lesson 16 risk management and problems

Upload: heris-sitompul

Post on 03-Jun-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Lesson 16 Risk Management and Problems

    1/89

  • 8/12/2019 Lesson 16 Risk Management and Problems

    2/89

    Harold Vance Department of Petroleum Engineering

    Risk Management and

    Downhole Problems

    Risk ManagementRisk Identification

    Quantitative Risk Analysis

    Risk Mitigation Planning

  • 8/12/2019 Lesson 16 Risk Management and Problems

    3/89

    Harold Vance Department of Petroleum Engineering

    Downhole Problems andTroubleshooting

    Wellbore Instability

    Excessive Vibration

    Fluid Influxes

    Stuck Pipe and Fishing

    Corrosion

    Risk Management and

    Downhole Problems

  • 8/12/2019 Lesson 16 Risk Management and Problems

    4/89

    Harold Vance Department of Petroleum Engineering

    Risk Management

    A major success factor in UBD ishow effectively the designers andimplementers identify risks and

    develop an effective plan to dealwith the risks.

    Introduction

  • 8/12/2019 Lesson 16 Risk Management and Problems

    5/89

    Harold Vance Department of Petroleum Engineering

    Risk Management

    Before implementing the finaldesign, the selected equipmentand operating procedures should

    be subjected to an exacting riskanalysis.

    Introduction

  • 8/12/2019 Lesson 16 Risk Management and Problems

    6/89

    Harold Vance Department of Petroleum Engineering

    Risk IdentificationQuantitative Risk Analysis

    Risk Mitigation PlanningRisk Response

    Risk Management

    Stages

  • 8/12/2019 Lesson 16 Risk Management and Problems

    7/89

    Harold Vance Department of Petroleum Engineering

    Risk IdentificationQuantitative Risk Analysis

    Risk Mitigation Planning

    Risk Management

  • 8/12/2019 Lesson 16 Risk Management and Problems

    8/89

    Harold Vance Department of Petroleum Engineering

    Source of Risk.

    Probability of Occurrence.Potential Impact.

    Action to Mitigate.

    Cost to Mitigate.

    Probability Mitigation Succeeds.

    Risk Identification

  • 8/12/2019 Lesson 16 Risk Management and Problems

    9/89

  • 8/12/2019 Lesson 16 Risk Management and Problems

    10/89

    Harold Vance Department of Petroleum Engineering

    Probability of Occurrence

    Can be on a scale of:1 to 10 or

    High, Medium, and Low

  • 8/12/2019 Lesson 16 Risk Management and Problems

    11/89

    Harold Vance Department of Petroleum Engineering

    Potential Impact

    High, Medium, or Low.

    May be referred to asConsequenceCan be defined by dollar amounts or

    other criteria, such as severity ofinjuries or death, or any combination

    of dollar amount and injury.Probability * Consequence = Risk

  • 8/12/2019 Lesson 16 Risk Management and Problems

    12/89

    Harold Vance Department of Petroleum Engineering

    Action to Mitigate

    Next, the decision whether to live

    with the risk or if risk mitigation isin order.

    Mitigation involves reducing the

    probability of occurrence or thepotential impact of a given risk.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    13/89

    Harold Vance Department of Petroleum Engineering

    Risks can be mitigated by:

    Choose substitute equipment types.

    Upgrade specifications such as

    materials strength, ratings, etc.Modify the basic design.

    Transpose steps in the procedure.

    Change mud systems, completionoptions, etc.

    Include backup equipment.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    14/89

    Harold Vance Department of Petroleum Engineering

    Cost to Mitigate

    The relative cost to mitigatemust be estimated, based onrough approximations, in order

    to evaluate the viability of themitigation actions.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    15/89

    Harold Vance Department of Petroleum Engineering

    Probability MitigationSucceeds

    Estimate the probabilitywill succeed.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    16/89

    Harold Vance Department of Petroleum Engineering

    Risk Mitigation Table

    Description of

    Risk

    Sourceof Risk

    Probabilityof

    occurrence

    PotentialImpact

    Action tomitigate

    Cost toMitigate

    ProbabilityMitigationSucceeds

    Hurricane strikeswhile drilling andrequires shut downof operations

    E Low Medium

    Create plan fortemporary shut-inof well andabandonment ofoffshore platform.

