lean deployment strategy for major construction projectsleanconstruction.org.uk/media/docs/richard...
TRANSCRIPT
Lean Deployment Strategy for Major Construction Projects - A Leadership View
Richard O’Connor
Lean Tools and Techniques
Applying the appropriate tool to the right situation.
Be prepared to adapt the approach.
Don’t become a ‘tool head’!
Apply within the context of an overall
Lean strategy
How to deploy lean to improve the set-up, organisation, delivery, performance and management of a construction project?
Lean StrategyLean Pre-
ConstructionLean
MobilisationLean Project
DeliveryLean Post
Construction
End-to-End Project Cycle
The Lean Project Pathway
Processes Culture Relationships Communication People
Lean StrategyLean Pre-
ConstructionLean
MobilisationLean Project
DeliveryLean Post
Construction
The Lean Project PathwayA Route for Success
• Ideally apply and set the framework for project delivery• Set-up, organisation, design, commercial, planning, operation,
performance & management
• Can be applied to an existing project• Stabilise
• Improve
• So what’s possible, what should / could you be doing?
The Lean Project Pathway
Lean Project StrategyActivity
Lean vision & objectives
Integrated high performing team
Collaboration – Design, costing, planning
Stable supply
Agree measurement processes
1% productivity improvement month on month
50% reduction in the cost of quality
CLC Landside facil ityLogistics scheduling Control
Point
Design production of approved drawings
Motts - P2 level
MaterialsMarshalling Area
(Airside - adjacent
to work area)
Erect Steelwork + Handrail Assembly
1 erection gang4 members
to erect as designed
steelwork
1 fol low-up gang3-4 members
on-s ite works to deal with late design
Qual ity Check
Process rates = quality = No. People = Gangs =
shi fts =
Assembly of Handrail
onto Steel Work done on-s ite
Daily (per shift) confirmation of timed materials supply
Control Point 18
-
600 moves/ day max
current load = xx %Lead-time =
Balfour Beatty system
Del ivery Management System &
Qual ity Management System
WatsonDevelop design + correction
foot plate drawing for approval
Watson- 3D modelling
- I.D. all components, Compt List + Fab. Drwgs- Set of instructions for CNC manufacture
- Bill of Materials + Auto orders to Steel Supplier(s)Securi ty and document
check
I
Excess Stock
25t Trailer
Steel SuppliersCorusTata
European - Recycled Steel
IMax =
Monthly prodn. run
Drivers drop-off loaded trailers
Shunt vehicles moce
between CLC and site, picking up loaded
trailers as required.Empty trailers dropped
off by shunt vehicle.Returning lorries take away empty trailer.
Lead time between 2 hours to over 2 days
No. of iterations?Lead time for Approval?
Auto order for Steel by month
RUUKI (Finland) PROROOF (Estonia)
Panel Assemblyoutput rate
= 250-300 sq m / wkII
3 Tra i ler Loads
PRATER
Mon & Weds Despatch2 Gridlines = 6 Tra i ler Loads
FERRY
- Detailed design drawings- Auto order for Roofing by month
2D-3D modelling- Positioning- Clash detection- Service penetrations
- Veri fied design drawings- Bi l l of materials & MRP
- Time & quantity order schedule
CORUS (Merseyside)
Itbc
Harwich or Tilbury Dock
25t Trailer1 shift load = 6 Trailers
Installation of roof panels- Production Rate = 1 gridline per shift- Just-In-Time delivery of 1 shift load called-off from CLC by BB logistics
when needed - avoids on-site congestion- Roof panels pre-assembled in factory and shipped direct to site via CLC- Additional pre-installation of roof lights - ensures quality and minimises
working at height- Each gridline becomes weathertight
DESIGN
- Panel sizes- Shop drawings
60m Mobile Tower CraneLoad panels directly from trailer to roof as needed
MaterialsMarshalling Area
(Airside)
Adjacent to work area
(Stops double-handling)
Install Roof Panels and Roof l ights
18 panels / shift1 panel = 21.6 sq m
1 gang6 people
Waste packaging materials segregated and full skips removed by site logistics
Production and Material Logistics Planning and Control - for all products / trades(Balfour Beatty, Byrne Brothers, Watsons, Prater Lindner)
Tuesday: 6 weekly co-ordination meeting with Client to review forward programmeWednesday : 2-Weekly look-ahead - Agree weekly production plan and material delivery schedulesThursday: Northern Logistics meeting + Integration meeting for night working and weekend working
