    However, there is little reliable historical LCC data held at a national or international level,

    accordingly the availability and quality of relevant data should be reviewed beforeundertaking a risk assessment exercise.

    When undertaking the risk assessment it is important to distinguish between planned costs

    (which assume everything goes well) and expected costs (which include an allowance based

    on experience for problems such as cost and time over-runs).

    Figure 4: Common tools and techniques in risk/uncertainty analysis

    Techniques for risk and

    uncertainty assessments

    Deterministic (numerical

    computation of risk)

    Qualitative (using subjective

    scoring techniques)

    Quantitative (statistical &probabilistic approaches)

    Benefit and cost estimating

    Break-even analysis

    Risk-adjusted discount rate

    Certainty equivalent technique

    Sensitivity analysisVariance & standard deviation

    Net present value

    Other 

    Mean-variance criterion

    Decision tree analysis

    Monte Carlo simulation

     Artificial Intelligence

    Fuzzy set theory

    Event trees

    Confidence modelling

    Other 

    Risk matrices

    Risk registers

    Event trees

    SWOT analysis

    Brainstorming

    Likelihood/consequence assessment

    Other 

     

    5.6 Qualitative risk assessment

    Qualitative risk assessment is essentially a subjective process relying on the knowledge,

    skills and experience of the participants, but undertaken in a managed manner. Methods of

    drawing out this information are broadly similar to those used for risk identification, that is,brainstorming, reference to databases, interviews, etc. For each of the identified risks the

    team will typically consider:

      Their likelihood

      Who / what is likely to be affected and to what extent

      Who owns them

      How important it is to mitigate them

      What action should be taken.

    A number of tools are available for qualitative risk assessment, of which risk registers are

    the most user-friendly and commonly used. Compiling a risk register is normally the first

    step in risk management and provides a format for systematically recording the outcomes ofrisk identification and assessment. The register should be regularly updated to contribute to

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    33/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    30

    risk management throughout the project life cycle. The information available in risk

    registers can be used to initiate quantitative risk analysis and to support subsequent risk

    mitigation.

    The typical headings used in compiling a risk register include:

      title and description of risk

      description of causes

      dates when the risk was identified / modified

      risk code

      ownership of the risk

      likelihood of occurrence

      potential impact

      ranking

      mitigation action plan and timescale

      residual risk effects.

    The level of detail on the risk register is a matter for judgement with reference to the scopeand complexity of the project.

    Other qualitative tools which may be applicable include probability matrices and impact

    assessment matrices, which can be used by the team to facilitate the related assessments for

    entry onto the risk register.

    A probability matrix facilitates the essentially subjective process of assessing the likelihood

    of a risk event occurring by clarifying the concept of ‘probability’. A typical matrix is

    illustrated in figure 5 below. The process depends fundamentally on the project team and

    key stakeholders contributing to the process – knowledge of the project and related

    activities within it, experience and historical data will all be relevant.

    Figure 5: Probability matrix

    An impact assessment matrix similarly facilitates the process of assessing the impact of

    each risk, requiring a comparable contribution of knowledge and experience.

  • 8/9/2019 Life Cycle Cost Analysis - Info 1

    34/80

    Life Cycle Costing (LCC) as a contribution to sustainable construction: a common methodology

    Davis Langdon Management Consulting May 2007 

    31

    5.7 Quantitative risk assessment

    Quantitative risk analysis involves formulation of a model for computing the risk impacts

    on quantifiable project performance measures such as cost and duration. In theory

    quantitative assessment provides much better insights into risk and risk management, but it

    can be difficult to apply in a construction context and expert advice is an essential

    prerequisite, both for setting up models and selecting relevant data and interpreting the

    results.

    In practice, two techniques are likely to be of particular value in the LCC context and are

    identified as such in ISO 15686 Part 5, namely sensitivity analysis and Monte Carlo

    simulation.

    5.7.1 Sensitivity analysis

    Sensitivity analysis measures the impact on project outcomes of changing key input values

    about which there is uncertainty, typically:

      discount rate

      future inflation assumptions

      period of analysis

      service life or maintenance, repair or replacement cycles

      operational cost data.

    For