    Low High

    Drill string failure I Medium Medium

    Institute tubulartesting programthat includespressure testing

    and magneticscanning of micro-fractures

    Medium High

  • 8/12/2019 Lesson 16 Risk Management and Problems

    17/89

    Harold Vance Department of Petroleum Engineering

    Risk IdentificationQuantitative Risk Analysis

    Risk Mitigation Planning

    Risk Management

  • 8/12/2019 Lesson 16 Risk Management and Problems

    18/89

    Harold Vance Department of Petroleum Engineering

    Quantitative Risk Analysis

    What is Uncertainty?

    Risk Analysis and Decision-Making.What is Quantitative Risk Analysis?

    When should I use Quantitative

    Risk Analysis?Why should I use Quantitative riskAnalysis?

  • 8/12/2019 Lesson 16 Risk Management and Problems

    19/89

    Harold Vance Department of Petroleum Engineering

    What is Uncertainty?

    Dictionary definition:

    the estimated amount orpercentage by which an observed orcalculated value may differ from thetrue value

    Benjamin Franklin pointed out:

    In this world nothing can be said tobe certain, except death and taxes

  • 8/12/2019 Lesson 16 Risk Management and Problems

    20/89

    Harold Vance Department of Petroleum Engineering

    Risk Analysisand Decision-Making

    Risk analysis and decision making arefundamentally related.

    A key component of Risk Analysis isto provide support for a particulardecision.

    In our industry, the decision that

    requires risk analysis is usuallysubject to acceptance by a team oftechnical professionals and approvalby management.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    21/89

    Harold Vance Department of Petroleum Engineering

    What isQuantitative Risk Analysis?

    Any technique for analyzinguncertainty and quantifying theeffects of that uncertainty on

    factors that will significantlyeffect decision making.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    22/89

    Harold Vance Department of Petroleum Engineering

    A method of quantifying the consequencesof the risks identified by intuition through a

    structured approach to decision makingbased on:

    what you think you know and dont

    know.What you can do.

    What you want the outcome to be.

    What isQuantitative Risk Analysis?

  • 8/12/2019 Lesson 16 Risk Management and Problems

    23/89

    Harold Vance Department of Petroleum Engineering

    When should I useQuantitative Risk Analysis?

    Risk analysis can be usedthroughout an UB project toimprove the quality of technical

    evaluations and improve riskmitigation techniques.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    24/89

  • 8/12/2019 Lesson 16 Risk Management and Problems

    25/89

    Harold Vance Department of Petroleum Engineering

    Probabilistic methods providebetter decisions than deterministicmethods because a full range ofpotential outcomes is examined.

    Why should I useQuantitative Risk Analysis?

  • 8/12/2019 Lesson 16 Risk Management and Problems

    26/89

    Harold Vance Department of Petroleum Engineering

    Quantitative Risk

    AnalysisThe Process

    Problem Identification.

    Deterministic Analysis.

    Probabilistic Analysis.

    Evaluation andCommunication.

    Decision and Action.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    27/89

    Harold Vance Department of Petroleum Engineering

    Problem Identification

    Identify the problem, the reason

    that a solution is required, andproject desires.

    Collect and review data.

    Verify accuracy of data, and ensureit is pertinent to the issue at hand.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    28/89

    Harold Vance Department of Petroleum Engineering

    Deterministic Analysis

    Construct a model relating inputs

    and possible outcomes.Perform a sensitivity analysis and

    present the results in graphs and

    tables.Identify key variables and examine

    them in more detail.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    29/89

    Harold Vance Department of Petroleum Engineering

    Probabilistic Analysis

    Assign key variables a range andprobability distribution.

    Conduct an assessment using

    Monte Carlo simulation.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    30/89

    Harold Vance Department of Petroleum Engineering

    Evaluation andCommunication

    Check if the results make sense,determine if additional informationis needed, and create graphs andtables to communicate the results of

    the analysis.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    31/89

    Harold Vance Department of Petroleum Engineering

    Decision and Action

    Recommend the best alternativeconsistent with the analysis andproject desires.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    32/89

    Harold Vance Department of Petroleum Engineering

    How to do a HAZOP

    HAZOP

  • 8/12/2019 Lesson 16 Risk Management and Problems

    33/89

    Harold Vance Department of Petroleum Engineering

    Essential Elements

    Procedure/System Layout.