Confirming work plans, key interfaces with client, handover areas and timing, weekly look-ahead logistics drawings
STRUCTURAL STEEL
ROOFING
Qual ity Check
Qual ity Check
Installation of Steelwork- Production Rate = 1 load per shift- Just-In-Time delivery of 1 shift load called-off from CLC by
BB logistics when needed - avoids on-site congestion- Pre-assemble handrails prior to erection - ensures quality
and minimises working at height
Log NCRs & RFIs for any design
changes
Feedback to Design Team according to Balfour Beatty Design Change Control procedure
Delivery as per timed schedule of finish painted steelwork
Watson Steel (Bolton or Thirsk)
I-Beam Section Pre-
FabricationII
2 days
Average
ShotblastIStore in Yard
Avg Qty = ??days
Paint&
Cure
Formal Quality Control Handoverinvolving Package Manager, Structural Engineer, Out-going
Trade, In-coming Trade
Formal Quality Control Handoverinvolving Package Manager, Structural Engineer, Out-going
Trade, In-coming Trade
Daily (per shift) confirmation of timed materials supply
25t Tra i ler1 shi ft load (6 + 2) Elements
Install Cladding
6-8 Elements / shift1 Element =
8.5x3m (2.3t) max.6x2m (1.2t) min.
1 gang6 people
+
Crane Operator
Waste packaging materials segregated and full skips removed by site logistics
Formal Quality Control Handoverinvolving Package Manager, Structural Engineer, Out-going
Trade, In-coming Trade
Qual ity Check
Single load pulled to site when required -typically afternoon delivery for night shift
Single load pulled to site when required -typically afternoon delivery for night shift
KALZIP ROOF(on top of ProRoof panel)
Delivery stil lages flat-packed abd returned as 1 load
(20 per load)
2 stil lages per trailer8 Elements per shift
Each Element pulled as required
60m Mobile Tower CraneOff-load from trailer
Sort into required installation sequence
Erect in position via crane
I
HEUCKProfile
Extrude & Paint(Lead time 8 weeks max)
I 1 Vehicle + Tra iler Load1 load per shift requirements + 2
8 Elements per journey(lead time = 1 day)
Dover Dock
FERRY
1 Vehicle LoadCal led-off per week9m painted lengths
TEILE (Germany)
1 Vehicle LoadAssembled double-glazed & coated
Supplier(s) (Germany)Gasket & Fixings
LIDNER FACADES - UK
Monthly Forward PlanWeekly Focus Meeting
Cal l -off process
Cal l -off Despatch plan
Lead time = Same day delivery (within 24 hours)
tbc
AIRBUILD - Material Control System
- Verified design drawings- Bill of materials & MRP- Time & quantity order schedule Installation of Cladding Elements
- Production Rate = 1 gridline per shift- Just-In-Time delivery of 1 shift load called-off from CLC by BB logistics
when needed - avoids on-site congestion- Cladding pre-assembled in factory and shipped direct to site via CLC- Additional on-site pre-assembly of Stick System- Each gridline becomes weathertight allowing follow-on internal fit-out
CLADDING
UK Suppliers- Glass
- Gaskets- Flashing
- Trims
Average 2 deliveries per
week
I
Various items2-3 days
maximum
Des ign Drawings+
Del ivery Schedule
I
Potential to hold up to 1.5 days of stock
(tbc) i f an issue occurs on-site
LINDER FACADES (Germany)
ICut Elements
Assemble and Inspect
Elements
Pack Elements
Dedicated production line
I
Max 50 stillagesMin 8 stillages
1 week'sMaterial
AIRBUILD:- Controls material movement from Suppliers into CLC and Marshalling areas- Airbuild allocates delivery time slots for access into CLC - slots being aligned to up-to-date construction requirements as
communicated from site- If vehicles do not have an Airbuild booking, then no access onto site- Ensures effective and efficient 'single-load' flow of material to site and provides the 'pull' signal for material movement
AllocateTransaction No. +
location of delivery Airbuild System
Daily confirmation of material
requirements to site logistics team
Transport company receives
informationMaterials delivered
Confirm delivery of materialsCLC Material, Delivery, Faciltiy controls
Excess design iterations + NCRs due to design
integration issues
Is sues associated with the
coordination of transport -resulting in excess deliveries
Excessive inventory due to poor integration of planning systems - on average over 2 weeks stock in the system
Use of shunt vehicles introduces double handling
and scheduling / coordination was complex
I
Excess Stock
Working at height and productivity i ssues due to assembling safety
handrails in situ as height. Slows fol low-on trades.
