learning earned value management using lego bricks

51
Predicting progress on your project - using Lego bricks to understand Earned Value Presented by Youssef Mourra Director, Principal Consultant 021 423 620 [email protected] @youssefmourra September 4 PM Conference 2015 Te Papa Museum, Wellington www.nonsuch.co [email protected]

Upload: youssef-mourra

Post on 14-Feb-2017

450 views

Category:

Leadership & Management


3 download

TRANSCRIPT

Predicting progress on your project

- using Lego bricks to understand Earned Value

Presented byYoussef MourraDirector, Principal Consultant

021 423 620 [email protected] @youssefmourra

September 4 PM Conference 2015

Te Papa Museum, Wellington

[email protected]

© Nonsuch Consulting 20152

A bit about me…

• 25 years’ experience in project, programme and portfolio management in various countries.

• For the past 12 years, based in Wellington and servicing customers and clients in NZ and Australia and nearby.

• I have three children under 13 and when I have time, I enjoy music, reading, fruit trees, cricket, theatre, travel, wine, politics and etymology (the history and study of words).

• I’m a regular presenter at the annual Project Management Conference in NZ and occasionally in Australia:

• Eddie Obeng – Project Types• The Zombies of Project Management• The Zombies of Programme and Portfolio Management• So You think you’re ready to be a Consultant?

© Nonsuch Consulting 20153

Today’s session

• On a Friday afternoon…• You’ve been out partying last night…• You’ve just had lunch…• Your eyelids are heavy…• You will fall asleep…• This is going to be great session, don’t you think?

© Nonsuch Consulting 20154

Predicting progress on your projectWhat are our options?

© Nonsuch Consulting 20155

Horoscope?

Imagine a Scorpio Project Manager!Or a Libran sponsor!

© Nonsuch Consulting 20156

Crystal Ball?

© Nonsuch Consulting 20157

Tarot Cards?

© Nonsuch Consulting 20158

Superstition?

© Nonsuch Consulting 20159

Mood?

© Nonsuch Consulting 201510

What is Earned Value Management?

• Earned Value Management (EVM) is a management methodology for integrating scope, schedule and resources for objectively measuring project performance and progress and for forecasting project outcome

• It is an industry standard way to:• measure a project’s progress,• forecast its completion date and final cost, and• provide schedule and budget variances along the way.

© Nonsuch Consulting 201511

Earned Value Management

• In English, please!• Okay, think about going to a friend’s bbq in a different city to your own…

• Scope – driving to a different city to catch up with friends and have a bbq• Schedule – the time you are due at your friend’s place along with an estimated duration of the

journey• Resources – your time, effort and costs involved in the journey

• However, at some point in the journey, you might find yourself or your partner asking these questions

• Are we on schedule?• Are we running a bit late? What will we do?• Are we running a bit too fast? What will we do?• Will we get there on time?• Will we be late? How late?

• With Earned Value Management, we can answer these questions confidently and more

© Nonsuch Consulting 201512

Point in time…

• So, Earned Value Management is about a ‘point in time’ calculation. In other words, it’s about what the future looks like based on performance to this point in time. It’s not a fixed prediction but rather a prediction at this point of time that still allows, hopefully, for time to intervene and in some cases wilfully and positively change the final prediction.

• Today, I will be taking you through the Change Management lifecycle to ensure that I help effect some change in your approach and understanding of Earned Value Management. The first step is Awareness and so I hope I’ve just made you aware of Earned Value and what it purports to do.

© Nonsuch Consulting 201513

Change Management : ADKAR

Current State Transition State Future State

Awarenessof the needfor change

Desireto participate and support the change (WIIFM)

Knowledgeon how to change

Abilityto implement required skills and behaviours

Reinforcementto sustain the change

Change Management

A D K A R

‘Unfreeze’ ‘Move’ ‘Refreeze’

© Nonsuch Consulting 201514

Earned Value

• What’s the problem we’re trying to fix here?• What’s in it for you and your organisation?

© Nonsuch Consulting 201515

What’s the problem?