    HAZOP Form.

    Small Group.

    Recorder.Co-ordinator.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    34/89

    Harold Vance Department of Petroleum Engineering

    Conventional MudLift with SAC and DSV (SS Pump on Inlet Pressure)

    Shut In-Drlg

    1. Raise kelly/top drive until the drivebushing clears the rotary.

    2. Stop pumps and check for flow.3. Open choke line fail safe valve (with

    choke closed).

    4. Close upper annular. (Someoperators may prefer to shut-in on

    rams instead)

    5. Check for leaks, notify supervisor,record SIDPP, SICP, Pit Gain, Time,

    Date.6. Close upper pipe rams. (Depending

    upon the stack, could be middle rams)7. Reduce closing pressure on upperannular, and lower drillstring untiltool joint rests on closed upper pipe

    ram.8. Open upper annular and restore

    closing pressure to normal.9. Prepare for kill.

    1. Raise kelly/top drive until the drive bushing clears the rotary.2. Isolate SAC from wellbore.3. Stop rig pumps (DP pressure falls to DSV opening pressure); SS pump maintains

    seawater hydro. If SS pump keeps running, well flow is verified.4. Stop subsea pump. Record SS inlet pressure (excess above sea hydro is SICP.)

    Pump slowly on DP until pressure flattens (DSV opens). SIDP is increase above

    pre-recorded DSV opening pressure.

    5. Close upper annular. (Some operators may prefer to shut-in on rams instead)6. Check for leaks, notify supervisor, record SIDPP, SICP, Pit Gain, Time, Date.7. Close upper pipe rams. (Depending upon the stack, could be middle rams)8. Reduce closing pressure on upper annular, and lower drillstring until tool joint

    rests on closed upper pipe ram.

    9.

    Open upper annular and restore closing pressure to normal.10.Prepare for kill.Discussion:

    The use of the DSV will allow faster shut in and flow measurements. Closure of the DSV after mud circulation is stopped will make measurement of SIDPP

    more complicated.

    There must be a means of isolating the SAC from the wellbore pressures upon shut-in. Isolation of SAC will slightly complicate the shut-in procedure relative to

    conventional riser drilling.

    Procedure

  • 8/12/2019 Lesson 16 Risk Management and Problems

    35/89

  • 8/12/2019 Lesson 16 Risk Management and Problems

    36/89

    Harold Vance Department of Petroleum Engineering

    System Layout

  • 8/12/2019 Lesson 16 Risk Management and Problems

    37/89

    Harold Vance Department of Petroleum Engineering

    Date: ______________

    HAZOP(RISK ASSESSMENT)

    WC-1_

    MUDLIFT MODE: WC-1 Drilling with SAC and DSV with Shut-In (Base Case) Page: ofACTIVITY: Kick Detection, Stop Flow/Shut-In, Measurement, Drillers Method

    REASON: Probably preferred MODE and procedures for most participants

    ASSUMPTIONS: Hangoff @ SI; SS Pump on Inlet Pressure = Sea Hydro Before Kick; DSV set for Positive Opening Pressure

    Probability (H,M,L) RISKHazard Consequence (H,M,L) Existing Safeguards

    Avg C x P

    Shut-In, Pit Gain,

    SIDP, KCP, DP Sch.

    Description

    1.2.3.4.5.6.7.8.9.10.11.12.Put Participants names in shaded boxes for individual assessment of Probability. Put weighted Average in Avgcolumn.

    HAZOP Form

  • 8/12/2019 Lesson 16 Risk Management and Problems

    38/89

    Harold Vance Department of Petroleum Engineering

    Small Group

    Large groups unwieldy.

    4 to 8 about right.

    All should take active part.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    39/89

    Harold Vance Department of Petroleum Engineering

    Recorder

    Act as Wordsmith.

    Good with a Laptop.