Additional handling and associated equipment -
impacts productivity.
Part finished components requiring excess on-site
remedial finishing works..
Issues with quality and installation methods causing
additional works on site.
Des ign issues resulting from poor integration of design team plus l imited use of design modelling.
Small component design and production - resulted in
excess inventory and transportation.
Is sues associated with the coordination of transport -
resulting in excess deliveries
Excess inventory due to poor integration of planning
systems - on average over 2 weeks stock in the system
Excess inventory
I
Small panels and components requires excess working at
height, excess material handling and associated plant.
Impacts productivi ty.
Qual ity check after installation - i f any NRFT quality i ssues,
then results in excessive rework effort, time and cost.
Integrate Tool /
Service
Business
JustificationBrief & Scope
Establish KPIs +
Associated
management
system
Feasibility Study
Review of
feasibility Study +
site visit to
discuss how to
overcome any
issues
Cost Study Business CaseBoard Approval /
Sign-off
Value
Management +
Whole Life Cost
Analysis + Risk
Management
workshop
Cost Challenge
Workshop 1
Update Cost Plan
+ Savings
Register
Outline Design +
Program
Review workshop
(SITE BASED??)
Room Data
Sheets
Sign-off Plan &
CostDetailed Design
Create Drawing
Schedule
Value
Engineering +
Risk Mgt
Cost Challenge
Workshop 2
Detailed Cost
Plan
Agree Target
Cost
Develop Sample
(panels, room,
etc)
Presentation,
review & sign-off
of Samples
Capital Board
Sign-off
Define decant
process / programPlace Order
Collaborative
Planning
Workshop
Pre-construction
Plan +
Documents
Start on site
Milestone Timing By 31st March 08 By 31st March 08
Board + FIC
Approval by 16th
(mid) May 08
by 30th May 08 by 27th June 08
Start Mid May
Finish by 18th
July 08
By 18th July 08 By 1st August 08
By 1st Sept 08 -
(predicted
construction time
of 24 wks)
Capital
Developments
Mgr
Estates StrategyDefine project
outputs
Agree KPIs +
process +
ownership to
drive / use on the
project
Appoint Architect
& review Brief +
other potential
works with
Architect
Define what is
required on the
scheme
Minimum build
standards (HBN)
Lessons learnt
from previous
projects
OverseeReview with
Program DirectorRaise Requisition Lead
ABCC-ordinate &
AuthorConsulted
Minimum build
standards (HBN)