• 70% of projects are:• Over budget• Behind schedule

• 52% of all projects finish at 189% of their initial budget

• And some, after huge investments of time and money, are simply never completed!

• Source: The Standish Group

© Nonsuch Consulting 201516

Have we done what we said we’d do?

• % complete estimating • % of Budget spent• % of work done• % of time elapsed

• subjective, incomplete • draws false conclusions

© Nonsuch Consulting 201517

What’s More Important

• Knowing where you are on schedule?

• Knowing where you are on budget?

• Knowing where you are on work accomplished?

• It’s difficult to judge one of the three over the other, so in fact all three are equally important.

© Nonsuch Consulting 201518

EVM Integrates All Three elements

• It compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST , SCHEDULE, and WORK ACCOMPLISHED are progressing as planned.

• Work is “Earned” or credited as it is completed.

• By integrating three measurements, it provides consistent, numerical indicators with which you can evaluate and compare projects.

© Nonsuch Consulting 201519

The challenging questions that EVM answers• Are we delivering more or less work than planned?• When is the project likely to be completed?• Are we currently over or under budget?• What is the remaining work likely to cost?• What is the entire project likely to cost?• How much will we be over or under budget at the end of the project?• What is driving the significant cost and/or schedule variances?

© Nonsuch Consulting 201520

Earned Value is Needed because….

• …it provides an Early Warning Indicator (EWI) for prompt corrective action when there is still time to intervene – timely change requests if required

• There is often a need to “roll up” progress of many tasks into an overall project status

• There is a need for a uniform unit of measure (dollars or work-hours).

© Nonsuch Consulting 201521

Change Management : ADKAR

Current State Transition State Future State

Awarenessof the needfor change

Desireto participate and support the change (WIIFM)

Knowledgeon how to change

Abilityto implement required skills and behaviours

Reinforcementto sustain the change

Change Management

A D K A R

‘Unfreeze’ ‘Move’ ‘Refreeze’

© Nonsuch Consulting 201522

What do I need to get started?

• You will need a Work Breakdown Structure (WBS)/ Product Breakdown Structure (PBS)

• It needs to be deliverable or product oriented• If it’s not in the WBS/PBS, then it is out-of-scope• Each descending level represents more detail

• Full (and accurate) definition is key• Defined deliverables/products• Timeframe for delivery of deliverables/products• Total cost (direct and indirect) to deliver deliverables/products

• Let’s look at an example…

© Nonsuch Consulting 201523

A sample schedule (with a WBS/PBS embedded)

© Nonsuch Consulting 201524

Requirements of Earned Value

• Proper PBS/WBS Design• Baseline Budget Baseline Schedule• Work measurement by work-hours, dollars, units, etc.• Good Project Scheduling Practices involving the following:

• A baselined schedule with costs (as mentioned above)• The recording of actual progress on effort and costs• The recording of estimates to completion for effort and costs

© Nonsuch Consulting 201525

Earned Value Terminology

• Let’s learn the terminology. We’ll start with the first two:• PV – Planned Value

(Formerly known as BCWS - Budgeted Cost of Work Scheduled)• Planned Value is the authorised, time-phased budget assigned to accomplish

the scheduled work. At any given point on a time line, PV describes how much of the project work was planned to be performed

• BAC – Budget at Completion• The sum of all budgets established for the work to be performed. The project

BAC is the sum of all the work package BACs• Please note. At the start of a project, before any progress has been made and after budgets

have been set and baselined, the PV and BAC are normally identical

© Nonsuch Consulting 201526

What does it look like?

Please note that the PV and BAC are identical at the start of the project before any work commences or any costs are incurred

© Nonsuch Consulting 201527

It’s getting too theoretical….

It’s Lego time!!

© Nonsuch Consulting 201528

Grab your worksheet

You have 100 bricks.You have 4 minutes

You will earn $10 per minute per person and $1 per brick

laid

You will build a wall

© Nonsuch Consulting 201529

[what happened with the audience]

• I asked them to build a wall like the one displayed here except it was to be 10 bricks wide and 10 bricks high. I promised them 4 minutes and emphasised it wasn’t a race and then I abruptly asked them to stop immediately after 2 minutes had passed and to record how many bricks they had laid in their incomplete wall. This number of bricks is significant.

