lecture

8
ARCHN305 Building Construction III BUILDING CONSTRUCTION III ARCHN305 QUANTITIES CALCULATION QUANTITIES CALCULATION Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 1 Sunday, March 21, 2010 QUANTITIES CALCULATION QUANTITIES CALCULATION HESHAM KHAIRY Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

Upload: aditya2053

Post on 03-Nov-2014

29 views

Category:

Documents


2 download

DESCRIPTION

lecture oimatesn est

TRANSCRIPT

ARCHN305 Building Construction III

BUILDING CONSTRUCTION III

ARCHN305

QUANTITIES CALCULATIONQUANTITIES CALCULATION

Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 1

Sunday, March 21, 2010

QUANTITIES CALCULATIONQUANTITIES CALCULATION

HESHAM KHAIRY

Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

ARCHN305 Building Construction III

Example in Quantities Calculation

Guard room

� Room 4.00 × 4.00 m Cl. To Cl.

� Room 4.25 × 4.25 m Total

� Total Height = 3.00 m W1

Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 2

Sunday, March 21, 2010Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

� Total Height = 3.00 m

� Wood Door 1.00 × 2.20 m

� Alum. Window 1.20 × 1.00 m

W1

D1

ARCHN305 Building Construction III

Example in Quantities Calculation

� Slab Thickness = 12 cm

� Beams = 25 × 60 cm

Guard room

Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 3

Sunday, March 21, 2010Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

� Beams = 25 × 60 cm

�Columns 25 × 25 cm

ARCHN305 Building Construction III

Example in Quantities Calculation

Guard room

Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 4

Sunday, March 21, 2010Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

ARCHN305 Building Construction III

Calculations

Excavation

Footing Excavation = 4 × 1.25 × 1.25 × 2.00 = 12.500 m³

Smells Excavation = 4 × 2.75 × 1.30 × 0.25 = 3.575 m³

Total Excavation = 16.075 m³

Plain Concrete

Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 5

Sunday, March 21, 2010Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

Footings = 4 × 1.25 × 1.25 × 0.40 = 2.500 m³

Total P.C.= 2.500 m³

Reinforced Concrete for Foundations

Footing = 4 × 0.75 × 0.75 × 0.30 = 0.675 m³

Smells = 4 × 0.25 × 0.40 × 3.75 = 1.500 m³

Total Foundation R.C. = 2.500 m³

Columns Necks = 4 × 0.25 × 0.25 × 1.30 = 0.325 m³

ARCHN305 Building Construction III

Calculations

Fill

Fill = 16.075 – 2.5 – 2.5 = 11.075 m³

Total Fill = 11.075 m³

Reinforced Concrete for Skelton

Columns = 4 × 0.25 × 0.25 × 2.40 = 0.600 m³

Beams = 4 × 3.75 × 0.25 × (0.60 – 0.12) = 1.800 m³

Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 6

Sunday, March 21, 2010Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

Beams = 4 × 3.75 × 0.25 × (0.60 – 0.12) = 1.800 m³

Total Skelton R.C. = 4.5675 m³

Slab = 4.25 × 4.25 × 0.12 = 2.1675 m³

Floor Tiles

Floor Tiles = (4 × 4) – (4 × 0.125 × 0.125) = 15.9375 m²

Total Floor Tiles = 15.9375 m²

Brick works

Brick = (4 × 3.75 × 2.40 ) – (1.00 × 1.20) – (1.00 × 2.20) = 32.600 m²

Total Brick works= 32.600 m²

ARCHN305 Building Construction III

Calculations

Plaster

Ceiling Plaster = (4 × 4) – (4 × 0.125 × 0.125) = 15.9375 m²

Total Plaster = 58.6175 m²

Walls Plaster = 4 × 4 × (3 – 0.12) – (1.20 × 1.00) – (2.20 × 1.00) = 42.68 m²

Painting

Ceiling Painting = (4 × 4) – (4 × 0.125 × 0.125) = 15.9375 m²

Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 7

Sunday, March 21, 2010Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

Corniche (الكورنيشه)

Corniche = 4 × 4 = 16.000 m

Corniche = 16.000 m

Ceiling Painting = (4 × 4) – (4 × 0.125 × 0.125) = 15.9375 m²

Total Painting = 58.6175 m²

Walls Painting = 4 × 4 × (3 – 0.12) – (1.20 × 1.00) – (2.20 × 1.00) = 42.68 m²

Cill (الوزره)

Cill = (4 × 4) – 1.00 = 15.000 m

Corniche = 15.000 m

ARCHN305 Building Construction III

Very important notes

In External work:

� Brick works:

� in case of flat openings……………....Deduct all openings.

� in case of Curved openings…………..Deduct half openings only.

Lecture 4, 5 - CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 8

Sunday, March 21, 2010Sunday, May 16, 2010 Lecture 10 – Quantities Calculation

� Plaster works:

� in case of openings less than 4m²……………......No Deduction.

� in case of openings more than 4m²……………....Deduct half openings only.