+ 100 scale
drawings + initial
program
Lessons learnt
from previous
projects
Lead
Project Manager
Agree KPIs +
process +
ownership to
drive / use on the
project
Design option,
program, cost +
narrative
Coordinate Lead Lead Coordinate Coordinate Coordinate Coordinate Coordinate
Constructor
Prices per sq m +
real costs on
items such as
ironmongery, etc
Ease of build +
phasing + input to
program
Lessons learnt
from previous
projects
Including sub-
contractors as
necessary
Get prices from
Sub-ContractorsLead
Place sub-
contract + long
lead item orders
Architects
Design option,
program, cost +
narrative
Basics for the
scheme + info
from specialists
Lessons learnt
from previous
projects
End User
Clinical
Justification +
Clinical Risks +
Decant
Define project
outputs
Define what is
required on the
scheme
Staff experience
and needs + any
key date
milestones /
considerations
1. Jackie; 2.
Eddie
Review and Sign-
off Detailed
Design
Input points to be
considered +
specific needs
QS
Design option,
program, cost +
narrative
Formulate Initial
Cost Plan
Outline
construction
costing + fees
Lead
Trust Finance
Review costs +
implications to the
service
Review costs +
implications to the
service
Performance
Manager
Lead / co-
ordinate
implementation
Lessons learnt
from previous
projects
COOReview Business
Case and Sign-off
Review and Sign-
off Detailed
Design
BoardReview Business
Case and Sign-off
Review and Sign-
off Detailed
Design
MobilisationOutline DesignFeasibility Detailed Design
Integrate Tool /
Service
Business
JustificationBrief & Scope
Establish KPIs +
Associated
management
system
Feasibility Study
Review of
feasibility Study +
site visit to
discuss how to
overcome any
issues
Cost Study Business CaseBoard Approval /
Sign-off
Milestone Timing By 31st March 08 By 31st March 08
Board + FIC
Approval by 16th
(mid) May 08
Capital
Developments
Mgr
Estates StrategyDefine project
outputs
Agree KPIs +
process +
ownership to
drive / use on the
project
Appoint Architect
& review Brief +
other potential
works with
Architect
Define what is
required on the
scheme
ABCC-ordinate &
AuthorConsulted
Feasibility
Activity
Good consistent processes
Gateway planning
Right first time design – BIM, FMEA, DFMA, design delivery
Collaborative programming including critical path / constraints analysis & pace + Plan-to-protect
Establish measurement processes
The Lean Project Pathway
Lean Pre-construction
The Lean Project Pathway
Lean Mobilisation
Activity
Plan, review & challenge all activities to ensure readiness and right first time construction
Detailed day-by-day look-a-head programme including challenge, pace, line balance
Mock-up training + draft standard operations
Pre-works readiness
Set project standards (e.g. 5S & visual management)
Issue Ref. No: Care Point Key
Issue Date: Safety
Quality
Page 3 of Knack
Main Task Step Main Task Step
Continue to work from the back of the plot to the front so as to
ease access
May have to use sledge hammer to help seat panel and to help
butt up against adjoining panel
For the reason of easy access, it is often beneficial to start
erecting inner wall panels before erecting final outer wall panel
(No. 17)
DPC used to provide water barrier bewteen outer walls at seams
and adjoining internal wall
Start at top edge and nail DPC to wall face to hold in position, then
unravel DPC roll downwards, measure & cut DPC to length, and
nail to wall face
Refer to drawing to ensure selection of correct Top Plate
Position each Top Plate so that outer edge is flush with outer face
of wall panel
Levelling Up all W allsLevelling all walls to ensure erection is within allowable vertical
tolerance
- Lay length of 90mm timber diagonally against
upright wall to be levelled
- Fix timber pad to floor Use Hilty gun to drive fixing through timber pad into floor pad
- Nail bottom end of timber diagonal into
timber pad
- Using spirit level check vertical edge of wall
panel for level of upright
Pushing against top of panel using a foot will often create the
required level of adjustment. Check drawing for allowable
tolerance level.
- If required, adjust panel by pushing top of wall
panel in the required direction
If greater force is required to achieve necessary adjustment then
drive a wedge between the outer face of the wall panel and the
scaffold (if erected)
- Use eye to check line of top face along panels
Alternatively, lever the whole frame in the required direction by
using a lever in the central void between the two properties
W hen specificied level of vertical is achieved,
nail top of timber stay to inner upright on wall
panel
Hammer 2 nails, not driving nails completely home, so later
removal of timber stay is easy
Recheck vertical position using spirit level
9
SketchOperator 2
Care Point
6
Repeat erection of remaining outer walls
following the basic steps defined in points
3, 4 5 & 6, and by following basic
sequence of panel erection as defined on
sequence drawing
No.Operator 1
Fit DPC to vertical faces down seam edges
as indicated on the drawing. Repeat for all
specified positions.
