lecture 10 monitor and control

Upload: nivi-senthil

Post on 14-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Lecture 10 Monitor and Control

    1/29

    Project Monitoring and Control

    1

  • 7/29/2019 Lecture 10 Monitor and Control

    2/29

    Project Monitoring and Control

    Monitoring collecting, recording, andreporting information concerning projectperformance that project manger and others

    2

    wish to know Controlling uses data from monitor activity

    to bring actual performance to planned

    performance

  • 7/29/2019 Lecture 10 Monitor and Control

    3/29

    Project Monitoring and Control

    Why do we monitor? What do we monitor?

    3

    How do we monitor?

  • 7/29/2019 Lecture 10 Monitor and Control

    4/29

    Why do we monitor?

    Simply because we know that thingsdont always go according to plan (no

    4

    To detect and react appropriately todeviations and changes to plans

  • 7/29/2019 Lecture 10 Monitor and Control

    5/29

    What do we monitor?

    Men (humanresources)

    Machines

    Space Time

    5

    Materials

    Money Quality/Technical

    Performance

  • 7/29/2019 Lecture 10 Monitor and Control

    6/29

    What do we monitor?

    Inputs

    Time

    Money

    Outputs

    Progress

    Costs

    6

    Material Usage

    Tasks

    Quality/TechnicalPerformance

    Job starts

    Job completion

    Engineering / Designchanges

    Variation order (VO)

  • 7/29/2019 Lecture 10 Monitor and Control

    7/29

    When do we monitor?

    End of the project Continuously

    Regularly

    7

    Logically While there is still time to react

    As soon as possible

    At task completion At pre-planned decision points (milestones)

  • 7/29/2019 Lecture 10 Monitor and Control

    8/29

    Where do we monitor?

    At head office?At the site office?

    8

    Depends on situation and the whats

  • 7/29/2019 Lecture 10 Monitor and Control

    9/29

    How do we monitor

    Through meetings with clients, parties involved inproject (Contractor, supplier,etc.)

    For schedule Update CPA, PERT Charts, UpdateGantt Charts

    9

    Using Earned Value Analysis Calculate Critical Ratios

    Milestones

    Reports Tests and inspections

    Delivery or staggered delivery

    PMIS (Project Management Info Sys) Updating

  • 7/29/2019 Lecture 10 Monitor and Control

    10/29

    Meetings Some monitoring issues

    What problems do you have and what is being doneto correct them?

    What problems do you anticipate in the future?

    Do ou need an resources ou do not et have?

    10

    Do you need information you do not have yet? Do you know anything that will give you schedule

    difficulties?

    Any possibility your task will finish early/late? Will your task be completed under/over/on budget?

  • 7/29/2019 Lecture 10 Monitor and Control

    11/29

    Project Control Cycle

    PLANSpecificationsProject ScheduleProject budget

    ACTION

    Correct

    11

    Vendor contracts MONITORRecord statusReport progressReport cost

    COMPARE

    Actual statusagainst plan

    -Schedule

    -Cost

    ev a onsfrom plan

    RE-PLAN asnecessary

  • 7/29/2019 Lecture 10 Monitor and Control

    12/29

    Project Control

    Control process and activities needed tocorrect deviations from plan

    Control the triple constraints

    12

    time (schedule) cost (budget, expenses, etc)

    performance (specifications, testing results, etc.)

  • 7/29/2019 Lecture 10 Monitor and Control

    13/29

    Techniques for monitoring andcontrol

    Earned Value Analysis Critical Ratio

    13

  • 7/29/2019 Lecture 10 Monitor and Control

    14/29

    Earned Value Analysis

    A way of measuring overall performance (notindividual task) is using an aggregate performancemeasure - Earned Value

    14

    for those tasks in progress found by multiplying theestimated percent physical completion of work foreach task by the planned cost for those tasks. The

    result is amount that should be spent on the task sofar. This can be compared with actual amount spent.

  • 7/29/2019 Lecture 10 Monitor and Control

    15/29

    Earned Value Analysis

    Methods for estimating percent completion The 50-50 estimate. 50% is assumed when task is begun, and

    remaining 50% when work completed.

    0-100% rule. This rule allows no credit for work until task iscomplete, highly conservative rule, project always seem late

    15

    until the very end of project when everything appears tosuddenly catch up

    Critical input rule. This rule assigns progress according toamount of critical input that has been used. Labor or skilleddependent, machine critical input buy machine complete task

    may be misinformation Proportional rule. This rule divides planned (or actual) time-to-

    date by total scheduled time(or budgeted (or actual ) cost-to-date by total budgeted cast] to calculate percent complete. Thisis commonly used rule.