    LCD Projector handy.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    40/89

    Harold Vance Department of Petroleum Engineering

    Co-ordinator

    Familiar with HAZOP process.

    Monitors discussion.

    Keeps focus.

    Dampens noise level.Helps Recorder.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    41/89

    Harold Vance Department of Petroleum Engineering

    What-If for Hazards

    Unobserved Event.

    Equipment Failure.

    Unworkable Procedure.

    Unrealized Expectation.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    42/89

    Harold Vance Department of Petroleum Engineering

    With a Hazard Named:

    Figure Out Consequences.

    Decide Probability.

    Calculate Risk.

    Stick to Agreed Definitions.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    43/89

    Harold Vance Department of Petroleum Engineering

    Consequence Effect

    HIGH

    Fatality

    Or

    Damage $ 1-10 MM

    MEDIUM

    LTI-Disability

    Or

    Damage $ 25K-1 MM

    LOW

    Non-LTI Injury

    Or

    Damage < $ 25K

    NOTE: These are possible consequences of hazards that can develop even with existing Safeguards inPlace prior to modifications resulting from the HAZOP.

    Qualify Consequence

  • 8/12/2019 Lesson 16 Risk Management and Problems

    44/89

  • 8/12/2019 Lesson 16 Risk Management and Problems

    45/89

    Harold Vance Department of Petroleum Engineering

    RISK MATRIX

    PROBABILITY

    LOW MEDIUM HIGH

    CONSEQUENCE

    HIGH H*L = M H*M = M H*H = H

    MEDIUM M*L = L M*M = M M*H = M

    LOW L*L = L L*M = L L*H = L

    For Well Control, Risk must be at Low Level.

    Risk = Consequence*Probability

    Risk

  • 8/12/2019 Lesson 16 Risk Management and Problems

    46/89

    Harold Vance Department of Petroleum Engineering

    With Risks Assessed

    Fill Out the Form.Final Entries inRiskColumn.

    OnlyLowRisks Acceptable.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    47/89

    Harold Vance Department of Petroleum Engineering

    Now What?

    Here

    Wrap it up!!Real World

    Three more steps.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    48/89

    Harold Vance Department of Petroleum Engineering

    Final Steps

    MitigationRevised Risk

    Proposed Action

  • 8/12/2019 Lesson 16 Risk Management and Problems

    49/89

    Harold Vance Department of Petroleum Engineering

    Slow process.

    Both constructive & destructive.

    Side issues can mess it up.

    Probably not right the first time.Consequence vs. Catastrophe.

    Perils & Pitfalls

  • 8/12/2019 Lesson 16 Risk Management and Problems

    50/89

    Harold Vance Department of Petroleum Engineering

    Problem withQuantitative Risk Analysis

    Determining the probabilities.

    Mis-understanding of the innerworkings of the model.

    Lack of reality checks.

    Ignoring relationships betweenvariables.

    Use of subjective judgments.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    51/89

    Harold Vance Department of Petroleum Engineering

    Risk IdentificationQuantitative Risk Analysis

    Risk Mitigation Planning

    Risk Management

  • 8/12/2019 Lesson 16 Risk Management and Problems

    52/89

    Harold Vance Department of Petroleum Engineering

    Risk Mitigation Planning

    Risk Mitigation Plan

    Risk Response

  • 8/12/2019 Lesson 16 Risk Management and Problems

    53/89

    Harold Vance Department of Petroleum Engineering

    Risk Mitigation Plan

    Should be incorporated into theindividual well program for each well.

    Should include a brief description ofthe operations risks identified andanalyzed in the previous phases and

    suggested mitigation measures thatwere derived.

    Keep is simple.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    54/89

    Harold Vance Department of Petroleum Engineering

    The plan should include:

    Emergency phone numbers.

    Engineering drawings andsketches.

    Risk mitigation procedures.

    Risk Mitigation Plan

  • 8/12/2019 Lesson 16 Risk Management and Problems

    55/89

    Harold Vance Department of Petroleum Engineering

    Risk Response

    Field personnel must be ready toimplement emergency responses.