7
Fix Top Plates to top edges of erected walls
(Repeat for all walls as indicated by
drawing)
2-PERSON JOB DETAIL SHEET
W ork / Job Description:
Timber Frame
Outer Wall Erection - Ground Floor
8
Suggested location
of timber pads used
when levelling-up
vertical walls
Position Timber pad so
that timber diagonal
lines up with an inner
upright of wall panel
Adjust panel level of
vertical by pushing top
edge of panel. W hen
vertical, nail timber
diagonal to inner
upright of wall panel
The Lean Project Pathway
Lean ConstructionActivity
Collaborative project management (weekly & daily)
5S workplace organisation
Production loss analysis
Problem solving
Best methods & productivity improvement
Visual management
Synchronised JIT material logistics
Preventative maintenance
0.0%
20.0%
40.0%
60.0%
80.0%
100.0%
0
10
20
30
40
50
60
70
Design Change IncorrectMaterials
Waiting forInformation
LabourAvailability
CraneBreakdown
Material PoorQuality
Late Deliveries
Lost Production Time
THE PROBLEM:
Date Raised: Where: How: Who:
Where:
Originator: Work Stream:
When:
Owner Target Date Owner Target Date Owner Target Date
PDCA applied Design revision required? SOP updated / created?
Team brief? Benefits realised? Issue resolution documented?
Improvement Sign-off Other areas where the Improvement can be applied
Other Decent Homes programmes
Excessive level of quality defects at handover
Over 148 properties, 50% of properties had
defects at handover13% of quality defects attributed
to Defective Radiators
Yes No Yes
Yes Yes - Issue resolvedYes and logged as part of learning
portal
F Smith 9th April '07 H Jaycock 16th April '07
Client team relied on Surveyor
experience and did not see the
need to define method
Not considered an important focus
and stuck with what was common
current practices
Work with Surveyors, Decent Homes
work stream supervisors and plumbers
to define an agreed method. Develop
standard operating procedure. Train
all relevant people.
Carry-out a 5S Workplace
Organisation activity to improve the
set-up, organisation, operation and
management of the central stores.
Rationalise stored stock. Develop
standard operating procedure to
support. Train all people in new
methods.
Define and standardise method (link to
root cause countermeasure as for
'Wrong Radiator Supplied'), train all
relevant people. Contractor and trade
supervision to ensure standard
approach to radiator position is
adhered to.
Poor materials planning and
management processesNot considered to be an issue
Main focus and effort directed towards works
delivery with limited visibility or understanding
of stores set-up and operation
Management never 'sighted' as the
issue due to no / limited data
A3 PROBLEM RESOLUTION SHEET
20th March '07
F Smith
Decent Homes Project XYZ
All
Toolbox talk to all trades plus
closer supervision and review
at property sign-off
Supervisors
All work streams
Immediate
Incorrect specification Poor storage practices & handlingVariable method of specifying position
of radiator in a room
Unclear and variable approach
between the Surveyors
Materials, parts and componentry stored
randomly and poorly, often on top of one another
resulting in double handling, scuffing and damage
Method not defined plus some Surveyors &/or
Plumbers changed optimum position in response to
Tenant request
INDENTIFY THE ROOT CAUSE
5 Why Analysis
CO
UN
TE
R M
EA
SUR
EV
ER
IFY
RE
SOLU
TIO
N /
IMP
RO
VE
ME
NT
AC
TIO
NR
OO
T C
AU
SEW
HY
2W
HY
3W
HY
4W
HY
5
Wrong Radiator Supplied Damaged Radiator Incorrect Location
WH
Y 1
Unclear method + different
assumptions used when calculating size
of radiator required
Too much stock stored and poor
organisation of central stores
Method never formally defined nor
enforced
Method never formally defined
INFORMATION RELATING TO THE ISSUE CONTAIN
Fishbone Analysis
INDENTIFY THE ROOT CAUSE
UNDERSTAND THE ISSUE
50%50%
Properites With Quality Snags
No. Properties with Snags No. Properties Snag Free
Data period: 19th-23rd Mar 07Sample Size: 148 PropertiesDate Drawn: 26th Mar 07Drawn By: J Smith
1310 9 9
3 3 2 1
26%
46%
64%
82%88%
94%98% 100%
0.0%
20.0%
40.0%
60.0%
80.0%
100.0%
0
10
20
30
40
50
Radiators BuildingWorks
Pipe work/ Trunking
Domestic& Blow
Off
Boiler VerticalFlues
ElectricalWorks
Gas
No
. o
f O
ccu
ren
ces
Analysis of Quality IssuesData period: 19th-23rd Mar 07Sample Size: 148 PropertiesDate Drawn: 26th Mar 07Drawn By: J Smith
8
3
1
0123456789
10
RadiatorChange
Damaged Grille MarkedRadiator
No
. o
f O
ccu
ren
ces
Analysis of Radiator Quality Issues
Data analysed to
understand types of
defects made up the
50%
The Decent Homes team used
fishbone analysis to identify
all possible contributory
factors to the Radiator
Change issue.
