lecture 10 monitor and control
TRANSCRIPT
-
7/29/2019 Lecture 10 Monitor and Control
1/29
Project Monitoring and Control
1
-
7/29/2019 Lecture 10 Monitor and Control
2/29
Project Monitoring and Control
Monitoring collecting, recording, andreporting information concerning projectperformance that project manger and others
2
wish to know Controlling uses data from monitor activity
to bring actual performance to planned
performance
-
7/29/2019 Lecture 10 Monitor and Control
3/29
Project Monitoring and Control
Why do we monitor? What do we monitor?
3
How do we monitor?
-
7/29/2019 Lecture 10 Monitor and Control
4/29
Why do we monitor?
Simply because we know that thingsdont always go according to plan (no
4
To detect and react appropriately todeviations and changes to plans
-
7/29/2019 Lecture 10 Monitor and Control
5/29
What do we monitor?
Men (humanresources)
Machines
Space Time
5
Materials
Money Quality/Technical
Performance
-
7/29/2019 Lecture 10 Monitor and Control
6/29
What do we monitor?
Inputs
Time
Money
Outputs
Progress
Costs
6
Material Usage
Tasks
Quality/TechnicalPerformance
Job starts
Job completion
Engineering / Designchanges
Variation order (VO)
-
7/29/2019 Lecture 10 Monitor and Control
7/29
When do we monitor?
End of the project Continuously
Regularly
7
Logically While there is still time to react
As soon as possible
At task completion At pre-planned decision points (milestones)
-
7/29/2019 Lecture 10 Monitor and Control
8/29
Where do we monitor?
At head office?At the site office?
8
Depends on situation and the whats
-
7/29/2019 Lecture 10 Monitor and Control
9/29
How do we monitor
Through meetings with clients, parties involved inproject (Contractor, supplier,etc.)
For schedule Update CPA, PERT Charts, UpdateGantt Charts
9
Using Earned Value Analysis Calculate Critical Ratios
Milestones
Reports Tests and inspections
Delivery or staggered delivery
PMIS (Project Management Info Sys) Updating
-
7/29/2019 Lecture 10 Monitor and Control
10/29
Meetings Some monitoring issues
What problems do you have and what is being doneto correct them?
What problems do you anticipate in the future?
Do ou need an resources ou do not et have?
10
Do you need information you do not have yet? Do you know anything that will give you schedule
difficulties?
Any possibility your task will finish early/late? Will your task be completed under/over/on budget?
-
7/29/2019 Lecture 10 Monitor and Control
11/29
Project Control Cycle
PLANSpecificationsProject ScheduleProject budget
ACTION
Correct
11
Vendor contracts MONITORRecord statusReport progressReport cost
COMPARE
Actual statusagainst plan
-Schedule
-Cost
ev a onsfrom plan
RE-PLAN asnecessary
-
7/29/2019 Lecture 10 Monitor and Control
12/29
Project Control
Control process and activities needed tocorrect deviations from plan
Control the triple constraints
12
time (schedule) cost (budget, expenses, etc)
performance (specifications, testing results, etc.)
-
7/29/2019 Lecture 10 Monitor and Control
13/29
Techniques for monitoring andcontrol
Earned Value Analysis Critical Ratio
13
-
7/29/2019 Lecture 10 Monitor and Control
14/29
Earned Value Analysis
A way of measuring overall performance (notindividual task) is using an aggregate performancemeasure - Earned Value
14
for those tasks in progress found by multiplying theestimated percent physical completion of work foreach task by the planned cost for those tasks. The
result is amount that should be spent on the task sofar. This can be compared with actual amount spent.
-
7/29/2019 Lecture 10 Monitor and Control
15/29
Earned Value Analysis
Methods for estimating percent completion The 50-50 estimate. 50% is assumed when task is begun, and
remaining 50% when work completed.
0-100% rule. This rule allows no credit for work until task iscomplete, highly conservative rule, project always seem late
15
until the very end of project when everything appears tosuddenly catch up
Critical input rule. This rule assigns progress according toamount of critical input that has been used. Labor or skilleddependent, machine critical input buy machine complete task
may be misinformation Proportional rule. This rule divides planned (or actual) time-to-
date by total scheduled time(or budgeted (or actual ) cost-to-date by total budgeted cast] to calculate percent complete. Thisis commonly used rule.