    Inspections, audits and field visitswill assist in ascertaining theability of operations personnel torespond to a particular risk.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    56/89

    Harold Vance Department of Petroleum Engineering

    Downhole Problems andTroubleshooting

    Wellbore Instability

    Excessive VibrationFluid Influxes

    Stuck Pipe and FishingCorrosion

  • 8/12/2019 Lesson 16 Risk Management and Problems

    57/89

    Harold Vance Department of Petroleum Engineering

    Wellbore Instability

    Causes of Instability

    Symptoms

    Prevention

    Solutions and Treatments

  • 8/12/2019 Lesson 16 Risk Management and Problems

    58/89

    Harold Vance Department of Petroleum Engineering

    Causes of Instability

    Mechanical - Most are related to mudweight, more specifically, to mud

    weight reduction while attempting toget underbalanced.

    Abnormal pressure, tectonic stress,

    and unconsolidated formations areall causes of mechanical wellboreinstability.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    59/89

    Harold Vance Department of Petroleum Engineering

    Chemical - related to reactivityof shale and/or clay that may bepresent in other formations.

    Most causes by exposure to freshwater.

    Causes of Instability

  • 8/12/2019 Lesson 16 Risk Management and Problems

    60/89

    Harold Vance Department of Petroleum Engineering

    Symptoms

    Most symptoms are due to rock failureand excessive amounts of formation in

    the wellbore. Include:

    increased torque/drag.

    increase fill on bottom duringconnections/trips.

    increased annular pressure.

    excessive cuttings at the surface.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    61/89

    Harold Vance Department of Petroleum Engineering

    Prevention

    Determine the cause.Adequate mud density.

    Proper chemical make-up of

    the drilling fluid.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    62/89

    Harold Vance Department of Petroleum Engineering

    Solutions and Treatments

    Increase circulation rate.

    Keep pipe moving at all times.

    Use inhibitive fluids.

    h l bl d

  • 8/12/2019 Lesson 16 Risk Management and Problems

    63/89

    Harold Vance Department of Petroleum Engineering

    Downhole Problems andTroubleshooting

    Wellbore Instability

    Excessive VibrationFluid Influxes

    Stuck Pipe and Fishing

    Corrosion

  • 8/12/2019 Lesson 16 Risk Management and Problems

    64/89

    Harold Vance Department of Petroleum Engineering

    Excessive Vibration

    Causes of Excess Vibration.

    Symptoms of Vibration.

    Prevention and Solution to

    Excessive Vibration.

    C f E

  • 8/12/2019 Lesson 16 Risk Management and Problems

    65/89

    Harold Vance Department of Petroleum Engineering

    Causes of ExcessVibration

    Drilling rough, highly fractured orabrasive rocks.

    Hard rocks.

    Improper handling of percussiontools.

    Gas drilling does not dampenvibrations as much as liquids.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    66/89

    Harold Vance Department of Petroleum Engineering

    Symptoms of Vibration

    Drillstring damage noticed throughinspection.

    High incidence of downhole toolfailure.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    67/89

    Harold Vance Department of Petroleum Engineering

    Prevention and Solution to

    Excessive VibrationKeep the drillpipe in tension.

    All compressive forces should becontained in the BHA.

    Calculate the neutral point so thatwhen the maximum WOB isapplied, the neutral point is in theBHA.

    D h l P bl d

  • 8/12/2019 Lesson 16 Risk Management and Problems

    68/89

    Harold Vance Department of Petroleum Engineering

    Wellbore Instability

    Excessive VibrationFluid Influxes

    Stuck Pipe and FishingCorrosion

    Downhole Problems andTroubleshooting

  • 8/12/2019 Lesson 16 Risk Management and Problems

    69/89

    Harold Vance Department of Petroleum Engineering

    Fluid Influxes

    Causes

    Symptoms of Unwanted Influxes

    Prevention of Influxes

    Solutions to Unwanted Influxes

  • 8/12/2019 Lesson 16 Risk Management and Problems

    70/89

    Harold Vance Department of Petroleum Engineering

    Causes

    Major cause is UBD.

    Three requirements for influx.some measurable porosity.

    Permeability.

    wellbore pressure < formationpressure.

    Symptoms of

  • 8/12/2019 Lesson 16 Risk Management and Problems

    71/89

    Harold Vance Department of Petroleum Engineering

    Symptoms ofUnwanted Influxes

    Fluids being returned to the surface thatare not pumped into the wellbore.