Data relating to
Defective Radiators
analysed to reveal
main quality issue
Radiator
Change
Person Material
Machine (Tools)
Method Environment
Incorrect
Fitting
Cutting
Corners
Grill
Damage
Wrong
Size
Wrong Radiator
Supplied
Specif ied
Lack of
Training
Lack of
Care
Damaged
Radiator
Handling
Packaging
Storage
Connector
Thread
Incorrect
Tools
Insuff icient
Tools
Damaged
Tools
Marking
Out
Incorrect
Location
Tenant
Preference /
Change
Incorrect
Fitting
Poor
Method
Poor On-site
Storage
Diff icult Working
Conditions
Cramped
Furniture not clearedSmall
Rooms
Additional data identified
3 factors that were the
main contributors to the
problem
Keep asking 'Why'
until you feel that you
have exposed the true
'root' cause of the
issue
PROJECT: ABC Overall % VA
OPERATION: 2nd Fix Carpentry Total Steps 14 4 3 0 0 21 31.1%
PROCESS: Total Distance % Waste
DATE: 2011 Total Time 40.0%
No. Workers Distance Time Oper'n Tran's Delay Insp'n Store VA NVA Waste
1 Unload materials from van 3 26 3 3
2 Sort materials for fix 1 12 12
3 Take off protection to boxes 1 57 6 6
4 Mark positions of switches and sockets 1 61 11 11
5 Cut plasterboard for light switch in living room 1 2 2
6 Fit back box for switch 1 1 1
7 Trim cables 1 1 1
8 Connect the switch 1 2 2
9 Move to sockets 2 7 0.5 0.5
10 Fit sockets 1 3 3
11 Unpack light fitting 1 1 1
12 Walk up step ladder 1 2 0.5 0.5
13 Fit light fitting 1 2 2
14 Repeat in the next room 2 10 16 12 4
15 Cut hole in plasterboard to find cable 1 12 12
16 Feed cable back to the correct position 1 4 4
17 Refit the plasterboard cut outs 1 8 8
18 Fit light switch 1 2 2
19 Cut back cables to sockets 1 1 1 1
20 Fit sockets 1 2 2 2
TOTALS 24 166 90 14 4 3 0 0 28 26 36
Dry liners hadn't pulled the cables through w hilst boarding
Running concurrently
Apprentice is passing materials
ValueComment / IssueNo. Activity / Element
Measurement Flow
COMPANY: XYX ACTIVITY
SAMPLING
SHEET
SUMMARY
Work Study
0 20 40 60 80 100
Minutes
2nd Fix Electrical
VA
NVA
Waste
Work AnalysisStandard
Operations
Issue Ref. No: Care Point Key
Issue Date: Safety
Quality
Page 2 of 5 Knack
Main Task Step Main Task Step
Clear path from panel stack to erection position.
Ensure safe lif ting method.
Refer to draw ing to select appropriate panel
Start erection in rear corner of plot - w ork from back
to front of property to aid access
Secure 1st outer panel in position Ensure trained & competent in the use of hilty gun Secure 1st outer panel in position
- Nail panel through bottom timber into so le
plate, one nail in each end + one in the middleUse Hilty Gun for rapid nailing
- Fit timber stay to hold panel uprightTimber stay used to hold panel upright w hilst fetchiing
next panel
Fetch, position & secure 2nd panel Ensure safe carrying & passage as for Step 1 Fetch, position & secure 2nd panel
- Nail panel through bottom timber into so le
plate, one nail in end next to 1st panel.
