Southwest Power Pool Renewables: >10,000 MW (including hydro from WAPA) Wind Peak: 9,948 MW (12/19/15) – 33% of total system load 3

TRANSCRIPT

Page 1: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

Lessons Learned from Existing RTOs

John MooreJanuary WCEA Meeting

January 7th, 2016

Page 2: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

2

Southwest Power Pool

• 18 million people• 56,142 miles of

transmission lines• Total installed

generating capacity: 77,366 MW (2015)

• Historic peak demand: 45,256 MW (2013)

Page 3: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

3

Southwest Power Pool

• Renewables: >10,000 MW (including hydro from WAPA)

• Wind Peak: 9,948 MW (12/19/15)– 33% of total system load

Page 4: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

4

MISO

• 18,400 MW Renewables (2015)– 9% wind, 3% hydro, 2%

other.• Wind Peak: 12,613 MW

(11/19/15)

Page 5: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

5

MISO

• 42 million people• 65,800 miles of

transmission lines• Total installed

generating capacity: 180,711 MW (2015)

• Historic peak demand: 127,125 MW (2015)

Page 6: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

6

PJM

• 61 million people• 62,556 miles of

transmission lines• Total installed

generating capacity: 183,604 MW (2015)

• Historic peak demand: 165,492 MW (2015)

Page 7: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

7

PJM

• Renewables: 13,000 MW– 7 GW wind, 2.5 GW solar

(350 MW utility scale).• Wind Peak: 5,588 MW

(11/17/15)– 8.1% of total system load

Page 8: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

8

Strategic Considerations• Who serves public interest?• Sector participation levels in governance and process

– States, environmental, consumer– State reluctance and consensus issues + resource

constraints for all• RTO “culture” drivers

– Utility mix– Restructured or vertically integrated, or both– State commissioner interest/personalities– Influence of states, TOs, and other sectors per agreements

Page 9: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

9

PJM Governance

• PJM is an LLC; 940+ members vote on tariff changes made under FPA 205– Weighted sector voting– Board can act independently under 206

• Strong committee role in committees; Problem Statements

• Observations on Board and executive leadership• Markets rule!

Page 10: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

10

PJM Governance• 16 committees, 19 subcommittees, 8 task forces, 4 user

groups• Sectors: Transmission Owner, Generation Owner, Electric

Distributor, End-Use Customer, Other Supplier.

Page 11: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

11

PJM Renewables Priorities• Distributed energy resources – especially PV• Better forecasting• Understanding operations impacts• FERC approved PJM’s enhanced inverter standards

proposal in 2015 for all new interconnected wind and solar resources 10 kW or larger

• Battery storage

• Light load criteria in planning• Congestion from MISO wind

• Wind ramping product not on agenda

Page 12: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

12

State Participation• Organization of PJM States (OPSI)– Not a PJM member, nor are individual states– No independent 205 filing authority– MOU with Board for access– Observes at Liaison Committee meetings– Funded through PJM ($587,000 in 2014)

• Independent State Agencies Committee (ISAC)– State utility commissions, energy and environmental agency

input into PJM– Stagnant at moment, some opportunity with CPP

Page 13: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

13

Top OPSI Interests• Limiting cost impacts of capacity market and

other PJM initiatives• Strong, INDEPENDENT market monitor• Protecting state jurisdiction• Clear “beneficiary pays” cost allocation rules for

Tx driven by public policies• Understanding the Clean Power Plan

Page 14: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

14

CPP – States Awash in Modeling

Page 15: Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016

15

PJM Planning and Cost Allocation• Historic focus on reliability and market efficiency planning• Increasing scenario and interregional planning • Competitive bidding on most projects

• Cost Allocation– Reliability– Economic– Multi-Driver Projects

• Proportional cost allocation• Incremental cost allocation• States pay for public policy projects - RESULT – no

projects