-
7/29/2019 Lecture 10 Monitor and Control
16/29
Earned Value Analysis
Refer to earned value chart basis for evaluatingcost and performance to date
If total value of the work accomplished is in balance
16
,
top mgmt has no particular need for a detailedanalysis of individual tasks
Earned value concept combines cost reporting &
aggregate performance reporting into onecomprehensive chart
-
7/29/2019 Lecture 10 Monitor and Control
17/29
Earned Value Analysis
Baseline cost to completion referred to asbudget at completion (BAC)
Actual cost to date referred to as estimated cost
17
Identify several variances according to twoguidelines
1. A negative variance is bad
2. Cost and schedule variances are calculated as earnedvalue minus some other measure
-
7/29/2019 Lecture 10 Monitor and Control
18/29
Earned Value Chart basis for evaluatingcost & performance to date
18
-
7/29/2019 Lecture 10 Monitor and Control
19/29
Earned Value Analysis - Variances
4 types of variances;
Cost (spending)variance (CV) differencebetween budgeted cost of work performed (earnedvalue) (BCWP) and actual cost of that work (ACWP)
19
Schedulevariance (SV) difference betweenearned value (BCWP) and cost of work we scheduledto perform to date (BCWS)
Timevariance (TV)difference between timescheduled for work performed (STWP) and actualtime to perform it (ATWP)
-
7/29/2019 Lecture 10 Monitor and Control
20/29
Earned Value Variance - Formula
CV = BCWP ACWP (negative value - cost overrun)SV = BCWP BCWS (negative value - behind schedule)
TV = STWP ATWP (negative value - delay)
20
In ex RatiosCost Performance Index (CPI) = BCWP/ACWP
Schedule Performance Index (SPI) = BCWP/BCWS
Time Performance Index (TPI) = STWP/ATWP
-
7/29/2019 Lecture 10 Monitor and Control
21/29
EXAMPLE
Assume that operations on a Work Package cost RM 1,500 tocomplete. They were originally scheduled to finish today. At thispoint, we actually spent RM1,350. And we estimate that wehave completed two thirds (2/3) of the work. What are the costand schedule variances?
21
CV = BCWP ACWP = 1500 (2/3) 1350 = - 350SV = BCWP BCWS = 1500 (2/3) 1500 = - 500
CPI = BCWP/ACWP = 1500(2/3)/1350 = 0.74
SPI = BCWP/BCWS = 1500(2/3)/1500 = 0.67
Spending higher than budget, and given what we have spent,we are not as far along as we should be (have not completedas much work as we should have)
-
7/29/2019 Lecture 10 Monitor and Control
22/29
Possible to have one of indicators to befavorable while the other unfavorable
22
costs
Six possibilities (see figure next slide)
-
7/29/2019 Lecture 10 Monitor and Control
23/29
6 Possibilities Earned Value Analysis
23
-
7/29/2019 Lecture 10 Monitor and Control
24/29
EXERCISE (Text P.544 Problem 4)
A project to develop a country park has an actual cost in month
17 of $350,000, a planned cost of $475,000, and a valuecompleted of $300,000. Find the cost and schedule variancesand the three indexes.
24
Month 17
$ Planned (Baseline) 475,000
Actual cost 350,000
Value completed 300,000 BCWP
ACWP
BCWS
Time t
-
7/29/2019 Lecture 10 Monitor and Control
25/29
SolutionBCWS = 475,000
BCWP = 300,000ACWP = 350,000
CV = 300 000 350 000 = -50 000 ne ative value - cost overrun
CV = BCWP ACWPSV = BCWP BCWS
25
SV = 300,000 475,000 = -175,000 (negative value - behind schedule)Cost Performance Index (CPI) = BCWP/ACWP = 300/350 = 0.86
Schedule Performance Index (SPI) = BCWP/BCWS = 300/475 = 0.63
Time Performance Index (TPI) = STWP/ATWP
Scheduled Time Work Performed (STWP) can be estimated
Time t = Schedule Variance/Slope of Planned costs =
-175,000/ (475,000/17) = - 6.26 months
Time Difference= 17- 6.26 = 10.74
TV = 10.74/17 = 0.63
-
7/29/2019 Lecture 10 Monitor and Control
26/29
Critical ratio
Sometimes, especially large projects, it may
be worthwhile calculating a set of criticalratios for all project activities
26
actual progress x budgeted costscheduled progress actual cost
If ratio is 1 everything is probably on target
The further away form 1 the ratio is, the more wemay need to investigate
-
7/29/2019 Lecture 10 Monitor and Control
27/29
Critical ratio exampleCalculate the critical ratios for the following activities andindicate which are probably on target and need to be
investigated.Activity Actual
progressScheduledProgress
BudgetedCost
Actualcost
Criticalratio (CR)
27
B 3 days 2 days 50 50
C 2 days 3 days 30 20
D 1 day 1 day 20 30
E 2 days 4 days 25 25
-
7/29/2019 Lecture 10 Monitor and Control
28/29
Critical ratio example
Can be on schedule and below budget (Act A)Why so good? Cutting corners?
Can be behind schedule but below budget
28
Can be on budget but physical progresslagging (Act E)
Can be on schedule but cost running higherthan budget (Act D)
On budget ahead of schedule (Act B)
-
7/29/2019 Lecture 10 Monitor and Control
29/29
Summary
Need proper project monitoring and controlmechanisms
Tools available to help in monitoring and
29
controlling activities There are human control and management
aspects not covered here