Ensure 2nd panel is in correct position w ith regard to
outer edge of sole plate, is butted-up f lush w ith
adjoining face of 1st panel
- Check position of 2nd panel and that both
panels are verticalUse spirit level to ensure both panels are vertical
- Nail 2nd panel to 1st panel down vertical
inner edge. Remove timber stay from 1st
panel.
Use hammer for easier access + claw to pull nails
from timber stay & panel
- Nail 2nd panel through bottom timber into
so le plate, one nail at least every 600mmUse Hilty Gun for rapid nailing
Fetch, position & secure 3rd panel Ensure safe carrying & passage as for Step 1 Fetch, position & secure 3rd panel
- Select next panel that adjo ins either o f the
first two panelsRefer to draw ing for panel identif ication
- Repeat nailing and butting-up procedure as
for step 3
Ensure panel is positioned correctly - flush against so le plate
edge & with vertical face of adjo ining panel
To ensure flush fit between adjo ining vertical faces lift bottom
corner o f panel currently being fitted (Figure 1)
Use Hilty Gun for rapid nailing - Hold Wall panel upright & in position
3
2
Operator 2
- Hold Wall panel upright & in position
Care Point
1
2-PERSON JOB DETAIL
SHEET
Work / Job Description:
Timber Frame
Outer Wall Erection - Ground Floor
Sketch
Get f irst outer w all panel and lif t to
position for erection
Get f irst outer w all panel and lif t to
position for erection
Ensure appropriate head protection is
w orn
No.Operator 1
- Hold Wall panel upright & in position
- Hold Wall panel upright & in position
4
Nail panels together hammering nails
dow n through top edge of one panel
into adjacent panelM ay have to use sledge hammer to help seat panels so as to
ensure level top face along adjacent panels
Nail panels at low er outer face through
panel overhang into sole plate6
5
Stand on appropriate raised w ork surface that is
properly erected and stable
Before using any tools, equipment or plant you must have undergone relevant training and possess evidence that proves competence in the safe use & effective operation such item(s)
Vertical f aces must be joined so that continuous
contact along length of
Fixed Panel
Figure 1
Erect f irst panel starting on one of
the rear corners of plot
Whilst 1st Operator adjusts panel into f inal position, 2nd operator
holds panel staedty & upright
Improve
Lean Deployment for Construction Projects
Benefits Delivered
On-time construction from 67% to 90+%
30% increase in design capacity
Up to £5 million per annum bottom line gain
Design predictability improved by over 50%
Pre-construction lead time reduced by 40%
Productivity doubled
NRFT quality reduced by over 70%
Programme stability
Questions – As a Leader …
• What do you think? Does ‘one size fit all’?
• Are you just applying Lean tools or do you have a deployment strategy?
• What might be the barriers?
• How should you create the right conditions for success?
• What is the role of a Leader for effective deployment?
Leading the Deployment of Lean for Construction Projects
• Client expectations
• Lean construction in the UK• It has been a slow start – is it really being applied?
• Movement in the market – Client driven?
• Some Leaders have seen the light – going beyond just tools!
• A need to ‘raise the bar’
• Competitive advantage
• Bottom line benefit
• Growth
“The significant
problems we have
cannot be solved at
the same level of
thinking with which
we created them”.
Insanity:
Doing the same thing
over and over again
and expecting
different results.
Summary• The Lean project pathway
• Developed over many years and types of projects• One size doesn’t fit all• It does deliver!
• Leadership – Leaders need to be strong and committed• Clear vision and objectives – ‘raise the bar’• The integrated team• Good processes• People development, engagement and empowerment• Apply a structured and proven approach• Grow a Lean continuous improvement culture• Walk-the-talk
• Maximise benefits if applied to the whole end-to-end project process
• Long term strategy to apply Lean within your business and the extended supply chain
Better 100 people take one step forward than
1 person 100 steps