© Nonsuch Consulting 201530

Work these out

• PV – Planned Value• (Formerly known as BCWS - Budgeted Cost of Work Scheduled)• Planned Value is the authorised, time-phased budget assigned to accomplish the

scheduled work. At any given point on a time line, PV describes how much of the project work was planned to be performed

• BAC – Budget at Completion• The sum of all budgets established for the work to be performed. The project BAC is

the sum of all the work package BACs

• Assuming there are 2 builders working on this and based on the assumptions outlined in Slide 28, the answers and workings are:

• PV = 100 bricks @ $1 [$100] plus 2 people @ $10/minute for 4 minutes [$80] = $180• BAC = same as above = $180

© Nonsuch Consulting 201531

The Answer sheet

Calculation 2 person teams 3 person teams

Planned Value – PV $180 $220Planned Value – PV2 $90 $110Budget At Completion $180 $220Cost per brick laid $1.80 $2.20

Note the use of PV with a little ‘2’. This denotes the Planned Value at 2 minutes into the 4 minute estimated duration of the task. This is significant as we use the PV2 value from here on as we are interested in measuring Earned Value at this point of time, namely 2 minutes into our 4 minute task. Please also note the cost per brick laid. This is significant later on.

© Nonsuch Consulting 201532

Earned Value Terminology

• Okay, another two:• AC – Actual Cost

• (Formerly known as ACWP - Actual Cost of Work Performed)• The realised cost incurred for the work performed on an activity during a specific time

period. This can be reported for cumulative to date or for a specific reporting period.

• EV – Earned Value• (Formerly known as BCWP – Budgeted Cost of Work Performed)• The measure of the work performed, expressed in terms of the budget authorised for that

work. Earned Value can be reported for cumulative to date or for a specific reporting period.

• Assuming there are 2 builders working on this and based on the assumptions outlined in Slide 28, and that only 60 bricks have been laid, the answers and workings are on the next slide

© Nonsuch Consulting 201533

The Answer sheetCategory 2 person

teams3 person teams

Planned Value – PV $180 $220Planned Value – PV2 $90 $110Budget At Completion - BAC $180 $220No. of bricks built = B B B 60

Actual Cost – AC (B *$1 ) + Cost of Effort to Date $100

Earned Value – EV B * Cost of Bricks Laid $108

© Nonsuch Consulting 201534

What does it look like?

Please note that the EV and the AC are often different values unless we are strictly on target wit progress.

© Nonsuch Consulting 201535

Some Derived Metrics

SV: Schedule Variance (BCWP-BCWS) or (EV – PV2) A comparison of amount of work performed during a given period of

time/earned value to what was scheduled to be performed/planned value. A negative variance means the project is behind schedule

CV: Cost Variance (BCWP-ACWP) or (EV – AC) A comparison of the budgeted cost of work performed /earned value with

actual cost. A negative variance means the project is over budget.

© Nonsuch Consulting 201536

The Answer sheetCategory 2 person teams 3 person 2 person

Planned Value – PV $180 $220 $180

Planned Value – PV2 $90 $110 $90

Budget At Completion - BAC $180 $220 $180

No. of bricks built = B B B 60

Actual Cost – AC (B *$1 ) + Cost of Effort to Date $100

Earned Value – EV B * Cost of Bricks Laid $108

Schedule Variation – SV EV - PV2$108 - $90 =$18

Cost Variation - CV EV - AC $108 - $100 = $8

© Nonsuch Consulting 201537

Some More Derived Metrics

SPI: Schedule Performance Index SPI=BCWP/BCWS or SPI = EV/PV2 SPI <1 means project is behind schedule

CPI: Cost Performance Index CPI= BCWP/ACWP or CPI = EV/AC CPI <1 means project is over budget

CSI: Cost Schedule Index (CSI=CPI x SPI) The further CSI is from 1.0, the less likely project recovery becomes.