  • 7/29/2019 Lecture 10 Monitor and Control

    16/29

    Earned Value Analysis

    Refer to earned value chart basis for evaluatingcost and performance to date

    If total value of the work accomplished is in balance

    16

    ,

    top mgmt has no particular need for a detailedanalysis of individual tasks

    Earned value concept combines cost reporting &

    aggregate performance reporting into onecomprehensive chart

  • 7/29/2019 Lecture 10 Monitor and Control

    17/29

    Earned Value Analysis

    Baseline cost to completion referred to asbudget at completion (BAC)

    Actual cost to date referred to as estimated cost

    17

    Identify several variances according to twoguidelines

    1. A negative variance is bad

    2. Cost and schedule variances are calculated as earnedvalue minus some other measure

  • 7/29/2019 Lecture 10 Monitor and Control

    18/29

    Earned Value Chart basis for evaluatingcost & performance to date

    18

  • 7/29/2019 Lecture 10 Monitor and Control

    19/29

    Earned Value Analysis - Variances

    4 types of variances;

    Cost (spending)variance (CV) differencebetween budgeted cost of work performed (earnedvalue) (BCWP) and actual cost of that work (ACWP)

    19

    Schedulevariance (SV) difference betweenearned value (BCWP) and cost of work we scheduledto perform to date (BCWS)

    Timevariance (TV)difference between timescheduled for work performed (STWP) and actualtime to perform it (ATWP)

  • 7/29/2019 Lecture 10 Monitor and Control

    20/29

    Earned Value Variance - Formula

    CV = BCWP ACWP (negative value - cost overrun)SV = BCWP BCWS (negative value - behind schedule)

    TV = STWP ATWP (negative value - delay)

    20

    In ex RatiosCost Performance Index (CPI) = BCWP/ACWP

    Schedule Performance Index (SPI) = BCWP/BCWS

    Time Performance Index (TPI) = STWP/ATWP

  • 7/29/2019 Lecture 10 Monitor and Control

    21/29

    EXAMPLE

    Assume that operations on a Work Package cost RM 1,500 tocomplete. They were originally scheduled to finish today. At thispoint, we actually spent RM1,350. And we estimate that wehave completed two thirds (2/3) of the work. What are the costand schedule variances?

    21

    CV = BCWP ACWP = 1500 (2/3) 1350 = - 350SV = BCWP BCWS = 1500 (2/3) 1500 = - 500

    CPI = BCWP/ACWP = 1500(2/3)/1350 = 0.74

    SPI = BCWP/BCWS = 1500(2/3)/1500 = 0.67

    Spending higher than budget, and given what we have spent,we are not as far along as we should be (have not completedas much work as we should have)

  • 7/29/2019 Lecture 10 Monitor and Control

    22/29

    Possible to have one of indicators to befavorable while the other unfavorable

    22

    costs

    Six possibilities (see figure next slide)

  • 7/29/2019 Lecture 10 Monitor and Control

    23/29

    6 Possibilities Earned Value Analysis

    23

  • 7/29/2019 Lecture 10 Monitor and Control

    24/29

    EXERCISE (Text P.544 Problem 4)

    A project to develop a country park has an actual cost in month

    17 of $350,000, a planned cost of $475,000, and a valuecompleted of $300,000. Find the cost and schedule variancesand the three indexes.

    24

    Month 17

    $ Planned (Baseline) 475,000

    Actual cost 350,000

    Value completed 300,000 BCWP

    ACWP

    BCWS

    Time t

  • 7/29/2019 Lecture 10 Monitor and Control

    25/29

    SolutionBCWS = 475,000

    BCWP = 300,000ACWP = 350,000

    CV = 300 000 350 000 = -50 000 ne ative value - cost overrun

    CV = BCWP ACWPSV = BCWP BCWS

    25

    SV = 300,000 475,000 = -175,000 (negative value - behind schedule)Cost Performance Index (CPI) = BCWP/ACWP = 300/350 = 0.86

    Schedule Performance Index (SPI) = BCWP/BCWS = 300/475 = 0.63

    Time Performance Index (TPI) = STWP/ATWP

    Scheduled Time Work Performed (STWP) can be estimated

    Time t = Schedule Variance/Slope of Planned costs =

    -175,000/ (475,000/17) = - 6.26 months

    Time Difference= 17- 6.26 = 10.74

    TV = 10.74/17 = 0.63

  • 7/29/2019 Lecture 10 Monitor and Control

    26/29

    Critical ratio

    Sometimes, especially large projects, it may

    be worthwhile calculating a set of criticalratios for all project activities

    26

    actual progress x budgeted costscheduled progress actual cost

    If ratio is 1 everything is probably on target

    The further away form 1 the ratio is, the more wemay need to investigate

  • 7/29/2019 Lecture 10 Monitor and Control

    27/29

    Critical ratio exampleCalculate the critical ratios for the following activities andindicate which are probably on target and need to be

    investigated.Activity Actual

    progressScheduledProgress

    BudgetedCost

    Actualcost

    Criticalratio (CR)

    27

    B 3 days 2 days 50 50

    C 2 days 3 days 30 20

    D 1 day 1 day 20 30

    E 2 days 4 days 25 25

  • 7/29/2019 Lecture 10 Monitor and Control

    28/29

    Critical ratio example

    Can be on schedule and below budget (Act A)Why so good? Cutting corners?

    Can be behind schedule but below budget

    28

    Can be on budget but physical progresslagging (Act E)

    Can be on schedule but cost running higherthan budget (Act D)

    On budget ahead of schedule (Act B)

  • 7/29/2019 Lecture 10 Monitor and Control

    29/29

    Summary

    Need proper project monitoring and controlmechanisms

    Tools available to help in monitoring and

    29

    controlling activities There are human control and management

    aspects not covered here