Completed construction of the Platform skidways. Completed loadout of Liquid Storage Module (LSM) onto the transportation barge. Completed removal of Living Quarters (LQ) and MEG Reclamation Unit (MRU) from Domestic Supply Module (DSM). Completed all platform hydrotests, flushing, and leak testing activities. Completed safety planning workshops with Heerema for Transportation & Installation (T&I) scope. Completed installation of the Subsea Distribution Assembly (SDA). Completed installation of 3 Well Jumpers and Wet Gas Flowmeter Modules. Completed flooding, pigging, and hydrotesting activities on the MEG Pipelines. Completed hydrotesting of Gas & Condensate Pipelines from Jacket to DVS. A Safe, Reliable, Environmentally Responsible Gas Supply JUNE 2019 Sami Zatout is a fabrication company with experience in fabrication and installation metal structures, facility piping and storage tanks in Israel. Past clients include refineries, power plants and water treatment plants. As part of the Leviathan Project, Noble Energy has contracted Zatout to fabricate and install the structural supports and the interconnect piping (ICP) for the Hagit terminal. Sami Zatout is another shining example of a local Israeli contractor successfully supporting and contributing to the success of the Leviathan Project as we are Energize the World and Bettering Peoples Lives. LEVIATHAN As a leader for onshore engineering, I feel privileged to take part in an exciting and challenging project which will make a significant impact for Noble Energy (Israel and the region). Its amazing to see across-the- ocean collaboration between engineers and contractors, from the US, Israel and other countries, all focusing on one big target, to bring Leviathan alive.- Simi Segal, Onshore Engineering Lead Contractor Spot- PROJECT HIGHLIGHTS: PROJECT PROGRESS UPDATE Platform skidways completed Living Quarters (LQ ) and MEG Reclamation Unit (MRU) removal from DSM Subsea Distribution Assembly (SDA) installation completed Liquid Storage Module (LSM) loadout completed

Upload: others

Post on 15-Mar-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LEVIATHAN...• Completed installation of the Subsea Distribution Assembly (SDA). • Completed installation of 3 Well Jumpers and Wet Gas Flowmeter Modules. • Completed flooding,

• Completed construction of the Platform skidways.

• Completed loadout of Liquid Storage Module (LSM) onto the transportation

barge.

• Completed removal of Living Quarters (LQ) and MEG Reclamation Unit

(MRU) from Domestic Supply Module (DSM).

• Completed all platform hydrotests, flushing, and leak testing activities.

• Completed safety planning workshops with Heerema for Transportation & Installation

(T&I) scope.

• Completed installation of the Subsea Distribution Assembly (SDA).

• Completed installation of 3 Well Jumpers and Wet Gas Flowmeter Modules.

• Completed flooding, pigging, and hydrotesting activities on the MEG

Pipelines.

• Completed hydrotesting of Gas & Condensate Pipelines from Jacket to DVS.

A Safe, Reliable, Environmentally Responsible Gas Supply

JUNE 2019

Sami Zatout is a fabrication company with experience in

fabrication and installation metal structures, facility piping and storage tanks in Israel. Past

clients include refineries, power plants and water treatment plants. As part of the Leviathan

Project, Noble Energy has contracted Zatout to fabricate and install the structural supports

and the interconnect piping (ICP) for the Hagit terminal.

Sami Zatout is another shining

example of a local Israeli contractor

successfully supporting and contributing

to the success of the Leviathan Project

as we are Energize the World and

Bettering People’s Lives.

LEVIATHAN

“As a leader for onshore engineering, I feel privileged to take part in an exciting and challenging project which will make a significant impact for Noble Energy (Israel and the region). It’s amazing to see across-the-ocean collaboration between engineers and contractors, from the US, Israel and other countries, all focusing on one big target, to bring Leviathan alive.”

- Simi Segal, Onshore Engineering Lead

Contractor Spot-

PROJECT HIGHLIGHTS:

PROJECT PROGRESS

UPDATE

Platform skidways completed

Living Quarters (LQ ) and MEG Reclamation Unit (MRU) removal from DSM

Subsea Distribution Assembly (SDA) installation completed

Liquid Storage Module (LSM) loadout completed