© Nonsuch Consulting 201538

The Answer sheetCategory 2 person teams 3 person 2 person

Planned Value – PV2 $90 $110 $90

Actual Cost – AC (B *$1 ) + Cost of Effort to Date $100

Earned Value – EV B * Cost of Bricks Laid $108

Schedule Variation – SV EV - PV $108 - $90 =$18

Cost Variation - CV EV - AC $108 - $100 = $8

Schedule Performance Index – SPI EV/PV2$108/$90 = 1.2

Cost Performance Index – CPI EV/AC $108/ $100 = 1.08

Cost Schedule Index - CSI CPI x CSI 1.2 * 1.08 = 1.296

© Nonsuch Consulting 201539

Making Projections

• Once a project is 10% complete, the overrun at completion will not be less than the current overrun.

• Once a project is 20% complete, the CPI does not vary from its current value by more than 10%.

• The CPI and SPI are statistically accurate indicators of final cost results.

Source: Defense Acquisition University

© Nonsuch Consulting 201540

Today’s Challenges

• Today’s executives must achieve critical outcomes, respond rapidly to business changes, and make strategic project decisions earlier than ever in the project life cycle—all with increased visibility into the decision-making process.

• Need for accurate and consistent status information• Numerous complex (and interrelated) projects with many activities

with many dependencies• Project managers are asked to reduce project costs while improving

forecasting and to compress schedules while increasing schedule accuracy.

© Nonsuch Consulting 201541

CPI / SPI charting

© Nonsuch Consulting 201542

Any shortcomings with Earned Value?

• Yes, sometimes quantifying/measuring work progress can be difficult. Think about the challenges that Agile project management might throw up. How might you tackle that? Is there value in Earned Value Management for projects using the Agile approach?

• The time required for data measurement, input, and manipulation can be considerable.

• You will need to be cognizant of effort curves and ensure you have that built into your baseline

• Front loaded, back loaded, turtle, double peak, etc.• It mustn’t be the SOLE arbitrator in making decisions about projets within

a portfolio. This is just one perspective in decision making – don’t forget benefits, strategic alignment, risk etc.

© Nonsuch Consulting 201543

Change Management : ADKAR

Current State Transition State Future State

Awarenessof the needfor change

Desireto participate and support the change (WIIFM)

Knowledgeon how to change

Abilityto implement required skills and behaviours

Reinforcementto sustain the change

Change Management

A D K A R

‘Unfreeze’ ‘Move’ ‘Refreeze’

© Nonsuch Consulting 201544

So, Is This Stuff New ?

• It’s been around since the sixties.

• It was also known as “Cost/Schedule Control Systems Criteria” (C/SCSC)

© Nonsuch Consulting 201545

Do I have to create this from scratch each time?• So where do I get one?

• Buy a prepackaged application. (Lots of them around)

• Make your own in Microsoft Excel

• Use Microsoft Project, or Microsoft Project Server

• Most PMIS (Project Management Information System) applications systems will Earned Value built into their views, reports and tables

© Nonsuch Consulting 201546

Earned Value – Reports & Views

© Nonsuch Consulting 201547

Earned Value - Tables

© Nonsuch Consulting 201548

In summary

• Need to get beyond misleading measures of progress.• Earned Value Management will help reduce guesswork in:

• measuring performance• forecasting

© Nonsuch Consulting 201549

One Final Caveat – a positive one

Past Performance is Not Necessarily Indicative of Future Results

How? If we are using Earned Value, we have time to intervene and help Shape the Future of our project’s results

© Nonsuch Consulting 201550

Change Management : ADKAR

Current State Transition State Future State

Awarenessof the needfor change

Desireto participate and support the change (WIIFM)

Knowledgeon how to change

Abilityto implement required skills and behaviours

Reinforcementto sustain the change

Change Management

A D K A R

‘Unfreeze’ ‘Move’ ‘Refreeze’

© Nonsuch Consulting 201551

Best of luck!

• Thanks for your attendance• For more information or if you have any questions, please

contact me on• Phone: 021 423 620• Website: www.nonsuch.co• Email: [email protected]• Twitter: @youssefmourra