    Damp cuttings when drilling with drygas.

    Reduction in the number of cuttings at

    the surface. Increased injection pressure.

    Loss of returns.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    72/89

    Harold Vance Department of Petroleum Engineering

    Prevention of Influxes

    Only real prevention is to drill

    overbalanced.

    But this is not possible if ourgoal is to purposefully drillunderbalanced.

    Solutions to

  • 8/12/2019 Lesson 16 Risk Management and Problems

    73/89

    Harold Vance Department of Petroleum Engineering

    Solutions toUnwanted Influxes

    Control influx rate.

    When drilling with gas or air,

    attempt to unload the liquids fromthe hole. May require a switch tomist drilling.

    Increase EMW in stages.

    Carefully weighting up the system.

    Do hole P oble d

  • 8/12/2019 Lesson 16 Risk Management and Problems

    74/89

    Harold Vance Department of Petroleum Engineering

    Wellbore Instability

    Excessive VibrationFluid Influxes

    Stuck Pipe and Fishing

    Corrosion

    Downhole Problems andTroubleshooting

  • 8/12/2019 Lesson 16 Risk Management and Problems

    75/89

    Harold Vance Department of Petroleum Engineering

    Stuck Pipe and Fishing

    Causes

    Symptoms

    Prevention

    Solutions

  • 8/12/2019 Lesson 16 Risk Management and Problems

    76/89

    Harold Vance Department of Petroleum Engineering

    Causes

    All causes of stuck pipe can

    occur during UBD exceptdifferential sticking.

    Keyseating.

    Excessive cuttings due towellbore instability.

    Mud rings.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    77/89

    Harold Vance Department of Petroleum Engineering

    Symptoms

    Cannot pick up the drillstring.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    78/89

    Harold Vance Department of Petroleum Engineering

    Prevention

    Proper design of thedrillstring.

    Adequate hole cleaning.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    79/89

    Harold Vance Department of Petroleum Engineering

    Solutions

    Fishing.

    Downhole Problems and

  • 8/12/2019 Lesson 16 Risk Management and Problems

    80/89

    Harold Vance Department of Petroleum Engineering

    Wellbore Instability

    Excessive VibrationFluid Influxes

    Stuck Pipe and FishingCorrosion

    Downhole Problems andTroubleshooting

  • 8/12/2019 Lesson 16 Risk Management and Problems

    81/89

    Harold Vance Department of Petroleum Engineering

    Corrosion

    Requirements for Corrosion.

    Causes and Factors EffectingCorrosion.Symptoms.Prevention.Solution.

    Requirements for

  • 8/12/2019 Lesson 16 Risk Management and Problems

    82/89

    Harold Vance Department of Petroleum Engineering

    Requirements forCorrosion

    Requires the presence of four

    components:an anode (component that corrodes).

    a cathode.

    an electrolyte.an external connection.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    83/89

    Harold Vance Department of Petroleum Engineering

    Simple Corrosion Cell

    Causes and Factors

  • 8/12/2019 Lesson 16 Risk Management and Problems

    84/89

    Harold Vance Department of Petroleum Engineering

    Causes and FactorsEffecting Corrosion

    Fluid utilized is the single largestsource of corrosion. The fluidbecomes the electrolyte.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    85/89

    Harold Vance Department of Petroleum Engineering

    Corrosion Rate Factors

    Oil content.

    Conductivity of electrolyte.

    pH of the fluid. Temperature and Pressure.

    Fluid velocity.

    Bacteria.

    Internal and External stressconcentrations.

    Presence of dissimilar metals.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    86/89

    Harold Vance Department of Petroleum Engineering

    Symptoms

    Generalized corrosion.Pitting.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    87/89

    Harold Vance Department of Petroleum Engineering

    Prevention

    Corrosion cannot be stopped,but it can be slowed.

  • 8/12/2019 Lesson 16 Risk Management and Problems

    88/89

    Harold Vance Department of Petroleum Engineering

    Solution

    Avoidance

    Inhibition

  • 8/12/2019 Lesson 16 Risk Management and Problems

    89/89

    END